This amendment modifies a solicitation for the procurement of smart display units. The amendment deletes clauses applicable to a five-year requirement, changes the delivery schedule, and extends the solicitation closing date from 15 February 2022 to 15 March 2022. The basic requirement is for 150 smart display units per year for five years. The amendment removes option quantities and changes inspection and acceptance terms. Pricing must be provided for the basic quantity as well as any exercised option quantities. The procurement is restricted to a single contractor.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| SPRDL121R0047-0001.pdf | ||
| SPRDL121R0047.pdf | ||
| SPI_AK16704971.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. Contract ID Code Page Of
2. Amendment/Modification No.
3. Effective Date
4. Requisition/Purchase Req No.
5. Project No. (If applicable)
6. Issued By Code 7. Administered By (If other than Item 6) Code
8. Name And Address Of Contractor (No., Street, City, County, State and Zip Code)
9A. Amendment Of Solicitation No.
9B. Dated (See Item 11)
10A. Modification Of Contract/Order No.
10B. Dated (See Item 13) Code Facility Code
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of Offers is extended, is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing items 8 and 15, and returning ____________ copies of the amendments: (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. Accounting And Appropriation Data (If required)
13. THIS ITEM ONLY APPLIES TO MODIFICATIONS OF CONTRACTS/ORDERS
It Modifies The Contract/Order No. As Described In Item 14.
A. This Change Order is Issued Pursuant To: The Changes Set Forth In Item 14 Are Made In
The Contract/Order No. In Item 10A.
B. The Above Numbered Contract/Order Is Modified To Reflect The Administrative Changes (such as changes in paying office, appropriation data, etc.) Set
Forth In Item 14, Pursuant To The Authority of FAR 43.103(b).
C. This Supplemental Agreement Is Entered Into Pursuant To Authority Of:
D. Other (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return _______________ copies to the Issuing Office.
14. Description Of Amendment/Modification (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Except as provided herein, all terms and conditions of the document referenced in item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. Name And Title Of Signer (Type or print)
16A. Name And Title Of Contracting Officer (Type or print)
15B. Contractor/Offeror 15C. Date Signed 16B. United States Of America 16C. Date Signed
By (Signature of person authorized to sign) (Signature of Contracting Officer)
NSN 7540-01-152-8070
PREVIOUS EDITIONS UNUSABLE
30-105-02 STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA FAR (48 CFR) 53.243
SEE SCHEDULE
X
Firm Fixed Price
0002 2022MAR04
SPRDL1
DLA LAND WARREN
WARREN, MI 48397-5000
SABINE MCCORRY
EMAIL: SABINE.MCCORRY@DLA.MIL
SPRDL1-21-R-0047
2021DEC17
X
X 2022MAR15 03:00pm
/SIGNED/
2 signed
SEE SECOND PAGE FOR DESCRIPTION
1 15
CONTINUATION SHEET
Reference No. of Document Being Continued Page of
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
SECTION A - SUPPLEMENTAL INFORMATION
Buyer Name: SABINE MCCORRY
Buyer Office Symbol/Telephone Number: ZGAC/(586)467-1167
Type of Contract 1: Firm Fixed Price
Kind of Contract: Supply Contracts and Priced Orders
*** End of Narrative A0000 ***
Amendment 0002 to Solicitation SPRDL1-21-R-0047
1. The purpose of Amendment 0002 to Solicitation SPRDL1-21-R-0047 is to add and delete several clauses. All clauses for the five year long-term requirement no longer apply and have been deleted.
2. Change the delivery schedule. Please refer to continuation pages.
3. The solicitation closing date is extended from 15 February 2022 to 15 March 2022 3:00 pm EST.
4. All other terms and conditions of the solicitation remain unchanged.
*** END OF NARRATIVE A0003 ***
2 15
SPRDL1-21-R-0047
PIIN/SIIN
Page of
Name of Offeror or Contractor:
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
Reference No. of Document Being Continued
MOD/AMD
SECTION B - SUPPLIES OR SERVICES AND PRICES/COSTS
0001 DISPLAY UNIT
NSN: 7025-01-670-4971
Mfr CAGE: 19207
Mfr Part Number: 12581798
0001AA Production Quantity 78 EA $ $ ___________________ ______________ __________________
COMMODITY NAME: DISPLAY UNIT
CLIN CONTRACT TYPE:
Firm Fixed Price
PRON: EH1L0059EH PRON AMD: 03
Description/Specs./Work Statement _________________________________
TOP DRAWING NR: 12581798
DATE: 15-JAN-2021
The Technical Data Package (TDP) is Source Controlled to Contractor: General Dynamics Mission Systems, Cage
05257, Part Number 1026680-901
Approved Sources must meet the requirements of the
Government TDP.
(End of narrative C001)
Packaging and Marking _____________________
PACKAGING/PACKING/SPECIFICATIONS:
SEE PACKAGING CLAUSE
INTERMEDIATE PACK: 001
LEVEL PRESERVATION: Military
LEVEL PACKING: B
Inspection and Acceptance _________________________
INSPECTION: Origin ACCEPTANCE: Origin
Inspection/Acceptance at origin means that you MUST contact the DCMA to arrange for a Government inspection BEFORE you ship the supplies called out in this order. Failure to have the items inspected and accepted will result in their rejection at the destination. The rejected supplies will be returned to you at your expense.
(End of narrative E001)
Deliveries or Performance _________________________
3 15
Page of
Name of Offeror or Contractor:
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
Reference No. of Document Being Continued
MOD/AMD
DOC SUPPL
REL CD MILSTRIP ADDR SIG CD MARK FOR TP CD ______ ________ ______ ______ ________ _____
001 W56HZW1013Z628 W562RP J 2
DEL REL CD QUANTITY DAYS AFTER AWARD __________ ______________ ________________
001 78 0365
FOB POINT: Destination
SHIP TO:
(W562RP) SR ARMY GENERAL SUPPLY LMP STOCK RE
DLA DISTRIBUTION ANNISTON
7 FRANKFORD AVE 362
ANNISTON,AL,36201-4199
4 15
Page of
Name of Offeror or Contractor:
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
Reference No. of Document Being Continued
MOD/AMD
0002 DISPLAY UNIT
NSN: 7025-01-670-4971
Mfr CAGE: 19207
Mfr Part Number: 12581798
0002AA UNEXERCISED OPTION QUANTITY 78 EA $ $ ___________________________ ______________ __________________
COMMODITY NAME: DISPLAY UNIT
CLIN CONTRACT TYPE:
Firm Fixed Price
OPTION QUANTITY,
PURSUANT TO THE NARRATIVE ENTITLED 'SEPARATELY PRICED
OPTION FOR INCREASED QUANTITY' IN SECTION I OF THE
BASIC CONTRACT.
The quantity stated for the option CLIN DOES NOT Form a part of the basic contractual quantity. Part or all of it may, however, be added to the contract IAW option narrative entitled "Separately Priced Options for Increased Quantity", at the discretion of the
Government.
The failure of the offeror to insert a unit price applicable to the option quantity shall mean that the offeror will supply all or any part of the option, if exercised by the Government, at the basic contract unit price, and the offer will be evaluated for award.
(End of narrative B001)
Description/Specs./Work Statement _________________________________
TOP DRAWING NR: 12581798
DATE: 15-JAN-2021
The Technical Data Package (TDP) is Source Controlled to Contractor: General Dynamics Mission Systems, Cage
05257, Part Number 1026680-901
Approved Sources must meet the requirements of the
Government TDP.
(End of narrative C001)
Packaging and Marking _____________________
PACKAGING/PACKING/SPECIFICATIONS:
SEE PACKAGING CLAUSE
INTERMEDIATE PACK: 001
LEVEL PRESERVATION: Military
LEVEL PACKING: B
5 15
Page of
Name of Offeror or Contractor:
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
Reference No. of Document Being Continued
MOD/AMD
Inspection and Acceptance _________________________
INSPECTION: Origin ACCEPTANCE: Origin
Inspection/Acceptance at origin means that you MUST contact the DCMA to arrange for a Government inspection BEFORE you ship the supplies called out in this order. Failure to have the items inspected and accepted will result in their rejection at the destination. The rejected supplies will be returned to you at your expense.
(End of narrative E001)
Deliveries or Performance _________________________
DOC SUPPL
REL CD MILSTRIP ADDR SIG CD MARK FOR TP CD ______ ________ ______ ______ ________ _____
DEL REL CD QUANTITY DAYS AFTER AWARD __________ ______________ ________________
001 78 0365
FOB POINT: Destination
SHIP TO:
(Y00000) SHIPPING INSTRUCTIONS FOR CONSIGNEE
(SHIP-TO) WILL BE FURNISHED PRIOR
TO THE SCHEDULED DELIVERY DATE FOR
ITEMS REQUIRED UNDER THIS
REQUISITION.
6 15
Page of
Name of Offeror or Contractor:
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
Reference No. of Document Being Continued
MOD/AMD
0011 DELETED _______
0012 DELETED _______
0013 DELETED _______
0014 DELETED _______
0015 DELETED _______
7 15
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
SECTION F - DELIVERIES OR PERFORMANCE
F.1 Delivery Schedule
(a) Delivery under this contract must conform to the required schedule specified below, unless acceleration is acceptable.
(b) DEFINITIONS:
(1) DAYS means the number of days after the date of contract award when you must deliver the stated quantity (QTY) of supplies.
(2) DELIVERY is defined as follows:
FOB Origin - Contractor is required to deliver its shipment as provided in FAR 52.247-29(a)(1)-(4) by the time specified in the individual contract; or
FOB Destination - Contractor is required to deliver its shipment as provided in FAR 52.247-34(a)(1)-(2) by the time specified in the individual contract. The Contractor must take into consideration the length of time necessary to deliver its shipment to the destination designated in the contract, to ensure that the item reaches its destination by the time reflected in the contract.
(c) The Government requires delivery to be made according to the following schedule:
(1) GOVERNMENT REQUIRED DELIVERY SCHEDULE WITH FIRST ARTICLE TEST (FAT)
ITEM NO. QTY WITHIN DAYS AFTER DATE OF
CONTRACT AWARD
(2) GOVERNMENT REQUIRED DELIVERY SCHEDULE IF THERE IS NO FIRST ARTICLE TEST (FAT), OR IF FAT IS WAIVED
ITEM NO. QTY WITHIN DAYS AFTER DATE OF
CONTRACT AWARD
0001AA 78 365 Days After Award
0002AA 78 365 Days After Option Exercise
(d) Accelerated delivery schedule IS acceptable.
(e) If an accelerated delivery schedule is not acceptable, the required delivery schedule above will apply. If it is acceptable, you may propose an accelerated delivery schedule at no additional cost; fill in the appropriate information here:
(1) OFFERORS PROPOSED ACCELERATED DELIVERY SCHEDULE WITH FIRST ARTICLE TEST (FAT)
ITEM NO. QTY WITHIN DAYS AFTER DATE OF
CONTRACT AWARD
(2) OFFERORS PROPOSED ACCELERATED DELIVERY SCHEDULE WITHOUT FIRST ARTICLE TEST (FAT), or IF FAT IS WAIVED
ITEM NO. QTY WITHIN DAYS AFTER DATE OF
CONTRACT AWARD
************ End of Narrative F.1 ************
*** END OF NARRATIVE F0002 ***
8 15
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
SECTION I - CONTRACT CLAUSES
I.2 Separately Priced Option for Increased Quantity
(a) The Government may require the delivery of the numbered item, identified in the schedule as an option item, in the quantity and at the price stated in the schedule. This option may be exercised by the Government at any time, but in any event not later than 90 days after either (i) award or, if FAT is required, (ii) after FAT approval. In addition, such option may be exercised in increments, subject to the stated total additional quantity limitations, price(s), and the above-stated time for exercise of the option.
(b) Delivery of the items added by the exercise of this option shall continue immediately after, and at the same rate as, delivery of like items called for under this contract, unless the parties hereto otherwise agree.
(c) Additionally, prior to the expiration of the original option period identified in paragraph (a) above, the Government may seek a bilateral extension of the option period for an additional period not to exceed 90 days from the expiration date of the original option period.
************ End of Narrative I.2 ************
*** END OF NARRATIVE I0002 ***
Status Regulatory Cite Title Date Status Regulatory Cite Title Date _______ _______________ ______________________________________________________________________ ____________ _______ _______________ ______________________________________________________________________ ____________
I-1 DELETED 52.216-18 ORDERING AUG/2020
I-2 DELETED 52.216-19 ORDER LIMITATIONS OCT/1995
I-3 DELETED 52.216-22 INDEFINITE QUANTITY OCT/1995
I-4 DELETED 52.232-16 PROGRESS PAYMENTS (NOV 2021)--ALTERNATE III (JUN 2020) (DEVIATION JUN/2020
2020-O0010)
I-5 CHANGED 52.232-16 PROGRESS PAYMENTS (DEVIATION 2020-O0010) NOV/2021
The Government will make progress payments to the Contractor when requested as work progresses, but not more frequently than monthly, in amounts of $2,500 or more approved by the Contracting Officer, under the following conditions:
(a) Computation of amounts.
(1) Unless the Contractor requests a smaller amount, the Government will compute each progress payment as 90 percent of the
Contractor's total costs incurred under this contract whether or not actually paid, plus financing payments to subcontractors (see paragraph (j) of this clause), less the sum of all previous progress payments made by the Government under this contract. The
Contracting Officer will consider cost of money that would be allowable under Federal Acquisition Regulation (FAR) 31.205-10 as an incurred cost for progress payment purposes.
(2) The amount of financing and other payments for supplies and services purchased directly for the contract are limited to the amounts that have been paid by cash, check, or other forms of payment, or that are determined due and will be paid to subcontractors--
(i) In accordance with the terms and conditions of a subcontract or invoice; and
(ii) Ordinarily within 30 days of the submission of the Contractor's payment request to the Government.
(3) The Government will exclude accrued costs of Contractor contributions under employee pension plans until actually paid unless-
(i) The Contractor's practice is to make contributions to the retirement fund quarterly or more frequently; and
(ii) The contribution does not remain unpaid 30 days after the end of the applicable quarter or shorter payment period (any contribution remaining unpaid shall be excluded from the Contractor's total costs for progress payments until paid).
(4) The Contractor shall not include the following in total costs for progress payment purposes in paragraph (a)(1) of this clause:
(i) Costs that are not reasonable, allocable to this contract, and consistent with sound and generally accepted accounting principles and practices.
(ii) Costs incurred by subcontractors or suppliers.
(iii) Costs ordinarily capitalized and subject to depreciation or amortization except for the properly depreciated or amortized
9 15
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
portion of such costs.
(iv) Payments made or amounts payable to subcontractors or suppliers, except for--
(A) Completed work, including partial deliveries, to which the Contractor has acquired title; and
(B) Work under cost-reimbursement or time-and-material subcontracts to which the Contractor has acquired title.
(5) The amount of unliquidated progress payments may exceed neither (i) the progress payments made against incomplete work (including allowable unliquidated progress payments to subcontractors) nor (ii) the value, for progress payment purposes, of the incomplete work.
Incomplete work shall be considered to be the supplies and services required by this contract, for which delivery and invoicing by the
Contractor and acceptance by the Government are incomplete.
(6) The total amount of progress payments shall not exceed 90 percent of the total contract price.
(7) If a progress payment or the unliquidated progress payments exceed the amounts permitted by subparagraphs (a)(4) or (a)(5) above, the Contractor shall repay the amount of such excess to the Government on demand.
(8) Notwithstanding any other terms of the contract, the Contractor agrees not to request progress payments in dollar amounts of less than $2,500. The Contracting Officer may make exceptions.
(9) The costs applicable to items delivered, invoiced, and accepted shall not include costs in excess of the contract price of the items.
(b) Liquidation. Except as provided in the Termination for Convenience of the Government clause, all progress payments shall be liquidated by deducting from any payment under this contract, other than advance or progress payments, the unliquidated progress payments, or 90 percent of the amount invoiced, whichever is less. The Contractor shall repay to the Government any amounts required by a retroactive price reduction, after computing liquidations and payments on past invoices at the reduced prices and adjusting the unliquidated progress payments accordingly. The Government reserves the right to unilaterally change from the ordinary liquidation rate to an alternate rate when deemed appropriate for proper contract financing.
(c) Reduction or suspension. The Contracting Officer may reduce or suspend progress payments, increase the rate of liquidation, or take a combination of these actions, after finding on substantial evidence any of the following conditions:
(1) The Contractor failed to comply with any material requirement of this contract (which includes paragraphs (f) and (g) below).
(2) Performance of this contract is endangered by the Contractor's (i) failure to make progress or (ii) unsatisfactory financial condition.
(3) Inventory allocated to this contract substantially exceeds reasonable requirements.
(4) The Contractor is delinquent in payment of the costs of performing this contract in the ordinary course of business.
(5) The fair value of the undelivered work is less than the amount of unliquidated progress payments for that work.
(6) The Contractor is realizing less profit than that reflected in the establishment of any alternate liquidation rate in paragraph
(b) above, and that rate is less than the progress payment rate stated in subparagraph (a)(1) above.
(d) Title.
(1) Title to the property described in this paragraph (d) shall vest in the Government. Vestiture shall be immediately upon the date of this contract, for property acquired or produced before that date. Otherwise, vestiture shall occur when the property is or should have been allocable or properly chargeable to this contract.
(2) Property, as used in this clause, includes all of the below-described items acquired or produced by the Contractor that are or should be allocable or properly chargeable to this contract under sound and generally accepted accounting principles and practices.
(i) Parts, materials, inventories, and work in process;
(ii) Special tooling and special test equipment to which the Government is to acquire title;
(iii) Nondurable (i.e., noncapital) tools, jigs, dies, fixtures, molds, patterns, taps, gauges, test equipment, and other similar manufacturing aids, title to which would not be obtained as special tooling under subparagraph (ii) above; and
(iv) Drawings and technical data, to the extent the Contractor or subcontractors are required to deliver them to the Government by
10 15
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
other clauses of this contract.
(3) Although title to property is in the Government under this clause, other applicable clauses of this contract, e.g., the termination clauses, shall determine the handling and disposition of the property.
(4) The Contractor may sell any scrap resulting from production under this contract without requesting the Contracting Officer's approval, but the proceeds shall be credited against the costs of performance.
(5) To acquire for its own use or dispose of property to which title is vested in the Government under this clause, the Contractor must obtain the Contracting Officer's advance approval of the action and the terms. The Contractor shall (i) exclude the allocable costs of the property from the costs of contract performance, and (ii) repay to the Government any amount of unliquidated progress payments allocable to the property. Repayment may be by cash or credit memorandum.
(6) When the Contractor completes all of the obligations under this contract, including liquidation of all progress payments, title shall vest in the Contractor for all property (or the proceeds thereof) not--
(i) Delivered to, and accepted by, the Government under this contract; or
(ii) Incorporated in supplies delivered to, and accepted by, the Government under this contract and to which title is vested in the
Government under this clause.
(7) The terms of this contract concerning liability for Government-furnished property shall not apply to property to which the
Government acquired title solely under this clause.
(e) Risk of loss. Before delivery to and acceptance by the Government, the Contractor shall bear the risk of loss for property, the title to which vests in the Government under this clause, except to the extent the Government expressly assumes the risk. The Contractor shall repay the Government an amount equal to the unliquidated progress payments that are based on costs allocable to property that is lost (see 45.101).
(f) Control of costs and property. The Contractor shall maintain an accounting system and controls adequate for the proper administration of this clause.
(g) Reports, forms, and access to records.
(1) The Contractor shall promptly furnish reports, certificates, financial statements, and other pertinent information (including estimates to complete) reasonably requested by the Contracting Officer for the administration of this clause. Also, the Contractor shall give the Government reasonable opportunity to examine and verify the Contractor's books, records, and accounts.
(2) The Contractor shall furnish estimates to complete that have been developed or updated within six months of the date of the progress payment request. The estimates to complete shall represent the Contractor's best estimate of total costs to complete all remaining contract work required under the contract. The estimates shall include sufficient detail to permit Government verification.
(3) Each Contractor request for progress payment shall:
(i) Be submitted on Standard Form 1443, Contractor's Request for Progress Payment, or the electronic equivalent as required by agency regulations, in accordance with the form instructions and the contract terms; and
(ii) Include any additional supporting documentation requested by the Contracting Officer.
(h) Special terms regarding default. If this contract is terminated under the Default clause, (i) the Contractor shall, on demand, repay to the Government the amount of unliquidated progress payments, and (ii) title shall vest in the Contractor, on full liquidation of progress payments, for all property for which the Government elects not to require delivery under the Default clause. The Government shall be liable for no payment except as provided by the Default clause.
(i) Reservations of rights.
(1) No payment or vesting of title under this clause shall (i) excuse the Contractor from performance of obligations under this contract or (ii) constitute a waiver of any of the rights or remedies of the parties under the contract.
(2) The Government's rights and remedies under this clause (i) shall not be exclusive but rather shall be in addition to any other rights and remedies provided by law or this contract and (ii) shall not be affected by delayed, partial, or omitted exercise of any right, remedy, power, or privilege, nor shall such exercise or any single exercise preclude or impair any further exercise under this clause or the exercise of any other right, power, or privilege of the Government.
(j) Financing payments to subcontractors. The financing payments to subcontractors mentioned in paragraphs (a)(1) and (a)(2) of this
11 15
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
clause shall be all financing payments to subcontractors or divisions, if the following conditions are met:
(1) The amounts included are limited to--
(i) The unliquidated remainder of financing payments made; plus
(ii) Any unpaid subcontractor requests for financing payments.
(2) The subcontract or interdivisional order is expected to involve a minimum of approximately 6 months between the beginning of work and the first delivery; or, if the subcontractor is a small business concern, 4 months.
(3) If the financing payments are in the form of progress payments, the terms of the subcontract or interdivisional order concerning progress payments--
(i) Are substantially similar to the terms of this clause for any subcontractor that is a large business concern, or this clause with its Alternate I for any subcontractor that is a small business concern;
(ii) Are at least as favorable to the Government as the terms of this clause;
(iii) Are not more favorable to the subcontractor or division than the terms of this clause are to the Contractor;
(iv) Are in conformance with the requirements of FAR 32.504(e); and
(v) Subordinate all subcontractor rights concerning property to which the Government has title under the subcontract to the
Government's right to require delivery of the property to the Government if--
(A) The Contractor defaults; or
(B) The subcontractor becomes bankrupt or insolvent.
(4) If the financing payments are in the form of performance-based payments, the terms of the subcontract or interdivisional order concerning payments--
(i) Are substantially similar to the Performance-Based Payments clause at FAR 52.232-32 and meet the criteria for, and definition of, performance-based payments in FAR Part 32;
(ii) Are in conformance with the requirements of FAR 32.504(f); and
(iii) Subordinate all subcontractor rights concerning property to which the Government has title under the subcontract to the
Government's right to require delivery of the property to the Government if--
(A) The Contractor defaults; or
(B) The subcontractor becomes bankrupt or insolvent.
(5) If the financing payments are in the form of commercial item financing payments, the terms of the subcontract or interdivisional order concerning payments--
(i) Are constructed in accordance with FAR 32.206(c) and included in a subcontract for a commercial item purchase that meets the definition and standards for acquisition of commercial items in FAR Parts 2 and 12;
(ii) Are in conformance with the requirements of FAR 32.504(g); and
(iii) Subordinate all subcontractor rights concerning property to which the Government has title under the subcontract to the
Government's right to require delivery of the property to the Government if--
(A) The Contractor defaults; or
(B) The subcontractor becomes bankrupt or insolvent.
(6) If financing is in the form of progress payments, the progress payment rate in the subcontract is the customary rate used by the contracting agency, depending on whether the subcontractor is or is not a small business concern.
(7) Concerning any proceeds received by the Government for property to which title has vested in the Government under the subcontract terms, the parties agree that the proceeds shall be applied to reducing any unliquidated financing payments by the Government to the
12 15
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
Contractor under this contract.
(8) If no unliquidated financing payments to the Contractor remain, but there are unliquidated financing payments that the Contractor has made to any subcontractor, the Contractor shall be subrogated to all the rights the Government obtained through the terms required by this clause to be in any subcontract, as if all such rights had been assigned and transferred to the Contractor.
(9) To facilitate small business participation in subcontracting under this contract, the Contractor shall provide financing payments to small business concerns, in conformity with the standards for customary contract financing payments stated in FAR 32.113. The
Contractor shall not consider the need for such financing payments as a handicap or adverse factor in the award of subcontracts.
(k) Limitations on undefinitized contract actions. Notwithstanding any other progress payment provisions in this contract, progress payments may not exceed 80 percent of costs incurred on work accomplished under undefinitized contract actions. A contract action is any action resulting in a contract, as defined in subpart 2.1, including contract modifications for additional supplies or services, but not including contract modifications that are within the scope and under the terms of the contract, such as contract modifications issued pursuant to the Changes clause, or funding and other administrative changes. This limitation shall apply to the costs incurred, as computed in accordance with paragraph (a) of this clause, and shall remain in effect until the contract action is definitized. Costs incurred which are subject to this limitation shall be segregated on Contractor progress payment requests and invoices from those costs eligible for higher progress payment rates. For purposes of progress payment liquidation, as described in paragraph (b) of this clause, progress payments for undefinitized contract actions shall be liquidated at 80 percent of the amount invoiced for work performed under the undefinitized contract action as long as the contract action remains undefinitized. The amount of unliquidated progress payments for undefinitized contract actions shall not exceed 80 percent of the maximum liability of the Government under the undefinitized contract action or such lower limit specified elsewhere in the contract. Separate limits may be specified for separate actions.
(l) Due date. The designated payment office will make progress payments on the 30 th day after the designated billing office receives a proper progress payment request. In the event that the Government requires an audit or other review of a specific progress payment request to ensure compliance with the terms and conditions of the contract, the designated payment office is not compelled to make payment by the specified due date. Progress payments are considered contract financing and are not subject to the interest penalty provisions of the Prompt Payment Act.
(m) Progress payments under indefinite-delivery contracts. The Contractor shall account for and submit progress payment requests under individual orders as if the order constituted a separate contract, unless otherwise specified in this contract.
(End of clause)
13 15
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
SECTION L - INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS
L.18 Destinations for Option Quantities
To compute a price for any option quantity, assume you will be shipping a proportional share of the option quantity to each destination scheduled to receive shipments of the same item under the basic contract. For example, if the basic contract involves one third of the quantity to go to destination X, and two thirds to destination Y, assume those same percentages will apply to any option quantities the Government will exercise.
************ End of Narrative L.18 ************
L.19 Packaging Level for Option Quantities
For purposes of computing a price for the option quantity specified in Section B of this solicitation and unless otherwise indicated in Section B, it is understood and agreed that the option unit price includes the same level(s) of packing/packaging as those that apply to the basic contract quantity.
************ End of Narrative L.19 ************
*** END OF NARRATIVE L0002 ***
14 15
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
SECTION M - EVALUATION FACTORS FOR AWARD
M.9 Evaluation of Incomplete Option Pricing
(a) Per FAR 17.203(d), Offerors may price the option CLIN in this solicitation incrementally, by entering different option unit prices that will apply to different subquantities or quantity ranges (in the event that the Government elects to exercise less than 100% of the option). Notwithstanding this, the provision entitled EVALUATION OF OPTIONS (FAR 52.217-5, located elsewhere in this Section M) indicates that the Government's evaluation for contract award will include each Offeror's price for 100% of the option quantity.
(b) If an Offeror specifies unit prices that apply to one or more option quantity ranges, but does not specify a unit price for 100% of the option, the Government will evaluate that offer for award as follows. The option price for such offer shall be deemed to be the higher of (i) the unit price that applies to the basic (non-option) quantity, or (ii) the highest unit price that is identified against any range or subquantity of the option CLIN.
************ End of Narrative M.9 ************
*** END OF NARRATIVE M0002 ***
Status Regulatory Cite Title Date Status Regulatory Cite Title Date _______ _______________ ______________________________________________________________________ ____________ _______ _______________ ______________________________________________________________________ ____________
M-1 ADDED 52.217-5 EVALUATION OF OPTIONS JUL/1990