Solicitation SPE4AX-13-R-0016
View the file
Other files for this federal contract opportunity
Show all 14
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
10. FOR
INFORMATION
CALL:
13. DISCOUNT FOR PROMPT PAYMENT
(See Section I, Clause No. 52.232-8)
SOLICITATION, OFFER AND AWARD 1. THIS CONTRACT IS A RATED ORDER
UNDER DPAS (15 CFR 700)
RATING
2. CONTRACT No.
SPE4AX-13-R-0016
3. SOLICITATION No. 4. TYPE OF SOLICITATION
SEALED BID (IFB)
NEGOTIATED (RFP)X
2013 JUN 03
5. DATE ISSUED
1000010035
6. REQUISITION/PURCHASE No.
7. ISSUED BY 8. ADDRESS OFFER TO (If other than Item 7)
NOTE : In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
9. Sealed offers in original and copies for furnishing the supplies or services in the Schedule will be received at the place specified in Item 8, or if handcarried, in the depository located in local time
CAUTION - LATE Submissions, Modifications, and Withdrawals: See Section L, Provision No. 52.214-7 or 52.215-1. All offers are subject to all terms and conditions contained in this solicitation.
11. TABLE OF CONTENTS
DESCRIPTION
25. PAYMENT WILL BE MADE BY
CODE
SOLICITATION
until (Hour) (Date)
AUTHORIZED FOR LOCAL REPRODUCTION
PREVIOUS EDITION NOT USABLE
STANDARD FORM 33 (Rev.9-97) Prescribed by GSA FAR (48 CFR) 53.214 (c)
OFFER (Must be fully completed by offeror ) NOTE: Item 12 does not apply if the solicitation includes the provisions at 52.214-16, Minimum Bid Acceptance Period.
AWARD (To be completed by Government)
16. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER
(Type or print)
14. ACKNOWLEDGMENT OF AMEND-
MENTS (The offeror acknowledges receipt of amendments to the SOLICITATION for offerors and related documents numbered and dated):
12. In compliance with the above, the undersigned agrees, if this offer is accepted within period is inserted by the offeror) from the date for receipt of offers specified above, to furnish any or all items upon which prices are offered at the price set opposite each item, delivered at the designated point(s), within the time specified in the schedule.
CONTRACT ADMINISTRATION DATA L INSTRS., CONDS., AND NOTICES TO OFFERORS
SPECIAL CONTRACT REQUIREMENTS M EVALUATION FACTORS FOR AWARD
IMPORTANT - Award will be made on this Form, or on Standard Form 26, or by other authorized official written notice.
(X) PAGE(S) SEC. DESCRIPTION PAGE(S)
SUPPLIES OR SERVICES AND PRICES/COSTS PART III - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACH.
PART I - THE SCHEDULE PART II - CONTRACT CLAUSES
I CONTRACT CLAUSESSOLICITATION/CONTRACT FORM
DESCRIPTION/SPECS./WORK STATEMENT J LIST OF ATTACHMENTS
INSPECTION AND ACCEPTANCE
PACKAGING AND MARKING PART IV - REPRESENTATIONS AND INSTRUCTIONS
DELIVERIES OR PERFORMANCE
K REPRESENTATIONS, CERTIFICATIONS AND OTHER
STATEMENTS OF OFFERORS
AMENDMENT NO. DATEAMENDMENT NO. DATE
G
H
SEC.
B
A
C
E
D
F
(X)
FACILITY
CODE
15C. CHECK IF REMITTANCE ADDRESS IS
DIFFERENT FROM ABOVE - ENTER SUCH
ADDRESS IN SCHEDULE
17. SIGNATURE
19. ACCEPTED AS TO ITEMS NUMBERED
23. SUBMIT INVOICES TO ADDRESS SHOWN IN22. AUTHORITY FOR USING OTHER THAN FULL AND OPEN COMPETITION:
24. ADMINISTERED BY (If other than item 7) CODE CODE
27. UNITED STATES OF AMERICA
(Signature of Contracting Officer )
26. NAME OF CONTRACTING OFFICER (Type or print) calendar days (60 calendar days unless a different
15A. NAME AND
ADDRESS
OF OFFER-
OR
10 U.S.C. 2304 (c) ( 41 U.S.C. 253 (c) () )
DLA AVIATION
SMSG AVIATION SUP CH CORPORATE LTC
8000 JEFFERSON DAVIS HWY
RICHMOND VA 23297
USA
See Block 7
Reception Area (Bldg 33) 3:00PM 2013-Sep-01
Melissa Small PARAH01
A. NAME
Phone: 256-876-1602
FAX: 256-876-1590
B. PHONE/FAX (NO COLLECT CALLS)
Melissa.Vandyne@dla.mil
C. EMAIL ADDRESS
X 1
X 2
X 5
X 6
X 6
X 7
X 7
X 20
X 20
X 27
X 32
15B. TELEPHONE NUMBER 18. OFFER DATE
28. AWARD DATE
20. AMOUNT
10 CALENDAR DAYS (%) 20 CALENDAR DAYS (%) CALENDAR DAYS (%)30 CALENDAR DAYS (%)
21. ACCOUNTING AND APPROPRIATION
ITEM
SPE4AX
EXT.NUMBERAREA CODE
PAGE OF PAGES
(4 copies unless otherwise specified)
CONTINUED ON NEXT PAGE
This solicitation is for military unique items only in accordance with Federal Acquisition Regulation (FAR) Part 15. Applicability of clauses as well as terms and conditions are identified throughout the solicitation.
Point of contact is Melissa Small at melissa.small@dla.mil or (256) 876-1602.
This solicitation is considered a joint opportunity for worldwide Defense Logistics Agency (DLA) direct (DD) supply of DLA consumable as well as depot level reparable (DLR) items. All items are sole source to Parker Hannifin Corporation (Parker). The requirements are identified by national stock number (NSN) and can be found in Section J, List of Attachments, within the Pricing Spreadsheet.
This procurement will result in the award of a new contract which will be a fixed-price, indefinite delivery, indefinite quantity (IDIQ) contract with prospective price redetermination with a three-year base period and two, three-year option periods in which additional quantities may be ordered. Price redetermination will occur every three years which the contract is in effect.
The guaranteed minimum dollar amount to be ordered under any the base period of any subsequent contract award from this solicitation is $700,000. The maximum estimated dollar amount is $477M.
The offeror shall identify individual(s) authorized to represent the offeror’s position and commit the offeror in all exchanges between the Government and the offeror below.
Name: __________________________ Title: ___________________________ Phone/Fax: _____________________ Email: __________________________
A small business subcontracting plan must be submitted in accordance with FAR 52.219-09. The Small Business, Small Disadvantaged Business, and Women-Owned Small Business Concerns Subcontracting Plan clauses in this contract will be administered by the cognizant contract administration office.
In cases where multiple orders for the same NSN exist, items are to be delivered in the order in which they are due unless otherwise negotiated and approved by the Contracting Officer.
Facsimile submissions are not authorized. The offeror may e-mail their proposal to melissa.small@dla.mil or mail to:
Defense Logistics Agency (DLA) Aviation ATTN: Melissa Small Building 5202 Martin Road Redstone Arsenal, AL 35898
In accordance with FAR 15.403-5(b)(1), submission of certified cost and pricing data must be in accordance with the format specified in Table 15-2 of FAR 15.408.
Various first article testing (FAT) clauses including FAR 52.209-3, 52.209-4, and DLA Directives (DLAD) 52.209-9019 will be filled in when included in a delivery order.
Addition of items to this acquisition is limited to those items manufactured by Parker and its business units; these currently include contractor and government entity (CAGE) codes 59211, 82106, 3H889, 93835, 49695, 86329, 09523, 26433, 33269, 99321, 1QTD9, 56300, 55813, 50948, and 11362.
The offeror is required to submit pricing for three years for the items identified within the Pricing Spreadsheet attachment referenced above and located in the attachments section of this solicitation. Pricing will be redetermined every three years after award in accordance with DLAD 52.216-9038 (DEVIATION).
This solicitation contains DLA surge and sustainment (S&S) requirements. The Pricing Spreadsheet identifies these items.
The total population of NSNs to be covered by this initiative is estimated at 2,998, with 2,834 identified as DLA consumable items and 164 identified as DLR items. A subset of the total population, 462 items (460 consumable items and 2 DLR items), is considered Phase I or the initial populaltion and is to be priced under this solicitation for evaluation at time of initial award. The total population of 2,998 items does not require pricing at this time, but NSNs may be added to the contract in future phases after initial award.
Performance metrics are intended to be a topic of discussion. However, the Government intends to apply an incentive to cost reduction as well as the performance metric of production lead-time (PLT) reduction.
The overall performance metrics goals for this initiative are as follows:
1. Increase on-time delivery (OTD) to 100%
2. Reduce administrative lead-time (ALT) to 15 days
3. Reduce PLT by 50%
4. Reduce material costs by 10%
Parker is incentivized to reduce its costs by using a 50 / 50 share ratio for a specific group of NSNs for each three-year price redetermination period as well as price re-look at the end of contract years two, five and eight. The specific group of NSNs for this action is a fixed set of cost drivers that will be mutually agreed upon by both parties. For an item to be included in the cost savings provision, Parker is required to submit either certified cost or pricing data or data other than certified cost or pricing data.
The price re-look will entail Parker submitting current cost information for these NSNs to determine if a price adjustment for the subsequent contract year is appropriate. If the price has decreased, the savings will be shared 50 / 50 between the Government and Parker by adjusting the contract unit price accordingly for the subsequent year (contract year three, six or nine). Any increases in actual costs experienced by Parker will be borne by Parker and will not be passed on to the Government. Thus, unit prices will not be adjusted upward for price increases at price re-look.
Example: a NSN is priced as follows:
• Current price (contract years 1-2): $106.40
• Price re-look price: $90.00 (demonstrating cost reduction) ‒ $106.40 - $90.00 = $16.40 in cost reduction ‒ $16.40 / 2 = $8.20 (both the Government and Parker share the savings 50 / 50)
• Year three price: $98.20
At the end of contract year three, prices will be redetermined in accordance with DLAD 52.216-9038 (DEVIATION), and any associated contract provisions, to establish new unit prices for contract years four through six. Any decreases in unit prices will be shared 50 / 50 with Parker and will be applied to the new unit prices as explained in the above example. A new group of cost driver NSNs will be determined and fixed at the end of contract year three. This fixed set of items will be the selected group of NSNs for which Parker will concentrate its cost reduction effort during contract years four through six. The same process will be used at the end of contract year six and be applicable to contract years seven through nine. Items added to the contract during a pricing period (e.g. contract year two or three, etc.) are not subject to this provision during the pricing period in which added.
Initial and redetermined prices will be proposed, evaluated, and negotiated in accordance with a memorandum of agreement (MOA) for all consumable items. If the use of a MOA is pursued for DLR items, DLA Aviation will establish a well-defined process of the intended methodology in conjunction with DLA Headquarters (HQ) prior to implementation. In addition, it is anticipated that all items will be provided on a freight on board (FOB) origin basis. Therefore, proposed pricing will not require evaluation of transportation costs.
SECTION B
SEE ATTACHED LTC SPREADSHEET
SECTION D - PACKAGING AND MARKING
252.211-7006 RADIO FREQUENCY IDENTIFICATION (SEP2011) DFARS
(b)(1) Except as provided in paragraph (b)(2) of this clause, the Contractor shall affix passive RFID tags, at the case- and palletized-unit-load packaging levels, for shipments of items that—
(i) Are in any of the following classes of supply, as defined in DoD 4140.1-R, DoD Supply Chain Materiel Management Regulation, AP1.1.11:
(A) Subclass of Class I – Packaged operational rations.
(B) Class II – Clothing, individual equipment, tentage, organizational tool kits, hand tools, and administrative and housekeeping supplies and equipment.
(C) Class IIIP – Packaged petroleum, lubricants, oils, preservatives, chemicals, and additives.
(D) Class IV – Construction and barrier materials.
(E) Class VI – Personal demand items (non-military sales items).
(F) Subclass of Class VIII – Medical materials (excluding pharmaceuticals, biologicals, and reagents – suppliers should limit the mixing of excluded and non-excluded materials).
(G) Class IX – Repair parts and components including kits, assemblies and subassemblies, reparable and consumable items required for maintenance support of all equipment, excluding medical-peculiar repair parts; and
(ii) Are being shipped to one of the locations listed at http://www.acq.osd.mil/log/rfid/ or to—
(A) A location outside the contiguous United States when the shipment has been assigned Transportation Priority 1, or to—
(B) The following location(s) deemed necessary by the requiring activity:
Contract Line, Subline, or Exhibit Line Item Number
Location Name
City
State
DoDAAC
(2) The following are excluded from the requirements of paragraph (b)(1) of this clause:
(i) Shipments of bulk commodities.
(ii) Shipments to locations other than Defense Distribution Depots when the contract includes the clause at FAR 52.213-1, Fast Payment Procedures.
(c) The Contractor shall—
(1) Ensure that the data encoded on each passive RFID tag are globally unique (i.e., the tag ID is never repeated across two or more RFID tags and conforms to the requirements in paragraph (d) of this clause;
(2) Use passive tags that are readable; and
(3) Ensure that the passive tag is affixed at the appropriate location on the specific level of packaging, in accordance with MIL-STD-129 (Section 4.9.2) tag placement specifications.
(d) Data syntax and standards. The Contractor shall encode an approved RFID tag using the instructions provided in the EPC™ Tag Data Standards in effect at the time of contract award. The EPC™ Tag Data Standards are available at http://www.epcglobalinc.org/standards/.
(1) If the Contractor is an EPCglobal™ subscriber and possesses a unique EPC™ company prefix, the Contractor may use any of the identifiers and encoding instructions described in the most recent EPC™ Tag Data Standards document to encode tags.
(2) If the Contractor chooses to employ the DoD identifier, the Contractor shall use its previously assigned Commercial and Government Entity (CAGE) code and shall encode the tags in accordance with the tag identifier details located at http://www.acq.osd.mil/log/rfid/tag_data.htm. If the Contractor uses a third-party packaging house to encode its tags, the CAGE code of the third-party packaging house is acceptable.
(3) Regardless of the selected encoding scheme, the Contractor with which the Department holds the contract is responsible for ensuring that the tag ID encoded on each passive RFID tag is globally unique, per the requirements in paragraph (c)(1).
(e) Advance shipment notice. The Contractor shall use Wide Area WorkFlow (WAWF), as required by DFARS 252.232-7003, Electronic Submission of Payment Requests, to electronically submit advance shipment notice(s) with the RFID tag ID(s) (specified in paragraph
(d) of this clause) in advance of the shipment in accordance with the procedures at https://wawf.eb.mil/.
http://www.acq.osd.mil/log/rfid/� http://www.epcglobalinc.org/standards/� http://www.acq.osd.mil/log/rfid/tag_data.htm� http://www.acq.osd.mil/dpap/dars/dfars/html/current/252232.htm� http://farsite.hill.af.mil/reghtml/regs/far2afmcfars/fardfars/dfars/%20https:/wawf.eb.mil/�
(End of clause)
52.211-9010 SHIPPING LABEL REQUIREMENTS – MILITARY-STANDARD (MIL-STD) 129P (MAR 2012) DLAD
52.211-9010 SHIPPING LABEL REQUIREMENTS – MILITARY STANDARD (MIL-STD) 129P (NOV 2011), ALT I (AUG 2005)
DLAD
52.211-9033 PACKAGING AND MARKING REQUIREMENTS (APR 2008) DLAD
52.247-9012 REQUIREMENTS FOR TREATMENT OF WOOD PACKAGING MATERIAL (WPM) (FEB 2007) DLAD
SECTION E - INSPECTION AND ACCEPTANCE
52.246-02 INSPECTION OF SUPPLIES FIXED PRICE (AUG 1996) FAR
52.246-16 RESPONSIBILITY FOR SUPPLIES (APR 1984) FAR
252.246-7000 MATERIAL INSPECTION AND RECEIVING REPORT (MAR 2008) DFARS
52.246-9008 INSPECTION AND ACCEPTANCE AT ORIGIN (NOV 2011) DLAD
(a) Inspection and Acceptance are at Origin.
(b) The point of acceptance will be the point of last inspection before shipment unless otherwise indicated by the offeror.
(c) The Offeror shall indicate below the location where supplies will be inspected:
Supplies:
Plant:
Commercial and Government Entity (CAGE) Code:
Street:
City/State/Zip:
Applicable to contract line-item(s) (CLIN(s):
(d) The Offeror shall indicate below the location where packaging will be inspected:
Packaging:
[ ] Same as for supplies, or, Plant:
Cage Code:
Street:
City/St/Zip:
Applicable to clin(s):
SECTION F - DELIVERIES OR PERFORMANCE
52.211-17 DELIVERY OF EXCESS QUANTITIES (SEP 1989) FAR
52.211-9020 TIME OF DELIVERY - ACCELERATED (JUN 2008) DLAD
52.242-15 STOP-WORK ORDER (AUG 1989) FAR
52.242-17 GOVERNMENT DELAY OF WORK (APR 1984) FAR
52.247-29 F.O.B. ORIGIN (FEB 2006) FAR
52.247-30 F.O.B. ORIGIN, CONTRACTOR'S FACILITY (FEB 2006) FAR
52.247-9056 ADDENDUM TO FAR 52.247-29 FREE ON BOARD (F.O.B.) ORIGIN (SEP 2012) DLAD
The offeror/contractor shall identify the location of origin below.
[ ] Same as Offeror (the Offeror shall fill in the city and state):
[ ] Other (the Offeror shall fill-in the city and state):
City
State
SECTION H - SPECIAL CONTRACT REQUIREMENTS
52.204-9001 ELECTRONIC ORDER TRANSMISSION (NOV 2011) DLAD
Supplies procured through the Defense Logistics Agency (DLA) may be ordered via electronic ordering. Offerors must check one of the following alternatives for paperless order transmission:
[ ] Electronic Data Interchange (EDI) transmissions in accordance with ANSI X12 Standards through DLA Transaction Services approved value added network (VAN).
[ ] Electronic Mail (email) award notifications containing Web links to electronic copies of the Department of Defense (DD) Form 1155, Order for Supplies or Services.
52.246-9039 REMOVAL OF GOVERNMENT IDENTIFICATION FROM NON-ACCEPTED SUPPLIES (NOV 2011) DLAD
SECTION I - CONTRACT CLAUSES
52.202-01 DEFINITIONS (JAN 2012) FAR
52.203-03 GRATUITIES (APR 1984) FAR
52.203-05 COVENANT AGAINST CONTINGENT FEES (APR 1984) FAR
52.203-06 RESTRICTIONS ON SUBCONTRACTOR SALES TO THE GOVERNMENT (SEP 2006) FAR
52.203-07 ANTI-KICKBACK PROCEDURES (OCT 2010) FAR
52.203-08 CANCELLATION, RECISSION, AND RECOVERY OF FUNDS FOR ILLEGAL OR IMPROPER ACTIVITY (JAN 1997)
FAR
52.203-10 PRICE OR FEE ADJUSTMENT FOR ILLEGAL OR IMPROPER ACTIVITY (JAN 1997) FAR
52.203-12 LIMITATION ON PAYMENTS TO INFLUENCE CERTAIN FEDERAL TRANSACTIONS (OCT 2010) FAR
252.203-7000 REQUIREMENTS RELATING TO COMPENSATION OF FORMER DOD OFFICIALS (SEP 2011) DFARS
252.203-7001 PROHIBITION ON PERSONS CONVICTED OF FRAUD OR OTHER DEFENSE-CONTRACT-RELATED FELONIES
(DEC 2004) DFARS
252.203-7002 REQUIREMENT TO INFORM EMPLOYEES OF WHISTLEBLOWER RIGHTS (JAN 2009) DFARS
52.204-04 PRINTED OR COPIED DOUBLE-SIDED ON POSTCONSUMER FIBER CONTENT PAPER (MAY 2011) FAR
52.204-07 CENTRAL CONTRACTOR REGISTRATION (AUG 2012) FAR
52.204-07 CENTRAL CONTRACTOR REGISTRATION MAINTENANCE (NOV 2012) FAR
252.204-7003 CONTROL OF GOVERNMENT PERSONNEL WORK PRODUCT (APR 1992) DFARS
252.204-7004 ALTERNATE A, CENTRAL CONTRACTOR REGISTRATION (FEB 2013) DFARS
252.204-7008 EXPORT-CONTROLLED ITEMS (APR 2010) DFARS
252.205-7000 PROVISION OF INFORMATION TO COOPERATIVE AGREEMENT HOLDERS (DEC 1991) DFARS
52.209-03 FIRST ARTICLE APPROVAL - CONTRACTOR TESTING (SEP 1989) FAR
(a) The Contractor shall test to be stated on each delivery order as applicable unit(s) of Lot/Item (as applicable) as specified in this contract. At least to be stated on each delivery order as applicable calendar days before the beginning of first article tests, the Contractor shall notify the Contracting Officer, in writing, of the time and location of the testing so that the Government may witness the tests.
(b) The Contractor shall submit the first article test report within to be stated on each delivery order as applicable calendar days from the date of this contract to to be stated on each delivery order as applicable [insert address of the Government activity to receive the report] marked “First Article Test Report: Contract No. to be stated on each delivery order as applicable, Lot/Item No. to be stated on each delivery order as applicable” Within to be stated on each delivery order as applicable calendar days after the Government receives the test report, the Contracting Officer shall notify the Contractor, in writing, of the conditional approval, approval, or disapproval of the first article. The notice of conditional approval or approval shall not relieve the Contractor from complying with all requirements of the specifications and all other terms and conditions of this contract. A notice of conditional approval shall state any further action required of the Contractor. A notice of disapproval shall cite reasons for the disapproval.
52.209-04 FIRST ARTICLE APPROVAL - GOVERNMENT TESTING (SEP 1989) FAR
(a) The Contractor shall deliver to be stated on each delivery order as applicable unit(s) of Lot/Item (as aplicable) within to be stated on each delivery order as applicable calendar days from the date of this contract to the Government at to be stated on each delivery order as applicable for first article tests. The shipping documentation shall contain this contract number and the Lot/Item identification. The characteristics that the first article must meet and the testing requirements are specified elsewhere in this contract.
(b) Within to be stated on each delivery order as applicable calendar days after the Government receives the first article, the Contracting Officer shall notify the Contractor, in writing, of the conditional approval, approval, or disapproval of the first article. The notice of conditional approval or approval shall not relieve the Contractor from complying with all requirements of the specifications and all other terms and conditions of this contract. A notice of conditional approval shall state any further action required of the Contractor. A notice of disapproval shall cite reasons for the disapproval.
52.209-06 PROTECTING THE GOVERNMENT'S INTEREST WHEN SUBCONTRACTING WITH CONTRACTORS DEBARRED, SUSPENDED, OR PROPOSED FOR SUSPENSION (DEC 2010) FAR
252.209-7004 SUBCONTRACTING WITH FIRMS THAT ARE OWNED OR CONTROLLED BY THE GOVERNMENT OF A
TERRORIST COUNTRY (DEC 2006) DFARS
252.209-7010 CRITICAL SAFETY ITEMS (AUG 2011) DFARS
(b) Identification of critical safety items. One or more of the items being procured under this contract is an aviation or ship critical safety item. The following items have been designated aviation critical safety items or ship critical safety items by the designated control activity:
52.209-9017 FIRST ARTICLE – CONTRACTOR TESTING – ADDITIONAL REQUIREMENTS (NOV 2011) DLAD
(a) For the Lots/Items identified in this contract as requiring “Contractor First Article Test (FAT) (including test report)” in accordance with the clause at FAR 52.209-3, the Contractor shall—
(1) Conform with technical requirements stated and/or referenced in the solicitation; including number of units to be tested, data required, performance or other characteristics that the first articles shall meet, sequence of processes, tests to which the first articles shall be subjected, and conformance criteria for each requirement specified; and
(2) Provide all facilities, equipment and personnel required to perform the examination and evaluation of the first article when first article testing will be conducted at the Contractor's plant. The Government reserves the right to charge the Contractor for any additional costs of examination and evaluation caused by failure of the Contractor to make available the first article or the required facilities, equipment or personnel, at the time the Contractor advised the testing would take place (see paragraph (a) of the clause at FAR 52.209-3).
(3) Prepare and disseminate the First Article Test Report as follows:
(i) Prepare the Test Report in accordance with Data Item Description DI-NDTI-80809B, entitled, “Test/Inspection Report;”
(ii) Mark the Test Report, “First Article Test Report – Contract Number: ________________ and Lot/Item Number: ____________ ;”
(iii) Present the test report to the inspecting activity quality assurance representative (QAR) for review. The QAR will –
(A) Prepare recommendations;
(B) Countersign the first article report;
(C) Forward two copies to the Contracting Officer at the buying activity; and
(D) Provide notification by e-mail, including award number, National Stock Number (NSN), and additive contract Line-item (CLIN) number, and provide copy of award, if not available in Electronic Document Access (EDA), to the Contracting Officer and to:
(1) For awards issued by DLA Land and Maritime DLA Land and Maritime FAT Monitor, BPI Post Office (P. O.) box 3990 Columbus, Ohio 43218-3990
(2) For awards issued by DLA Troop Support:
(i) DLA Troop Support Attention: First Article Testing Monitor Building 3 700 Robbins Avenue Philadelphia, Pennsylvania 19111; or
(ii) For acquisitions of Clothing and Textile (C&T) items, Medical and Subsistence items, and Meal, Ready-To-Eat (MRE) and Tray Pack Items, the Contracting Officer, who acts as FAT/Testing Monitor;
(3) For awards issued by DLA Aviation:
DLA Aviation Test Coordinator Office 8000 Jefferson Davis Highway Richmond, Virginia 23297-5516
(4) For awards issued by Naval Surface Warfare Center, Carderock Division:
Commanding Officer Naval Surface Warfare Center Code 954, Building 77L, Philadelphia Business Center, Carderock Division Philadelphia, Pennsylvania 19112-5083 Telephone: (215) 897-1146
(5) For awards issued by Naval Sea Systems Command, Washington Navy Yard:
Commander Naval Sea Systems Command, Sea 05M3 1333 ISAAC Hull Avenue, SE Stop 5160 Washington Navy Yard, District of Columbia (DC) 20376-5160 Telephone: (202) 781-3729
(iv) Submit the First Article Test Report to the Government activity specified in the contract within the number of calendar days from date of contract (or date of first delivery order, for indefinite delivery contracts) specified in the contract; accompanied by –
(A) Department of Defense (DD) Form 250, Material Inspection and Receiving Report, signed by the QAR and indicating Contract Quality Assurance was accomplished prior to signing the DD Form 250; and
(B) Contractor’s certification that the same processes and facilities used to manufacture the first article units will be used to manufacture the production units; and
(4) Pay all costs incurred for transportation of first article samples and test reports under this contract; and, if applicable, any costs of manufacturing and re-testing additional first articles, and administrative costs to the Government for re-procurement.
(b) The Contractor shall enter an offered price in the CLIN for “Contractor First Article Test (FAT) (including test report)” that includes all costs associated with the production and testing of the first articles and the preparation of the First Article Test Report. Offers that do not cite a separate price for the “Contractor First Article Test (FAT) (including test report)” CLIN, or do not specify there is a separate charge for the “Contractor First Article Test (FAT) (including test report)” shall be evaluated under the presumption that there is no separate charge for the production and testing of the first articles and the preparation of the First Article Test Report.
(End of Clause)
52.209-9018 FIRST ARTICLE – GOVERNMENT TEST – ADDITIONAL REQUIREMENTS (NOV 2011) DLAD
(a) For the lots/items identified in this contract as requiring Government first article test (FAT) in accordance with the clause at Federal Acquisition Regulation (FAR) 52.209-4, the Contractor shall—
(1) Conform with technical requirements stated and/or referenced in the solicitation; including number of units to be produced, data required, performance or other characteristics that the first articles shall meet, sequence of processes, tests to which the first articles shall be subjected, and conformance criteria for each requirement specified.
(2) Provide all facilities, equipment and personnel required to perform the examination and evaluation of the first article units when first article testing will be conducted at the Contractor's plant. The Government reserves the right to charge the Contractor for any additional costs of examination and evaluation caused by failure of the Contractor to make available the first article units or the required facilities, equipment or personnel, at the times specified in the above mentioned notice to the Contracting Officer.
(3)(i) At least fourteen (14) calendar days, or as otherwise specified in the contract, prior to the date when the Contractor will present the first articles to the quality assurance representative (QAR) for inspection to determine compliance with specification requirements, provide written notice to:
(A) The Contracting Officer;
(B) The QAR; and
(C) The following:
(1) For awards issued by DLA Land and Maritime:
DLA Land and Maritime FAT Monitor, BPI Post office (P. O.) box 3990 Columbus, Ohio 43218-3990;
(2) For awards issued by DLA Troop Support:
(i) DLA Troop Support Attention: First Article Testing Monitor Building 3 700 Robbins Avenue Philadelphia, Pennsylvania 19111; or
(ii) For acquisitions of Clothing and Textile (C&T) items; Medical and Subsistence items; and Meal, Ready-To-Eat (MRE) and Tray Pack Items, the Contracting Officer, who acts as FAT/Testing Monitor;
(3) For awards issued by DLA Aviation:
DLA Aviation Test Coordinator Office 8000 Jefferson Davis Highway Richmond, Virginia 23297-5516
(4) For awards issued by Naval Surface Warfare Center, Carderock Division:
Commanding Officer Naval Surface Warfare Center Code 954, Building 77L Philadelphia Business Center, Carderock Division Philadelphia, Pennsylvania 19112-5083 Telephone: (215) 897-1146
(5) For awards issued by Naval Sea Systems Command, Washington Navy Yard:
Commander Naval Sea Systems Command Sea 05M3, 1333 ISAAC Hull Avenue, SE Stop 5160 Washington Navy Yard, District of Columbia (DC) 20376-5160 Telephone: (202) 781-3729
(ii) When first article units are presented to the QAR, provide the Contractor’s certification that the same processes and facilities used to manufacture the first article units shall be used to manufacture the production units.
(iii) Prior to shipping the first article units to the Government testing facility specified in paragraph (a) of the clause FAR 52.209-4 (or resubmitting any first article units after conditional approval or disapproval by the Government testing facility), obtain a statement from the QAR that the first article units have been inspected and determined to comply with the specification requirements.
(4) Prepare shipping containers for first article units in accordance with the following:
(i) Exterior marking and shipping documentation.
(A) Mark packages containing first article units in bold letters, below and to the left of the address, as follows: “First Article Exhibits:
Contract Number [Contractor insert] and Lot/Item Number [Contractor insert];” and
(B) Use a hard copy of the Department of Defense (DD) Form 250 as a packing list on the exterior of the shipping container, in accordance with military standard (MIL-STD) 129, paragraph 5.3, Exterior Container Documentation.
(ii) Interior documentation requirements. Include the following with all shipments of first article units:
(A) Hard copies of the Statement of Inspection and DD Form 250, signed by the QAR;
(B) Copy of the contract, or those portions of the contract that pertain to the Government First Article Test (FAT) requirements;
(C) Copies of test reports, showing actual results;
(D) Material certifications;
(E) Process operations sheets;
(F) Copies of drawings used to manufacture the first article units. (Contractor may mark documents, as appropriate, to restrict from public disclosure and/or from Government use other than for evaluation);
(G) Contractor’s certification that the same processes and facilities used to manufacture the first article units shall be used to manufacture the production units;
(H) Documents required under a contract deliverables requirements list, if applicable; and
(I) Any other documentation required by the contract;
(5)(i) Send all first article units by traceable means (e.g., certified or registered mail, United Parcel Service, Federal Express, etc.).
(ii) At the time first article units are shipped, provide copies of the signed DD Form 250, the QAR Statement of Inspection, and transportation tracking information to the—
(A) Contracting Officer; and
(B) Points of contact identified at paragraph (a)(3)(i)(C) of this clause.
(6) Submit first articles to the Government testing facility identified in paragraph (a) of the clause at FAR 52.209-4, within the number of calendar days from date of contract as specified in paragraph (a) of the clause at FAR 52.209-4; and
(7) Pay all costs incurred for transportation of first article units under this contract; and, if applicable -
(i) Costs of manufacturing and re-testing additional first articles; and
(ii) Administrative costs for re-procurement by the Government.
(b) The Contractor shall enter an offered price in the contract line-item (CLIN) for “Government First Article Test (FAT)” that includes all costs associated with the production and testing of the first articles. Offers that do not cite a separate price for the “Government First Article Test (FAT)” CLIN, or do not specify there is a separate charge for the “Government First Article Test (FAT)”, shall be evaluated under the presumption that there is no separate charge for producing and testing the first article units.
(c) Upon completion of the first article testing, the Government test facility will submit its report of testing in duplicate) to the Contracting Officer and to the points of contact identified at paragraph (a)(3)(i)(C) of this clause.
(d) If first article units are conditionally approved or disapproved, the Government shall take action in accordance with the clause at
FAR 52.209-4.
(1) Final disposition of conditionally approved or disapproved first article units is determined at the discretion of the Government.
(2)(A) Disapproved first article units may be returned to the Contractor at the Government’s discretion, if the Contractor submitted the following information to the Contracting Officer and to the points of contact identified at paragraph (a)(3)(i)(C) of this clause within fifteen
(15) calendar days after receiving notification of disapproval of the first article unit:
(1) Contractor’s complete “Ship To” address; DEFENSE LOGISTICS ACQUISITION DIRECTIVE
(2) Name of Contractor’s point of contact (POC)/addressee;
(3) Phone number of Contractor’s POC; and
(4) Transportation cost codes (e.g., Contractor’s FED-EX, DHL, UPS shipping account numbers, etc.).
(B) In the event the Contractor fails to provide the information required above, the Agency may, at its discretion, dispose of the material.
(End of Clause)
52.209-9019 REQUESTS FOR WAIVER OF FIRST ARTICLE TESTING REQUIREMENTS (SEP 2008) DLAD
(a) The Government reserves the right to waive the first article testing requirement when all the following criteria are met [Offeror shall insert information in space provided below, attach documentation to offer, or provide under separate cover to Contracting Officer.] (1)(i) Source has manufactured the product within the last five (5) years; or
(ii) Identical or similar supplies were previously furnished by the Offeror within the past three (3) years and approved by the Government:
(A) Contract Number(s): ____________________________ Date(s): _________________________________________ Issuing Government Agency(ies): ______________________
ALTERNATIVE PRICES OFFERED IF FIRST ARTICLE TESTING REQUIREMENT IS WAIVED:
ITEM NUMBER: ________________________________
PRICE: _________________________________________
52.209-9024 GOVERNMENT FIT VERIFICATION TESTING (SEP 2008) DLAD
52.209-9025 GOVERNMENT FIT VERIFICATION TESTING APPROVAL (SEP 2008) DLAD
(a) The Contractor shall deliver to be stated on each delivery order as applicable [Contracting Officer insert number of units] units of Lot/Item (as aplicable) [Contracting Officer insert Lot/Item number] within to be stated on each delivery order as applicable [Contracting Officer insert number of days]calendar days from the date of this contract to the Government at to be stated on each delivery order as applicable
[Contracting Officer insert name and address of testing facility] for the purpose of fit verification testing.
(b) Any packages containing Government fit verification testing units shall be marked in bold letters, below and to the left of the address, as follows:
GOVERNMENT FIT VERIFICATION UNITS
Contract Number: [Contractor insert contract number] Lot/Item No: [Contractor insert Lot/Item No.]
(c) Within to be stated on each delivery order as applicable [Contracting Officer insert number of days] calendar days after the Government receives the units for testing on the aircraft, the Contracting Officer shall notify the Contractor, in writing, of the results of Government fit verification testing, e.g., approval, conditional approval or disapproval. The notice of approval or conditional approval shall not relieve the Contractor from complying with all requirements of the specifications and all other terms and conditions of this contract. A notice of conditional approval shall state any further action required of the Contractor. A notice of disapproval shall cite reasons for the disapproval.
52.210-01 MARKET RESEARCH (APR 2011) FAR
52.211-05 MATERIAL REQUIREMENTS (AUG 2000) FAR
252.211-7003 ITEM IDENTIFICATION AND VALUATION (JUN 2011) DFARS
(1) The Contractor shall provide a unique item identifier for the following:
(i) All delivered items for which the Government’s unit acquisition cost is $5,000 or more.
(ii) The following items for which the Government’s unit acquisition cost is less than $5,000:
Contract Line, Subline, or Exhibit Line Item Number / Item Description
(iii) Subassemblies, components, and parts embedded within delivered items as specified in Attachment Number .
252.211-7005 SUBSTITUTIONS FOR MILITARY OR FEDERAL SPECIFICATIONS AND STANDARDS (NOV 2005) DFARS
(4) If the proposed SPI process has been accepted at the facility at which it is proposed for use, but is not yet listed at the Internet site specified in paragraph (b) of this clause, submit documentation of Department of Defense acceptance of the SPI process.
(d) Absent a determination that an SPI process is not acceptable for this procurement, the Contractor shall use the following SPI processes in lieu of military or Federal specifications or standards:
(Offeror insert information for each SPI process) SPI Process:
Facility:
Military or Federal Specification or Standard:
Affected Contract Line Item Number, Subline Item Number, Component, or Element:
52.211-9000 GOVERNMENT SURPLUS MATERIAL (NOV 2011) DLAD
(c) With respect to the surplus material being offered, the Offeror represents that:
(1) The material is new, unused, and not of such age or so deteriorated as to impair its usefulness or safety.
Yes [ ] No [ ] The material conforms to the technical requirements cited in the solicitation (e.g., Commercial and Government Entity (CAGE) code and part number, specification, etc.).
Yes [ ] No [ ] The material conforms to the revision letter/number, if any is cited.
Yes [ ] No [ ] Unknown [ ] If no, the revision offered does not affect form, fit, function, or interface.
Yes [ ] No [ ] Unknown [ ] The material was manufactured by:
(Name) (Address)
(2) The Offeror currently possesses the material. Yes [ ] No [ ] If no, the Offeror must attach or forward to the Contracting Officer an explanation as to how the offered quantities will be secured. If yes, the Offeror purchased the material from a Government selling agency or other source. Yes [ ] No [ ] If yes, provide the information below:
Government Selling Agency
Contract Number
Contract Date (Month, Year)
Other Source
Address Date Acquired (Month, Year)
(3) The material has been altered or modified.
Yes [ ] No [ ] If yes, the Offeror must attach or forward to the Contracting Officer a complete description of the alterations or modifications.
(4) The material has been reconditioned. Yes [ ] No [ ] If yes, (i) the price offered includes the cost of reconditioning/refurbishment.
Yes [ ] No [ ]; and (ii) the Offeror must attach or forward to the Contracting Officer a complete description of any work done or to be done, including the components to be replaced and the applicable rebuild standard. The material contains cure-dated components.
Yes [ ] No [ ] If yes, the price includes replacement of cure-dated components. Yes [ ] No [ ]
(5) The material has data plates attached. Yes [ ] No [ ] If yes, the Offeror must state below all information contained thereon, or forward a copy or facsimile of the data plate to the Contracting Officer.
(6) The offered material is in its original package. Yes [ ] No [ ] (If yes, the Offeror has stated below all original markings and data cited on the package; or has attached or forwarded to the Contracting Officer a copy or facsimile of original package markings.)
Contract Number National Stock Number
(NSN)
Commercial and Government Entity
(Cage) Code
Part Number Other Markings/Data
(7) The Offeror has supplied this same material (National Stock Number) to the Government before.
If yes, (i) the material being offered is from the same original Government contract number as that provided previously.
Yes [ ] No [ ]; and (ii) state below the Government Agency and contract number under which the material was previously provided:
Agency Contract Number
(8) The material is manufacturered in accordance with a specification or drawing.
If yes, (i) the specification/drawing is in the possession of the Offeror. Yes [ ] No [ ];
and (ii) the Offeror has stated the applicable information below, or forwarded a copy or facsimile to the Contracting Officer.
Yes [ ] No [ ] Specitication/Drawing
Number
Revision (if any)
Date
(9) The material has been inspected for correct part number and for absence of corrosion or any obvious defects.
If yes, (i) Material has been re-preserved. Yes [ ] No [ ];
(ii) Material has been repackaged. Yes [ ] No [ ];
(iii) Percentage of material that has been inspected is ______% and/or number of items inspected is _____; and (iv) a written report was prepared. Yes [ ] No [ ] If yes, the Offeror has attached it or forwarded it to the Contracting Officer. Yes [ ] No [ ]
(d) The Offeror agrees that in the event of award and notwithstanding the provisions of the solicitation, inspection and acceptance of the surplus material will be performed at source or destination subject to all applicable provisions for source or destination inspection.
(e) The Offeror has attached or forwarded to the Contracting Officer one of the following, to demonstrate that the material being offered was previously owned by the Government (Offeror check which one applies):
[ ] For national or local sales, conducted by sealed bid, spot bid or auction methods, a solicitation/Invitation For Bid and corresponding DLA Distribution Services 1427, Notice of Award, Statement and Release Document.
[ ] For DLA Distribution Services Commercial Venture (CV) Sales, the shipment receipt/delivery pass document and invoices/receipts used by the original purchaser to resell the material.
[ ] For DLA Distribution Services Recycling Control Point (RCP) term sales, the statement of account or billing document.
[ ] For property sold under the exchange or sale regulation, conducted by sealed bid, auction or retail methods, a solicitation/Invitation for Bid and corresponding DLA Distribution Services Form 1427.
[ ] When the above documents are not available, or if they do not identify the specific NSN being acquired, a copy or facsimile of all original package markings and data, including NSN, Commercial and Government Entity (CAGE) code and part number, and original contract number. (This information has already been provided in paragraph (c)(6) of this clause. Yes [ ] No [ ]) [ ] When none of the above are available, other information to demonstrate that the offered material was previously owned by the Government.
Describe and/or attach.
52.211-9002 PRIORITY RATING (NOV 2011) DLAD
52.211-9004 PRIORITY RATING FOR VARIOUS LONG-TERM CONTRACTS (NOV 2011) DLAD
52.211-9012 OBSOLETE COMPONENTS/MATERIALS (NOV 2011) DLAD
52.211-9014 CONTRACTOR RETENTION OF TRACEABILITY DOCUMENTATION (OCT 2008) DLAD
52.215-02 AUDIT AND RECORDS - NEGOTIATION (OCT 2010) FAR
52.215-08 ORDER OF PRECEDENCE - UNIFORM CONTRACT FORMAT (OCT 1997) FAR
52.215-10 PRICE REDUCTION FOR DEFECTIVE CERTIFIED COST OR PRICING DATA (AUG 2011) FAR
52.215-11 PRICE REDUCTIONS FOR DEFECTIVE CERTIFIED COST OR PRICING DATA - MODIFICATIONS (AUG 2011)
FAR
52.215-12 SUBCONTRACTOR CERTIFIED COST OR PRICING DATA (OCT 2010) FAR
52.215-13 SUBCONTRACTOR CERTIFIED COST OR PRICING DATA - MODIFICATIONS (OCT 2010) FAR
52.215-14 INTEGRITY OF UNIT PRICES (OCT 2010) FAR
52.215-21 REQUIREMENTS FOR CERTIFIED COST OR PRICING DATA AND DATA OTHER THAN CERTIFIED COST OR
PRICING DATA - MODIFICATIONS (OCT 2010) FAR
52.215-21 REQUIREMENTS FOR CERTIFIEDCOST OR PRICING DATA AND DATA OTHER THAN CERTIFIED COST OR
PRICING DATA - MODIFICATIONS (OCT 2010), ALT III (OCT 1997) FAR
(c) Submit the cost portion of the proposal via the following electronic media:
electronic spreadsheet by electronic mail [Insert media format]
52.215-22 LIMITATIONS ON PASS - THROUGH CHARGES - IDENTIFICATION OF SUBCONTRACT EFFORT (OCT 2009) FAR
252.215-7000 PRICING ADJUSTMENTS (DEC 1991) DFARS
252.215-7002 COST ESTIMATING SYSTEM REQUIREMENTS (FEB 2012) DFARS
52.215-9013 PRODUCTION FACILITY CHANGES (NOV 2011) DLAD
52.215-9016 NOTICE TO CONTRACTORS AND DEFENSE FINANCE ACCOUNTING SERVICES (DFAS) (NOV 2011) DLAD
52.216-05 PRICE REDETERMINATION - PROSPECTIVE (OCT 1997) FAR
(c) Price redetermination periods. For the purpose of price redetermination, performance of this contract is divided into successive periods. The first period shall extend from the date of the contract to ________, (see Note (1)) and the second and each s ucceeding period shall extend for ________ [insert appropriate number] months from the end of the last preceding period, except that the parties may agree to vary the length of the final period. The first day of the second and each succeeding period shall be the effective date of price redetermination for that period.
(d) Data submission.
(1) Not more than _______ nor less than ______ (see Note (2)) days before the end of each redetermination period, except the last, the Contractor shall submit—
(i) Pro posed prices for supplies that may be delivered or services that may be performed in the next succeeding period, and—
(A) An estimate and breakdown of the costs of these supplies or services in the format of Table 15-2, FAR 15.408, or in any other form on which the parties may agree;
(B) Sufficient data to support the accuracy and reliability of this estimate; and
(C) An explanation of the differences between this estimate and the original (or last preceding) estimate for the same supplies or services; a nd
(ii) A statement of all costs incurred in performing this contract through the end of the _______________ month (see Note (3)) before the submission of proposed prices in the format of Table 15-2, FAR 15.408 (or in any other form on which the parties m ay agree), with sufficient supporting data to disclose unit costs and cost trends for—
(A) Supplies delivered and services performed; and
(B) Inventories of work in process and undelivered contract supplies on hand (estimated to the extent necessary).
52.216-19 ORDER LIMITATIONS (OCT 1995) FAR
(a) Minimum order. When the Government requires supplies or services covered by this contract in an amount of less than N / A, the Government is not obligated to purchase, nor is the Contractor obligated to furnish, those supplies or services under the contract.
(b) Maximum order. The Contractor is not obligated to honor—
(1) Any order for a single item in excess of $447M ;
(2) Any order for a combination of items in excess of $447M ; or
(3) A series of orders from the same ordering office within 30 days that together call for quantities exceeding the limitation in paragraph (b)(1) or (2) of this section.
(c) If this is a requirements contract (i.e., includes the Requirements clause at subsection 52.216-21 of the Federal Acquisition Regulation (FAR)), the Government is not required to order a part of any one requirement from the Contractor if that requirement exceeds the maximum-order limitations in paragraph (b) of this section.
(d ) Notwithstanding paragraphs (b) and (c) of this section, the Contractor shall honor any order exceeding the maximum order limitations in paragraph (b), unless that order (or orders) is returned to the ordering office within 3 days after issuance, with written notice stating the Contractor’s intent not to ship the item (or items) called for and the reasons. Upon receiving this notice, the Government may acquire the supplies or services from another source.
(End of clause)
52.216-22 INDEFINITE QUANTITY (OCT 1995) FAR
(a) This is an indefinite-quantity contract for the supplies or services specified, and effective for the period stated, in the Schedule. The quantities of supplies and services specified in the Schedule are estimates only and are not purchased by this contract.
(b) Delivery or performance shall be made only as authorized by orders issued in accordance with the Ordering clause. The Contractor shall furnish to the Government, when and if ordered, the supplies or services specified in the Schedule up to and including the quantity designated in the Schedule as the “maximum.” The Government shall order at least the quantity of supplies or services designated in the Schedule as the “minimum.”
(c) Except for any limitations on quantities in the Order Limitations clause or in the Schedule, there is no limit on the number of orders that may be issued. The Government may issue orders requiring delivery to multiple destinations or performance at multiple locations.
(d) Any order issued during the effective period of this contract and not completed within that period shall be completed by the Contractor within the time specified in the order.
This is the start of the file's text. The full file is on GovTribe.