SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS

Offeror To Complete Block 12, 17, 23, 24, & 30

1. Requisition Number Page Of

2. Contract No. 3. Award/Effective Date 4. Order Number 5. Solicitation Number 6. Solicitation Issue Date

7. For Solicitation Information Call:

A. Name B. Telephone Number (No Collect Calls) 8. Offer Due Date/Local Time

9. Issued By Code 10. This Acquisition is Unrestricted OR Set Aside: % For:

Small Business Women-Owned Small Business (WOSB) Eligible Under the Women-Owned Small Business Program

Hubzone Small Business EDWOSB

Service-Disabled Veteran-Owned Small Business NAICS:

Email: 8(A) Size Standard:

11. Delivery For FOB Destination Unless Block Is Marked

12. Discount Terms 13a. This Contract Is A Rated Order Under DPAS (15 CFR 700) 13b. Rating

See Schedule 14. Method Of Solicitation RFQ IFB RFP

15. Deliver To Code 16. Administered By Code

Telephone No.

17a. Contractor/Offeror Code Facility 18a. Payment Will Be Made By Code

Telephone No.

17b. Check If Remittance Is Different And Put Such Address In Offer

18b. Submit Invoices To Address Shown In Block 18a Unless Block Below Is Checked See Addendum

19.

Item No.

20.

Schedule Of Supplies/Services

21.

Quantity

22.

Unit

23.

Unit Price

24.

Amount

(Use Reverse and/or Attach Additional Sheets As Necessary)

25. Accounting And Appropriation Data 26. Total Award Amount (For Govt. Use Only)

27a.Solicitation Incorporates By Reference FAR 52.212-1, 52.212-4. FAR 52.212-3 And 52.212-5 Are Attached. Addenda Are Are Not Attached.

27b.Contract/Purchase Order Incorporates By Reference FAR 52.212-4. FAR 52.212-5 Is Attached. Addenda Are Are Not Attached.

28. Contractor Is Required To Sign This Document And Return _________ 29. Award Of Contract: Ref. Offer Copies to Issuing Office. Contractor Agrees To Furnish And Deliver All Items Set Forth Or Otherwise Identified Above And On Any Additional Sheets Subject To The Terms And Conditions Specified.

Dated . Your Offer On Solicitation (Block 5), Including Any Additions Or Changes Which Are Set Forth Herein, Is Accepted As To Items:

30a. Signature Of Offeror/Contractor 31a. United States Of America (Signature Of Contracting Officer)

30b. Name And Title Of Signer (Type Or Print) 30c. Date Signed 31b. Name Of Contracting Officer (Type Or Print) 31c. Date Signed

Authorized For Local Reproduction Previous Edition Is Not Usable

Standard Form 1449 (Rev. 2/2012) Prescribed By GSA-FAR (48 CFR) 53.212

SPRDL1-19-Q-0264 2019OCT10

MICHAEL IVKOV (586)467-1180

MICHAEL.G.IVKOV.CIV@MAIL.MIL

2019NOV11 01:00pm

SPRDL1

DLA LAND WARREN

WARREN, MI 48397-5000

X

333415

X DOA4

X

SEE SCHEDULE

SEE SCHEDULE

X X

X 1

1 73

19.

Item No.

20.

Schedule Of Supplies/Services

21.

Quantity

22.

Unit

23.

Unit Price

24.

Amount

32a. Quantity In Column 21 Has Been

Received Inspected Accepted, And Conforms To The Contract, Except As Noted: _________________________________________________

32b. Signature Of Authorized Government Representative 32c. Date 32d. Printed Name and Title of Authorized Government Representative

32e. Mailing Address of Authorized Government Representative 32f. Telephone Number of Authorized Government Representative

32g. E-Mail of Authorized Government Representative

33. Ship Number 34. Voucher Number 35. Amount Verified 36. Payment 37. Check Number Correct For Partial Final Complete Partial Final

38. S/R Account No. 39. S/R Voucher Number 40. Paid By

41a. I Certify This Account Is Correct And Proper For Payment 42a. Received By (Print) 41b. Signature And Title Of Certifying Officer 41c. Date 42b. Received At (Location)

42c. Date Rec’d (YY/MM/DD) 42d. Total Containers

Standard Form 1449 (Rev. 2/2012) Back

CONTINUATION SHEET

Reference No. of Document Being Continued Page of

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

SUPPLEMENTAL INFORMATION

Buyer Name: MICHAEL IVKOV

Buyer Office Symbol/Telephone Number: ZGBB/(586)467-1180

Type of Contract 1: Firm Fixed Price

Kind of Contract: Supply Contracts and Priced Orders

*** End of Narrative A0000 ***

Acknowledgment of Amendments____________________________

Acknowledge all the amendments you've received from us by identifying the amendment number and its issue date below:

Amendment Number Date

Notice of Reverse Auction Provision___________________________________

This Request For Quotes (RFQ) solicitation will use the simplified acquisition procedures of FAR Part 13. Therefore, the following terminology in the reverse auction provision is changed as follows: replace proposal with quote, replace offer with quote, replace offeror with quoter, and replace final proposal revision with quotation.

After receipt of quotes, the contracting officer will determine if a reverse auction will be conducted. However, the use of a reverse auction does not preclude additional methods of price and/or cost analysis. The quoted prices received up until the start of the auction will be evaluated for award in accordance with the evaluation factors listed in the solicitation. After the start of the auction, the only way to revise prices is to participate in the auction by placing bids. Therefore, quotes received after the start of the auction will not be considered unless the contracting officer determines further correspondence is required.

If a reverse auction is held, Contractors must be registered in the reverse auction system in order to participate in the auction.

Additionally, the Contractor representative participating in the auction must have taken the on-line reverse auction training prior to the auction. Registration, on-line training, and other information regarding the reverse auction can be found at ://dla.procurexinc.com

. If a reverse auction is held and a Contractor that provided a quote to the solicitation does not participate in the auction, the_ initially quoted price(s) will be considered and evaluated.

Any other questions can be directed to the contract specialist listed in this solicitation.

Electronic Contracting Provision________________________________

(a) All DLA Land Warren solicitations will be publicized on the Federal Business Opportunities website (://www.fbo.gov ). Any additional attachments, including Technical Data Packages (TDPs) when available electronically, will be separate attachments or links embedded in the solicitation.

(b) Unless directed to do otherwise in Section L of this solicitation, vendors are required to submit a quote or proposal via the

Federal Business Opportunities (FBO) system.

(c) Requirements for the online FBO bid submission:

2 73

SPRDL1-19-Q-0264 REPRINT

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

1. Vendors must log into the FBO System to be able to submit electronic responses for opportunities.

2. Vendors must be registered in the System for Award Management (SAM) at sam.gov (a Federal Government owned and operated free web site) and have a CAGE Code and CCR Marketing Partner Identification Number (MPIN).

3. Once logged into the FBO System, vendors will be asked to enter basic information and directed to upload one or more files containing the proposal/quote and any additional information as outlined in the solicitation.

4. FBO will send an email to the vendors registered email address confirming the electronic submission.

5. For additional information on submitting electronic bid responses via the FBO system see the FBO Vendor Guide Section

4.3.1 Submitting an Electronic Response (://www.fbo.gov/downloads/FBO_Vendor_Guide.pdf ).

(d) Note to offerors:

Please pay close attention to the solicitation closing date and time as stated on the cover page of this solicitation, local time (EST), for DLA Land Warren. In accordance with FAR 15.208(a), offerors are responsible for submitting proposals, and any revisions, and modifications, so as to be received by the Government office designated in the solicitation by the time specified.

It is Offeror's responsibility to ensure the proposal/quote is received by the date and time specified on the cover page of this solicitation. In accordance with FAR 15.208, if the proposal/quote was not received at the initial point of entry to the Government infrastructure (in this case, received through FBO) by the exact date and time specified on the cover page of this solicitation, it will be determined late. Proposal/quote is defined to mean that ALL volumes or parts required in the solicitation are included in the electronic submission.

Note: There is no "expected" or "target" length of time for proposal submission; size and content may be factors, therefore offerors are strongly cautioned when submitting proposals to allow adequate time for submission.

Solicitations may remain posted on the FBO after the solicitation closing date. If the response deadline has passed for the solicitation, vendors will no longer be able to submit electronic responses. In this case, send any late quotes, if applicable, directly to the contract specialist identified on the cover page of this solicitation.

(e) Any award issued as a result of this solicitation will be distributed electronically. In the event of a FOIA request for a copy of any award issued as a result of this solicitation, or any subsequent modifications to the contract, the contract and modifications will be released, including the awarded unit price. This is the notice required by Executive Order 12600 (June 23, 1987) of our intention to release unit prices in response to any request under the Freedom of Information Act (FOIA), 5 USC 552. Unit price is defined as the contract price per unit or item purchased as it appears in Section B of the contract and is NOT referring to nor does it include Cost or

Pricing data/information. If you object to such release in the base contract or contract modifications, and you intend to submit an offer, notify the contracting officer in writing prior to the closing date identified in this solicitation and include the rationale for your objection consistent with the provisions of FOIA. A release determination will be made based on rationale given.

(f) Questions pertaining to this solicitation should be directed to the Contract Specialist identified on the cover page of this solicitation. For technical assistance in doing business with the Government, and doing business electronically, please visit the

Procurement Technical Assistance Center (PTAC) website at ://www.sba.gov/tools/local-assistance/ptac to locate a regional center.

All or None Provision_____________________

Offers in response to this solicitation must be submitted for the total quantity of the items identified in the solicitation.

(1) ONLY ONE AWARD WILL BE MADE AS A RESULT OF THIS SOLICITATION.

(2) OFFERS SUBMITTED FOR LESS THAN THE TOTAL QUANTITIES OF ALL THE ITEMS IN THIS SOLICITATION ARE INELIGIBLE FOR AWARD.

*** END OF NARRATIVE A0001 ***

3 73

PIIN/SIIN

Page of

Name of Offeror or Contractor:

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

Reference No. of Document Being Continued

MOD/AMD

SUPPLIES OR SERVICES AND PRICES/COSTS

0001 COOLER UNIT,AIR

NSN: 4130-01-562-6391

Mfr CAGE: 19207

Mfr Part Number: 12424367

0001AA PRODUCTION QUANTITY 6 EA $ $ ___________________ ______________ __________________

COMMODITY NAME: COOLER UNIT,AIR

CLIN CONTRACT TYPE:

Firm Fixed Price

PRON: EH9C1441EH PRON AMD: 01

AMS CD: SM2B1100000

Description/Specs./Work Statement _________________________________

TOP DRAWING NR: 12424367

DATE: 16-SEP-2016

The Technical Data Package (TDP) is Source Controlled to Contractor: Stewart & Stevenson, Cage OFW39, Part

Number TV060004

OR

Red Dot Corp, Cage 62534, Part Number R-5760-0.

Approved Sources must meet the requirements of the

Government TDP.

(End of narrative C001)

First Article Test is required. Waiver may be authorized; see waiver provision in Section L.

(End of narrative C002)

Packaging and Marking _____________________

PACKAGING/PACKING/SPECIFICATIONS:

SEE PACKAGING REQUIREMENTS CLAUSE

LEVEL PRESERVATION: Military

LEVEL PACKING: A

Inspection and Acceptance _________________________

INSPECTION: Origin ACCEPTANCE: Origin

Inspection/Acceptance at origin means that you MUST contact the DCMA to arrange for a Government inspection BEFORE you ship the supplies called out in this order. Failure to have the items inspected and accepted will result in their rejection at the destination. The rejected supplies will be returned to you at your expense.

4 73

Page of

Name of Offeror or Contractor:

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

Reference No. of Document Being Continued

MOD/AMD

(End of narrative E001)

Deliveries or Performance _________________________

DOC SUPPL

REL CD MILSTRIP ADDR SIG CD MARK FOR TP CD ______ ________ ______ ______ ________ _____

001 W56HZW9254151W W562RM J 2

DEL REL CD QUANTITY DAYS AFTER AWARD __________ ______________ ________________

001 6 0450

FOB POINT: Destination

SHIP TO:

(W562RM) SU W0MC ARMY GENERAL SUPPLY

DLA DISTRIBUTION RED RIVER

HIGHWAY 82 WEST

TEXARKANA,TX,75507-5000

5 73

Page of

Name of Offeror or Contractor:

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

Reference No. of Document Being Continued

MOD/AMD

0002 AIR COOLER UNIT

NSN: 4130-01-562-6391

Mfr CAGE: 19207

Mfr Part Number: 12424367

0002AA UNEXERCISED OPTION QUANTITY 6 EA $ $ ___________________________ ______________ __________________

COMMODITY NAME: AIR COOLER UNIT

OPTION QUANTITY,

PURSUANT TO THE CLAUSE ENTITLED OPTION FOR

INCREASED QUANTITY --- SEPARATELY PRICED LINE ITEM

(52.217-4001).

The quantity stated for the option CLIN DOES NOT Form a part of the basic contractual quantity. Part or all of it may, however, be added to the contract by exercise of the option clause, at the discretion of the Government.

The failure of the offeror to insert a unit price applicable to the option quantity shall mean that the offeror will supply all or any part of the option, if exercised by the Government, at the basic contract unit price, and the offer will be evaluated for award.

(End of narrative B001)

Description/Specs./Work Statement _________________________________

TOP DRAWING NR: 12424367

DATE: 16-SEP-2019

The Technical Data Package (TDP) is Source Controlled to Contractor: Stewart & Stevenson, Cage OFW39, Part

Number TV060004

OR

Red Dot Corp, Cage 62534, Part Number R-5760-0.

Approved Sources must meet the requirements of the

Government TDP.

(End of narrative C001)

Packaging and Marking _____________________

PACKAGING/PACKING/SPECIFICATIONS:

SEE PACKAGING REQUIREMENTS CLAUSE

LEVEL PRESERVATION: Military

LEVEL PACKING: A

Inspection and Acceptance _________________________

6 73

Page of

Name of Offeror or Contractor:

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

Reference No. of Document Being Continued

MOD/AMD

INSPECTION: Origin ACCEPTANCE: Origin

Inspection/Acceptance at origin means that you MUST contact the DCMA to arrange for a Government inspection BEFORE you ship the supplies called out in this order. Failure to have the items inspected and accepted will result in their rejection at the destination. The rejected supplies will be returned to you at your expense.

(End of narrative E001)

Deliveries or Performance _________________________

DOC SUPPL

REL CD MILSTRIP ADDR SIG CD MARK FOR TP CD ______ ________ ______ ______ ________ _____

DEL REL CD QUANTITY DAYS AFTER AWARD __________ ______________ ________________

001 6 0180

FOB POINT: Destination

SHIP TO:

(Y00000) SHIPPING INSTRUCTIONS FOR CONSIGNEE

(SHIP-TO) WILL BE FURNISHED PRIOR

TO THE SCHEDULED DELIVERY DATE FOR

ITEMS REQUIRED UNDER THIS

REQUISITION.

7 73

Page of

Name of Offeror or Contractor:

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

Reference No. of Document Being Continued

MOD/AMD

0003 FIRST ARTICLE TEST REPORT

Mfr CAGE: 19207

Mfr Part Number: 12424367

0003AA FAT REPORT- SEPERATELY PRICED $ $ _____________________________ ______________ __________________

COMMODITY NAME: FIRST ARTICLE TEST REPORT

A FIRST ARTICLE TEST REPORT IS REQUIRED IN ACCORDANCE

WITH THE CLAUSE ENTITLED "FIRST ARTICLE APPROVAL--

CONTRACTOR TESTING", FAR 52.209-3.

(End of narrative B001)

Description/Specs./Work Statement _________________________________

TOP DRAWING NR: 12424367

DATE: 16-SEP-2019

Packaging and Marking _____________________

Government Approval/Disapproval Days: 30

Deliveries or Performance _________________________

FOB POINT:

SHIP TO:

(Y00000) SHIPPING INSTRUCTIONS FOR CONSIGNEE

(SHIP-TO) WILL BE FURNISHED PRIOR

TO THE SCHEDULED DELIVERY DATE FOR

ITEMS REQUIRED UNDER THIS

REQUISITION.

See first article test clause for distribution.

(End of narrative F001)

8 73

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

DESCRIPTION/SPECIFICATIONS/WORK STATEMENT

Drawing Limitations___________________

(a) The drawings supplied with this contract are not shop or process drawings. They are engineering design drawings. They are ___ adequate to permit manufacture, and:

(1) depict the completed (item(s), and

(2) serve as the basis for inspection of the completed item(s).

(b) These drawings DON'T cover intermediate drawings/specifications or steps in the manufacturing process. As a result, even if you meet all the dimensions and tolerances specified in the engineering design drawing for each individual part, a cumulative unacceptable fit for the contract item could result.

(c) The Contractor is responsible for producing the shop or process drawings needed to cover intermediate steps in the _____________________________ manufacturing process.

(d) The Contractor is responsible for obtaining all specifications and drawings necessary to manufacture the items being solicited _____________________________ in accordance with the TDP including all incorporated specifications and drawings. Delivery delays are not excusable where the contractor asserts that it did not have a specification or drawing and has failed to request, in writing, the specification from either the Contracting Officer or Contract Specialist prior to the solicitation closing date.

(e) If you fail to produce an end item with a cumulative fit that conforms to Government drawings, specifications or other supplemental manufacturing documentation, you'll be responsible for correcting this condition at no additional cost to the Government and no delivery schedule extension.

Configuration Control Engineering Changes__________________________________________

(a) The contractor may submit Engineering Change Proposal(s) (ECPs) and Request for Variance(s) (RFVs) for the requirements in the

Government provided Technical Data Package (TDP). If a Value Engineering Change Proposal(s) (VECPs) clause is included on this contract, VECPs shall be submitted in the same manner as ECPs.

(1) ECPs - The contractor may request a permanent change to the requirements specified in the TDP or any other baseline documentation by submitting an ECP. ECPs shall be submitted to include all NORs necessary to completely define the requested change. Each ECP shall be accompanied with at least one NOR per affected document. The contractor shall not present any production items for acceptance that incorporate any change to the TDP or other baseline documentation until notified by the Government the ECP has been approved and incorporated in the contract.

(i) Page 1 of DD Form 1692 (or equivalent) shall be submitted for all ECPs. Pages 2-7 of DD Form 1692 shall be submitted when required to properly explain all the potential logistics and technical impacts of the proposed change. DD Form 1695 NOR or DD

Form 1695-1 Tabulated NOR (or equivalents) shall be submitted to completely describe the desired change on each affected document.

(ii) All ECPs submitted by the contractor will be routine priority unless otherwise justified. If the contractor considers the ECP to be emergency or urgent, they shall include justification within 48 hours of submittal of the ECP.

(2) RFVs - The contractor may request to temporarily depart from a requirement specified in the TDP or any other baseline documentation, by submitting an RFV. RFVs may be submitted either pre-production (formerly known as Request for Deviation (RFD)) or post-production and prior to acceptance by the Government (formerly known as Request for Waiver (RFW)). DD Form 1694 (or equivalent) shall be submitted for all RFVs. The contractor shall not present any production items for acceptance with any nonconformance to the requirements in the TDP or other baseline documentation until notified by the Government the RFV has been approved and incorporated in the contract.

(b) Submission of requested changes - The submission of an ECP or RFV by the Contractor does not affect the required delivery dates specified within the contract, shall not constitute excusable delay in the performance of this Contract by the Contractor or in any way relieve the contractor from compliance with the contract delivery schedule. If a delivery date change is needed, it must be negotiated with the Contracting Officer and documented via modification to the contract. The submission of an ECP and/or RFV by the Contractor shall not preclude the Government from exercising its rights under any clause of the Contract.

(c) Specifications - Permanent proposed changes to specifications which are part of the TDP or baseline documentation shall be requested with an ECP and NOR (i.e. Specification Change Notices (SCNs) are not required).

(d) Forms If any of the above listed forms are not included with the solicitation or contract, the contractor may locate forms on the

DOD Forms Website (://www.dtic.mil/whs/directives/forms/ ) or contact the contract specialist listed on page 1 of the solicitation or contract for copies of the forms.

9 73

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

Acquisition of Source-Controlled Part Number____________________________________________

Acquisition under this contract is restricted to:

(1) The manufacturer's part number or numbers set forth in the Schedule or the Technical Data Package; and

(2) Other manufacturer's part numbers that are physically, functionally, and mechanically interchangeable with the manufacturer's part number(s) listed in the Technical Data Package; provided (i) that these nonlisted part numbers have been furnished ________ to one of the approved manufacturers listed in the Technical Data Package, which firm has then, without making any changes in the characteristics or properties of the part, redesignated that part with one of the approved part numbers; and (ii) that firms tendering a nonlisted part number as described in this paragraph (2) have executed the provision 52.211-4038 entitled REPRESENTATION OF INTENT TO

SUPPLY A SOURCE-CONTROLLED ITEM herein.

Technical Data Package Information (FBO) Version________________________________________________

The following Xd item applies to this solicitation:

[ ] 1. There is no Technical Data Package (TDP) included with this solicitation.

[ ] 2. This solicitation contains one or more web-located TDPs. If multiple Contract Line Item Numbers (CLINS) are listed below, each one will have its own URL just under the CLIN listing. The URL will take you to that CLINs Web-located TDP. To access the TDP, you will have to copy or type the links URL to your web browser address bar at the top of the screen.

Note: To copy a link from a .pdf file, click on the Text Select Tool, then highlight the URL, copy and paste it into your browser, and hit the Enter key.

CLIN: N/A

TDP Link (URL): N/A

[ X ] 3. The TDP for this solicitation resides within FedBizOpps (://http://www.fbo.gov ), and is associated with this solicitation number and can be accessed via this URL:

"https://www.fbo.gov/fedteds/SPRDL119Q0264"

a. Log on to the FBO web site.

b. Enter your Marketing Partner Identification Number (MPIN).

c. Search for the solicitation number.

d. If solicitation is Export Controlled, select Verify MPIN.

(1) TDPs that have an Export Control Warning Notice are subject to the Arms Export Control Act (Title 22, U.S.C., Sec 2751, et.seq.) or the Export Administration Act of 1979, as amended, Title 50, U.S.C, App. 2401 et. seq.

(2) Further dissemination must be in accordance with provisions of DoD Directive 5230.25. This also applies to distribution of the TDP to all SUBCONTRACTORS at every level.

(3) To obtain these TDPs, vendors and contractors must have a current DD 2345, Militarily Critical Technical Data

Agreement on file with Defense Logistics Information Service (DLIS).\~ If you are currently certified, your MPIN will be verified and you may proceed to the next step.\~ To obtain certification, go to

://public.logisticsinformationservice.dla.mil/PublicHome/jcp/default.aspx click on documents and follow instructions provided.\~ Processing time is estimated at six (6) to ten (10) weeks after receipt. FBO will allow you to access export controlled TDPs once certification is confirmed.

(4) Upon completion of the purposes for which Government Technical Data has been provided, the Contractor is required to destroy all documents, including all reproductions, duplications, or copies thereof as may have been further distributed by the Contractor. Destruction of this technical data shall be accomplished by: shredding, pulping, burning, 10 73

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

or melting any physical copies of the TDP and/or deletion or removal of downloaded TDP files from computer drives and electronic devices, and any copies of those files.

e. If technical data is otherwise restricted, select Request Explicit Access. This will generate an email to the FBO system administrator at DLA Warren with all the information needed for them to grant you access. FBO will subsequently automatically generate an email stating when you have permission to view or download TDP items. Allow 2 3 working days to complete this FBO-TDP access/approval process through the FBO system.

f. If multiple individuals in your company need access to the Technical Data Package (TDP) for a solicitation and an explicit access request is required, each individual MUST submit an explicit access request to be granted approval to view the TDP. Those same individuals MUST be registered in Federal Business Opportunities (FBO). Any individuals no longer with the company should be deleted. Questions related to registration in FBO should be directed to https://www.fbo.gov/index The FBO helpdesk phone number is

(866) 606-8220. Vendors are responsible for placing correct information in FBO.

g. It is strongly suggested that you submit the explicit access request and provide the contract specialist with the completed Use and Non-Disclosure Agreement at the same time if the solicitation requires both to gain access to view the TDP.

h. A user guide for FBO can be found at https://http://www.fbo.gov - on the right is User Guides - click on Vendor.

[ ] 4. The Government requires a Use and Non-Disclosure Agreement (NDA) to be signed by an authorized representative of your firm before you are granted access to the technical data. The appropriate Agreement is titled N/A, and is:

[ ] available by emailing the contract specialist listed on page 1 of this solicitation.

[ ] available as an attachment to this solicitation.

Follow the instructions on the Agreement, and email/fax it to the contract specialist at N/A. The contract specialist will notify the

FBO administrator upon receiving the NDA. The administrator will grant approval to view/download the TDP. An email stating approval has been granted will be sent to the vendor. It can take up to 24 hours after approval before you are able to view the TDP. If you have any questions/problems viewing the TDP contact the contract specialist

Use of Class 1 Ozone Depleting Substances (CIODS)_________________________________________________

(a) Definitions.

(1) Class I and Class II Ozone-Depleting Substances (CIODS) refers to the class of substances identified in Section 602(a) of the Clean Air Act, (42 U.S.C. 7671a(a)), complete list provided at: ://www.epa.gov/ozone/science/ods/index.html .

(2) Directly requires the use of CIODS means that the Government's specification or technical data package, at any tier, explicitly requires the use of any Class I Ozone-Depleting Substance (CIODS) in performance of the contract.

(3) Indirectly requires the use of CIODS means that the Government's specification or technical data package, while not explicitly requiring the use of any CIODS, does require a feature that you can meet or produce only by the use of CIODS.

(b) No CIODS shall be used in meeting the requirements of this contract. If the use of CIODS is required in the performance of this contract, please notify the Contracting Officer immediately in writing.

(c) No Class II Ozone Depleting Substances shall be required in the performance of this contract without government approval. If the use of Class II ODS is required in the performance of this contract, please notify the Contracting Officer immediately in writing.

*** END OF NARRATIVE C0001 ***

PACKAGING AND MARKING

Packaging Requirements (Specifications Standards)__________________________________________________

(a) The preservation, packing, and marking requirements for this contract/order shall be accomplished in accordance with the

11 73

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

requirements in the specification/standard defined below.

(b) The following requirements shall apply:

(1) LEVEL OF PRESERVATION: Military

(2) LEVEL OF PACKING: A

(3) QUANTITY PER UNIT PACKAGE: 001

(4) SPECIFICATION/STANDARD: MIL-STD-2073-1

(c) The specification/standard cited is intended to give a clear and accurate description of the technical packaging requirements for the item being procured, including the procedure by which it can be determined that the requirements have been met. Specific instructions and/or tailoring of the specification/standard is detailed in the supplemental instructions below. Any design changes or changes in the method of preservation that provide a cost savings without degrading the method of preservation or packing and without affecting the serviceability of the item will be considered and responded to within 10 days of submission to PCO with copies to the ACO.

The government reserves the right to require testing to validate alternate industrial preservation methods, materials, blocking, bracing, cushioning, and packing.

(d) Marking:

(1) In addition to any special markings called out by the specification/standard above, all unit packages, intermediate packs, exterior shipping containers, and, as applicable, unitized loads shall be marked in accordance with MIL-STD-129, Revision R, including bar coding and Military Shipment Label (MSL). The contractor is responsible for application of special markings as discussed in the Military Standard regardless of whether specified in the contract/order or not. Special markings include, but are not limited to, Shelf-life markings, structural markings, and transportation special handling markings. The marking of pilferable and sensitive material will not identify the nature of the material. NOTE: Passive RFID tagging is required in all contracts that contain DFARS clause

252.211-7006. Contractors must check the solicitation and/or contract for this clause. For details and most recent information, see

://www.acq.osd.mil/log/sci/ait.html for the current DoD Suppliers Passive RFID Information Guide and Supplier Implementation Plan. When an item has Unique Item Identifier (UII) markings as indicated by the inclusion of contract clause DFARS 252.211-7006, refer to the DoD

Guide to Uniquely Identifying Items for development of the UII and MIL-STD-129, Revision R for UII package marking requirements.

Contractors must verify the RFID and UII clauses cited above are included in this solicitation/contract.

(e) Heat Treatment and Marking of Wood Packaging Materials (WPM):

(1) In accordance with DOD 4140.625-M and the requirements of the International Standards for Phytosanitary Measures 15

(ISPM), Regulation of Wood Packaging Material in International Trade, current edition, (hereinafter ISPM 15), the following commercial heat treatment and marking process has been approved by the American Lumber Standards Committee (ALSC) and is required for all Wood

Packaging Material (WPM). Foreign manufacturers shall comply with ISPM 15, and have the WPM heat treatment and marking verified in accordance with their National Plant Protection Organizations compliance program.

(2) Boxes/pallets and any wood used as inner packaging made of non-manufactured wood shall be heat-treated. All WPM using a conventional steam or dry kiln heat chamber (treatment code for the mark: HT) shall be heat treated to a minimum core temperature of 56 degrees Celsius for a minimum of 30 minutes, and certified by an agency accredited by the ALSC in accordance with Wood Packaging

Material Policy and Wood Packaging Material Enforcement Regulations (see URL: ://www.alsc.org ). WPM heat treated wood using dielectric heating (treatment code for the mark: DH) shall follow the requirements in ISPM 15, and shall be certified by an agency accredited by the ALSC in accordance with Wood Packaging Material Policy and Wood Packaging Material Enforcement Regulations (see URL:

://www.alsc.org ). The box/pallet manufacturer and the manufacturer of wood used as inner packaging shall ensure the materials used in manufacture can be traced to the original source of heat treatment, and that the original source of the heat treatment obtained the necessary certifications.

(3) Marking. Each box/pallet shall be marked to show the conformance to the International Plant Protection Convention

Standard. The ALSC approved quality mark shall be placed on both ends of the outer packaging, between the end cleats or end battens.

Pallet markings shall be applied to the side of the stringer or end of the block on diagonally opposite sides and ends of the pallet and be contrasting and clearly visible. All dunnage used in configuring and/or securing the load shall also comply with ISPM 15 and be marked with an ALSC approved DUNNAGE stamp.

(f) Hazardous Materials (As applicable):

(1) Hazardous Materials is defined as a substance, or waste which has been determined by the Secretary of Transportation to be capable of posing an unreasonable risk to health, safety, and property when transported in commerce and which has been so designated.

(This includes all items listed as hazardous in Titles 29, 40 and 49 CFR and other applicable modal regulations effective at the time of shipment.)

12 73

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

(2) When applicable, packaging and marking for hazardous material shall comply with the requirements herein for the mode of transport and the applicable performance packaging contained in the following documents:

- International Air Transport Association (IATA) Dangerous Goods Regulations

- International Maritime Dangerous Goods Code (IMDG)

- Code of Federal Regulations (CFR) Title 29, Title 40 and Title 49

- Joint Service Regulation AFJMAN24-204(I)/TM38-250/NAVSUPPUB 505/MCO

P4030.19(I)/DLAM 4145.3(I) (for military air shipments).

(3) If the shipment originates from outside the continental United States, the shipment shall be prepared in accordance with the United Nations Recommendations on the Transport of Dangerous Goods in a manner acceptable to the Competent Authority of the nation of origin and in accordance with regulations of all applicable carriers.

A Product Material Safety Data Sheets (MSDS) is required to be included with every unit pack and intermediate container and shall be included with the packing list inside the sealed pouch attached to the outside of the package.

(g) SUPPLEMENTAL INSTRUCTIONS: N/A

*** END OF NARRATIVE D0001 ***

INSPECTION AND ACCEPTANCE

Drawings for Inspection_______________________

(a) When requested, the Contractor shall make available to the Government Inspector the drawings and specifications to which the product was manufactured. Upon completion of product inspection and acceptance by the Government inspector, all drawings and specifications will be returned to the Contractor.

(b) If the Contractor is not the actual manufacturer of the item being procured (i.e. dealer, distributor, etc.), the Contractor shall ensure that subcontractor drawings are available for review to support the Government's inspection requirements.

(c) The Government may rely on the Contractor's Certificate of Conformance, IAW FAR 52.246-15, that the item tendered for acceptance conforms to the contract requirements. However, conditions may warrant that the Contractor be required to make available to the

Government the drawings, specifications, or other technical data such that the Government can determine if the item meets the contract requirements. These conditions may include, but are not limited to, the following: 1) Complex items or items which have quality characteristics for which contractual conformance must be established through precise measurements and functional operation, either as an individual item or in conjunction with other items. 2) Items used in critical applications or items denoted as critical on technical data. 3) Items with known quality conformance issues. 4) Items with an unstable design history. 5) Contractor changes in technical requirements, technical data, and/or production processes which impact the fit, form, or function of the item.

Inspection and Acceptance Points - Origin_________________________________________

The Government's inspection and acceptance of the supplies offered under this contract/purchase order shall take place at ORIGIN.

Offeror must specify below the exact name, address, and CAGE of the facility where supplies to be furnished under this contract/purchase order will be available for inspection/acceptance.

INSPECTION POINT:

(Name) (CAGE)

(Address) (City) (State) (Zip)

ACCEPTANCE POINT:

(Name) (CAGE)

13 73

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

Address) (City) (State) (Zip)

Alternatives to Lot Acceptance Sampling_______________________________________

(a) Offerors are encouraged to propose a defect prevention strategy in lieu of lot acceptance inspection and testing requirement cited in the technical data package. The Government recognizes that industry has developed numerous prevention based strategies which result in reduced process variation and promote continuous process improvement initiatives. Use of alternatives to lot acceptance sampling can provide offerors the latitude of implementing prevention based programs that are suitable to their particular mode of operation. Offerors are encouraged to submit their alternative proposals prior to award. Although the Government will entertain post award requests, there is no guarantee such requests will be accepted.

(b) Requests to use alternatives to lot acceptance sampling shall be provided to the Contracting Officer for review and approval or disapproval. Such request shall include:

(1) Identification of the specific inspections and tests to be reduced or eliminated.

(2) A description of your prevention based program. This should include such topics as training program and the performance of audits.

(3) A description of the tools used to monitor and control the specific processes being evaluated. This should include such topics as criteria for determining out of control conditions and procedures to be used when an out of control condition is detected.

(4) The results of a process performance study, and if available, the results of a process capability study.

(5) For SPC data to be used as an alternative to lot acceptance sampling, the following conditions shall be met:

(i) The process is in a state of statistical control using SPC control chart methods.

(ii) Variable data: for Critical characteristics a CPK =/> 2.00 (or equivalent capability) is achieved; for Major characteristics a CPK =/> 1.33 (or equivalent capability) is achieved.

(iii) Attribute data: for Critical Characteristics a process average of 100% of the product conforming to the specification; for Major characteristics a process average of 99.9937% of the product conforming to the specification.

(c) Proposals offered after award. The Contracting Officer is responsible for accepting or rejecting the alternate lot acceptance procedure submitted by the contractor. The contractor may submit an alternate lot acceptance procedure at any time during the performance of this contract. The Contracting Officer is responsible for accepting or rejecting the alternate procedure within 30 days of receipt. If the Government needs more time evaluate the alternate procedure, the Contracting Officer shall notify the contractor in writing, giving the reasons and the anticipated decision date. The contractor may withdraw its proposal at anytime prior to its incorporation by contract modification. Because offerors may withdraw their proposal at anytime, the Contracting Officer's failure to timely accept or reject the proposal shall not constitute grounds for claim against the Government. Any proposed and accepted procedure is not accepted, the Contracting Officer shall provide the contractor with written notification, explaining the reasons for rejection.

(d) Any equitable adjustment resulting from approval of an alternate lot acceptance procedure described in paragraph (c) above will be handled in accordance with the Changes clause of this contract.

(e) Until notification is received, the contractor is required to perform under this contract in accordance with the requirements herein, including lot acceptance inspection and testing.

Notice Regarding First Article______________________________

(a) Notwithstanding the provisions for waiver of first article, an additional first article sample (or portion thereof) may be ordered by the Contracting Officer in writing when (i) a major change is made to the technical data, (ii) whenever there is a lapse in production for a period in excess of one year, or (iii) whenever a change occurs in place of performance, manufacturing process, material used, drawing, specification or source of supply.

(b) When any of the conditions above occurs, the Contractor shall notify the Contracting Officer so that a determination can be made concerning the need for the additional first article sample (or portion thereof), and instructions can be provided concerning the submission, inspection, and notification of results.

14 73

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

(c) Costs of any additional testing and inspection resulting from conditions specified above shall be borne by the Contractor, unless the change was directed by the Government. Further, any production delays caused by additional testing and inspection will not be the basis for an excusable delay as defined in the default clause of this contract. Such delays shall not form the basis for adjustment in contract price or delivery schedule.

Notice Regarding First Article Test Sample__________________________________________

(a) The approved first article items, as described elsewhere in this contract, consist of a quantity of 1 that will be consumed or destroyed in testing. Any items consumed or destroyed in testing shall not be delivered as part of the contractually required quantity as set forth in the schedule. The cost of any items that are consumed or destroyed shall be included in the overall offer or contract price. A quantity of 0 that successfully passes all specified tests, less the destructive tests, if any, SHALL serve as a manufacturing standard for the remainder of the contract.

(b) A manufacturing standard is an item, which conforms to all technical performance requirements. A manufacturing standard will serve as 1) an aid in identifying configuration changes not controlled by the contractual design. 2) as an aid in identifying any process changes, or 3) as the approved workmanship sample, when required, unless alternate samples are submitted for specific characteristics by the Contractor and approved by the Government.

(c) The manufacturing standard will only be used to supplement contractual acceptance/rejection criteria for those process characteristics that require approved workmanship samples. For other characteristics, if configuration or process changes are identified in production units, the contractor will notify the contracting officer for disposition. Manufacturing items that serve as a manufacturing standard may be delivered as part of the contractual quantity with the last shipment made under this contract provided it meets all contractual requirements existing at time of delivery.

Inspection and Acceptance First Article Approval________________________________________________

In addition to inspection requirements specified in applicable drawings and/or specifications, the following provisions shall apply to this contract:

(1) FIRST ARTICLE APPROVAL-CONTRACTOR TESTING: First Article Approval-Contractor Testing shall be performed in accordance with 12505692 Cooler Unit / Heater Evaporator All Notes 1-48, FAT, First article Test 17 (All performance note requirements)

(2) The First Article Test Report (FATR) shall be compiled by the contractor to the contractor's own format. The FATR shall document the results of all inspections and tests (including supplier's and vendor's inspection records and certifications, when applicable). The FATR shall include actual inspections and test results to include all measurements, recorded test data, and certifications (if applicable) keyed to each drawing, specification and Quality Assurance Provision (QAP) requirement and identified by each individual QAP characteristic, drawing/specification characteristic and unlisted characteristic. The FATR shall contain sufficient narrative content, technical data, illustrations or photographic evidence, and an objective determination by the contractor to allow the designated Government representative to determine that the First Article Test was successfully completed.

Requirements for Pretreatment and CARC Painted Material________________________________________________________

(a) Scope

(1) This clause applies to contracts requiring Chemical Conversion Coatings and Pretreatments for Metallic Substrates, Chemical

Agent Resistant Coating (CARC), and their related materials. The requirements in this clause clarify and supplement those in the contract, unless nullified elsewhere in the contract or through an approved Request for Deviation.

(2) Coating qualification, spot paint repair, and MIL-DTL-16232 Phosphate Coating, Heavy, Manganese or Zinc Base coatings are not within the scope of this clause.

(b) Definitions

(1) The contracting agency, appropriate agency, procuring authority, engineering authority, procuring agency, and procuring activity is the PCO or designee.

(2) The prime contractor is the company awarded this contract, and the subcontractors comprise all companies involved in providing coated parts to the prime contractor, including companies that apply the coatings.

(c) General Requirements Clarifications

(1) The government retains the right for onsite verification of the prime contractors and its subcontractors products, processes, procedures, and test reports.

(2) The prime contractor shall be responsible for itself and its subcontractors to produce and maintain detailed process control plans, process control data, pre-production approval testing, ongoing quality control & quality control testing, and test reports.

This information shall be available upon government request.

(3) The prime contractor shall immediately notify the PCO and the Defense Contract Management Agency (DCMA) of any failure to meet preproduction and production requirements.

(4) Each cleaning method shall be treated as a separate step in the process documentation.

(5) The Gage Repeatability and Reproducibility (Gage R&R) error shall be less than 30 percent for all process and product

15 73

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

measurement systems.

(6) Products with hexavalent chromium, including but not limited to certain fastener finishes, shall not be used. Additionally, CARC topcoats containing siliceous additives to control gloss are prohibited.

(7) CARC primer and CARC topcoat shall not be applied directly to bare metal or plastic, except as provided for in MIL-DTL-53072.

(8) If the contract specifies application of CARC materials over a non-CARC coating, then both CARC primer and CARC topcoat are required. The complete coating system shall meet the requirements for CARC defined in TT-C-490.

(9) Neutral salt spray (NSS) testing shall not be used to validate compliance with materiel life cycle requirements; NSS is a production quality test and does not predict field performance.

(d) Pre-Production Approval Clarifications

(1) Pre-production testing shall include:

(i) Thickness of each layer of the coating system;

(ii) Coating system adhesion;

(iii) Salt spray performance; and

(iv) For phosphate pretreatments, the phosphate coating weight, crystal size and shape, and scanning electron microscope photos of the phosphate coatings at 500x and 1000x magnification.

(2) Pre-production test samples shall be from the material used for production parts, pieces cut from production representative parts, or production representative parts. Standardized test coupons shall not be used.

(3) Nine samples shall be produced for the required testing and shall include: three cleaned and pretreated test samples, three samples with the complete paint system and, depending on the CARC paint system, either three samples with pretreatment plus primer or three samples with metal-rich primer plus primer.

(4) One or more ISO 17025 laboratories shall conduct pre-production testing on the nine test samples in accordance with (IAW) the applicable test method accreditations. The applicable ISO 17025 test method accreditations include ASTM B117 Salt Spray, ASTM B244

Thickness of Non-Conductive Coatings on Non-Magnetic Metals, ASTM B487 Measurement of Metal and Oxide Coating Thickness, ASTM B499

Thickness of Non-Conductive Coatings on Magnetic Metals, and ASTM D3359 Measuring Adhesion by Tape Test.

(5) Unless required elsewhere in the contract and specifications, the CARC coating system applied to hot and cold rolled steel shall meet a minimum of 336 hours neutral salt spray resistance IAW ASTM B117.

(6) Test procedures shall be submitted IAW the Contract Data Requirements List (CDRL)…