ADDITIONAL QUESTIONS BASED ON VENDOR QUESTIONS.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| ADDITIONAL_CLARIFICATIONS_RUBBER_PRESS_DATED_12_MAY.docx | DOCX document | |
| ATTACHMENT_(2)_CLARIFICATIONS.pdf | ||
| FORMAL_SOLICITATION.pdf | ||
| ATTACHMENT_(1)_SLIENT_CHARACTERISTICS.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ADDITIONAL CLARIFICATOINS RUBBER PRESS
(Q 1) Is the press up or down acting. Meaning does the bottom platen move up to meet the top platen, or does the top platen move down to meet the bottom platen.
DOWN ACTING.
(Q 2) Is there a required working height from the floor to the bottom platen.
HEIGHT: 38"-42"
(Q 3) Are there any holes or tee slots in the platens to mount tooling/ molds to them.
NO
(Q 4) 3.3.2.2 States you want 3 access 3 side and you mention the left side , which other 2 sides do you require.
THE FRAME OF THE PRESS SHALL ALLOW ACCESS TO AT LEAST THREE SIDES OF THE
PLATENS, ONE OF THE 3 ACCESS SIDES SHALL BE ON THE LEFT SIDE.
(Q 5) 3.3.2.4 States safety gate do you want 3 safety gates or 1 gate that covers 3 sides and again which 3 sides should the 4 side have a fixed guard.
THERE SHOULD BE 3 SEPARATE SAFETY GATES.
(Q 6) 3.3.2..2 Regarding heaters, do you want each heater monitored or each control loop monitored.
EACH CONTROL LOOP MONITORED