REQUEST FOR QUOTATION This RFQ is is not a small business set-aside Page Of

(This is NOT an Order)

1. Request No. 2. Date Issued 3. Requisition/Purchase Request No. 4. Cert For Nat Def. Under BDSA Rating

See Schedule Reg. 2 and/or DMS Reg. 1 5A. Issued By 6. Deliver by (Date)

See Schedule

7. Delivery

FOB Other Destination

5B. For Information Call: (Name and telephone no.) (No collect calls)

8. To: Name and Address, Including Zip Code 9. Destination (Consignee and address, including Zip Code)

See Schedule

10. Please Furnish Quotations to the Issuing Office in Block 5A On or Before Close of Business (Date)

IMPORTANT: This is a request for information, and quotations furnished are not offers. If you are unable to quote, please indicate on this form and return it to the address in Block 5B. This request does not commit the Government to pay any costs incurred in the preparation of the submission of this quotation or to contract for supplies or services.

Supplies are of domestic origin unless otherwise indicated by quoter. Any interpretations and/or certifications attached to this Request for Quotation must be completed by the quoter.

11. Schedule (Include applicable Federal, State, and local taxes)

Item Number (a)

Supplies/Services (b)

Quantity (c)

Unit (d)

Unit Price (e)

Amount (f)

(See Schedule)

12. Discount For Prompt Payment a. 10 Calendar Days b. 20 Calendar Days c. 30 Calendar Days d. Calendar Days % % % Number Percentage

NOTE: Additional provisions and representations are are not attached.

13. Name and Address of Quoter (Street, City, County, State and 14. Signature of Person Authorized to Sign 15. Date of Quotation Zip Code) Quotation

16. Signer

a. Name (Type or Print) b. Telephone

Area Code

c. Title (Type or Print) Number

AUTHORIZED FOR LOCAL REPRODUCTION Standard Form 18 (Rev. 8-95) PREVIOUS EDITIONS NOT USABLE 18-118 Prescribed by GSA-FAR (43 CFR) 53.215-1(a)

X

SPRDL1-16-Q-0047 2015DEC17 DOA4

SPRDL1DLA LAND WARREN

WARREN, MI 48397-5000

HTTP://CONTRACTING.TACOM.ARMY.MIL

RALPH MCCARTHY (586)282-2876

ZGA

EMAIL: RALPH.F.MCCARTHY.CIV@MAIL.MIL

X

2016JAN20

1 65

CONTINUATION SHEET

Reference No. of Document Being Continued Page of

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

SUPPLEMENTAL INFORMATION

Buyer Name: RALPH MCCARTHY

Buyer Office Symbol/Telephone Number: ZGA/(586)282-2876

Type of Contract 1: Firm Fixed Price

Kind of Contract: Supply Contracts and Priced Orders

*** End of Narrative A0000 ***

Regulatory Cite Title Date Regulatory Cite Title Date _______________ ______________________________________________________________________ ____________ _______________ ______________________________________________________________________ ____________

1 52.204-4016 WARREN ELECTRONIC CONTRACTING OCT/2015

(TACOM)

(a) All DLA Land Warren solicitations will be publicized on the Federal Business Opportunities website (https://www.fbo.gov). Any additional attachments, including Technical Data Packages (TDPs) when available electronically, will be separate attachments or links embedded in the solicitation.

(b) Unless directed to do otherwise in Section L of this solicitation, vendors are required to submit a quote or proposal via the

Federal Business Opportunities (FBO) system.

(c) Requirements for the online FBO bid submission:

1. Vendors must log into the FBO System to be able to submit electronic responses for opportunities.

2. Vendors must be registered in the System for Award Management (SAM) at www.sam.gov (a Federal Government owned and operated free web site) and have a CAGE Code and CCR Marketing Partner Identification Number (MPIN).

3. Once logged into the FBO System, vendors will be asked to enter basic information and directed to upload one or more files containing the proposal/quote and any additional information as outlined in the solicitation.

4. FBO will send an email to the vendors registered email address confirming the electronic submission.

5. For additional information on submitting electronic bid responses via the FBO system see the FBO Vendor Guide Section

4.3.1 Submitting an Electronic Response (https://www.fbo.gov/downloads/FBO_Vendor_Guide.pdf).

(d) Note to offerors:

Please pay close attention to the solicitation closing date and time as stated on the cover page of this solicitation, local time (EST), for DLA Land Warren. In accordance with FAR 15.208(a), offerors are responsible for submitting proposals, and any revisions, and modifications, so as to be received by the Government office designated in the solicitation by the time specified.

It is Offeror's responsibility to ensure the proposal/quote is received by the date and time specified on the cover page of this solicitation. In accordance with FAR 15.208, if the proposal/quote was not received at the initial point of entry to the Government infrastructure (in this case, received through FBO) by the exact date and time specified on the cover page of this solicitation, it will be determined late. Proposal/quote is defined to mean that ALL volumes or parts required in the solicitation are included in the electronic submission.

Note: There is no "expected" or "target" length of time for proposal submission; size and content may be factors, therefore offerors are strongly cautioned when submitting proposals to allow adequate time for submission.

Solicitations may remain posted on the FBO after the solicitation closing date. If the response deadline has passed for the solicitation, vendors will no longer be able to submit electronic responses. In this case, send any late quotes, if applicable, directly to the contract specialist identified on the cover page of this solicitation.

(e) Any award issued as a result of this solicitation will be distributed electronically. In the event of a FOIA request for a copy of any award issued as a result of this solicitation, or any subsequent modifications to the contract, the contract and modifications will be released, including the awarded unit price. This is the notice required by Executive Order 12600 (June 23, 1987) of our intention to release unit prices in response to any request under the Freedom of Information Act (FOIA), 5 USC 552. Unit price is defined as the contract price per unit or item purchased as it appears in Section B of the contract and is NOT referring to nor does it include Cost or

Pricing data/information. If you object to such release in the base contract or contract modifications, and you intend to submit an offer, notify the contracting officer in writing prior to the closing date identified in this solicitation and include the rationale for your objection consistent with the provisions of FOIA. A release determination will be made based on rationale given.

2 65

SPRDL1-16-Q-0047

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

(f) Questions pertaining to this solicitation should be directed to the Contract Specialist identified on the cover page of this solicitation. For technical assistance in doing business with the Government, and doing business electronically, please visit the

Procurement Technical Assistance Center (PTAC) website at http://www.aptac-us.org/ to locate a regional center.

[End of Provision]

2 52.214-4000 ACKNOWLEDGMENT OF AMENDMENTS OCT/1993

Acknowledge all the amendments you've received from us by identifying the amendment number and its issue date below:

Amendment Number Date

(End of Provision)

3 52.214-4003 ALL OR NONE MAR/1998

(TACOM)

Offers in response to this solicitation must be submitted for the total quantity of the items identified in the solicitation.

(1) ONLY ONE AWARD WILL BE MADE AS A RESULT OF THIS SOLICITATION.

(2) OFFERS SUBMITTED FOR LESS THAN THE TOTAL QUANTITIES OF ALL THE ITEMS IN THIS SOLICITATION ARE INELIGIBLE FOR AWARD.

[End of clause]

4 52.215-4800 NOTICE OF REVERSE AUCTION PROVISION JAN/2014

(DLA LAND-

WARREN)

This solicitation contains standard DLAD provision 52.215-9023, Reverse Auction. This Request For Quotes (RFQ) solicitation will use the simplified acquisition procedures of FAR Part 13. Therefore, the following terminology in the reverse auction provision is changed as follows: replace proposal with quote, replace offer with quote, replace offeror with quoter, and replace final proposal revision with quotation.

After receipt of quotes, the contracting officer will determine if a reverse auction will be conducted. However, the use of a reverse auction does not preclude additional methods of price and/or cost analysis. The quoted prices received up until the start of the auction will be evaluated for award in accordance with the evaluation factors listed in the solicitation. After the start of the auction, the only way to revise prices is to participate in the auction by placing bids. Therefore, quotes received after the start of the auction will not be considered unless the contracting officer determines further correspondence is required.

3 65

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

If a reverse auction is held, Contractors must be registered in the reverse auction system in order to participate in the auction.

Additionally, the Contractor representative participating in the auction must have taken the on-line reverse auction training prior to the auction. Registration, on-line training, and other information regarding the reverse auction can be found at https://dla.procurexinc.com. If a reverse auction is held and a Contractor that provided a quote to the solicitaiton does not participate in the auction, the initially quoted price(s) will be considered and evaluated.

Questions related to the reverse auction system or process can be directed to dla.detroit.tacom.mbx.land-wrn-reverse-auction@mail.mil.

Any other questions can be directed to the contract specialist listed in this solicitation.

[End of Provision]

This procurement has been designated as a 100% Small Business Set Aside.

*** END OF NARRATIVE A0001 ***

4 65

PIIN/SIIN

Page of

Name of Offeror or Contractor:

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

Reference No. of Document Being Continued

MOD/AMD

SUPPLIES OR SERVICES AND PRICES/COSTS

This procurement is designated as a 100% Small

Business Set Aside.

(End of narrative A001)

0001 VALVE, LINEAR, DIRECT

NSN: 4810-00-690-1175

Mfr CAGE: 19207

Mfr Part Number: 10867174

0001AA PRODUCTION QUANTITY 6 EA $ $ ______________________ ______________ __________________

COMMODITY NAME: VALVE, LINEAR, DIRECT

CLIN CONTRACT TYPE:

Firm Fixed Price

PRON: EH66E077EH PRON AMD: 01

AMS CD: SM2B1100000

Packaging and Marking _____________________

PACKAGING/PACKING/SPECIFICATIONS:

SEE PACKAGING CLAUSE FOR DETAILS

UNIT PACK: 001

LEVEL PRESERVATION: Military

LEVEL PACKING: B

Inspection and Acceptance _________________________

INSPECTION: Origin ACCEPTANCE: Origin

Inspection/Acceptance at origin means that you MUST contact the DCMA to arrange for a Government inspection BEFORE you ship the supplies called out in this order. Failure to have the items inspected and accepted will result in their rejection at the destination. The rejected supplies will be returned to you at your expense.

(End of narrative E001)

Deliveries or Performance _________________________

DOC SUPPL

REL CD MILSTRIP ADDR SIG CD MARK FOR TP CD ______ ________ ______ ______ ________ _____

001 W56HZV5288971Z W562RP J 2

DEL REL CD QUANTITY DAYS AFTER AWARD __________ ______________ ________________

001 6 0300

FOB POINT: Destination

SHIP TO:

(W562RP) SR W0LX ARMY GENERAL SUPPLY

5 65

Page of

Name of Offeror or Contractor:

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

Reference No. of Document Being Continued

MOD/AMD

DLA DISTRIBUTION ANNISTON

7 FRANKFORD AVE

ANNISTON,AL,36201-4199

6 65

Page of

Name of Offeror or Contractor:

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

Reference No. of Document Being Continued

MOD/AMD

0001AB FAT TEST NOT SEPARATELY PRICED 1 EA $ $ ______________________________ ______________ __________________

COMMODITY NAME: FIRST ARTICLE TEST REPORT

CLIN CONTRACT TYPE:

Firm Fixed Price

FIRST ARTICLE TEST REPORT, PERSUANT TO THE

REQUIREMENTS OF THE CLAUSE ENTITLED "FIRST ARTICLE

APPROVAL - CONTRACTOR TESTING".

THE PRICE OF THE FIRST ARTICLE TESTING IN THE AMOUNT

OF $______________, IS INCLUDED IN THE TOTAL

AMOUNT(S) FOR ITEM 0001AA.

(End of narrative C001)

Packaging and Marking _____________________

Inspection and Acceptance _________________________

INSPECTION: Origin ACCEPTANCE: Origin

Deliveries or Performance _________________________

DOC SUPPL

REL CD MILSTRIP ADDR SIG CD MARK FOR TP CD ______ ________ ______ ______ ________ _____

DEL REL CD QUANTITY DAYS AFTER AWARD __________ ______________ ________________

001 1 0180

FOB POINT: Destination

SHIP TO:

(Y00006) SEE FIRST ARTICLE TEST CLAUSE

FOR DISTRIBUTION

7 65

Page of

Name of Offeror or Contractor:

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

Reference No. of Document Being Continued

MOD/AMD

This procurement is designated as a 100% Small

Business Set Aside

(End of narrative A001)

0002 VALVE, LINEAR, DIRECT

NSN: 4810-00-690-1175

Mfr CAGE: 19207

Mfr Part Number: 10867174

0002AA UNEXERCISED OPTION QUANTITY 6 EA $ $ ___________________________ ______________ __________________

COMMODITY NAME: VALVE, LINEAR, DIRECT

CLIN CONTRACT TYPE:

Firm Fixed Price

OPTION QUANTITY, pursuant to the clause entitled

Option for increased quantity separately priced line item (52.217-4001)

The quantity stated for the option clin DOES NOT form a part of the basic contractual quantity. Part or all of it may, however, be added to the contract by exercise of the option clause, at the discretion of the Government.

The failure of the offeror to insert a unit price applicable to the option quantity shall mean that the offeror will supply all or any part of the option, if exercised by the Government, at the basic contract unit price, and the offer will be evaluated for award accordingly.

(End of narrative B001)

Packaging and Marking _____________________

PACKAGING/PACKING/SPECIFICATIONS:

SEE PACKAGING CLAUSE FOR DETAILS

UNIT PACK: 001

LEVEL PRESERVATION: Military

LEVEL PACKING: B

Inspection and Acceptance _________________________

INSPECTION: Origin ACCEPTANCE: Origin

Deliveries or Performance _________________________

DOC SUPPL

REL CD MILSTRIP ADDR SIG CD MARK FOR TP CD ______ ________ ______ ______ ________ _____

DEL REL CD QUANTITY DAYS AFTER AWARD __________ ______________ ________________

001 6 0090

8 65

Page of

Name of Offeror or Contractor:

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

Reference No. of Document Being Continued

MOD/AMD

FOB POINT: Destination

SHIP TO:

(Y00000) SHIPPING INSTRUCTIONS FOR CONSIGNEE

(SHIP-TO) WILL BE FURNISHED PRIOR

TO THE SCHEDULED DELIVERY DATE FOR

ITEMS REQUIRED UNDER THIS

REQUISITION.

9 65

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

DESCRIPTION/SPECIFICATIONS/WORK STATEMENT

5 52.211-4015 CONFIGURATION CONTROL - ENGINEERING CHANGES DEC/2005

(TACOM)

(a) DEFINITIONS:

(1) Engineering Change Proposal (ECP). An ECP is a suggestion that we (the Government) permanently change some requirement of the Technical Data Package (TDP). ECPs can be issued before or during contract performance. NOTE: The current Government Standard allows us ninety days to process routine ECPs. If you (the contractor) need a response in less than ninety days to meet contract requirements, you should consider submitting a deviation along with your ECP.

(2) Notice of Revision (NOR). A NOR describes the proposed changes to a technical document being requested by an ECP.

(3) Value Engineering Change Proposal (VECP). A proposal that --

(i) Requires a change to the instant contract; and

(ii) Results in reducing the overall projected cost to the agency without impairing essential functions or characteristics; provided, that it does not involve a change --

(A) In deliverable end item quantities only;

(B) In research and development (R&D) end items or R&D test quantities that is due solely to results of previous testing under this contract; or

(C) To the contract type only.

(4) Request for Deviation (RFD). A RFD is a one-time request to deviate from TDP requirements. You must submit your deviation request once you realize that you desire to deviate from the TDP requirements. You can request a deviation for a specific number of parts or the entire contract quantity.

(b) When will TACOM start processing change requests? TACOM won't start processing any ECP, VECP, or RFD until we receive the

ACO's comments (see paragraph (e) below) and the ECP, VECP, or RFD documentation.

(c) Contractor Responsibility. ECPs, VECPs, and RFD shall contain information per the instructions outlined on the Data Delivery

Descriptions (DDDs) which can be found at the following website: http://contracting.tacom.army.mil/engr/engrchange.htm. Forms for preparing an ECP, VECP, or a RFD can also be found at this website. You may use other media, as long as you give us all the information outlined in the DDDs.

(1) Identify the two-digit Weapon System Code (WSC) on your submittal. The WSC for this procurement is JT.

(2) The Contractor shall submit ECPs/VECPs/RFDs to the Government electronically. You must use one of the following electronic mediums: 3 1/2 inch disk, 650 megabyte CD ROM, or E-mail. (E-mail files must be sized 3.5 mb or less.) Identify the software application, and version, that you used to create each file submitted.

(3) ECPs/VECPs/RFDs submitted in paper form are unacceptable and will be returned. You must use one of the following electronic formats:

(i) Files readable using these Microsoft 97 Office Products or later versions: Word, Excel, PowerPoint, or Access.

Spreadsheets must be sent in a file format that includes all formulae, macro and format information. Print image is not acceptable.

(ii) Files in Adobe PDF (Portable Document Format).

(iii) Files in HTML (Hypertext Markup Language). HTML documents must not contain active links to live Internet sites or pages. All linked information must be contained within your electronic ECPs/VECPs/RFDs and be accessible offline.

(iv) Other electronic formats. Before preparing your ECPs, VECPs or RFDs in any other electronic format, please e-mail the engineer, copy-furnished to the buyer and ACO, to obtain a decision as to the format's acceptability. Failure to e-mail the engineer to seek an alternate format's acceptability may result in rejection of your submission. All alternate methods must be at no cost to the Government. NOTE: The above formats may be submitted in compressed form using self-extracting files.

(d) Submittal Procedures for ECPs/VECPs/RFDs.

10 65

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

(1) Send one copy of the ECP, VECP or RFD in electronic format to your ACO.

(2) Send one copy of the ECP, VECP or RFD in electronic format to the buyer listed on the solicitation/ contract document.

WARNING - Submit complete, legible, virus free packages per paragraphs 1 and 2 above, or we may return your ECP/VECP/RFD without processing them.

(e) ACO Responsibility. Within ten working days from the day you receive the contractor's request, the ACO must prepare Comments on the ECP, VECP, or RFD in electronic format, and forward it as follows:

Email a copy of the contractor's request and ACO comments (DD Form 1998) to the buyer identified in block 7 of the solicitation cover sheet (SF 33), block 5 on the Standard Form 26, or block 6 on the DD Form 1155. Indicate end item application (if known) in subject line, along with the NSN and contract number.

(f) Approval of ECPs, VECPs and RFDs.

(1) ECPs should be used to make permanent changes in the Government Technical Data Package (TDP). Contractual relief should be requested using a Request for Deviation. This is because the Government requires more time to analyze any proposal to permanently change the specification or TDP. Cost saving improvements to the TDP should be submitted as a VECP, if a VE clause is contained in the contract.

(2) ECPs. TACOM will review and make a decision within the ninety day timeframe. Notification of our decision will be made by the contracting officer or representative.

(3) RFDs. Decision on RFDs will be made within 30 days from the date we receive them from the ACO.

(g) Processing Emergency and Urgent ECPs. Ordinarily, ECPs submitted by the contractor will be deemed routine. If you submit an

ECP that you consider to be an emergency or urgent (as defined in paragraph 11 of DDD for ECPs), you must immediately notify the PCO.

TACOM will review the criticality of the ECP, and, if we determine that it is urgent or critical, we'll follow the appropriate processing time-frames as outlined in paragraph 11 of the DDD for ECPs.

(h) Reminder - Only the PCO can change the Contract. NO OTHER GOVERNMENT REPRESENTATIVE is authorized to make a commitment for, or bind the Government.

(i) RFDs shall contain sufficient pricing data to determine if a downward equitable adjustment to the contract is required.

(j) Questions.

(1) Questions about preparation and submittal of change request should be directed to the Government Quality Assurance

Representative (QAR).

(2) Questions about the status of change requests you've already submitted, contact the buyer. You can find the buyer's name, number and e-mail address in block 7 of the solicitation cover sheet (SF 33), block 5 on the Standard Form 26, or block 6 on the DD Form

1155.

[End of Clause]

6 52.211-4072 TECHNICAL DATA PACKAGE INFORMATION SEP/2015

(TACOM)

The following Xd item applies to this solicitation:

[ ] 1. There is no Technical Data Package (TDP) included with this solicitation.

[ ] 2. This solicitation contains one or more web-located TDPs. If multiple Contract Line Item Numbers (CLINS) are listed below, each one will have its own URL just under the CLIN listing. The URL will take you to that CLINs Web-located TDP. To access the TDP, you will have to copy or type the links URL to your web browser address bar at the top of the screen.

Note: To copy a link from a .pdf file, click on the Text Select Tool, then highlight the URL, copy and paste it into your browser, and hit the Enter key.

CLIN: N/A

11 65

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

TDP Link (URL): N/A

[ X ] 3. The TDP for this solicitation resides within FedBizOpps (https://http://www.fbo.gov), and is associated with this solicitation number and can be accessed via this URL: https://www.fbo.gov/fedteds/SPRDL116Q0047

a. Log on to the FBO web site.

b. Enter your Marketing Partner Identification Number (MPIN).

c. Search for the solicitation number.

d. If solicitation is Export Controlled, select Verify MPIN.

(1) TDPs that have an Export Control Warning Notice are subject to the Arms Export Control Act (Title 22, U.S.C., Sec

2751, et.seq.) or the Export Administration Act of 1979, as amended, Title 50, U.S.C, App. 2401 et. seq..

(2) Further dissemination must be in accordance with provisions of DoD Directive 5230.25. This also applies to distribution of the TDP to all SUBCONTRACTORS at every level.

(3) To obtain these TDPs, vendors and contractors must have a current DD 2345, Militarily Critical Technical Data

Agreement on file with Defense Logistics Information Service (DLIS). If you are currently certified, your MPIN will be verified and you may proceed to the next step. To obtain certification, go to http://www.dlis.dla.mil/jcp/ click on documents and follow instructions provided. Processing time is estimated at six (6) to ten (10) weeks after receipt. FBO will allow you to access export controlled TDPs once certification is confirmed.

(4) Upon completion of the purposes for which Government Technical Data has been provided, the Contractor is required to destroy all documents, including all reproductions, duplications, or copies thereof as may have been further distributed by the

Contractor. Destruction of this technical data shall be accomplished by: shredding, pulping, burning, or melting any physical copies of the TDP and/or deletion or removal of downloaded TDP files from computer drives and electronic devices, and any copies of those files.

e. If technical data is otherwise restricted, select Request Explicit Access. This will generate an email to the FBO system administrator at TACOM Warren with all the information needed for them to grant you access. FBO will subsequently automatically generate an email stating when you have permission to view or download TDP items. Allow 2 3 working days to complete this FBO-TDP access/approval process through the FBO system.

f. If multiple individuals in your company need access to the Technical Data Package (TDP) for a solicitation and an explicit access request is required, each individual MUST submit an explicit access request to be granted approval to view the TDP. Those same individuals MUST be registered in Federal Business Opportunities (FBO). Any individuals no longer with the company should be deleted.

Questions related to registration in FBO should be directed to https://www.fbo.gov/index The FBO helpdesk phone number is (866) 606-

8220. Vendors are responsible for placing correct information in FBO.

g. It is strongly suggested that you submit the explicit access request and provide the contract specialist with the completed Use and

Non-Disclosure Agreement at the same time if the solicitation requires both to gain access to view the TDP.

h. A user guide for FBO can be found at https://http://www.fbo.gov - on the right is User Guides - click on Vendor.

[ ] 4. The Government requires a Use and Non-Disclosure Agreement (NDA) to be signed by an authorized representative of your firm before you are granted access to the technical data. The appropriate Agreement is titled N/A, and is:

[ ] available by emailing the contract specialist listed on page 1 of this solicitation.

[ ] available as an attachment to this solicitation.

Follow the instructions on the Agreement, and email/fax it to the contract specialist at N/A. The contract specialist will notify the

FBO administrator upon receiving the NDA. The administrator will grant approval to view/download the TDP. An email stating approval has been granted will be sent to the vendor. It can take up to 24 hours after approval before you are able to view the TDP. If you have any questions/problems viewing the TDP contact the contract specialist.

[End of Clause]

12 65

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

7 52.246-4053 USE OF MIL-STD 1916 JAN/2001

(TACOM)

The Government will not accept lots whose samples submitted for acceptance contain nonconformances unless appropriately documented and approved by the contracting officer. The contractor shall use MIL-STD-1916, DOD Preferred Methods of Acceptance of Product. The

Verification Level (VL) shall be VL IV for major characteristics and VL II for minor characteristics. MIL-HDBK-1916 provides guidance on the use of MIL-STD 1916.

[End of Clause]

8 52.211-4008 DRAWING LIMITATIONS NOV/2005

(TACOM)

(a) The drawings supplied with this contract are not shop or process drawings. They are engineering design drawings. They are ___ adequate to permit manufacture, and:

(1) depict the completed (item(s), and

(2) serve as the basis for inspection of the completed item(s).

(b) These drawings DON'T cover intermediate drawings/specifications or steps in the manufacturing process. As a result, even if you meet all the dimensions and tolerances specified in the engineering design drawing for each individual part, a cumulative unacceptable fit for the contract item could result.

(c) YOU ARE RESPONSIBLE for producing the shop or process drawings needed to cover intermediate steps in the manufacturing ___________________ process.

(d) You, the contractor, are responsible for obtaining all specifications and drawings necessary to manufacture the items being solicited in accordance with the TDP including all incorporated specifications and drawings. Delivery delays are not excusable where the contractor asserts that it did not have a specification or drawing and has failed to request, in writing, the specification from either the Contracting Officer or Contract Specialist prior to the solicitation closing date.

(e) If you fail to produce an end item with a cumulative fit that conforms to Government drawings, specifications or other supplemental manufacturing documentation, you'll be responsible for correcting this condition at no additional cost to the Government and no delivery schedule extension.

[End of clause]

PACKAGING AND MARKING

9 52.211-4515 PACKAGING REQUIREMENTS (SPECIAL PACKAGING INSTRUCTIONS) DEC/2007

(TACOM)

@ (a) Military preservation, packing, and marking for this contract/order shall be accomplished in accordance with the specific requirements identified below, all the applicable requirements of, MIL-STD-2073-1, Revision D, Dated 15 Dec 1999 and Notice 1, dated 10

May 2002, and the Special Packaging Instruction, see below.

(1) LEVEL OF PRESERVATION: Military

(2) LEVEL OF PACKING: B

(3) QUANTITY PER UNIT PACKAGE: 001

(4) SPECIAL PACKAGING INSTRUCTION NUMBER: AK06901175

(a) REVISION: E

(b) DATE OF REVISION: N/A

(c) THE REQUIRED SPECIAL PACKAGING INSTRUCTION (SPI) IS AVAILABLE ON THE WEB AT THE FOLLOWING URL:

https://www.tacom.army.mil/ilsc/tdps/phst/SPI/05/70/97.pdf

13 65

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

(Note: You must have the Adobe Acrobat reader installed on your PC to view the SPI. See the Army Contracting Command - Warren (DTA) web site (http://contracting.tacom.army.mil/faq.htm) for information on obtaining the latest version of the reader. If you're experiencing problems opening the Special Packaging Instructions in Adobe .PDF images using Internet Explorer, try the following: Go to "Tools," then

"Internet Options." Click on the "Advanced" tab. Scroll down to the "Security" section. Uncheck "Do not save encrypted pages to disk."

Click "Apply." Click "OK.")

(b) Unitization: Shipments of identical items going to the same destination shall be palletized if they have a total cubic displacement of 50 cubic feet or more unless skids or other forklift handling features are included on the containers. Pallet loads must be stable, and to the greatest extent possible, provide a level top for ease of stacking. A palletized load shall be of a size to allow for placement of two loads high and wide in a conveyance. The weight capacity of the pallet must be adequate for the load. The preferred pallet is a 40 x 48 inch, 4-way entry pallet although variations may be permitted as dictated by the characteristics of the items being unitized. The load shall be contained in a manner that will permit safe handling during shipment and storage.

(c) Marking:

(1) In addition to any special markings called out on the SPI, all unit packages, intermediate packs, exterior shipping containers, and, as applicable, unitized loads shall be marked in accordance with MIL-STD-129, Revision P-Change Notice 4, dated 19 Sep

2007, including bar coding and Military Shipment Label (MSL). The contractor is responsible for application of special markings as discussed in the Military Standard regardless of whether specified in the contract/order or not. Special markings include, but are not limited to, Shelf-life markings, structural markings, and transportation special handling markings. The marking of pilferable and sensitive materiel will not identify the nature of the materiel. Passive RFID tagging is required in all contracts that contain DFARS clause 252.211-7006. Contractors must check the solicitation and/or contract for this clause. For details and most recent information, see http://www.acq.osd.mil/log/rfid/index.htm for the current DoD Suppliers Passive RFID Information Guide and Supplier Implementation

Plan. If the item has Unique Item Identifier (UII) markings then the concatenated UII needs to be 2D bar coded and applied on the unit package, intermediate and exterior containers, and the palletized unit load.

(d) Heat Treatment and Marking of Wood Packaging Materials (WPM): Boxes/pallets and any wood used as inner packaging made of non-manufactured wood shall be heat-treated. All WPM shall be constructed from heat treated (treated to 56 degrees Celsius -core temperature-for 30 minutes) lumber and certified by an accredited agency accredited by the ALSC in accordance with Wood Packaging Material Policy and Wood Packaging Material Enforcement Regulations (see URL: http://www.alsc.org). The box/pallet manufacturer and the manufacturer of wood used as inner packaging shall ensure traceability to the original source of heat treatment. Marking: Each box/pallet shall be marked to show the conformance to the International Plant Protection Convention Standard. The quality mark shall be placed on both ends of the outer packaging, between the end cleats or end battens. Pallet markings shall be applied to the stringer or block on diagonally opposite sides and ends of the pallet and be contrasting and clearly visible. All dunnage used in configuring and/or securing the load shall also comply with https://www.ippc.int/servlet/BinaryDownloaderServlet/133703_ISPM15_2002_with_Ann.pdf?filename=1152091663986_ISPM_15_2002_with_Annex1_2006

_E.pdf&refID=133703 and be marked with an ALSC approved dunnage stamp, marked at two foot intervals (in the case of dunnage shorter than

2 feet, each piece must still have the mark present). Foreign manufacturers shall have the heat treatment and marking of non-manufactured wood products verified in accordance with their National Plant Protection Organizations compliance program.

(e) Hazardous Materials (As applicable):

(1) Hazardous Materials is defined as a substance, or waste which has been determined by the Secretary of Transportation to be capable of posing an unreasonable risk to health, safety, and property when transported in commerce and which has been so designated.

(This includes all items listed as hazardous in Titles 29, 40 and 49 CFR and other applicable modal regulations effective at the time of shipment.)

(2) Unless otherwise specified, packaging and marking for hazardous material shall comply with the requirements herein for the mode of transport and the applicable performance packaging contained in the following documents:

- International Air Transport Association (IATA) Dangerous Goods Regulations

- International Maritime Dangerous Goods Code (IMDG)

- Code of Federal Regulations (CFR) Title 29, Title 40 and Title 49

- Joint Service Regulation AFJMAN24-204(I)/TM38-250/NAVSUPPUB 505/MCO

P4030.19(I)/DLAM 4145.3(I) (for military air shipments).

(3) If the shipment originates from outside the continental United States, the shipment shall be prepared in accordance with the United Nations Recommendations on the Transport of Dangerous Goods in a manner acceptable to the Competent Authority of the nation of origin and in accordance with regulations of all applicable carriers.

A Product Material Safety Data Sheets (MSDS) is required to be included with every unit pack and intermediate container and shall be included with the packing list inside the sealed pouch attached to the outside of the package.

(f) This SPI has been validated and the method of preservation/packing has proven successful in meeting the needs of the military distribution system, including indeterminate storage and shipment throughout the world. Special instructions and/or tailoring of the

14 65

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

SPI is detailed in the Supplemental Instructions below. A prototype package is required to validate the sizes and fit requirements of the SPI. Minor dimensional and size changes are acceptable provided contractor provides the PCO and ACO with notification 60 days prior to delivery. Any design changes or changes in the method of preservation that provide a cost savings without degrading the method of preservation or packing or affecting the serviceability of the item will be considered and responded to within 10 days of submission to

PCO and ACO. Government reserves the right to require testing to validate alternate industrial preservation methods, materials, alternate blocking, bracing, cushioning, and packing.

(g) SUPPLEMENTAL INSTRUCTIONS: N/A

[End of Clause]

INSPECTION AND ACCEPTANCE

This document incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at these addresses:

http://farsite.hill.af.mil/VFFARA.HTM or http://farsite.hill.af.mil/VFDFARA.HTM or http://farsite.hill.af.mil/VFAFARa.HTM

If the clause requires additional or unique information, then that information is provided immediately after the clause title.

10 52.246-2 INSPECTION OF SUPPLIES--FIXED-PRICE AUG/1996

11 52.246-16 RESPONSIBILITY FOR SUPPLIES APR/1984

12 52.246-11 HIGHER-LEVEL CONTRACT QUALITY REQUIREMENT DEC/2014

(a) The contractor shall comply with the higher-level quality standard(s) listed below.

ISO 9001:2008 (tailored: delete 7.3)

(b) The contractor shall include applicable requirements of the higher-level quality standard(s) listed in paragraph (a) of this clause and the requirement to flow down such standards, as applicable, to lower-tier subcontracts in--

(1) Any subcontract for critical and complex items (see 46.203(b) and (c)); or

(2) When the technical requirements of a subcontract require--

(i) Control of such things as design, work operations, in-process control, testing and inspection; or

(ii) Attention to such factors as organization, planning, work instructions, documentation control, and advanced metrology.

(End of clause)

13 52.209-4000 NOTICE REGARDING FIRST ARTICLE TEST SAMPLE MAR/2000

(TACOM)

(a) The approved first article items, as described elsewhere in this contract, consist of a quantity of 1 that will be consumed or destroyed in testing. Any items consumed or destroyed in testing shall not be delivered as part of the contractually required quantity as set forth in the schedule. The cost of any items that are consumed or destroyed shall be included in the overall offer or contract price. A quantity of 1 that successfully passes all specified tests, less the destructive tests, if any, shall serve as a manufacturing standard for the remainder of the contract.

(b) A manufacturing standard is an item, which conforms to all technical performance requirements. A manufacturing standard will serve as 1) an aid in identifying configuration changes not controlled by the contractual design. 2) as an aid in identifying any process changes, or 3) as the approved workmanship sample, when required, unless alternate samples are submitted for specific characteristics by the Contractor and approved by the Government.

(c) The manufacturing standard will only be used to supplement contractual acceptance/rejection criteria for those process characteristics that require approved workmanship samples. For other characteristics, if configuration or process changes are identified in production units, the contractor will notify the contracting officer for disposition. Manufacturing items that serve as a manufacturing standard may be delivered as part of the contractual quantity with the last shipment made under this contract provided it meets all contractual requirements existing at time of delivery.

15 65

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

14 52.209-4333 INSPECTION AND ACCEPTANCE (FIRST ARTICLE APPROVAL) APR/2006

(TACOM)

In addition to inspection requirements specified in applicable drawings and/or specifications, the following provisions shall apply to this contract:

(1) FIRST ARTICLE APPROVAL-CONTRACTOR TESTING: First Article Approval-Contractor Testing shall be performed in accordance with:

FAT IAW DWG 10867174

(2) The First Article Test Report (FATR) shall be compiled by the contractor to the contractor's own format.The FATR shall document the results of all inspections and tests (including supplier's and vendor's inspection records and certifications, when applicable). The FATR shall include actual inspections and test results to include all measurements, recorded test data, and certifications (if applicable) keyed to each drawing, specification and Quality Assurance Provision (QAP) requirement and identified by each individual QAP characteristic, drawing/specification characteristic and unlisted characteristic. The FATR shall contain sufficient narrative content, technical data, illustrations or photographic evidence, and an objective determination by the contractor to allow the designated Government representative to determine that the First Article Test was successfully completed.

[End of Clause]

15 52.209-4012 NOTICE REGARDING FIRST ARTICLE APR/2000

(TACOM)

(a) Notwithstanding the provisions for waiver of first article, an additional first article sample (or portion thereof) may be ordered by the Contracting Officer in writing when (i) a major change is made to the technical data, (ii) whenever there is a lapse in production for a period in excess of one year, or (iii) whenever a change occurs in place of performance, manufacturing process, material used, drawing, specification or source of supply.

(b) When any of the conditions above occurs, the Contractor shall notify the Contracting Officer so that a determination can be made concerning the need for the additional first article sample (or portion thereof), and instructions can be provided concerning the submission, inspection, and notification of results.

(c) Costs of any additional testing and inspection resulting from conditions specified above shall be borne by the Contractor, unless the change was directed by the Government. Further, any production delays caused by additional testing and inspection will not be the basis for an excusable delay as defined in the default clause of this contract. Such delays shall not form the basis for adjustment in contract price or delivery schedule.

[End of Clause]

16 52.211-4017 REQUIREMENTS FOR PRETREATMENTS AND CHEMICAL AGENT RESISTANT COATINGS NOV/2014

(TACOM) LOCAL WARREN - PAINTED MATERIEL

(a) Scope

(1) This clause applies to contracts requiring Chemical Conversion Coatings and Pretreatments for Metallic Substrates, Chemical

Agent Resistant Coating (CARC), and their related materials. The requirements in this clause clarify and supplement those in the contract, unless nullified elsewhere in the contract or through an approved Request for Deviation.

(2) Coating qualification, spot paint repair, and MIL-DTL-16232 Phosphate Coating, Heavy, Manganese or Zinc Base coatings are not within the scope of this clause.

(b) Definitions

(1) The contracting agency, appropriate agency, procuring authority, engineering authority, procuring agency, and procuring activity is the PCO or designee.

(2) The prime contractor is the company awarded this contract, and the subcontractors comprise all companies involved in providing coated parts to the prime contractor, including companies that apply the coatings.

(c) General Requirements Clarifications

(1) The government retains the right for onsite verification of the prime contractors and its subcontractors products, processes, procedures, and test reports.

(2) The prime contractor shall be responsible for itself and its subcontractors to produce and maintain detailed process control plans, process control data, pre-production approval testing, ongoing quality control & quality control testing, and test reports.

16 65

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

This information shall be available upon government request.

(3) The prime contractor shall immediately notify the PCO and the Defense Contract Management Agency (DCMA) of any failure to meet preproduction and production requirements.

(4) Each cleaning method shall be treated as a separate step in the process documentation.

(5) The Gage Repeatability and Reproducibility (Gage R&R) error shall be less than 30 percent for all process and product measurement systems.

(6) Products with hexavalent chromium, including but not limited to certain fastener finishes, shall not be used. Additionally, CARC topcoats containing siliceous additives to control gloss are prohibited.

(7) CARC primer and CARC topcoat shall not be applied directly to bare metal or plastic, except as provided for in MIL-DTL-53072.

(8) If the contract specifies application of CARC materials over a non-CARC coating, then both CARC primer and CARC topcoat are required. The complete coating system shall meet the requirements for CARC defined in TT-C-490.

(9) Neutral salt spray (NSS) testing shall not be used to validate compliance with materiel life cycle requirements; NSS is a production quality test and does not predict field performance.

(d) Pre-Production Approval Clarifications

(1) Pre-production testing shall include:

(i) Thickness of each layer of the coating system;

(ii) Coating system adhesion;

(iii) Salt spray performance; and

(iv) For phosphate pretreatments, the phosphate coating weight, crystal size and shape, and scanning electron microscope photos of the phosphate coatings at 500x and 1000x magnification.

(2) Pre-production test samples shall be from the material used for production parts, pieces cut from production representative parts, or production representative parts. Standardized test coupons shall not be used.

(3) Nine samples shall be produced for the required testing and shall include: three cleaned and pretreated test samples, three samples with the complete paint system and, depending on the CARC paint system, either three samples with pretreatment plus primer or three samples with metal-rich primer plus primer.

(4) One or more ISO 17025 laboratories shall conduct pre-production testing on the nine test samples in accordance with (IAW) the applicable test method accreditations. The applicable ISO 17025 test method accreditations include ASTM B117 Salt Spray, ASTM B244

Thickness of Non-Conductive Coatings on Non-Magnetic Metals, ASTM B487 Measurement of Metal and Oxide Coating Thickness, ASTM B499

Thickness of Non-Conductive Coatings on Magnetic Metals, and ASTM D3359 Measuring Adhesion by Tape Test.

(5) Unless required elsewhere in the contract and specifications, the CARC coating system applied to hot and cold rolled steel shall meet a minimum of 336 hours neutral salt spray resistance IAW ASTM B117.

(6) Test procedures shall be submitted IAW the Contract Data Requirements List (CDRL) DI-NDTI-80603 documenting Pretreatment and

Chemical Agent Resistant Coating procedures when this CDRL is included in the contract.

(7) Test reports from the ISO 17025 accredited labs shall be submitted for Pretreatment and Chemical Agent Resistant Coating testing specified in paragraph (d)(4) of this clause IAW the Contract Data Requirements List (CDRL) DI-NDTI-80809 when this CDRL is included in the contract.

(e) Production Testing Clarifications

(1) At a minimum, ongoing production quality tests shall conducted and recorded daily for coating adhesion and coating thickness, and monthly for salt spray testing. Use of ISO accredited laboratories is optional for these ongoing tests of production parts.

(2) Production parts or pieces cut from production parts shall be used for ongoing production quality testing. Standardized test coupons shall not be used.

(3) Unless specified elsewhere in the contract and specifications, the CARC coating system applied to hot and cold rolled steel shall meet a minimum of 336 hours neutral salt spray resistance IAW ASTM B117.

[End of Clause]

17 52.211-4029 INTERCHANGEABILITY OF COMPONENTS MAY/1994

(TACOM)

(a) DESIGN CHANGES TO ITEMS NOT UNDER GOV'T DESIGN CONTROL. Once the Government accepts the first production test item, or ______________________________________________________ accepts the first end item you deliver, (whichever comes first) you must not make design changes to any item or part that is not under

Government design control.

(b) WHEN THE POLICY CAN BE WAIVED. The Procuring Contracting Officer (PCO) will consider waiving this policy at your request. If _____________________________ your request reaches the CO after the first production item test has been performed, then we may conduct another first production test at your expense.

(c) PRODUCTION OR DELIVERY DELAYS. Any production or delivery delays caused by this retesting will not be the basis for: _____________________________

(1) an "excusable delay" as defined in the DEFAULT clause of this contract.

(2) be the basis for an increase in contract price or delivery schedule extension.

[End of clause]

17 65

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

18 52.242-4008 ROUTING OF SPECIAL PROCESS APPROVALS DEC/2005

(TACOM)

(a) The Technical Data Package for this contract contains one or more of the following specifications:

MIL-DTL-16232 Phosphate Coating, Heavy, Manganese or Zinc Base

TT-C-490 Chemical Conversion Coatings and Pretreatment for Ferrous Surfaces (Base for Organic Coatings)

MIL-W-12332 Welding Resistance, Spot: Weldable Aluminum Alloys

MIL-W-45210 Welding Resistance, Spot: Weldable Aluminum Alloys

*Drawing 12479550 Ground Combat Vehicle Welding Code - Steel

*Drawing 12472301 Ground Combat Vehicle Welding Code - Aluminum

* If these drawings are not available with your procurement package, please contact the contract specialist on page 1.

(b) The specifications listed in paragraph 1 may require you to get approval from the Government prior to production for one or more special processes involved in producing the item. The following shall apply, unless stated elsewhere in the contract:

(1) You shall prepare the written procedures as the specification requires.

(2) Procedures requiring Government approval shall be routed to the Administrative Contracting Officer (ACO) for review and approval. If the ACO is unable to perform a review, the ACO shall forward the procedure to the Procuring Contracting Officer (PCO) for assistance in the review and approval process. The correct address for the PCO is on the face page of this contract.

(3) You shall cite (i) the contract number and (ii) the governing specification or standard on all procedures you submit for approval.

(4) The DCMA will provide a copy of their approval/rejection notices to the PCO.

(5) DCMA is required to qualify the processes of the major coating subcontractors used by the prime contractors.

[End of Clause]

19 52.246-4028 INSPECTION AND ACCEPTANCE POINTS: ORIGIN NOV/2005