KTR_EH5V0424EH-SPRDL115Q0199.pdf

PDF 129 KB Posted

Attached to
ENGINE COOLANT RADIATOR Federal contract opportunity
Solicitation number
sprdl115q0199
Issued by
Department of the Army Materiel Command TACOM Life Cycle Management Command

About this file

SOLICITATION

View the file

Other files for this federal contract opportunity

Other files attached to ENGINE COOLANT RADIATOR, newest first.
File Type Posted
SPRDL115Q0199-0005.pdf PDF
SPRDL115Q0199_-OOO4-__Extension_and_increase_in_QTY_amendment.pdf PDF
SPRDL115Q0199.PDF PDF
SPRDL115Q0199-_amendment_0002.pdf PDF
KTR_EH5V0424EH_SPRDL115Q0199-0001.pdf PDF
SPRDL115Q0199-0001.pdf PDF
KTR_EH5V0424EH_SPRDL115Q0199-0001.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REQUEST FOR QUOTATION This RFQ is is not a small business set-aside Page Of

(This is NOT an Order)

1. Request No. 2. Date Issued 3. Requisition/Purchase Request No. 4. Cert For Nat Def. Under BDSA Rating

See Schedule Reg. 2 and/or DMS Reg. 1 5A. Issued By 6. Deliver by (Date)

See Schedule

7. Delivery

FOB Other Destination

5B. For Information Call: (Name and telephone no.) (No collect calls)

8. To: Name and Address, Including Zip Code 9. Destination (Consignee and address, including Zip Code)

See Schedule

10. Please Furnish Quotations to the Issuing Office in Block 5A On or Before Close of Business (Date)

IMPORTANT: This is a request for information, and quotations furnished are not offers. If you are unable to quote, please indicate on this form and return it to the address in Block 5B. This request does not commit the Government to pay any costs incurred in the preparation of the submission of this quotation or to contract for supplies or services.

Supplies are of domestic origin unless otherwise indicated by quoter. Any interpretations and/or certifications attached to this Request for Quotation must be completed by the quoter.

11. Schedule (Include applicable Federal, State, and local taxes)

Item Number (a)

Supplies/Services (b)

Quantity (c)

Unit (d)

Unit Price (e)

Amount (f)

(See Schedule)

12. Discount For Prompt Payment a. 10 Calendar Days b. 20 Calendar Days c. 30 Calendar Days d. Calendar Days % % % Number Percentage

NOTE: Additional provisions and representations are are not attached.

13. Name and Address of Quoter (Street, City, County, State and 14. Signature of Person Authorized to Sign 15. Date of Quotation Zip Code) Quotation

16. Signer

a. Name (Type or Print) b. Telephone

Area Code

c. Title (Type or Print) Number

AUTHORIZED FOR LOCAL REPRODUCTION Standard Form 18 (Rev. 8-95) PREVIOUS EDITIONS NOT USABLE 18-118 Prescribed by GSA-FAR (43 CFR) 53.215-1(a)

X

SPRDL1-15-Q-0199 2015AUG06 DOA4

SPRDL1DLA LAND WARREN

WARREN, MI 48397-5000

HTTP://CONTRACTING.TACOM.ARMY.MIL

KAREEM WALTON (586)282-3205

ZGA

EMAIL: KAREEM.J.WALTON.CIV@MAIL.MIL

X

2015SEP09

1 61

CONTINUATION SHEET

Reference No. of Document Being Continued Page of

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

SUPPLEMENTAL INFORMATION

Buyer Name: KAREEM WALTON

Buyer Office Symbol/Telephone Number: ZGA/(586)282-3205

Type of Contract 1: Firm Fixed Price

Kind of Contract: Supply Contracts and Priced Orders

*** End of Narrative A0000 ***

Regulatory Cite Title Date Regulatory Cite Title Date _______________ ______________________________________________________________________ ____________ _______________ ______________________________________________________________________ ____________

1 52.204-4016 TACOM-WARREN ELECTRONIC CONTRACTING SEP/2008

(TACOM)

(a) All DLA Land Warren solicitations are distributed on the TACOM-Warren Procurement Network (ProcNet) Business Opportunities website

(http://contracting.tacom.army.mil/opportunity.htm) and are no longer available in hard copy. The Technical Data Packages (TDPs) and other documents, when available electronically, will be attachments or links to the solicitation package on ProcNet.

(b) You may need to use special software to view documents that we post on ProcNet. This viewing software is freeware, available for download at no cost from commercial websites like Microsoft and Adobe. In cases where such software is required, we provide a link from

ProcNet to the commercial site where the software is available. Once you arrive at the software developer's site, follow its instructions to download the free viewer. You can then return to the ProcNet.

(c) Unless otherwise authorized in this solicitation, you are required to submit your offer, bid, or quote electronically, via the Army

Single Face to Industry (ASFI) Online Bid Response System (BRS). For detailed information about submitting your offer electronically, please see http://contracting.tacom.army.mil/acqinfo/ebidnotice.htm.

(d) Requirements for online bid submission:

(1) You must be registered in the System for Award Management (SAM) and have a Marketing Partner Identification Number (MPIN) and CAGE Code.

(2) If you found the solicitation on ProcNet, use the following link to the Start Bid Page on the ASFI BRS website for this solicitation:

https://acquisition.army.mil/asfi/solicitation_view.cfm?psolicitationnbr=SPRDL115Q0199

(3) If you found the solicitation by searching on ASFI, you can start the online bidding process by using the Start Bid button on the ASFI Solicitation View page. You may also access the ASFI BRS by going to https://acquisition.army.mil/asfi/ and clicking on the

Contracting Opportunities Search to find the solicitation.

(4) Once in the ASFI BRS, you will be asked to enter basic information and will then be directed to upload one or more files containing your offer and information required by the solicitation.

(5) You will receive a confirmation of your bid upon completion of the bid submission process. You can find detailed BRS user instructions on the ASFI website at https://acquisition.army.mil/asfi/BRS_guide.doc.

(e) Note to offerors:

Your attention is called to the solicitation closing date and time as stated on the cover page of this solicitation, local time for the

DLA Land - Warren, (DTA), Michigan. In accordance with FAR 15.208(a), offerors are responsible for submitting proposals, and any revisions, and modifications, so as to be received by the Government office designated in the solicitation by the time specified.

It is the offeror's responsibility to ensure its proposal is received by the date and time specified on the cover page of this solicitation. In accordance with FAR 15.208, if your proposal is not received at the initial point of entry to the Government infrastructure (in this case, received through ASFI) by the exact date and time specified on the cover page of this solicitation, it will be determined late. Proposal, as the term is used here, means ALL volumes and/or parts of the proposal.

Note: There is no "expected" or "target" length of time for proposal submission; size and content may be factors, therefore offerors are strongly cautioned to submit their proposals allowing adequate time for submission.

Solicitations may remain posted on the AFSI Open Solicitation Web page after the solicitation closes. Even though the system will allow you to submit a proposal after the closing date/time, your proposal will be considered late and may not be considered for award.

If you are responding to a Request for Proposal, your offer will not be considered if it is submitted after the closing date and time

2 61

SPRDL1-15-Q-0199

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

unless one of the exceptions is met at FAR 15.208(b). If you are responding to a Request for Quotation, your quote may be considered if it is received after the closing date, and it will not unduly delay award.

(f) Any award issued as a result of this solicitation will be distributed electronically and will include the awarded unit price. This is the notice required by Executive Order 12600 (June 23, 1987) of our intention to release unit prices in response to any request under the Freedom of Information Act (FOIA), 5 USC 552. Unit price is defined as the contract price per unit or item purchased as it appears in Section B of the contract and is NOT referring to nor does it include Cost or Pricing data/information. If you object to such release, and you intend to submit an offer, notify the contracting officer in writing prior to the closing date identified in this solicitation and include the rationale for your objection consistent with the provisions of FOIA. A release determination will be made based on rationale given.

(g) If you have questions or need help using ProcNet, call our Electronic Contracting Help Desk at (586) 282-7059, or send an email to usarmy.detroit.acc.mbx.wrn-web-page-request@mail.mil. If you have questions about the content of any specific item posted on the

ProcNet, please call the contract specialist or point of contact listed for the item. For technical assistance in doing business with the Government, and doing business electronically, please visit the Procurement Technical Assistance Center website at http://www.dla.mil/SmallBusiness/Pages/ptap.aspx to find a location near you.

2 52.214-4000 ACKNOWLEDGMENT OF AMENDMENTS OCT/1993

Acknowledge all the amendments you've received from us by identifying the amendment number and its issue date below:

Amendment Number Date

(End of Provision)

3 52.214-4003 ALL OR NONE MAR/1998

(TACOM)

Offers in response to this solicitation must be submitted for the total quantity of the items identified in the solicitation.

(1) ONLY ONE AWARD WILL BE MADE AS A RESULT OF THIS SOLICITATION.

(2) OFFERS SUBMITTED FOR LESS THAN THE TOTAL QUANTITIES OF ALL THE ITEMS IN THIS SOLICITATION ARE INELIGIBLE FOR AWARD.

[End of clause]

4 52.215-4800 NOTICE OF REVERSE AUCTION PROVISION JAN/2014

(DLA LAND-

WARREN)

3 61

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

This solicitation contains standard DLAD provision 52.215-9023, Reverse Auction. This Request For Quotes (RFQ) solicitation will use the simplified acquisition procedures of FAR Part 13. Therefore, the following terminology in the reverse auction provision is changed as follows: replace proposal with quote, replace offer with quote, replace offeror with quoter, and replace final proposal revision with quotation.

After receipt of quotes, the contracting officer will determine if a reverse auction will be conducted. However, the use of a reverse auction does not preclude additional methods of price and/or cost analysis. The quoted prices received up until the start of the auction will be evaluated for award in accordance with the evaluation factors listed in the solicitation. After the start of the auction, the only way to revise prices is to participate in the auction by placing bids. Therefore, quotes received after the start of the auction will not be considered unless the contracting officer determines further correspondence is required.

If a reverse auction is held, Contractors must be registered in the reverse auction system in order to participate in the auction.

Additionally, the Contractor representative participating in the auction must have taken the on-line reverse auction training prior to the auction. Registration, on-line training, and other information regarding the reverse auction can be found at https://dla.procurexinc.com. If a reverse auction is held and a Contractor that provided a quote to the solicitaiton does not participate in the auction, the initially quoted price(s) will be considered and evaluated.

Questions related to the reverse auction system or process can be directed to dla.detroit.tacom.mbx.land-wrn-reverse-auction@mail.mil.

Any other questions can be directed to the contract specialist listed in this solicitation.

[End of Provision]

DLA Land-Warren intends to negotiate and award a Firm-Fixed Price type Contract for ENGINE COOLANT RADIATOR.

A.1.1. Notice Regarding Fill-ins. This solicitation contains several clauses and provisions which require you to complete a fill-in or_________________________________ representation. So please be careful to read and complete each such clauses and provision.

A.1.2. Notice Regarding CAGE Codes. DFARS provision 252.204-7001 requires you to include your Commercial and Government Entity (CAGE)___________________________________ code in block 15A on page (1) of this solicitation, along with your name and address. If it will not fit in the space provided in block

15A insert it here.

A.1.3. Required Notification to Subcontractors. If awarded the contract, you should advise all potential suppliers and subcontractors_______________________________________________ of the DO/DX Rating assigned to orders resulting from your subcontractors. The Rating can be found in Block 1 of the SF 33.

A.1.4. Acknowledgement of Amendments. Please acknowledge any amendments to this solicitation in the space provided on page 3 of the SF_____________________________________

33. Include the number and date of each amendment.

A.1.5. Question/Problem Resolution. Routine questions regarding this solicitation should be directed to the buyer identified in block___________________________________

10 of the SF 33.

*** END OF NARRATIVE A0001 ***

4 61

PIIN/SIIN

Page of

Name of Offeror or Contractor:

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

Reference No. of Document Being Continued

MOD/AMD

SUPPLIES OR SERVICES AND PRICES/COSTS

0001 RADIATOR,ENGINE COO

NSN: 2930-01-102-0245

Mfr CAGE: 19207

Mfr Part Number: 12269450

0001AA Production Quantity 65 EA $ $ ____________________ ______________ __________________

COMMODITY NAME: RADIATOR,ENGINE COO

CLIN CONTRACT TYPE:

Firm Fixed Price

PRON: EH5V0424EH PRON AMD: 02

THERE IS A REQUIREMENT FOR FIRST

ARTICLE TESTING.

Your proposed price for this Production __________

SubCLIN 0001AA must include the cost___________________________ of the First Article Testing.

See Data Item SubCLIN 0001AB: First

Article Test Report.

The Data Item SubCLIN 0001AB is

"Not Separately Priced", which is _____________________ why the cost of testing must be included in this Production

SubCLIN 0001AA.

(End of narrative B001)

Packaging and Marking _____________________

PACKAGING/PACKING/SPECIFICATIONS:

SEE PACKAGING REQUIREMENTS CLAUSE

LEVEL PRESERVATION: Military

LEVEL PACKING: A

Inspection and Acceptance _________________________

INSPECTION: Origin ACCEPTANCE: Origin

Deliveries or Performance _________________________

DOC SUPPL

REL CD MILSTRIP ADDR SIG CD MARK FOR TP CD ______ ________ ______ ______ ________ _____

001 W56HZV5132969Z W62G2T J 2

DEL REL CD QUANTITY DAYS AFTER AWARD __________ ______________ ________________

001 65 0300

FOB POINT: Destination

SHIP TO:

5 61

Page of

Name of Offeror or Contractor:

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

Reference No. of Document Being Continued

MOD/AMD

(W62G2T) XU W1BG DLA DISTRIBUTION

25600 S CHRISMAN ROAD

REC WHSE 57

TRACY,CA,95304-5000

0001AB FIRST ARTICLE TEST REPORT 1 EA $ $ _________________________ ______________ __________________

COMMODITY NAME: ENGINE COOLANT RADIATOR

CLIN CONTRACT TYPE:

Firm Fixed Price

A first article test report is required in accordance with the clause entitled "First

Article Approval -- Contractor

Testing", FAR 52.209-3. The price for first article testing in the total amount of $________ is included in the total amount for CLIN 0001AA.

(End of narrative B001)

Packaging and Marking _____________________

PACKAGING/PACKING/SPECIFICATIONS:

SEE PACKAGING REQUIREMENTS CLAUSE

LEVEL PRESERVATION: Military

LEVEL PACKING: A

Inspection and Acceptance _________________________

INSPECTION: Origin ACCEPTANCE: Origin

Government Approval/Disapproval Days: 30

After submission of the test report, the

Government will have 30 days to approve or disapprove.

(End of narrative E001)

Deliveries or Performance _________________________

DOC SUPPL

REL CD MILSTRIP ADDR SIG CD MARK FOR TP CD ______ ________ ______ ______ ________ _____

DEL REL CD QUANTITY DAYS AFTER AWARD __________ ______________ ________________

001 1 0120

FOB POINT: Destination

SHIP TO:

(Y00006) SEE FIRST ARTICLE TEST CLAUSE

FOR DISTRIBUTION

FOB: Destination

SHIP TO: See first article test

6 61

Page of

Name of Offeror or Contractor:

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

Reference No. of Document Being Continued

MOD/AMD

clause for distribution

(End of narrative F001)

0002 ENGINE COOLANT RADIATOR

0002AA UNEXERCISED OPTION QUANTITY 65 EA $ $ ___________________________ ______________ __________________

COMMODITY NAME: ENGINE COOLANT RADIATOR

Packaging and Marking _____________________

PACKAGING/PACKING/SPECIFICATIONS:

SEE PACKAGING REQUIREMENTS CLAUSE

LEVEL PRESERVATION: Military

LEVEL PACKING: A

Inspection and Acceptance _________________________

INSPECTION: Origin ACCEPTANCE: Origin

Deliveries or Performance _________________________

DOC SUPPL

REL CD MILSTRIP ADDR SIG CD MARK FOR TP CD ______ ________ ______ ______ ________ _____

DEL REL CD QUANTITY DAYS AFTER AWARD __________ ______________ ________________

001 65 0150

FOB POINT: Destination

SHIP TO:

(Y00000) SHIPPING INSTRUCTIONS FOR CONSIGNEE

(SHIP-TO) WILL BE FURNISHED PRIOR

TO THE SCHEDULED DELIVERY DATE FOR

ITEMS REQUIRED UNDER THIS

REQUISITION.

7 61

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

DESCRIPTION/SPECIFICATIONS/WORK STATEMENT

5 52.211-4015 CONFIGURATION CONTROL - ENGINEERING CHANGES DEC/2005

(TACOM)

(a) DEFINITIONS:

(1) Engineering Change Proposal (ECP). An ECP is a suggestion that we (the Government) permanently change some requirement of the Technical Data Package (TDP). ECPs can be issued before or during contract performance. NOTE: The current Government Standard allows us ninety days to process routine ECPs. If you (the contractor) need a response in less than ninety days to meet contract requirements, you should consider submitting a deviation along with your ECP.

(2) Notice of Revision (NOR). A NOR describes the proposed changes to a technical document being requested by an ECP.

(3) Value Engineering Change Proposal (VECP). A proposal that --

(i) Requires a change to the instant contract; and

(ii) Results in reducing the overall projected cost to the agency without impairing essential functions or characteristics; provided, that it does not involve a change --

(A) In deliverable end item quantities only;

(B) In research and development (R&D) end items or R&D test quantities that is due solely to results of previous testing under this contract; or

(C) To the contract type only.

(4) Request for Deviation (RFD). A RFD is a one-time request to deviate from TDP requirements. You must submit your deviation request once you realize that you desire to deviate from the TDP requirements. You can request a deviation for a specific number of parts or the entire contract quantity.

(b) When will TACOM start processing change requests? TACOM won't start processing any ECP, VECP, or RFD until we receive the

ACO's comments (see paragraph (e) below) and the ECP, VECP, or RFD documentation.

(c) Contractor Responsibility. ECPs, VECPs, and RFD shall contain information per the instructions outlined on the Data Delivery

Descriptions (DDDs) which can be found at the following website: http://contracting.tacom.army.mil/engr/engrchange.htm. Forms for preparing an ECP, VECP, or a RFD can also be found at this website. You may use other media, as long as you give us all the information outlined in the DDDs.

(1) Identify the two-digit Weapon System Code (WSC) on your submittal. The WSC for this procurement is (MQ).

(2) The Contractor shall submit ECPs/VECPs/RFDs to the Government electronically. You must use one of the following electronic mediums: 3 1/2 inch disk, 650 megabyte CD ROM, or E-mail. (E-mail files must be sized 3.5 mb or less.) Identify the software application, and version, that you used to create each file submitted.

(3) ECPs/VECPs/RFDs submitted in paper form are unacceptable and will be returned. You must use one of the following electronic formats:

(i) Files readable using these Microsoft 97 Office Products or later versions: Word, Excel, PowerPoint, or Access.

Spreadsheets must be sent in a file format that includes all formulae, macro and format information. Print image is not acceptable.

(ii) Files in Adobe PDF (Portable Document Format).

(iii) Files in HTML (Hypertext Markup Language). HTML documents must not contain active links to live Internet sites or pages. All linked information must be contained within your electronic ECPs/VECPs/RFDs and be accessible offline.

(iv) Other electronic formats. Before preparing your ECPs, VECPs or RFDs in any other electronic format, please e-mail the engineer, copy-furnished to the buyer and ACO, to obtain a decision as to the format's acceptability. Failure to e-mail the engineer to seek an alternate format's acceptability may result in rejection of your submission. All alternate methods must be at no cost to the Government. NOTE: The above formats may be submitted in compressed form using self-extracting files.

(d) Submittal Procedures for ECPs/VECPs/RFDs.

8 61

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

(1) Send one copy of the ECP, VECP or RFD in electronic format to your ACO.

(2) Send one copy of the ECP, VECP or RFD in electronic format to the buyer listed on the solicitation/ contract document.

WARNING - Submit complete, legible, virus free packages per paragraphs 1 and 2 above, or we may return your ECP/VECP/RFD without processing them.

(e) ACO Responsibility. Within ten working days from the day you receive the contractor's request, the ACO must prepare Comments on the ECP, VECP, or RFD in electronic format, and forward it as follows:

Email a copy of the contractor's request and ACO comments (DD Form 1998) to the buyer identified in block 7 of the solicitation cover sheet (SF 33), block 5 on the Standard Form 26, or block 6 on the DD Form 1155. Indicate end item application (if known) in subject line, along with the NSN and contract number.

(f) Approval of ECPs, VECPs and RFDs.

(1) ECPs should be used to make permanent changes in the Government Technical Data Package (TDP). Contractual relief should be requested using a Request for Deviation. This is because the Government requires more time to analyze any proposal to permanently change the specification or TDP. Cost saving improvements to the TDP should be submitted as a VECP, if a VE clause is contained in the contract.

(2) ECPs. TACOM will review and make a decision within the ninety day timeframe. Notification of our decision will be made by the contracting officer or representative.

(3) RFDs. Decision on RFDs will be made within 30 days from the date we receive them from the ACO.

(g) Processing Emergency and Urgent ECPs. Ordinarily, ECPs submitted by the contractor will be deemed routine. If you submit an

ECP that you consider to be an emergency or urgent (as defined in paragraph 11 of DDD for ECPs), you must immediately notify the PCO.

TACOM will review the criticality of the ECP, and, if we determine that it is urgent or critical, we'll follow the appropriate processing time-frames as outlined in paragraph 11 of the DDD for ECPs.

(h) Reminder - Only the PCO can change the Contract. NO OTHER GOVERNMENT REPRESENTATIVE is authorized to make a commitment for, or bind the Government.

(i) RFDs shall contain sufficient pricing data to determine if a downward equitable adjustment to the contract is required.

(j) Questions.

(1) Questions about preparation and submittal of change request should be directed to the Government Quality Assurance

Representative (QAR).

(2) Questions about the status of change requests you've already submitted, contact the buyer. You can find the buyer's name, number and e-mail address in block 7 of the solicitation cover sheet (SF 33), block 5 on the Standard Form 26, or block 6 on the DD Form

1155.

[End of Clause]

6 52.211-4072 TECHNICAL DATA PACKAGE INFORMATION JUN/2013

(TACOM)

The following Xd item applies to this solicitation:

[ ] 1. There is no Technical Data Package (TDP) included with this solicitation.

[ ] 2. This solicitation contains one or more web-located TDPs. If multiple Contract Line Item Numbers (CLINS) are listed below, each one will have its own URL just under the CLIN listing. The URL will take you to that CLINs Web-located TDP. To access the TDP, you will have to copy or type the links URL to your web browser address bar at the top of the screen.

Note: To copy a link from a .pdf file, click on the Text Select Tool, then highlight the URL, copy and paste it into your browser, and hit the Enter key.

CLIN:

9 61

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

TDP Link (URL):

[ X ] 3. The TDP for this solicitation resides within FedBizOpps (https://http://www.fbo.gov), and is associated with this solicitation number and can be accessed via this URL:

https://www.fbo.gov/fedteds/SPRDL115Q0199

a. Log on to the FBO web site.

b. Enter your Marketing Partner Identification Number (MPIN).

c. Search for the solicitation number.

d. If solicitation is Export Controlled, select Verify MPIN.

(1) TDPs that have an Export Control Warning Notice are subject to the Arms Export Control Act (Title 22, U.S.C., Sec 2751, et.seq.) or the Export Administration Act of 1979, as amended, Title 50, U.S.C, App. 2401 et. seq..

(2) Further dissemination must be in accordance with provisions of DoD Directive 5230.25. This also applies to distribution of the TDP to all SUBCONTRACTORS at every level.

(3) To obtain these TDPs, vendors and contractors must have a current DD 2345, Militarily Critical Technical Data

Agreement on file with Defense Logistics Information Service (DLIS).\~ If you are currently certified, your MPIN will be verified and you may proceed to the next step.\~ To obtain certification, go to http://www.dlis.dla.mil/jcp/ click on documents and follow instructions provided.\~ Processing time is estimated at six (6) to ten (10) weeks after receipt.

FBO will allow you to access export controlled TDPs once certification is confirmed.

(4) Upon completion of the purposes for which Government Technical Data has been provided, the Contractor is required to destroy all documents, including all reproductions, duplications, or copies thereof as may have been further distributed by the Contractor. Destruction of this technical data shall be accomplished by: shredding, pulping, burning, or melting any physical copies of the TDP and/or deletion or removal of downloaded TDP files from computer drives and electronic devices, and any copies of those files.

e. If technical data is otherwise restricted, select Request Explicit Access. This will generate an email to the FBO system administrator at TACOM Warren with all the information needed for them to grant you access. FBO will subsequently automatically generate an email stating when you have permission to view or download TDP items. Allow 2 3 working days to complete this FBO-TDP access/approval process through the FBO system.

f. If multiple individuals in your company need access to the Technical Data Package (TDP) for a solicitation and an explicit access request is required, each individual MUST submit an explicit access request to be granted approval to view the TDP. Those same individuals MUST be registered in Federal Business Opportunities (FBO). Any individuals no longer with the company should be deleted. Questions related to registration in FBO should be directed to https://www.fbo.gov/index The FBO helpdesk phone number is

(866) 606-8220. Vendors are responsible for placing correct information in FBO.

g. It is strongly suggested that you submit the explicit access request and provide the buyer with the completed Use and Non-

Disclosure Agreement at the same time if the solicitation requires both to gain access to view the TDP.

h. A user guide for FBO can be found at https://http://www.fbo.gov - on the right is User Guides - click on Vendor.

[ ] 4. The Government requires a Use and Non-Disclosure Agreement (NDA) to be signed by an authorized representative of your firm before you are granted access to the technical data. The appropriate Agreement is:

[ ] available at http://contracting.tacom.army.mil/acqinfo/contractorforms.htm titled:

[ ] available as an attachment to this solicitation.

Follow the instructions on the Agreement, and email/fax it to the buyer at . The buyer will notify the FBO administrator upon receiving the NDA. The administrator will grant approval to view/download the TDP. An email stating approval has been granted will be sent to the vendor. It can take up to 24 hours after approval before you are able to view the TDP. If you have any questions/problems viewing the TDP contact the buyer.

10 61

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

[End of Clause]

7 52.246-4053 USE OF MIL-STD 1916 JAN/2001

(TACOM)

The Government will not accept lots whose samples submitted for acceptance contain nonconformances unless appropriately documented and approved by the contracting officer. The contractor shall use MIL-STD-1916, DOD Preferred Methods of Acceptance of Product. The

Verification Level (VL) shall be VL IV for major characteristics and VL II for minor characteristics. MIL-HDBK-1916 provides guidance on the use of MIL-STD 1916.

[End of Clause]

8 52.211-4008 DRAWING LIMITATIONS NOV/2005

(TACOM)

(a) The drawings supplied with this contract are not shop or process drawings. They are engineering design drawings. They are ___ adequate to permit manufacture, and:

(1) depict the completed (item(s), and

(2) serve as the basis for inspection of the completed item(s).

(b) These drawings DON'T cover intermediate drawings/specifications or steps in the manufacturing process. As a result, even if you meet all the dimensions and tolerances specified in the engineering design drawing for each individual part, a cumulative unacceptable fit for the contract item could result.

(c) YOU ARE RESPONSIBLE for producing the shop or process drawings needed to cover intermediate steps in the manufacturing ___________________ process.

(d) You, the contractor, are responsible for obtaining all specifications and drawings necessary to manufacture the items being solicited in accordance with the TDP including all incorporated specifications and drawings. Delivery delays are not excusable where the contractor asserts that it did not have a specification or drawing and has failed to request, in writing, the specification from either the Contracting Officer or Contract Specialist prior to the solicitation closing date.

(e) If you fail to produce an end item with a cumulative fit that conforms to Government drawings, specifications or other supplemental manufacturing documentation, you'll be responsible for correcting this condition at no additional cost to the Government and no delivery schedule extension.

[End of clause]

PACKAGING AND MARKING

9 52.211-4515 PACKAGING REQUIREMENTS (SPECIAL PACKAGING INSTRUCTIONS) DEC/2007

(TACOM)

@ (a) Military preservation, packing, and marking for this contract/order shall be accomplished in accordance with the specific requirements identified below, all the applicable requirements of, MIL-STD-2073-1, Revision D, Dated 15 Dec 1999 and Notice 1, dated 10

May 2002, and the Special Packaging Instruction, see below.

(1) LEVEL OF PRESERVATION: Military

(2) LEVEL OF PACKING: A

(3) QUANTITY PER UNIT PACKAGE: 001

11 61

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

(4) SPECIAL PACKAGING INSTRUCTION NUMBER. AK11020245

(a) REVISION D

(b) DATE OF REVISION As listed on SPI

(c) THE REQUIRED SPECIAL PACKAGING INSTRUCTION (SPI) IS AVAILABLE ON THE WEB AT THE FOLLOWING URL:

https://www.tacom.army.mil/ilsc/tdps/phst/SPI/06/88/50.pdf

(Note: You must have the Adobe Acrobat reader installed on your PC to view the SPI. See the Army Contracting Command - Warren (DTA) web site (http://contracting.tacom.army.mil/faq.htm) for information on obtaining the latest version of the reader. If you're experiencing problems opening the Special Packaging Instructions in Adobe .PDF images using Internet Explorer, try the following: Go to "Tools," then

"Internet Options." Click on the "Advanced" tab. Scroll down to the "Security" section. Uncheck "Do not save encrypted pages to disk."

Click "Apply." Click "OK.")

(b) Unitization: Shipments of identical items going to the same destination shall be palletized if they have a total cubic displacement of 50 cubic feet or more unless skids or other forklift handling features are included on the containers. Pallet loads must be stable, and to the greatest extent possible, provide a level top for ease of stacking. A palletized load shall be of a size to allow for placement of two loads high and wide in a conveyance. The weight capacity of the pallet must be adequate for the load. The preferred pallet is a 40 x 48 inch, 4-way entry pallet although variations may be permitted as dictated by the characteristics of the items being unitized. The load shall be contained in a manner that will permit safe handling during shipment and storage.

(c) Marking:

(1) In addition to any special markings called out on the SPI, all unit packages, intermediate packs, exterior shipping containers, and, as applicable, unitized loads shall be marked in accordance with MIL-STD-129, Revision P-Change Notice 4, dated 19 Sep

2007, including bar coding and Military Shipment Label (MSL). The contractor is responsible for application of special markings as discussed in the Military Standard regardless of whether specified in the contract/order or not. Special markings include, but are not limited to, Shelf-life markings, structural markings, and transportation special handling markings. The marking of pilferable and sensitive materiel will not identify the nature of the materiel. Passive RFID tagging is required in all contracts that contain DFARS clause 252.211-7006. Contractors must check the solicitation and/or contract for this clause. For details and most recent information, see http://www.acq.osd.mil/log/rfid/index.htm for the current DoD Suppliers Passive RFID Information Guide and Supplier Implementation

Plan. If the item has Unique Item Identifier (UII) markings then the concatenated UII needs to be 2D bar coded and applied on the unit package, intermediate and exterior containers, and the palletized unit load.

(d) Heat Treatment and Marking of Wood Packaging Materials (WPM): Boxes/pallets and any wood used as inner packaging made of non-manufactured wood shall be heat-treated. All WPM shall be constructed from heat treated (treated to 56 degrees Celsius -core temperature-for 30 minutes) lumber and certified by an accredited agency accredited by the ALSC in accordance with Wood Packaging Material Policy and Wood Packaging Material Enforcement Regulations (see URL: http://www.alsc.org). The box/pallet manufacturer and the manufacturer of wood used as inner packaging shall ensure traceability to the original source of heat treatment. Marking: Each box/pallet shall be marked to show the conformance to the International Plant Protection Convention Standard. The quality mark shall be placed on both ends of the outer packaging, between the end cleats or end battens. Pallet markings shall be applied to the stringer or block on diagonally opposite sides and ends of the pallet and be contrasting and clearly visible. All dunnage used in configuring and/or securing the load shall also comply with https://www.ippc.int/servlet/BinaryDownloaderServlet/133703_ISPM15_2002_with_Ann.pdf?filename=1152091663986_ISPM_15_2002_with_Annex1_2006

_E.pdf&refID=133703 and be marked with an ALSC approved dunnage stamp, marked at two foot intervals (in the case of dunnage shorter than

2 feet, each piece must still have the mark present). Foreign manufacturers shall have the heat treatment and marking of non-manufactured wood products verified in accordance with their National Plant Protection Organizations compliance program.

(e) Hazardous Materials (As applicable):

(1) Hazardous Materials is defined as a substance, or waste which has been determined by the Secretary of Transportation to be capable of posing an unreasonable risk to health, safety, and property when transported in commerce and which has been so designated.

(This includes all items listed as hazardous in Titles 29, 40 and 49 CFR and other applicable modal regulations effective at the time of shipment.)

(2) Unless otherwise specified, packaging and marking for hazardous material shall comply with the requirements herein for the mode of transport and the applicable performance packaging contained in the following documents:

- International Air Transport Association (IATA) Dangerous Goods Regulations

- International Maritime Dangerous Goods Code (IMDG)

12 61

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

- Code of Federal Regulations (CFR) Title 29, Title 40 and Title 49

- Joint Service Regulation AFJMAN24-204(I)/TM38-250/NAVSUPPUB 505/MCO

P4030.19(I)/DLAM 4145.3(I) (for military air shipments).

(3) If the shipment originates from outside the continental United States, the shipment shall be prepared in accordance with the United Nations Recommendations on the Transport of Dangerous Goods in a manner acceptable to the Competent Authority of the nation of origin and in accordance with regulations of all applicable carriers.

A Product Material Safety Data Sheets (MSDS) is required to be included with every unit pack and intermediate container and shall be included with the packing list inside the sealed pouch attached to the outside of the package.

(f) This SPI has been validated and the method of preservation/packing has proven successful in meeting the needs of the military distribution system, including indeterminate storage and shipment throughout the world. Special instructions and/or tailoring of the

SPI is detailed in the Supplemental Instructions below. A prototype package is required to validate the sizes and fit requirements of the SPI. Minor dimensional and size changes are acceptable provided contractor provides the PCO and ACO with notification 60 days prior to delivery. Any design changes or changes in the method of preservation that provide a cost savings without degrading the method of preservation or packing or affecting the serviceability of the item will be considered and responded to within 10 days of submission to

PCO and ACO. Government reserves the right to require testing to validate alternate industrial preservation methods, materials, alternate blocking, bracing, cushioning, and packing.

(g) SUPPLEMENTAL INSTRUCTIONS:

Distribution Data Report data is NOT required.

UNIT PACKAGE WEIGHT (lbs): 0001385

UNIT PACKAGE CUBE (cubic feet): 0006375

UNIT PACKAGE SIZE (length x width x depth inches): 000370 x 000270 x 000110

[End of Clause]

INSPECTION AND ACCEPTANCE

This document incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at these addresses:

http://farsite.hill.af.mil/VFFARA.HTM or http://farsite.hill.af.mil/VFDFARA.HTM or http://farsite.hill.af.mil/VFAFARa.HTM

If the clause requires additional or unique information, then that information is provided immediately after the clause title.

10 52.246-2 INSPECTION OF SUPPLIES--FIXED-PRICE AUG/1996

11 52.246-16 RESPONSIBILITY FOR SUPPLIES APR/1984

12 52.246-11 HIGHER-LEVEL CONTRACT QUALITY REQUIREMENT DEC/2014

(a) The contractor shall comply with the higher-level quality standard(s) listed below.

ISO 9001:2008 (untailored)

(b) The contractor shall include applicable requirements of the higher-level quality standard(s) listed in paragraph (a) of this clause and the requirement to flow down such standards, as applicable, to lower-tier subcontracts in--

(1) Any subcontract for critical and complex items (see 46.203(b) and (c)); or

(2) When the technical requirements of a subcontract require--

(i) Control of such things as design, work operations, in-process control, testing and inspection; or

(ii) Attention to such factors as organization, planning, work instructions, documentation control, and advanced metrology.

(End of clause)

13 52.209-4000 NOTICE REGARDING FIRST ARTICLE TEST SAMPLE MAR/2000

(TACOM)

(a) The approved first article items, as described elsewhere in this contract, consist of a quantity of ONE that will be consumed or destroyed in testing. Any items consumed or destroyed in testing shall not be delivered as part of the contractually required quantity as set forth in the schedule. The cost of any items that are consumed or destroyed shall be included in the overall offer or contract price. A quantity of ONE that successfully passes all specified tests, less the destructive tests, if any, SHALL serve as a

13 61

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

manufacturing standard for the remainder of the contract.

(b) A manufacturing standard is an item, which conforms to all technical performance requirements. A manufacturing standard will serve as 1) an aid in identifying configuration changes not controlled by the contractual design. 2) as an aid in identifying any process changes, or 3) as the approved workmanship sample, when required, unless alternate samples are submitted for specific characteristics by the Contractor and approved by the Government.

(c) The manufacturing standard will only be used to supplement contractual acceptance/rejection criteria for those process characteristics that require approved workmanship samples. For other characteristics, if configuration or process changes are identified in production units, the contractor will notify the contracting officer for disposition. Manufacturing items that serve as a manufacturing standard may be delivered as part of the contractual quantity with the last shipment made under this contract provided it meets all contractual requirements existing at time of delivery.

14 52.209-4333 INSPECTION AND ACCEPTANCE (FIRST ARTICLE APPROVAL) APR/2006

(TACOM)

In addition to inspection requirements specified in applicable drawings and/or specifications, the following provisions shall apply to this contract:

(1) FIRST ARTICLE APPROVAL-CONTRACTOR TESTING: First Article Approval-Contractor Testing shall be performed in accordance with

FIRST ARTICLE INSPECTIONS/TESTING SHALL BE PERFORMED IAW DRWG/QS:

12269450. PERFORMANCE/ENVIRONMENTAL REQUIREMENTS NECESSITATE A

FAT.

(2) The First Article Test Report (FATR) shall be compiled by the contractor to the contractor's own format.The FATR shall document the results of all inspections and tests (including supplier's and vendor's inspection records and certifications, when applicable). The FATR shall include actual inspections and test results to include all measurements, recorded test data, and certifications (if applicable) keyed to each drawing, specification and Quality Assurance Provision (QAP) requirement and identified by each individual QAP characteristic, drawing/specification characteristic and unlisted characteristic. The FATR shall contain sufficient narrative content, technical data, illustrations or photographic evidence, and an objective determination by the contractor to allow the designated Government representative to determine that the First Article Test was successfully completed.

[End of Clause]

15 52.209-4012 NOTICE REGARDING FIRST ARTICLE APR/2000

(TACOM)

(a) Notwithstanding the provisions for waiver of first article, an additional first article sample (or portion thereof) may be ordered by the Contracting Officer in writing when (i) a major change is made to the technical data, (ii) whenever there is a lapse in production for a period in excess of one year, or (iii) whenever a change occurs in place of performance, manufacturing process, material used, drawing, specification or source of supply.

(b) When any of the conditions above occurs, the Contractor shall notify the Contracting Officer so that a determination can be made concerning the need for the additional first article sample (or portion thereof), and instructions can be provided concerning the submission, inspection, and notification of results.

(c) Costs of any additional testing and inspection resulting from conditions specified above shall be borne by the Contractor, unless the change was directed by the Government. Further, any production delays caused by additional testing and inspection will not be the basis for an excusable delay as defined in the default clause of this contract. Such delays shall not form the basis for adjustment in contract price or delivery schedule.

[End of Clause]

16 52.211-4029 INTERCHANGEABILITY OF COMPONENTS MAY/1994

(TACOM)

(a) DESIGN CHANGES TO ITEMS NOT UNDER GOV'T DESIGN CONTROL. Once the Government accepts the first production test item, or ______________________________________________________ accepts the first end item you deliver, (whichever comes first) you must not make design changes to any item or part that is not under

14 61

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

Government design control.

(b) WHEN THE POLICY CAN BE WAIVED. The Procuring Contracting Officer (PCO) will consider waiving this policy at your request. If _____________________________ your request reaches the CO after the first production item test has been performed, then we may conduct another first production test at your expense.

(c) PRODUCTION OR DELIVERY DELAYS. Any production or delivery delays caused by this retesting will not be the basis for: _____________________________

(1) an "excusable delay" as defined in the DEFAULT clause of this contract.

(2) be the basis for an increase in contract price or delivery schedule extension.

[End of clause]

17 52.246-4017 ALTERNATIVES TO LOT ACCEPTANCE SAMPLING (INCLUDING STATISTICAL FEB/2000

(TACOM) PROCESS CONTROL (SPC))

(a) Offerors are encouraged to propose a defect prevention strategy in lieu of lot acceptance inspection and testing requirement cited in the technical data package. The Government recognizes that industry has developed numerous prevention based strategies which result in reduced process variation and promote continuous process improvement initiatives. Use of alternatives to lot acceptance sampling can provide offerors the latitude of implementing prevention based programs that are suitable to their particular mode of operation. Offerors are encouraged to submit their alternative proposals prior to award. Although the Government will entertain post award requests, there is no guarantee such requests will be accepted.

(b) Requests to use alternatives to lot acceptance sampling shall be provided to the Contracting Officer for review and approval or disapproval. Such request shall include:

(1) Identification of the specific inspections and tests to be reduced or eliminated.

(2) A description of your prevention based program. This should include such topics as training program and the performance of audits.

(3) A description of the tools used to monitor and control the specific processes being evaluated. This should include such topics as criteria for determining out of control conditions and procedures to be used when an out of control condition is detected.

(4) The results of a process performance study, and if available, the results of a process capability study.

(5) For SPC data to be used as an alternative to lot acceptance sampling, the following conditions shall be met:

(i) The process is in a state of statistical control using SPC control chart methods.

(ii) Variable data: for Critical characteristics a CPK =/> 2.00 (or equivalent capability) is achieved; for Major characteristics a CPK =/> 1.33 (or equivalent capability) is achieved.

(iii) Attribute data: for Critical Characteristics a process average of 100% of the product conforming to the specification; for Major characteristics a process average of 99.9937% of the product conforming to the specification.

(c) Proposals offered after award. The Contracting Officer is responsible for accepting or rejecting the alternate lot acceptance procedure submitted by the contractor. The contractor may submit an alternate lot acceptance procedure at any time during the performance of this contract. The Contracting Officer is responsible for accepting or rejecting the alternate procedure within 30 days of receipt. If the Government needs more time evaluate the alternate procedure, the Contracting Officer shall notify the contractor in writing, giving the reasons and the anticipated decision date. The contractor may withdraw its proposal at anytime prior to its incorporation by contract modification. Because offerors may withdraw their proposal at anytime, the Contracting Officer's failure to timely accept or reject the proposal shall not constitute grounds for claim against the Government. Any proposed and accepted procedure is not accepted, the Contracting Officer shall provide the contractor with written notification, explaining the reasons for rejection.

(d) Any equitable adjustment resulting from approval of an alternate lot acceptance procedure described in paragraph (c) above will be handled in accordance with the Changes clause of this contract.

(e) Until notification is received, the contractor is required to perform under this contract in accordance with the requirements herein, including lot acceptance inspection and testing.

(End of Clause)

15 61

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

18 52.246-4028 INSPECTION AND ACCEPTANCE POINTS: ORIGIN NOV/2005

(TACOM)

The Government's inspection and acceptance of the supplies offered under this contract/purchase order shall take place at ORIGIN.

Offeror must specify below the exact name, address, and CAGE of the facility where supplies to be furnished under this contract/purchase order will be available for inspection/acceptance.

INSPECTION POINT: ___________________________________________________________________________

(Name) (CAGE)

(Address) (City) (State) (Zip)

ACCEPTANCE POINT: ____________________________________________________________________________

(Name) (CAGE)

(Address) (City) (State) (Zip)

[End of Clause]

DELIVERIES OR PERFORMANCE

This document incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at these addresses:

http://farsite.hill.af.mil/VFFARA.HTM or http://farsite.hill.af.mil/VFDFARA.HTM or http://farsite.hill.af.mil/VFAFARa.HTM

If the clause requires additional or unique information, then that information is provided immediately after the clause title.

19 52.242-15 STOP-WORK ORDER AUG/1989

20 52.242-17 GOVERNMENT DELAY OF WORK APR/1984

21 52.247-48 F.O.B. DESTINATION--EVIDENCE OF SHIPMENT FEB/1999

22 252.211-7003 ITEM UNIQUE IDENTIFICATION AND VALUATION DEC/2013

(a) Definitions. As used in this clause--

"Automatic identification device" means a device, such as a reader or interrogator, used to retrieve data encoded on machine-readable media.

"Concatenated unique item identifier" means

(1) For items that are serialized within the enterprise identifier, the linking together of the unique…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .