Exhibit_A_Technical_Requirements_13AUG2019_011.pdf
PDF 303 KB Posted
- Attached to
- 5995-01-219-4706 CABLE ASSEMBLY Federal contract opportunity
- Solicitation number
- SPRBL119Q0137
About this file
Technical Requirements
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| SPRBL119Q0137-0001.pdf | ||
| Attachment_0003_Packaging_NAS_3426_1996AUG30_003.pdf | ||
| SPRBL119Q0137.pdf | ||
| Attachment_002_SPI-AG00000573_1996JUN01_005.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Exhibit A SPRBL1-19-Q-0137 Page 1 of 11 Issue: 13 AUG 2019
TECHNICAL REQUIREMENTS
NSN 5995-01-219-4706 CABLE ASSEMBLY
Exhibit A SPRBL1-19-Q-0137 Page 2 of 11
TABLE OF CONTENTS
APPLICABLE DOCUMENTS
CONFIGURATION BASELINE
PACKAGING
Wood Packing Material Military Package
SPECIALIZED TESTING
CONTRACT DATA REQUIREMENT LIST (CDRL) DD 1423-1
CDRL List
Individual CDRLs ............................................................................................ Error! Bookmark not defined.0
Exhibit A SPRBL1-19-Q-0137 Page 3 of 11
APPLICABLE DOCUMENTS
Military and Federal Standards MIL-STD-129R(1) Military Marking for Shipment and Storage
Military and Federal Specifications
MIL-HDBK-61A Configuration Management Guidance (Dated 7 Feb 2001)
Other Documents
CECOM- AG00000573F CECOM Special Packaging Instruction A3014056 (Revision T) Cable Specification, SINCGARS Installation Kit
Commercial Documents ISPM 15 Regulation of Wood Packaging Material in International Trade NAS 3426 Electrical Harness-Cable Assemblies, Packaging Of SAE EIA-649-1 Configuration Management Requirements for Denfense Contracts
Security Documents
CONFIGURATION BASELINE
The applicable Configuration Baselines (CB), for the listed Configuration Item (CI) and/or Computer Software Configuration Item (CSCI), are as listed in the table below.
NSN Nomenclature Part Numbers / Drawings
5995-01-219-4706 Cable Assembly, Special Purpose, Electrical CX-13292/VRC (18FT 0IN) A3014038-5
Configuration Responsibility. Each CI/CSCI, as developed/built and delivered, shall conform to the cited CB and (if applicable) all subsequent CB’s that will be made contractually binding by the Procuring Contracting Officer (PCO). Configuration changes not directly effecting the configuration baseline do not require Government approval prior to incorporation, but must be documented by the contractor and shall be made available to the Government upon request. The contractor may use MIL-HDBK-61A and SAE EIA-649-1, Configuration Management Requirements for Defense Contracts, which was adapted on 04 March 2015 for use by the Department of Defense (DoD), as guidance for establishing a Configuration Management Program.
Departures from CB. No changes or departures from the CB are acceptable except for changes or departures which are submitted in accordance with DI-MISC-80711A and are approved by the Government Configuration Manager or Configuration Management Officer (CMO) and which are made applicable to the contract by the PCO. Configuration Control shall be affected by the Configuration Control Documents (CCDs) as follows:
Exhibit A SPRBL1-19-Q-0137 Page 4 of 11
a. Engineering Change Proposal (ECP) includes both the engineering change and the supporting documentation by which the change is described and suggested. An ECP describes changes to the CI/CSCI and associated Government documents and data that are affected by the proposed engineering change. An ECP shall be submitted using the latest revision of DD Form 1692.
b. A Notice of Revision (NOR) shows the detailed changes that must be made to technical documentation, except specifications, (one NOR per document) following approval of an ECP. The NOR is submitted as part of the ECP. A NOR shall be submitted using the latest revision of DD Form 1695.
c. A Specification Change Notice (SCN) is used to delineate the exact change(s) in a specification that will be distributed to users when the ECP is approved. The SCN is submitted as part of the ECP. The SCN is not used for a military or federal document. A SCN shall be submitted using the latest revision of DD Form 1696.
d. Value Engineering Change Proposal (VECP) is the same as an ECP except there are proposed cost savings for the program. The contractor shall follow the guidance in Section I of this contract for VECPs.
e. Request for Variance (RFV) is a temporary departure from requirements and do not constitute a permanent change to the Functional Configuration Document, Allocated Configuration Document, or Product Configuration Document. Prior to or after manufacture of an item, the supplying activity may request a variance. The supplying activity shall not build items, or present items for acceptance, that incorporate a known departure from requirements, unless a request for a variance has been approved.
Where it is determined that a change should be permanent, an ECP must be processed in accordance with this document. A RFV shall be submitted using the latest revision of DD Form 1694.
f. Contractor shall provide all supporting program or cost data with the CCD. The contractor shall uniquely and sequentially identify (including the use of the contract number) each ECP, VECP, NOR, SCN or RFW. The identification number should use less than 16 characters.
Identification of Authorized Personnel. The contractor shall identify to the PCO, Administrative Contracting Officer (ACO), and the technical office identified on the DD Form 1423 for DI-MISC-80711A, the name(s) of the official(s) of its organization who are authorized to submit CCDs 30 Days after Contract (DAC).
Exhibit A SPRBL1-19-Q-0137 Page 5 of 11
PACKAGING
Wood Packing Material [E/IM: Identify if applicable.] [KO/KS: If not applicable, remove this section.] Wood packing material includes pallets. See DLAD 52.247-9012 Requirements for Treatment of Wood Packaging Material (WPM).
Wood packaging material (WPM) shall meet the requirements below. Wood packaging material (WPM) includes but is not limited to pallets, skids, load boards, pallet collars, wooden boxes, reels, dunnage, crates, frame and cleats. This requirement excludes materials that have undergone a manufacturing process, such as corrugated fiberboard, plywood, particleboard, veneer, and oriented strand board (OSB).
a. All WPM shall meet the requirements of International Standards for Phytosanitary Measures (ISPM) Number 15, “Regulation of Wood Packaging Material in International Trade”. DoD shipments inside and outside of the United States shall meet the requirements of ISPM 15 whenever WPM is used to ship DoD cargo.
b. All WPM shall comply with the official quality control program for heat treatment (HT) or kiln dried heat treatment (KD HT) (IAW) American Lumber Standard Committee (ALSC), Incorporated, Wood Packaging Material Program and WPM Enforcement Regulations (see http://www.alsc.org/).
c. All WPM shall include certification/quality markings IAW the ALSC standard. Markings shall be placed in an unobstructed area that will be readily visible to inspectors. Pallet markings shall be applied to the stringer or block on diagonally opposite sides of the pallet and be contrasting and clearly visible. All containers shall be marked on a side other than the top or bottom, contrasting and clearly visible. All dunnage used in configuring and/or securing the load shall also comply with ISPM 15 and be marked with an ASLC approved DUNNAGE stamp.
d. Failure to comply with these requirements may result in refusal, destruction, or treatment of materials at the point of entry. The Government reserves the right to recoup from the contractor any remediation costs incurred by the Government.
Military Packaging DS7029 and/or DS7033 Preservation, Packing and Marking Instructions [E/IM: Identify if applicable and fill out table DS7029 - DS7033 below.] APPLICABLE.
[KO/KS: If not applicable, remove this section.]
DS7029 - DS7033 LEGEND
Qty Quantity Prot Req Protection Required PKG-REF Packaging Reference (Military/Federal Specification or Standard) SPI Special Packaging Instruction http://www.alsc.org/
Exhibit A SPRBL1-19-Q-0137 Page 6 of 11
LPK Level of Packing QUP Quantity per Unit Pack ICQ Intermediate Container Quantity Pkg Reqmt Codes Packaging Requirement Codes when PKG-REF cites MIL-STD-2073 The below codes are for special markings:
PC Project Code WG Warranty/Guarantee SL Shelf Life BC Bar Code FMS Foreign Military Sales
Exhibit A SPRBL1-19-Q-0137 Page 7 of 11
DS7029 - DS7033
NSN Prot Req PKG-REF or SPI LPK QUP ICQ Special Markings
Pkg J. J J J J J J J J J Reqmt I. II. III. IV. V. VI. VII. VII.a IX X Codes (MP) (CD) (PM) (WM) (CD) (CT) (UC) (IC) (PK) (SM) 5995-01-219-4706 Military AG00000573 B 001 - n/a n/a n/a n/a n/a n/a n/a n/a/ n/a n/a BC
Exhibit A SPRBL1-19-Q-0137 Page 8 of 11
SPECIALIZED TESTING
Final Inspection and Test. The contractor shall implement and maintain a Final Inspection and Test System that meets or exceeds the requirements established below. These requirements are commonly accepted practices employed by industry.
a. Quality System. The contractor shall establish/maintain an effective inspection and test system for final inspection and test of completed products.
b. Inspection and Testing Procedures. The contractor shall utilize documented procedures for final inspection and testing of finished products to ensure that all contract requirements are satisfied.
c. Fianl Inspection and AcceptanceTesting. The quality system shall assure that all final inspections and tests required satisfying contract requirements are conducted. All deliverables (100%) under this contract prior to delivery to the Government shall undergo acceptance test in accordance with Paragraph 4.2b of Cable Specification A3014056 to verify compliance with the requirements set forth in Paragraph 3.0 of the Cable Specification A3014056. The Government has the right to perform an inspection at any time during normal business hours with a contractor quality representative present. Equipment and facilities required for inspection and testing shall be the contractor’s responsibility. The contractor shall obtain written approval from the Government for utilization of testing facilities other than the primary production testing facility prior to the commencement of any acceptance tests, and shall notify the Government, in writing, of the scheduled test(s), in accordance with FAR 52.246-2, to allow Government representatives to witness and verify inspection and test.
d. Records. The contractor shall maintain adequate records of final inspections and tests to demonstrate that the product satisfies contract requirements.
e. Measuring, Testing, and Inspection Equipment. The contractor shall provide and maintain gages (including production tooling used for inspection purposes) and other measuring and testing equipment to assure that finished products conform to contract requirements. These devices shall be calibrated against certified measurement standards that are traceable back to national/international standards.
f. Inspection and Test Status. The contractor shall maintain a system for the identification of the final inspection and test status of all products.
g. Nonconforming Material. The contractor shall establish and maintain a system for controlling material that does not satisfy contract requirements, including procedures for its identification, segregation, and disposition (rework/repair, scrap, etc.).
h. Corrective Action. The contractor shall promptly act to correct nonconforming materials and processes to preclude the recurrence of the problem and to satisfy contract requirements.
i. Training Requirements. The contractor shall identify/provide for the training needs of their personnel performing inspections and tests.
Exhibit A SPRBL1-19-Q-0137 Page 9 of 11
j. Handling, Storage, Preservation, Packaging, and Shipping. The contractor shall control the handling, storage, preservation, packaging, and shipping to protect the quality of finished products.
Exhibit A SPRBL1-19-Q-0137 Page 10 of 11
CONTRACT DATA REQUIREMENT LIST (CDRL) DD 1423-1
CDRL List
CDRL
Data Line No. DID Identification Title A001 DI-MISC- 80711A Scientific and Technical Reports – Configuration Control
Exhibit A SPRBL1-19-Q-0137 Page 11 of 11
CONTRACT DATA REQUIREMENTS LIST
(1 Data Item)
Original Form Approved OMB No. 0704-0188
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA. 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:
0001 A TDP X TM OTHER
D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR
SINCGARS SPRBL1-19-Q-0137 TBD
1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE 17. PRICE GROUP
A001 Scientific and Technical Reports Configuration Control
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED
TOTAL PRICE
DI-MISC-80711A Attachment 0001-Techncial Requirements
RDER-PRC-TR INSERT
7. DD 250 REQ 9.DIST STATEMENT
REQUIRED
10. FREQUENCY 12. DATE OF FIRST
SUBMISSION 14. DISTRIBUTION IN
DD As Request See Item 16 b. COPIES
SECT. B
8. APP CODE N/A 11. AS OF DATE 13. DATE OF SUBSEQUENT
SUBMISSION
a. ADDRESSEE Draft
Final
See Item 16 Reg
Repro
16. REMARKS:
Data Item Description DI-MISC-80711A: Delete block 10 instructions entirely and follow instructions in this Technical Requirements Document.
The contractor shall prepare and submit Configuration Control Documents in accordance with the Technical Requirements Document section for Configuration Control when a change to or departure from a contractual baseline document is deemed necessary.
The Government will have 30 days to review, accept, and/or comment on the draft submission. The contractor shall incorporate changes into the electronic deliverable within 30 days after receipt of Government comments. The Government will have 30 days to review, accept, and/or comment on the final submission.
All deliveries shall be in digital format, compatible with Microsoft Office 2007 software and adobe Acrobat version 7.0 and delivered via AMRDEC SAFE (https://safe.amrdec.army.mil) with a notification email to the Government personnel listed in the distribution list. Alternative delivery media may be discussed with the Contracting Officer prior to delivery. The Government personnel listed in the distribution list will receive a copy of the submittals. Name and electronic address of the Government personnel are specified below:
PCO: Matina Culik Moore, Martina.CulikMoore@dla.mil
ACO: TBA
QAR: TBA
RDER-PRC-TR: Stanley Chan, stanley.u.chan.civ@mail.mil AMSEL-ILSC-LEO-CMDI: Eric Jones, eric.jones5.civ@mail.mil AMSEL-LCL-EIE: Diane L. Sheehan, diane.l.sheehan.civ@mail.mil
If the CDRL Data Deliverable is priced and is not NSP (Not Separately Priced), then an electronic DD Form 250 will be required via the Wide Area Workflow website in order for the contractor to receive payment for the data deliverable (see section G of the Contract). E-mail notification is required with any electronic submission.
RDER-PRC-TR
PCO
ACO
QAR
AMSEL-ILSC-LEO-CMDI
AMSEL-LCL-EIE*
*1 COPY VECP ONLY
15. TOTAL 0 6 0
G. PREPARED BY H. DATE I. APPROVED BY J. DATE
Stanley U. Chan
FCDD-ISP-TR
Electronics Engineer
08/12/2019 Daniel Webster
FCDD-ISP-TR
Chief, Tactical Radio Branch
08/12/2019
Based upon DD Form 1423-1, 1 Jun 90
| APPLICABLE DOCUMENTS |
| CONFIGURATION BASELINE |
| PACKAGING |
| Wood Packing Material |
| Military Packaging |
| SPECIALIZED TESTING |
| CONTRACT DATA REQUIREMENT LIST (CDRL) DD 1423-1 |
| CDRL List |
File details come from the government source that posted it.