SP330021B0002A0001-AMENDMENT 0001.pdf

PDF 357 KB Posted

Attached to
Building 732 Sprinkler System Repairs Federal contract opportunity
Solicitation number
SP330021B0002
Issued by
Defense Logistics Agency Distribution

View the file

Other files for this federal contract opportunity

Other files attached to Building 732 Sprinkler System Repairs, newest first.
File Type Posted
OF_1419 Bid Abstract Pg1.pdf PDF
OF_1419A BID ABSTRACT - Pg2.pdf PDF
Site Vister ATTENDANCE SHEET.pdf PDF
ATTACHMENT 6 - DL1818.pdf PDF
ATTACHMENT 5 - SF24 - Bid Bond.pdf PDF
ATTACHMENT 2 - 3976 Combined Drawings 06242021.pdf PDF
ATTACHMENT 1 -3976 Combined Specifications 6-24-21.pdf PDF
ATTACHMENT 3 - 3976 Submittal Register Combined 3-24-21.pdf PDF
ATTACHMENT 4 - CONSTRUCTION WAGE RATE.pdf PDF
SP330021B0002.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1. CONTRACT ID CODE

2. AMENDMENT/MODIFICAITON NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicble)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICIATION NO.

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 11)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a)By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPIRATION DATA (If required)

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

NSN 7540-01-152-8070

Previous edition unusable

SP330021B0002

Building 732 Sprinkler System Repairs

AMENDMENT 0001

DATED 8/17/2021

Amendment 0001 is hereby incorporated into SP330021B0002 for the Building 732 Sprinkler System Repairs, DLA Distribution Susquehanna and shall become part of any contract issued.

Amendment 0001 is being issued to answer vendor’s questions.

Question 1: The drawings call for Schedule 10 pipe and Specifications call for Schedule 40 pipe. Please confirm which is to be used.

Answer 1: It is DLA’s standard to use Schedule 40 pipe for all sprinkler piping however, all existing piping within Building 732 was installed with Schedule 10 pipe. Therefore, for this project only, DLA will allow the use of Schedule 10 pipe.

Question 2: I notice pipe is to be painted. Will powder coating of the piping with a red finish be acceptable?

Answer 2: Unfortunately, that will not be acceptable. All sprinkler piping within Building 732 has been painted white and we want to maintain this color for all new piping as well. We would accept a white powder coating finish.

Question 3: The specification calls for all sprinkler system components to be painted. The grooved fittings come with a factory orange color coating. Will this be acceptable?

Answer 3: We are familiar with Victaulic’s color standard, but we want to remain consistent with the existing building piping. All existing piping including fittings has been painted white and so this will be required for this installation as well.

Question 4: Will all pipe hangers also be required to be painted?

Answer 4: In reviewing pictures of the existing installation, we find that most supports for sprinkler piping have been painted white as well. As such, we will require that all supports for new sprinkler piping be painted white.

Question 5: Valve tags and updated hydraulic riser plaques are required. Will the pipe also be required to have pipe labels installed?

Answer 5: Beyond the NFC Code requirement for plaques and signs on any specific features such as “Inspectors Test Valve”, etc., no additional pipe labels will be required.

Question 6: Will earthquake type bracing be required for the new 4” sprinkler mains?

Answer 6: No, seismic design of new sprinkler piping is not required.

Question 7: I see the Bid Bond is required. Will there also be requirements for Payment & Performance Bonds?

Answer 7: Yes

Question 8: I see notes in the specifications regarding system flushing. Will all these systems be required to be flushed/chlorinated?

Answer 8: Specification Section 21 95 00.00 10, Paragraph 3.1.1 indicates “systems that are required to be

SP330021B0002

Building 732 Sprinkler System Repairs

AMENDMENT 0001

DATED 8/17/2021

flushed….” However, in Section 01 11 00, Paragraph 1.4.1, it is indicated that there is no flushing of systems included (or required) in the scope of work for this project. In other words, no flushing is required on this project.

Question 9: The system(s) would be drained and recharged at the end of each work day. Will a fire watch be required while the work is being performed during the day? If so, who is going to be responsible for this?

Answer 9: The quick answer to this questions is yes and yes. A fire watch is required and it will be the contractor’s responsibility. Please reread Specification 21 95 00.00 10 – especially paragraph 3.3 regarding the requirements for sprinkler system impairment.

Question 10: I noticed a 180 day completion schedule from the time of notice to proceed. What is the anticipated “notice to proceed” date?

Answer 10: Once the Performance/Payment bonds and the Certificate Of Liability Insurance have been reviewed and are determined to be acceptable- a Notice To Proceed will then be issued (approximately 14 days after the award).

END OF AMENDMENT 0001

SP330021B0002 A0001.Page 1
Amend 0001 SP330016B0016 for FBO
SP3300-15-R-5004 0003 page 1

Amendment 0001 - 732 SPRINKLER

IDCode:
Page: 1
Pages: 3
Text4: AMENDMENT/MODIFICATION NO.
AmendNo: 0001
ReqNo:
ProjNo:
IssCode: SP3300
IssuedBy: DLA Distribution

Acquisition Operations, J-7 Mifflin Avenue, Bldg 430 New Cumberland, PA 17070

AdmCode: MPGADM
AdminBy: POC: Mogen Gilson

717-770-4757 (P)

MOGEN.GILSON@DLA.MIL

ContName:
ContStrt:
ContCnty:
ContSt:
ContZIP:
Code:
FacCode:
SolChgYs: Yes
SolChgNo: Off
SolAmdNo: SP3300-21-B-0002
AmendDate: 07/23/21
ModNo:
ModDate:
NoCopies: 1
Amended: Yes
OffrExt: Off
OffrNoEx: No
ChgeOrd: Off
ChgeOrder:
Modify: Off
SuppAgre: Off
SuppAuth:
ModOthr: Off
OthrSpec:
NoReq: Off
Require: Off
Copies:
Descript:

SEE CONTINUATION PAGE(S)

SignName:
SignTitl:
ContDate:
CoName:
CoTitle:
CODate:
Text1: August 17, 2021
Text2:
Text3:

File details come from the government source that posted it. Updated .