SPRDL117R0402-0001.pdf
PDF 26 KB Posted
- Attached to
- Wiring Harness, Bran Federal contract opportunity
- Solicitation number
- SPRDL1-17-R-0402
About this file
Solicitation Amendment 0001
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| SPRDL117R0402.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. Contract ID Code Page Of
2. Amendment/Modification No.
3. Effective Date
4. Requisition/Purchase Req No.
5. Project No. (If applicable)
6. Issued By Code 7. Administered By (If other than Item 6) Code
8. Name And Address Of Contractor (No., Street, City, County, State and Zip Code)
9A. Amendment Of Solicitation No.
9B. Dated (See Item 11)
10A. Modification Of Contract/Order No.
10B. Dated (See Item 13) Code Facility Code
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of Offers is extended, is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing items 8 and 15, and returning ____________ copies of the amendments: (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. Accounting And Appropriation Data (If required)
13. THIS ITEM ONLY APPLIES TO MODIFICATIONS OF CONTRACTS/ORDERS
It Modifies The Contract/Order No. As Described In Item 14.
A. This Change Order is Issued Pursuant To: The Changes Set Forth In Item 14 Are Made In
The Contract/Order No. In Item 10A.
B. The Above Numbered Contract/Order Is Modified To Reflect The Administrative Changes (such as changes in paying office, appropriation data, etc.) Set
Forth In Item 14, Pursuant To The Authority of FAR 43.103(b).
C. This Supplemental Agreement Is Entered Into Pursuant To Authority Of:
D. Other (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return _______________ copies to the Issuing Office.
14. Description Of Amendment/Modification (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Except as provided herein, all terms and conditions of the document referenced in item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. Name And Title Of Signer (Type or print)
16A. Name And Title Of Contracting Officer (Type or print)
15B. Contractor/Offeror 15C. Date Signed 16B. United States Of America 16C. Date Signed
By (Signature of person authorized to sign) (Signature of Contracting Officer)
NSN 7540-01-152-8070
PREVIOUS EDITIONS UNUSABLE
30-105-02 STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA FAR (48 CFR) 53.243
SEE SCHEDULE
X
Firm Fixed Price
0001 2018JAN31
SPRDL1
DLA LAND WARREN
WARREN, MI 48397-5000
ROBERT HARRISON
EMAIL: ROBERT.W.HARRISON30.CIV@MAIL.MIL
SPRDL1-17-R-0402
2017NOV29
X
X 2018MAR02 04:00pm
/SIGNED/
2 signed
SEE SECOND PAGE FOR DESCRIPTION
1 11
CONTINUATION SHEET
Reference No. of Document Being Continued Page of
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
SECTION A - SUPPLEMENTAL INFORMATION
Buyer Name: ROBERT HARRISON
Buyer Office Symbol/Telephone Number: ZGA/(586)282-3160
Type of Contract 1: Firm Fixed Price
Kind of Contract: Supply Contracts and Priced Orders
*** End of Narrative A0000 ***
1) Exhibit A: Contract Data Requirements List, which includes Data Items A001 - A004
2) For Delivery, See Narrative(s) in Section J.
*** END OF NARRATIVE A0001 ***
The purpose of Amendment 0001 is for the following:
1) Remove the Small Business Set Aside restriction. Solicitation is now Full and Open. Any reference to a Small Business Set Aside should be disregarded.
2) Increase quantity by 22 each; from 31 each to 53 each.
3) Closing date will be extended to 02 March 2018.
All other terms and conditions, not changed/stated above, on the base solicitation remain unchanged.
*** END OF NARRATIVE A0002 ***
2 11
SPRDL1-17-R-0402 0001
PIIN/SIIN
Page of
Name of Offeror or Contractor:
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
Reference No. of Document Being Continued
MOD/AMD
SECTION B - SUPPLIES OR SERVICES AND PRICES/COSTS
0001 WIRING HARNESS,BRAN
NSN: 5995-01-581-0862
Mfr CAGE: 51880
Mfr Part Number: 56325
0001AA PRODUCTION QUANTITY 53 EA $ $ ____________________ ______________ __________________
COMMODITY NAME: WIRING HARNESS,BRAN
CLIN CONTRACT TYPE:
Firm Fixed Price
PRON: EH7C1333EH PRON AMD: 02
AMS CD: SM2B1100000
Description/Specs./Work Statement _________________________________
TOP DRAWING NR: 12473063-2
DATE: 28-OCT-2016
First Article Test is required. Waiver may be authorized; see waiver provision in Section L.
(End of narrative C001)
Packaging and Marking _____________________
PACKAGING/PACKING/SPECIFICATIONS:
SEE PACKAGING REQUIREMENTS CLAUSE
LEVEL PRESERVATION: Commercial
LEVEL PACKING: Commercial
Inspection and Acceptance _________________________
INSPECTION: Origin ACCEPTANCE: Origin
Deliveries or Performance _________________________
DOC SUPPL
REL CD MILSTRIP ADDR SIG CD MARK FOR TP CD ______ ________ ______ ______ ________ _____
001 W56HZV7158051Z W90454 J 2
DEL REL CD QUANTITY DAYS AFTER AWARD __________ ______________ ________________
001 53 0480
FOB POINT: Destination
SHIP TO:
(W90454) SU W4GG HQ US ARMY TACOM
TEAM ARMOR PARTNERSHIP FACILITY
WHSE BLDG 88037 LOGISTICS LANE
FORT HOOD,TX,76544-5060
3 11
Page of
Name of Offeror or Contractor:
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
Reference No. of Document Being Continued
MOD/AMD
0001AB DATA ITEM: FIRST ARTICLE TEST REPORT 1 EA $ ** NSP ** $ ** NSP ** ____________________________________ ______________ __________________
COMMODITY NAME: FIRST ARTICLE TEST REPORT
A FIRST ARTICLE TEST REPORT IS REQUIRED IN ACCORDANCE
WITH THE CLAUSE
ENTITLED "FIRST ARTICLE APPROVAL--CONTRACTOR TESTING",
FAR 52.209-3.
THE PRICE FOR FIRST ARTICLE TESTING IN THE TOTAL
AMOUNT OF $_______________ IS INCLUDED IN THE TOTAL
AMOUNT FOR CLIN 0001AA.
(End of narrative B001)
Packaging and Marking _____________________
Inspection and Acceptance _________________________
INSPECTION: Origin ACCEPTANCE: Destination
Government Approval/Disapproval Days: 30
Deliveries or Performance _________________________
DOC SUPPL
REL CD MILSTRIP ADDR SIG CD MARK FOR TP CD ______ ________ ______ ______ ________ _____
001 3
DEL REL CD QUANTITY DAYS AFTER AWARD __________ ______________ ________________
001 1 0270
FOB POINT: Destination
SHIP TO:
(Y00006) SEE FIRST ARTICLE TEST CLAUSE
FOR DISTRIBUTION
4 11
Page of
Name of Offeror or Contractor:
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
Reference No. of Document Being Continued
MOD/AMD
0002 WIRING HARNESS, BRAN
NSN: 5995-01-581-0862
Mfr CAGE: 19207
Mfr Part Number: 12473063-2
0002AA UNEXERCISED OPTION QUANTITY 53 EA $ $ ___________________________ ______________ __________________
COMMODITY NAME: WIRING HARNESS, BRAN
CLIN CONTRACT TYPE:
Firm Fixed Price
OPTION QUANTITY,
PURSUANT TO THE CLAUSE ENTITLED OPTION FOR
INCREASED QUANTITY --- SEPARATELY PRICED LINE ITEM
(52.217-4001).
The quantity stated for the option CLIN DOES NOT Form a part of the basic contractual quantity. Part or all of it may, however, be added to the contract by exercise of the option clause, at the discretion of the Government.
The failure of the offeror to insert a unit price applicable to the option quantity shall mean that the offeror will supply all or any part of the option, if exercised by the Government, at the basic contract unit price, and the offer will be evaluated for award.
(End of narrative B001)
Description/Specs./Work Statement _________________________________
TOP DRAWING NR: 12473063-2
DATE: 28-OCT-2016
Packaging and Marking _____________________
PACKAGING/PACKING/SPECIFICATIONS:
SEE PACKAGING REQUIREMENTS CLAUSE
LEVEL PRESERVATION: Commercial
LEVEL PACKING: Commercial
Inspection and Acceptance _________________________
INSPECTION: Origin ACCEPTANCE: Origin
Deliveries or Performance _________________________
DOC SUPPL
REL CD MILSTRIP ADDR SIG CD MARK FOR TP CD ______ ________ ______ ______ ________ _____
DEL REL CD QUANTITY DAYS AFTER AWARD __________ ______________ ________________
001 53 0180
5 11
Page of
Name of Offeror or Contractor:
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
Reference No. of Document Being Continued
MOD/AMD
FOB POINT: Destination
SHIP TO:
(Y00000) SHIPPING INSTRUCTIONS FOR CONSIGNEE
(SHIP-TO) WILL BE FURNISHED PRIOR
TO THE SCHEDULED DELIVERY DATE FOR
ITEMS REQUIRED UNDER THIS
REQUISITION.
6 11
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
SECTION F - DELIVERIES OR PERFORMANCE
Status Regulatory Cite Title Date Status Regulatory Cite Title Date _______ _______________ ______________________________________________________________________ ____________ _______ _______________ ______________________________________________________________________ ____________
F-1 CHANGED 52.242-4022 DELIVERY SCHEDULE SEP/2008
(TACOM)
(a) Delivery under this contract must conform to the required schedule specified below, unless acceleration is acceptable.
(b) DEFINITIONS:
(1) DAYS means the number of days after the date of contract award when you must deliver the stated quantity (QTY) of supplies.
(2) DELIVERY is defined as follows:
FOB Origin - Contractor is required to deliver its shipment as provided in FAR 52.247-29(a)(1)-(4) by the time specified in the individual contract; or
FOB Destination - Contractor is required to deliver its shipment as provided in FAR 52.247-34(a)(1)-(2) by the time specified in the individual contract. The contractor must take into consideration the length of time necessary to deliver its shipment to the destination designated in the contract, to ensure that the item reaches its destination by the time reflected in the contract.
(c) The Government requires delivery to be made according to the following schedule:
(1) GOVERNMENT REQUIRED DELIVERY SCHEDULE WITH FIRST ARTICLE TEST (FAT)
ITEM NO. QTY WITHIN DAYS AFTER DATE OF CONTRACT AWARD
0001AA 53 480 DARO
0001AB 1 270 DARO
0002AA 53 180 DARO
(2) GOVERNMENT REQUIRED DELIVERY SCHEDULE IF THERE IS NO FIRST ARTICLE TEST (FAT), OR IF FAT IS WAIVED
ITEM NO. QTY WITHIN DAYS AFTER DATE OF CONTRACT AWARD
0001AA 53 180 DARO
0002AA 53 180 DARO
(d) Accelerated delivery schedule IS acceptable.
(e) If an accelerated delivery schedule is not acceptable, the required delivery schedule above will apply. If it is acceptable, you may propose an accelerated delivery schedule at no additional cost; fill in the appropriate information here:
(1) OFFERORS PROPOSED ACCELERATED DELIVERY SCHEDULE WITH FIRST ARTICLE TEST (FAT)
ITEM NO. QTY WITHIN DAYS AFTER DATE OF CONTRACT AWARD
(2) OFFERORS PROPOSED ACCELERATED DELIVERY SCHEDULE WITHOUT FIRST ARTICLE TEST (FAT), or IF FAT IS WAIVED
ITEM NO. QTY WITHIN DAYS AFTER DATE OF CONTRACT AWARD
[End of Clause]
F-2 ADDED 52.247-4009 DELIVERY OF SUPPLIES FROM FOREIGN FIRMS TO U.S. PORT OF ENTRY AUG/2003
7 11
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
(TACOM)
This clause applies only to foreign firms when shipments are required to destinations within the Continental United States (CONUS).
(1) The F.O.B. point for this acquisition is DESTINATION. You must arrange and pay for (i) transportation to the U.S. port of entry, (ii) port handling, (iii) customs clearance, and (iv) all transportation from the port of entry to the consignee(s) listed in this solicitation.
(2) Acceptance will be at destination if the awardee is an OCONUS (Outside Continental United States) foreign firm.
(3) Identification of shipment. The Contractor must insure that all shipments be clearly marked in accordance with MIL-STD-
129 and other marking requirements specified in the Schedule. The Duty-Free Entry clauses in this contract contain instructions on the documentation required to accompany the shipment for duty-free entry.
(4) Notification of Shipment. The Contractor shall send electronic notification to the Procuring Contracting Officer (PCO) when shipment is made, which includes the following information:
(i) Mode of transportation, carrier, bill of lading number, customs broker (if any), and estimated time of arrival of materiel at OCONUS port authority
(ii) Mode of transportation, carrier, bill of lading number, and estimated dates for pick-up from CONUS port authority and delivery to final destination.
(5) You assume all responsibility for risk of loss or damage to the supplies until received at the destination. See the clause entitled RESPONSIBILITY FOR SUPPLIES (FAR 52.246-16).
[End of Clause]
8 11
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
SECTION I - CONTRACT CLAUSES
Status Regulatory Cite Title Date Status Regulatory Cite Title Date _______ _______________ ______________________________________________________________________ ____________ _______ _______________ ______________________________________________________________________ ____________
I-1 DELETED 52.219-6 NOTICE OF TOTAL SMALL BUSINESS SET-ASIDE NOV/2011
I-2 DELETED 52.219-14 LIMITATIONS ON SUBCONTRACTING JAN/2017
I-3 ADDED 52.219-4 NOTICE OF PRICE EVALUATION PREFERENCE FOR HUBZONE SMALL BUSINESS OCT/2014
CONCERNS
(a) Definition. See 13 CFR 125.6(e) for definitions of terms used in paragraph (d).
(b) Evaluation preference.
(1) Offers will be evaluated by adding a factor of 10 percent to the price of all offers, except
(i) Offers from HUBZone small business concerns that have not waived the evaluation preference; and
(ii) Otherwise successful offers from small business concerns.
(2) The factor of 10 percent shall be applied on a line item basis or to any group of items on which award may be made. Other evaluation factors described in the solicitation shall be applied before application of the factor.
(3) When the two highest rated offerors are a HUBZone small business concern and a large business, and the evaluated offer of the
HUBZone small business concern is equal to the evaluated offer of the large business after considering the price evaluation preference, award will be made to the HUBZone small business concern.
(c) Waiver of evaluation preference. A HUBZone small business concern may elect to waive the evaluation preference, in which case the factor will be added to its offer for evaluation purposes. The agreements in paragraphs (d) and (e) of this clause do not apply if the offeror has waived the evaluation preference.
___ Offer elects to waive the evaluation preference.
(d) Agreement. A HUBZone small business concern agrees that in the performance of the contract, in the case of a contract for
(1) Services (except construction), at least 50 percent of the cost of personnel for contract performance will be spent for employees of the concern or employees of other HUBZone small business concerns;
(2) Supplies (other than procurement from a nonmanufacturer of such supplies), at least 50 percent of the cost of manufacturing, excluding the cost of materials, will be performed by the concern or other HUBZone small business concerns;
(3) General construction. (i) At least 15 percent of the cost of contract performance to be incurred for personnel will be spent on the prime contractor's employees;
(ii) At least 50 percent of the cost of the contract performance to be incurred for personnel will be spent on the prime contractor's employees or on a combination of the prime contractor's employees and employees of HUBZone small business concern subcontractors;
(iii) No more than 50 percent of the cost of contract performance to be incurred for personnel will be subcontracted to concerns that are not HUBZone small business concerns; or
(4) Construction by special trade contractors. (i) At least 25 percent of the cost of contract performance to be incurred for personnel will be spent on the prime contractor's employees;
(ii) At least 50 percent of the cost of the contract performance to be incurred for personnel will be spent on the prime contractor's employees or on a combination of the prime contractor's employees and employees of HUBZone small business concern subcontractors;
(iii) No more than 50 percent of the cost of contract performance to be incurred for personnel will be subcontracted to concerns that are not HUBZone small business concerns.
(e) A HUBZone joint venture agrees that the aggregate of the HUBZone small business concerns to the joint venture, not each concern separately, will perform the applicable percentage of work requirements.
(f)(1) When the total value of the contract exceeds $25,000, a HUBZone small business concern nonmanufacturer agrees to furnish in performing this contract only end items manufactured or produced by HUBZone small business concern manufacturers.
9 11
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
(2) When the total value of the contract is equal to or less than $25,000, a HUBZone small business concern nonmanufacturer may provide end items manufactured by other than a HUBZone small business concern manufacturer provided the end items are produced or manufactured in the United States.
(3) Paragraphs (f)(1) and (f)(2) of this section do not apply in connection with construction or service contracts.
(g) Notice. The HUBZone small business offeror acknowledges that a prospective HUBZone awardee must be a HUBZone small business concern at the time of award of this contract. The HUBZone offeror shall provide the Contracting Officer a copy of the notice required by 13 CFR
126.501 if material changes occur before contract award that could affect its HUBZone eligibility. If the apparently successful HUBZone offeror is not a HUBZone small business concern at the time of award of this contract, the Contracting Officer will proceed to award to the next otherwise successful HUBZone small business concern or other offeror.
(End of clause)
10 11
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
SECTION L - INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS
Status Regulatory Cite Title Date Status Regulatory Cite Title Date _______ _______________ ______________________________________________________________________ ____________ _______ _______________ ______________________________________________________________________ ____________
L-1 ADDED 252.215-7008 ONLY ONE OFFER OCT/2013