SOLICITATION

View the file

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REQUEST FOR QUOTATION This RFQ is is not a small business set-aside Page Of

(This is NOT an Order)

1. Request No. 2. Date Issued 3. Requisition/Purchase Request No. 4. Cert For Nat Def. Under BDSA Rating

See Schedule Reg. 2 and/or DMS Reg. 1 5A. Issued By 6. Deliver by (Date)

See Schedule

7. Delivery

FOB Other Destination

5B. For Information Call: (Name and telephone no.) (No collect calls)

8. To: Name and Address, Including Zip Code 9. Destination (Consignee and address, including Zip Code)

See Schedule

10. Please Furnish Quotations to the Issuing Office in Block 5A On or Before Close of Business (Date)

IMPORTANT: This is a request for information, and quotations furnished are not offers. If you are unable to quote, please indicate on this form and return it to the address in Block 5B. This request does not commit the Government to pay any costs incurred in the preparation of the submission of this quotation or to contract for supplies or services.

Supplies are of domestic origin unless otherwise indicated by quoter. Any interpretations and/or certifications attached to this Request for Quotation must be completed by the quoter.

11. Schedule (Include applicable Federal, State, and local taxes)

Item Number (a)

Supplies/Services (b)

Quantity (c)

Unit (d)

Unit Price (e)

Amount (f)

(See Schedule)

12. Discount For Prompt Payment a. 10 Calendar Days b. 20 Calendar Days c. 30 Calendar Days d. Calendar Days % % % Number Percentage

NOTE: Additional provisions and representations are are not attached.

13. Name and Address of Quoter (Street, City, County, State and 14. Signature of Person Authorized to Sign 15. Date of Quotation Zip Code) Quotation

16. Signer

a. Name (Type or Print) b. Telephone

Area Code

c. Title (Type or Print) Number

AUTHORIZED FOR LOCAL REPRODUCTION Standard Form 18 (Rev. 8-95) PREVIOUS EDITIONS NOT USABLE 18-118 Prescribed by GSA-FAR (43 CFR) 53.215-1(a)

X

SPRDL1-16-Q-0220 2016MAY09 DOA4

SPRDL1DLA LAND WARREN

WARREN, MI 48397-5000

SHIVA BONGU (586)282-3179

ZGA

EMAIL: SHIVA.K.BONGU.CIV@MAIL.MIL

X

2016JUN10

1 51

CONTINUATION SHEET

Reference No. of Document Being Continued Page of

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

SUPPLEMENTAL INFORMATION

Buyer Name: SHIVA BONGU

Buyer Office Symbol/Telephone Number: ZGA/(586)282-3179

Type of Contract 1: Firm Fixed Price

Kind of Contract: Supply Contracts and Priced Orders

*** End of Narrative A0000 ***

Top drawing is source controlled to Niagara Thermal Products, CAGE 61228 P/N: 10001A and Aero-Classics DBA Pacific Oil Cooler, CAGE

1QJ31 P/N: 12275820.

*** END OF NARRATIVE A0001 ***

Regulatory Cite Title Date Regulatory Cite Title Date _______________ ______________________________________________________________________ ____________ _______________ ______________________________________________________________________ ____________

1 52.204-4016 WARREN ELECTRONIC CONTRACTING OCT/2015

(TACOM)

(a) All DLA Land Warren solicitations will be publicized on the Federal Business Opportunities website (https://www.fbo.gov). Any additional attachments, including Technical Data Packages (TDPs) when available electronically, will be separate attachments or links embedded in the solicitation.

(b) Unless directed to do otherwise in Section L of this solicitation, vendors are required to submit a quote or proposal via the

Federal Business Opportunities (FBO) system.

(c) Requirements for the online FBO bid submission:

1. Vendors must log into the FBO System to be able to submit electronic responses for opportunities.

2. Vendors must be registered in the System for Award Management (SAM) at www.sam.gov (a Federal Government owned and operated free web site) and have a CAGE Code and CCR Marketing Partner Identification Number (MPIN).

3. Once logged into the FBO System, vendors will be asked to enter basic information and directed to upload one or more files containing the proposal/quote and any additional information as outlined in the solicitation.

4. FBO will send an email to the vendors registered email address confirming the electronic submission.

5. For additional information on submitting electronic bid responses via the FBO system see the FBO Vendor Guide Section

4.3.1 Submitting an Electronic Response (https://www.fbo.gov/downloads/FBO_Vendor_Guide.pdf).

(d) Note to offerors:

Please pay close attention to the solicitation closing date and time as stated on the cover page of this solicitation, local time (EST), for DLA Land Warren. In accordance with FAR 15.208(a), offerors are responsible for submitting proposals, and any revisions, and modifications, so as to be received by the Government office designated in the solicitation by the time specified.

It is Offeror's responsibility to ensure the proposal/quote is received by the date and time specified on the cover page of this solicitation. In accordance with FAR 15.208, if the proposal/quote was not received at the initial point of entry to the Government infrastructure (in this case, received through FBO) by the exact date and time specified on the cover page of this solicitation, it will be determined late. Proposal/quote is defined to mean that ALL volumes or parts required in the solicitation are included in the electronic submission.

Note: There is no "expected" or "target" length of time for proposal submission; size and content may be factors, therefore offerors are strongly cautioned when submitting proposals to allow adequate time for submission.

Solicitations may remain posted on the FBO after the solicitation closing date. If the response deadline has passed for the solicitation, vendors will no longer be able to submit electronic responses. In this case, send any late quotes, if applicable, 2 51

SPRDL1-16-Q-0220

REPRINT

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

directly to the contract specialist identified on the cover page of this solicitation.

(e) Any award issued as a result of this solicitation will be distributed electronically. In the event of a FOIA request for a copy of any award issued as a result of this solicitation, or any subsequent modifications to the contract, the contract and modifications will be released, including the awarded unit price. This is the notice required by Executive Order 12600 (June 23, 1987) of our intention to release unit prices in response to any request under the Freedom of Information Act (FOIA), 5 USC 552. Unit price is defined as the contract price per unit or item purchased as it appears in Section B of the contract and is NOT referring to nor does it include Cost or

Pricing data/information. If you object to such release in the base contract or contract modifications, and you intend to submit an offer, notify the contracting officer in writing prior to the closing date identified in this solicitation and include the rationale for your objection consistent with the provisions of FOIA. A release determination will be made based on rationale given.

(f) Questions pertaining to this solicitation should be directed to the Contract Specialist identified on the cover page of this solicitation. For technical assistance in doing business with the Government, and doing business electronically, please visit the

Procurement Technical Assistance Center (PTAC) website at http://www.aptac-us.org/ to locate a regional center.

[End of Provision]

2 52.214-4003 ALL OR NONE MAR/1998

(TACOM)

Offers in response to this solicitation must be submitted for the total quantity of the items identified in the solicitation.

(1) ONLY ONE AWARD WILL BE MADE AS A RESULT OF THIS SOLICITATION.

(2) OFFERS SUBMITTED FOR LESS THAN THE TOTAL QUANTITIES OF ALL THE ITEMS IN THIS SOLICITATION ARE INELIGIBLE FOR AWARD.

[End of clause]

3 52.215-4000 ACKNOWLEDGMENT OF AMENDMENTS OCT/1993

Acknowledge all the amendments you've received from us by identifying the amendment number and its issue date below:

Amendment Number Date

(End of Provision)

4 52.215-4800 NOTICE OF REVERSE AUCTION PROVISION JAN/2014

(DLA LAND-

WARREN)

3 51

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

This solicitation contains standard DLAD provision 52.215-9023, Reverse Auction. This Request For Quotes (RFQ) solicitation will use the simplified acquisition procedures of FAR Part 13. Therefore, the following terminology in the reverse auction provision is changed as follows: replace proposal with quote, replace offer with quote, replace offeror with quoter, and replace final proposal revision with quotation.

After receipt of quotes, the contracting officer will determine if a reverse auction will be conducted. However, the use of a reverse auction does not preclude additional methods of price and/or cost analysis. The quoted prices received up until the start of the auction will be evaluated for award in accordance with the evaluation factors listed in the solicitation. After the start of the auction, the only way to revise prices is to participate in the auction by placing bids. Therefore, quotes received after the start of the auction will not be considered unless the contracting officer determines further correspondence is required.

If a reverse auction is held, Contractors must be registered in the reverse auction system in order to participate in the auction.

Additionally, the Contractor representative participating in the auction must have taken the on-line reverse auction training prior to the auction. Registration, on-line training, and other information regarding the reverse auction can be found at https://dla.procurexinc.com. If a reverse auction is held and a Contractor that provided a quote to the solicitaiton does not participate in the auction, the initially quoted price(s) will be considered and evaluated.

Questions related to the reverse auction system or process can be directed to dla.detroit.tacom.mbx.land-wrn-reverse-auction@mail.mil.

Any other questions can be directed to the contract specialist listed in this solicitation.

[End of Provision]

4 51

PIIN/SIIN

Page of

Name of Offeror or Contractor:

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

Reference No. of Document Being Continued

MOD/AMD

SUPPLIES OR SERVICES AND PRICES/COSTS

0001 COOLER,FLUID,TRANSM

NSN: 2520-01-162-7035

Mfr CAGE: 19207

Mfr Part Number: 12275820

0001AA PRODUCTION QUANTITY 37 EA $ $ ____________________ ______________ __________________

COMMODITY NAME: COOLER,FLUID,TRANSM

PRON: EH66E103EH PRON AMD: 01

AMS CD: SM2B1100000

Description/Specs./Work Statement _________________________________

TOP DRAWING NR: 12275820

DATE: 13-JAN-2016

Top drawing is source controlled.

NIAGRA DEVELOPMENT & MFG (CAGE-61228) P/N: 10001A

PACIFIC OIL COOLER OF OHIO (CAGE-1QJ31) P/N: 12275820

(End of narrative C001)

Packaging and Marking _____________________

PACKAGING/PACKING/SPECIFICATIONS:

SEE PACKAGING CLAUSE REQUIREMENT

UNIT PACK: 001

LEVEL PRESERVATION: Military

LEVEL PACKING: B

Inspection and Acceptance _________________________

INSPECTION: Origin ACCEPTANCE: Origin

Deliveries or Performance _________________________

DOC SUPPL

REL CD MILSTRIP ADDR SIG CD MARK FOR TP CD ______ ________ ______ ______ ________ _____

001 W56HZV6008968Z W562RP J 2

DEL REL CD QUANTITY DAYS AFTER AWARD __________ ______________ ________________

001 37 0110

FOB POINT: Destination

SHIP TO:

(W562RP) SR W0LX ARMY GENERAL SUPPLY

DLA DISTRIBUTION ANNISTON

7 FRANKFORD AVE

ANNISTON,AL,36201-4199

5 51

Page of

Name of Offeror or Contractor:

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

Reference No. of Document Being Continued

MOD/AMD

0002 COOLER,FLUID,TRANSM

NSN: 2520-01-162-7035

Mfr CAGE: 19207

Mfr Part Number: 12275820

0002AA UNEXERCISED OPTION 37 EA $ $ ____________________ ______________ __________________

COMMODITY NAME: COOLER,FLUID,TRANSM

CLIN CONTRACT TYPE:

Firm Fixed Price

OPTION QUANTITY, PURSUANT TO THE CLAUSE ENTITLED

OPTION FOR INCREASED QUANTITY---SEPARATELY

PRICED LINE ITEM (52.217-4001).

The quantity stated for the option CLIN DOES NOT form a part of the basic contractual quantity.

Part or all of it may, however, be added to the contract by exercise of the option clause, at the discretion of the Government.

The failure of the offeror to insert a unit price applicable to the option quantity shall mean that the offeror will supply all or any part of the option, if exercised by the

Government at the basic contract unit price, and the offer will be evaluated for award accordingly.

(End of narrative B001)

Description/Specs./Work Statement _________________________________

TOP DRAWING NR: 12275820

DATE: 13-JAN-2016

Top drawing is source controlled.

NIAGRA DEVELOPMENT & MFG (CAGE-61228) P/N: 10001A

PACIFIC OIL COOLER OF OHIO (CAGE-1QJ31) P/N: 12275820

(End of narrative C001)

Packaging and Marking _____________________

PACKAGING/PACKING/SPECIFICATIONS:

SEE PACKAGING CLAUSE REQUIREMENT

UNIT PACK: 001

LEVEL PRESERVATION: Military

LEVEL PACKING: B

Inspection and Acceptance _________________________

INSPECTION: Origin ACCEPTANCE: Origin

6 51

Page of

Name of Offeror or Contractor:

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

Reference No. of Document Being Continued

MOD/AMD

Deliveries or Performance _________________________

DOC SUPPL

REL CD MILSTRIP ADDR SIG CD MARK FOR TP CD ______ ________ ______ ______ ________ _____

DEL REL CD QUANTITY DAYS AFTER AWARD __________ ______________ ________________

001 37 0110

FOB POINT: Destination

SHIP TO:

(Y00000) SHIPPING INSTRUCTIONS FOR CONSIGNEE

(SHIP-TO) WILL BE FURNISHED PRIOR

TO THE SCHEDULED DELIVERY DATE FOR

ITEMS REQUIRED UNDER THIS

REQUISITION.

7 51

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

DESCRIPTION/SPECIFICATIONS/WORK STATEMENT

5 52.211-4015 CONFIGURATION CONTROL - ENGINEERING CHANGES DEC/2005

(TACOM)

(a) DEFINITIONS:

(1) Engineering Change Proposal (ECP). An ECP is a suggestion that we (the Government) permanently change some requirement of the Technical Data Package (TDP). ECPs can be issued before or during contract performance. NOTE: The current Government Standard allows us ninety days to process routine ECPs. If you (the contractor) need a response in less than ninety days to meet contract requirements, you should consider submitting a deviation along with your ECP.

(2) Notice of Revision (NOR). A NOR describes the proposed changes to a technical document being requested by an ECP.

(3) Value Engineering Change Proposal (VECP). A proposal that --

(i) Requires a change to the instant contract; and

(ii) Results in reducing the overall projected cost to the agency without impairing essential functions or characteristics; provided, that it does not involve a change --

(A) In deliverable end item quantities only;

(B) In research and development (R&D) end items or R&D test quantities that is due solely to results of previous testing under this contract; or

(C) To the contract type only.

(4) Request for Deviation (RFD). A RFD is a one-time request to deviate from TDP requirements. You must submit your deviation request once you realize that you desire to deviate from the TDP requirements. You can request a deviation for a specific number of parts or the entire contract quantity.

(b) When will TACOM start processing change requests? TACOM won't start processing any ECP, VECP, or RFD until we receive the

ACO's comments (see paragraph (e) below) and the ECP, VECP, or RFD documentation.

(c) Contractor Responsibility. ECPs, VECPs, and RFD shall contain information per the instructions outlined on the Data Delivery

Descriptions (DDDs) which can be found at the following website: http://contracting.tacom.army.mil/engr/engrchange.htm. Forms for preparing an ECP, VECP, or a RFD can also be found at this website. You may use other media, as long as you give us all the information outlined in the DDDs.

(1) Identify the two-digit Weapon System Code (WSC) on your submittal. The WSC for this procurement is JT.

(2) The Contractor shall submit ECPs/VECPs/RFDs to the Government electronically. You must use one of the following electronic mediums: 3 1/2 inch disk, 650 megabyte CD ROM, or E-mail. (E-mail files must be sized 3.5 mb or less.) Identify the software application, and version, that you used to create each file submitted.

(3) ECPs/VECPs/RFDs submitted in paper form are unacceptable and will be returned. You must use one of the following electronic formats:

(i) Files readable using these Microsoft 97 Office Products or later versions: Word, Excel, PowerPoint, or Access.

Spreadsheets must be sent in a file format that includes all formulae, macro and format information. Print image is not acceptable.

(ii) Files in Adobe PDF (Portable Document Format).

(iii) Files in HTML (Hypertext Markup Language). HTML documents must not contain active links to live Internet sites or pages. All linked information must be contained within your electronic ECPs/VECPs/RFDs and be accessible offline.

(iv) Other electronic formats. Before preparing your ECPs, VECPs or RFDs in any other electronic format, please e-mail the engineer, copy-furnished to the buyer and ACO, to obtain a decision as to the format's acceptability. Failure to e-mail the engineer to seek an alternate format's acceptability may result in rejection of your submission. All alternate methods must be at no cost to the Government. NOTE: The above formats may be submitted in compressed form using self-extracting files.

(d) Submittal Procedures for ECPs/VECPs/RFDs.

8 51

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

(1) Send one copy of the ECP, VECP or RFD in electronic format to your ACO.

(2) Send one copy of the ECP, VECP or RFD in electronic format to the buyer listed on the solicitation/ contract document.

WARNING - Submit complete, legible, virus free packages per paragraphs 1 and 2 above, or we may return your ECP/VECP/RFD without processing them.

(e) ACO Responsibility. Within ten working days from the day you receive the contractor's request, the ACO must prepare Comments on the ECP, VECP, or RFD in electronic format, and forward it as follows:

Email a copy of the contractor's request and ACO comments (DD Form 1998) to the buyer identified in block 7 of the solicitation cover sheet (SF 33), block 5 on the Standard Form 26, or block 6 on the DD Form 1155. Indicate end item application (if known) in subject line, along with the NSN and contract number.

(f) Approval of ECPs, VECPs and RFDs.

(1) ECPs should be used to make permanent changes in the Government Technical Data Package (TDP). Contractual relief should be requested using a Request for Deviation. This is because the Government requires more time to analyze any proposal to permanently change the specification or TDP. Cost saving improvements to the TDP should be submitted as a VECP, if a VE clause is contained in the contract.

(2) ECPs. TACOM will review and make a decision within the ninety day timeframe. Notification of our decision will be made by the contracting officer or representative.

(3) RFDs. Decision on RFDs will be made within 30 days from the date we receive them from the ACO.

(g) Processing Emergency and Urgent ECPs. Ordinarily, ECPs submitted by the contractor will be deemed routine. If you submit an

ECP that you consider to be an emergency or urgent (as defined in paragraph 11 of DDD for ECPs), you must immediately notify the PCO.

TACOM will review the criticality of the ECP, and, if we determine that it is urgent or critical, we'll follow the appropriate processing time-frames as outlined in paragraph 11 of the DDD for ECPs.

(h) Reminder - Only the PCO can change the Contract. NO OTHER GOVERNMENT REPRESENTATIVE is authorized to make a commitment for, or bind the Government.

(i) RFDs shall contain sufficient pricing data to determine if a downward equitable adjustment to the contract is required.

(j) Questions.

(1) Questions about preparation and submittal of change request should be directed to the Government Quality Assurance

Representative (QAR).

(2) Questions about the status of change requests you've already submitted, contact the buyer. You can find the buyer's name, number and e-mail address in block 7 of the solicitation cover sheet (SF 33), block 5 on the Standard Form 26, or block 6 on the DD Form

1155.

[End of Clause]

6 52.211-4072 TECHNICAL DATA PACKAGE INFORMATION SEP/2015

(TACOM)

The following Xd item applies to this solicitation:

[ ] 1. There is no Technical Data Package (TDP) included with this solicitation.

[ ] 2. This solicitation contains one or more web-located TDPs. If multiple Contract Line Item Numbers (CLINS) are listed below, each one will have its own URL just under the CLIN listing. The URL will take you to that CLINs Web-located TDP. To access the TDP, you will have to copy or type the links URL to your web browser address bar at the top of the screen.

Note: To copy a link from a .pdf file, click on the Text Select Tool, then highlight the URL, copy and paste it into your browser, and hit the Enter key.

CLIN: NA

9 51

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

TDP Link (URL): NA

[X ] 3. The TDP for this solicitation resides within FedBizOpps (https://http://www.fbo.gov), and is associated with this solicitation number and can be accessed via this URL:

https://www.fbo.gov/fedteds/SPRDL116Q0220

a. Log on to the FBO web site.

b. Enter your Marketing Partner Identification Number (MPIN).

c. Search for the solicitation number.

d. If solicitation is Export Controlled, select Verify MPIN.

(1) TDPs that have an Export Control Warning Notice are subject to the Arms Export Control Act (Title 22, U.S.C., Sec

2751, et.seq.) or the Export Administration Act of 1979, as amended, Title 50, U.S.C, App. 2401 et. seq..

(2) Further dissemination must be in accordance with provisions of DoD Directive 5230.25. This also applies to distribution of the TDP to all SUBCONTRACTORS at every level.

(3) To obtain these TDPs, vendors and contractors must have a current DD 2345, Militarily Critical Technical Data

Agreement on file with Defense Logistics Information Service (DLIS). If you are currently certified, your MPIN will be verified and you may proceed to the next step. To obtain certification, go to http://www.dlis.dla.mil/jcp/ click on documents and follow instructions provided. Processing time is estimated at six (6) to ten (10) weeks after receipt. FBO will allow you to access export controlled TDPs once certification is confirmed.

(4) Upon completion of the purposes for which Government Technical Data has been provided, the Contractor is required to destroy all documents, including all reproductions, duplications, or copies thereof as may have been further distributed by the

Contractor. Destruction of this technical data shall be accomplished by: shredding, pulping, burning, or melting any physical copies of the TDP and/or deletion or removal of downloaded TDP files from computer drives and electronic devices, and any copies of those files.

e. If technical data is otherwise restricted, select Request Explicit Access. This will generate an email to the FBO system administrator at TACOM Warren with all the information needed for them to grant you access. FBO will subsequently automatically generate an email stating when you have permission to view or download TDP items. Allow 2 3 working days to complete this FBO-TDP access/approval process through the FBO system.

f. If multiple individuals in your company need access to the Technical Data Package (TDP) for a solicitation and an explicit access request is required, each individual MUST submit an explicit access request to be granted approval to view the TDP. Those same individuals MUST be registered in Federal Business Opportunities (FBO). Any individuals no longer with the company should be deleted.

Questions related to registration in FBO should be directed to https://www.fbo.gov/index The FBO helpdesk phone number is (866) 606-

8220. Vendors are responsible for placing correct information in FBO.

g. It is strongly suggested that you submit the explicit access request and provide the contract specialist with the completed Use and

Non-Disclosure Agreement at the same time if the solicitation requires both to gain access to view the TDP.

h. A user guide for FBO can be found at https://http://www.fbo.gov - on the right is User Guides - click on Vendor.

[ ] 4. The Government requires a Use and Non-Disclosure Agreement (NDA) to be signed by an authorized representative of your firm before you are granted access to the technical data. The appropriate Agreement is titled NA, and is:

[ ] available by emailing the contract specialist listed on page 1 of this solicitation.

[ ] available as an attachment to this solicitation.

Follow the instructions on the Agreement, and email/fax it to the contract specialist at NA. The contract specialist will notify the

FBO administrator upon receiving the NDA. The administrator will grant approval to view/download the TDP. An email stating approval has been granted will be sent to the vendor. It can take up to 24 hours after approval before you are able to view the TDP. If you have any questions/problems viewing the TDP contact the contract specialist.

[End of Clause]

10 51

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

7 52.211-4008 DRAWING LIMITATIONS NOV/2005

(TACOM)

(a) The drawings supplied with this contract are not shop or process drawings. They are engineering design drawings. They are ___ adequate to permit manufacture, and:

(1) depict the completed (item(s), and

(2) serve as the basis for inspection of the completed item(s).

(b) These drawings DON'T cover intermediate drawings/specifications or steps in the manufacturing process. As a result, even if you meet all the dimensions and tolerances specified in the engineering design drawing for each individual part, a cumulative unacceptable fit for the contract item could result.

(c) The Contractor is responsible for producing the shop or process drawings needed to cover intermediate steps in the _____________________________ manufacturing process.

(d) The Contractor is responsible for obtaining all specifications and drawings necessary to manufacture the items being solicited _____________________________ in accordance with the TDP including all incorporated specifications and drawings. Delivery delays are not excusable where the contractor asserts that it did not have a specification or drawing and has failed to request, in writing, the specification from either the Contracting Officer or Contract Specialist prior to the solicitation closing date.

(e) If you fail to produce an end item with a cumulative fit that conforms to Government drawings, specifications or other supplemental manufacturing documentation, you'll be responsible for correcting this condition at no additional cost to the Government and no delivery schedule extension.

[End of clause]

8 52.211-4010 ACQUISITION OF SOURCE-CONTROLLED PART NUMBER FEB/1998

(TACOM)

Acquisition under this contract is restricted to:

(1) The manufacturer's part number or numbers set forth in the Schedule or the Technical Data Package; and

(2) Other manufacturer's part numbers that are physically, functionally, and mechanically interchangeable with the manufacturer's part number(s) listed in the Technical Data Package; provided (i) that these nonlisted part numbers have been furnished ________ to one of the approved manufacturers listed in the Technical Data Package, which firm has then, without making any changes in the characteristics or properties of the part, redesignated that part with one of the approved part numbers; and (ii) that firms tendering a nonlisted part number as described in this paragraph (2) have executed the provision 52.211-4038 entitled REPRESENTATION OF INTENT TO

SUPPLY A SOURCE-CONTROLLED ITEM herein.

[End of Clause]

PACKAGING AND MARKING

9 52.211-4515 PACKAGING REQUIREMENTS (SPECIAL PACKAGING INSTRUCTIONS) DEC/2014

(TACOM)

78 (a) Military preservation, packing, and marking for this contract/order shall be accomplished in accordance with the specific requirements identified below, all the applicable requirements of MIL-STD-2073-1, and the Special Packaging Instruction, see below.

(1) LEVEL OF PRESERVATION: Military

(2) LEVEL OF PACKING: B

(3) QUANTITY PER UNIT PACKAGE: 001

11 51

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

(4) SPECIAL PACKAGING INSTRUCTION NUMBER. AK11627035

(a) REVISION B

(b) DATE OF REVISION 1-10-2000

(c) THE REQUIRED SPECIAL PACKAGING INSTRUCTION (SPI) IS AVAILABLE ON THE WEB AT THE FOLLOWING URL:

https://www.tacom.army.mil/ilsc/tdps/phst/SPI/01/62/89.pdf

(Note: You must have the Adobe Acrobat reader installed on your PC to view the SPI. See Adobes website (http://get.adobe.com/reader/for information on obtaining the latest version of the reader. If you're experiencing problems opening the Special Packaging Instructions in

Adobe .PDF images using Internet Explorer, try the following: Go to "Tools," then "Internet Options." Click on the "Advanced" tab.

Scroll down to the "Security" section. Uncheck "Do not save encrypted pages to disk." Click "Apply." Click "OK.")

(b) Unitization: Shipments of identical items going to the same destination shall be palletized if they have a total cubic displacement of 50 cubic feet or more unless skids or other forklift handling features are included on the containers. Pallet loads must be stable, and to the greatest extent possible, provide a level top for ease of stacking. A palletized load shall be of a size to allow for placement of two loads high and wide in a conveyance. The weight capacity of the pallet must be adequate for the load. The preferred pallet is a 40 x 48 inch, 4-way entry pallet although variations may be permitted as dictated by the characteristics of the items being unitized. The load shall be contained in a manner that will permit safe handling during shipment and storage.

(c) Marking:

(1) In addition to any special markings called out on the SPI, all unit packages, intermediate packs, exterior shipping containers, and, as applicable, unitized loads shall be marked in accordance with MIL-STD-129, Revision P-Change Notice 4, dated 19 Sep

2007, including bar coding and Military Shipment Label (MSL). The contractor is responsible for application of special markings as discussed in the Military Standard regardless of whether specified in the contract/order or not. Special markings include, but are not limited to, Shelf-life markings, structural markings, and transportation special handling markings. The marking of pilferable and sensitive materiel will not identify the nature of the materiel.

(2) Passive RFID tagging is required in all contracts that contain DFARS clause 252.211-7006. For details and most recent information, see http://www.acq.osd.mil/log/sci/ait.html for the current DoD Suppliers Passive RFID Information Guide.

When an item is assigned a Unique Item Identifier (UII) as indicated by the inclusion of contract clause DFARS 252.211-7006, refer to the DoD Guide to Uniquely Identifying Items for development of the UII and MIL-STD-129 for UII package marking requirements.

Contractors must verify the RFID and UII clauses cited above are included in this solicitation/contract.

(d) Heat Treatment and Marking of Wood Packaging Materials (WPM):

(1) In accordance with DOD 4140.625-M and the requirements of the International Standards for Phytosanitary Measures 15

(ISPM), Regulation of Wood Packaging Material in International Trade, current edition, (hereinafter ISPM 15), the following commercial heat treatment and marking process has been approved by the American Lumber Standards Committee (ALSC) and is required for all Wood

Packaging Material (WPM). Foreign manufacturers shall comply with ISPM 15, and have the WPM heat treatment and marking verified in accordance with their National Plant Protection Organizations compliance program.

(2) Boxes/pallets and any wood used as inner packaging made of non-manufactured wood shall be heat-treated. All WPM using a conventional steam or dry kiln heat chamber (treatment code for the mark: HT) shall be heat treated to a minimum core temperature of 56 degrees Celsius for a minimum of 30 minutes, and certified by an agency accredited by the ALSC in accordance with Wood Packaging

Material Policy and Wood Packaging Material Enforcement Regulations (see URL: http://www.alsc.org). WPM heat treated wood using dielectric heating (treatment code for the mark: DH) shall follow the requirements in ISPM 15, and shall be certified by an agency accredited by the ALSC in accordance with Wood Packaging Material Policy and Wood Packaging Material Enforcement Regulations (see URL:

http://www.alsc.org). The box/pallet manufacturer and the manufacturer of wood used as inner packaging shall ensure the materials used in manufacture can be traced to the original source of heat treatment, and that the original source of the heat treatment obtained the necessary certifications.

(3) Marking. Each box/pallet shall be marked to show the conformance to the International Plant Protection Convention

Standard. The ALSC approved quality mark shall be placed on both ends of the outer packaging, between the end cleats or end battens.

Pallet markings shall be applied to the side of the stringer or end of the block on diagonally opposite sides and ends of the pallet and be contrasting and clearly visible. All dunnage used in configuring and/or securing the load shall also comply with ISPM 15 and be marked with an ALSC approved DUNNAGE stamp.

(e) Hazardous Materials (As applicable):

(1) Hazardous Materials is defined as a substance, or waste which has been determined by the Secretary of Transportation to be

12 51

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

capable of posing an unreasonable risk to health, safety, and property when transported in commerce and which has been so designated.

(This includes all items listed as hazardous in Titles 29, 40 and 49 CFR and other applicable modal regulations effective at the time of shipment.)

(2) Unless otherwise specified, packaging and marking for hazardous material shall comply with the requirements herein for the mode of transport and the applicable performance packaging contained in the following documents:

- International Air Transport Association (IATA) Dangerous Goods Regulations

- International Maritime Dangerous Goods Code (IMDG)

- Code of Federal Regulations (CFR) Title 29, Title 40 and Title 49

- Joint Service Regulation AFJMAN24-204(I)/TM38-250/NAVSUPPUB 505/MCO

P4030.19(I)/DLAM 4145.3(I) (for military air shipments).

(3) If the shipment originates from outside the continental United States, the shipment shall be prepared in accordance with the United Nations Recommendations on the Transport of Dangerous Goods in a manner acceptable to the Competent Authority of the nation of origin and in accordance with regulations of all applicable carriers.

A Product Material Safety Data Sheets (MSDS) is required to be included with every unit pack and intermediate container and shall be included with the packing list inside the sealed pouch attached to the outside of the package.

(f) This SPI has been validated and the method of preservation/packing has proven successful in meeting the needs of the military distribution system, including indeterminate storage and shipment throughout the world. Special instructions and/or tailoring of the

SPI is detailed in the Supplemental Instructions below. A prototype package is required to validate the sizes and fit requirements of the SPI. Minor dimensional and size changes are acceptable provided contractor provides the PCO and ACO with notification 60 days prior to delivery. Any design changes or changes in the method of preservation that provide a cost savings without degrading the method of preservation or packing or affecting the serviceability of the item will be considered and responded to within 10 days of submission to

PCO and ACO. Government reserves the right to require testing to validate alternate industrial preservation methods, materials, alternate blocking, bracing, cushioning, and packing.

(g) SUPPLEMENTAL INSTRUCTIONS: NA

[End of Clause]

INSPECTION AND ACCEPTANCE

This document incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at these addresses:

http://farsite.hill.af.mil/VFFARA.HTM or http://farsite.hill.af.mil/VFDFARA.HTM or http://farsite.hill.af.mil/VFAFARa.HTM

If the clause requires additional or unique information, then that information is provided immediately after the clause title.

10 52.246-2 INSPECTION OF SUPPLIES--FIXED-PRICE AUG/1996

11 52.246-16 RESPONSIBILITY FOR SUPPLIES APR/1984

12 52.211-4017 REQUIREMENTS FOR PRETREATMENTS AND CHEMICAL AGENT RESISTANT COATINGS NOV/2014

(TACOM) LOCAL WARREN - PAINTED MATERIEL

(a) Scope

(1) This clause applies to contracts requiring Chemical Conversion Coatings and Pretreatments for Metallic Substrates, Chemical

Agent Resistant Coating (CARC), and their related materials. The requirements in this clause clarify and supplement those in the contract, unless nullified elsewhere in the contract or through an approved Request for Deviation.

(2) Coating qualification, spot paint repair, and MIL-DTL-16232 Phosphate Coating, Heavy, Manganese or Zinc Base coatings are not within the scope of this clause.

(b) Definitions

(1) The contracting agency, appropriate agency, procuring authority, engineering authority, procuring agency, and procuring activity is the PCO or designee.

(2) The prime contractor is the company awarded this contract, and the subcontractors comprise all companies involved in providing coated parts to the prime contractor, including companies that apply the coatings.

13 51

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

(c) General Requirements Clarifications

(1) The government retains the right for onsite verification of the prime contractors and its subcontractors products, processes, procedures, and test reports.

(2) The prime contractor shall be responsible for itself and its subcontractors to produce and maintain detailed process control plans, process control data, pre-production approval testing, ongoing quality control & quality control testing, and test reports.

This information shall be available upon government request.

(3) The prime contractor shall immediately notify the PCO and the Defense Contract Management Agency (DCMA) of any failure to meet preproduction and production requirements.

(4) Each cleaning method shall be treated as a separate step in the process documentation.

(5) The Gage Repeatability and Reproducibility (Gage R&R) error shall be less than 30 percent for all process and product measurement systems.

(6) Products with hexavalent chromium, including but not limited to certain fastener finishes, shall not be used. Additionally, CARC topcoats containing siliceous additives to control gloss are prohibited.

(7) CARC primer and CARC topcoat shall not be applied directly to bare metal or plastic, except as provided for in MIL-DTL-53072.

(8) If the contract specifies application of CARC materials over a non-CARC coating, then both CARC primer and CARC topcoat are required. The complete coating system shall meet the requirements for CARC defined in TT-C-490.

(9) Neutral salt spray (NSS) testing shall not be used to validate compliance with materiel life cycle requirements; NSS is a production quality test and does not predict field performance.

(d) Pre-Production Approval Clarifications

(1) Pre-production testing shall include:

(i) Thickness of each layer of the coating system;

(ii) Coating system adhesion;

(iii) Salt spray performance; and

(iv) For phosphate pretreatments, the phosphate coating weight, crystal size and shape, and scanning electron microscope photos of the phosphate coatings at 500x and 1000x magnification.

(2) Pre-production test samples shall be from the material used for production parts, pieces cut from production representative parts, or production representative parts. Standardized test coupons shall not be used.

(3) Nine samples shall be produced for the required testing and shall include: three cleaned and pretreated test samples, three samples with the complete paint system and, depending on the CARC paint system, either three samples with pretreatment plus primer or three samples with metal-rich primer plus primer.

(4) One or more ISO 17025 laboratories shall conduct pre-production testing on the nine test samples in accordance with (IAW) the applicable test method accreditations. The applicable ISO 17025 test method accreditations include ASTM B117 Salt Spray, ASTM B244

Thickness of Non-Conductive Coatings on Non-Magnetic Metals, ASTM B487 Measurement of Metal and Oxide Coating Thickness, ASTM B499

Thickness of Non-Conductive Coatings on Magnetic Metals, and ASTM D3359 Measuring Adhesion by Tape Test.

(5) Unless required elsewhere in the contract and specifications, the CARC coating system applied to hot and cold rolled steel shall meet a minimum of 336 hours neutral salt spray resistance IAW ASTM B117.

(6) Test procedures shall be submitted IAW the Contract Data Requirements List (CDRL) DI-NDTI-80603 documenting Pretreatment and

Chemical Agent Resistant Coating procedures when this CDRL is included in the contract.

(7) Test reports from the ISO 17025 accredited labs shall be submitted for Pretreatment and Chemical Agent Resistant Coating testing specified in paragraph (d)(4) of this clause IAW the Contract Data Requirements List (CDRL) DI-NDTI-80809 when this CDRL is included in the contract.

(e) Production Testing Clarifications

(1) At a minimum, ongoing production quality tests shall conducted and recorded daily for coating adhesion and coating thickness, and monthly for salt spray testing. Use of ISO accredited laboratories is optional for these ongoing tests of production parts.

(2) Production parts or pieces cut from production parts shall be used for ongoing production quality testing. Standardized test coupons shall not be used.

(3) Unless specified elsewhere in the contract and specifications, the CARC coating system applied to hot and cold rolled steel shall meet a minimum of 336 hours neutral salt spray resistance IAW ASTM B117.

[End of Clause]

13 52.211-4029 INTERCHANGEABILITY OF COMPONENTS MAY/1994

(TACOM)

(a) DESIGN CHANGES TO ITEMS NOT UNDER GOV'T DESIGN CONTROL. Once the Government accepts the first production test item, or ______________________________________________________ accepts the first end item you deliver, (whichever comes first) you must not make design changes to any item or part that is not under

Government design control.

(b) WHEN THE POLICY CAN BE WAIVED. The Procuring Contracting Officer (PCO) will consider waiving this policy at your request. If _____________________________ your request reaches the PCO after the first production item test has been performed, then we may conduct another first production test at your expense.

(c) PRODUCTION OR DELIVERY DELAYS. Any production or delivery delays caused by this retesting will not be the basis for: _____________________________

14 51

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

(1) an "excusable delay" as defined in the DEFAULT clause of this contract.

(2) be the basis for an increase in contract price or delivery schedule extension.

[End of clause]

14 52.246-4028 INSPECTION AND ACCEPTANCE POINTS: ORIGIN NOV/2005

(TACOM)

The Government's inspection and acceptance of the supplies offered under this contract/purchase order shall take place at ORIGIN.

Offeror must specify below the exact name, address, and CAGE of the facility where supplies to be furnished under this contract/purchase order will be available for inspection/acceptance.

INSPECTION POINT: ___________________________________________________________________________

(Name) (CAGE)

(Address) (City) (State) (Zip)

ACCEPTANCE POINT: ____________________________________________________________________________

(Name) (CAGE)

(Address) (City) (State) (Zip)

[End of Clause]

15 52.246-4803 DRAWINGS FOR INSPECTION JAN/2013

(DLA LAND

WARREN)

Data not printed.

DELIVERIES OR PERFORMANCE

This document incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at these addresses:

http://farsite.hill.af.mil/VFFARA.HTM or http://farsite.hill.af.mil/VFDFARA.HTM or http://farsite.hill.af.mil/VFAFARa.HTM

If the clause requires additional or unique information, then that information is provided immediately after the clause title.

16 52.242-15 STOP-WORK ORDER AUG/1989

17 52.242-17 GOVERNMENT DELAY OF WORK APR/1984

18 52.247-48 F.O.B. DESTINATION--EVIDENCE OF SHIPMENT FEB/1999

19 252.211-7006 PASSIVE RADIO FREQUENCY IDENTIFICATION SEP/2011

(a) Definitions. As used in this clause--

"Advance shipment notice" means an electronic notification used to list the contents of a shipment of goods as well as additional information relating to the shipment, such as passive radio frequency dentification (RFID) or item unique identification (IUID) information, order information, product description, physical characteristics, type of packaging, marking, carrier information, and configuration of goods within the transportation equipment.

"Bulk commodities" means the following commodities, when shipped in rail tank cars, tanker trucks, trailers, other bulk wheeled conveyances, or pipelines:

15 51

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

(1) Sand.

(2) Gravel.

(3) Bulk liquids (water, chemicals, or petroleum products).

(4) Ready-mix concrete or similar construction materials.

(5) Coal or combustibles such as firewood.

(6) Agricultural products such as seeds, grains, or animal feed.

"Case" means either a MIL-STD-129 defined exterior container within a palletized unit load or a MIL-STD-129 defined individual shipping container.

"Electronic Product Code\TM\ (EPC)" means an identification scheme for universally identifying physical objects via RFID tags and other means. The standardized EPC\TM\ data consists of an EPC\TM\ (or EPC\TM\ identifier) that uniquely identifies an individual object, as well as an optional filter value when judged to be necessary to enable effective and efficient reading of the EPC\TM\ tags. In addition to this standardized data, certain classes of EPC\TM\ tags will allow user-defined data. The EPC\TM\ Tag Data Standards will define the length and position of this data, without defining its content.

"EPCglobal" means a subscriber-driven organization comprised of industry leaders and organizations focused on creating global standards for the adoption of passive RFID technology.

"Exterior container" means a MIL-STD-129 defined container, bundle, or assembly that is sufficient by reason of material, design, and construction to protect unit packs and intermediate containers and their contents during shipment and storage. It can be a unit pack or a container with a combination of unit packs or intermediate containers. An exterior container may or may not be used as a shipping container.

"Palletized unit load" means a MIL-STD-129 defined quantity of items, packed or unpacked, arranged on a pallet in a specified manner and secured, strapped, or fastened on the pallet so that the whole palletized load is handled as a single unit. A palletized or skidded load is not considered to be a shipping container. A loaded 463L System pallet is not considered to be a palletized unit load. Refer to the

Defense Transportation Regulation, DoD 4500.9-R, Part II, Chapter 203, for marking of 463L System pallets.

"Passive RFID tag" means a tag that reflects energy from the reader/interrogator or that receives and temporarily stores a small amount of energy from the reader/interrogator signal in order to generate the tag response. The only acceptable tags are EPC Class 1 passive

RFID tags that meet the EPCglobal\TM\ Class 1 Generation 2 standard.

"Radio frequency identification (RFID)" means an automatic identification and data capture technology comprising one or more reader/interrogators and one or more radio frequency transponders in which data transfer is achieved by means of suitably modulated inductive or radiating electromagnetic carriers.

"Shipping container" means a MIL-STD-129 defined exterior container that meets carrier regulations and is of sufficient strength, by reason of material, design, and construction, to be shipped safely without further packing (e.g., wooden boxes or crates, fiber and metal drums, and corrugated and solid fiberboard boxes).

(b)(1) Except as provided in paragraph (b)(2) of this clause, the Contractor shall affix passive RFID tags, at the case- and palletized-unit-load packaging levels, for shipments of items that--

(i) Are in any of the following classes of supply, as defined in DoD 4140.1-R, DoD Supply Chain Materiel Management Regulation, AP1.1.11:

(A) Subclass of Class I--Packaged operational rations.

(B) Class II--Clothing, individual equipment, tentage, organizational tool kits, hand tools, and administrative and housekeeping supplies and equipment.

(C) Class IIIP--Packaged petroleum, lubricants, oils, preservatives, chemicals, and additives.

(D) Class IV--Construction and barrier materials.

(E) Class VI--Personal demand items (non-military sales items).

(F) Subclass of Class VIII--Medical materials (excluding pharmaceuticals, biologicals, and reagents--suppliers should limit the mixing of excluded and non-excluded materials).

(G) Class IX--Repair parts and components including kits, assemblies and subassemblies, reparable and consumable items required for maintenance support of all equipment, excluding medical-peculiar repair parts; and

(ii) Are being shipped to one of the locations listed at http://www.acq.osd.mil/log/rfid/ or to--

16 51

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

(A) A location outside the contiguous United States when the shipment has been assigned Transportation Priority 1, or to--

(B) The following location(s) deemed necessary by the requiring activity:

Contract line, subline, or exhibit Location name City State DoDAAC line item number

NONE

(2) The following are excluded from the requirements of paragraph (b)(1) of this clause:

(i) Shipments of bulk commodities.

(ii) Shipments to locations other than Defense…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .