ATTACHMENT_2_-_SCHEDULE_OF_SUPPLIES.docx

DOCX document 17 KB Posted

Attached to
NITROGENE/ACETYLENE RENTAL Federal contract opportunity
Solicitation number
SP330019Q0097
Issued by
Defense Logistics Agency Distribution

View the file

Other files for this federal contract opportunity

Other files attached to NITROGENE/ACETYLENE RENTAL, newest first.
File Type Posted
SF_30_AMENDMENT_0001.pdf PDF
ATTACHMENT_1_-_STATEMENT_OF_WORK.pdf PDF
Combined_Synopsis-Solicitation_-_SP330019Q0097.doc DOC document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

For Official Use Only

ATTACHMENT 2 SCHEDULE OF SUPPLIES

PERIOD OF PERFORMANCE:

8/19/2019 through 8/18/2020 – BASE YEAR 8/19/2020 through 8/18/2021 - OPTION YEAR ONE 8/19/2021 through 8/18/2022 - OPTION YEAR TWO

Base Year CLINS:

CLIN 0001 – MONTHLY RENTAL CHARGES FOR FOURTEEN (14) HIGH PURITY NITROGEN CYLINDERS. OPEN SHED LOCATION.

$______________ PER MONTH x 12 MONTHS (MO) = $______________

CLIN 0002 – HIGH PURITY NITROGEN CYLINDER EXCHANGE, REPLACE EMPTY CYLINDERS WITH FULL CYLINDERS ON AN AS-NEEDED BASIS. OPEN SHED LOCATION.

$ PER EXCHANGE x 30 EXCHANGES (UN) (ESTIMATED, AS-NEEDED BASIS) = $____________

CLIN 0003 – GOVERNMENT-OWNED 255 CUBIC FOOT NITROGEN CYLINDERS. CYLINDER REFILL ON AN AS-NEEDED BASIS. CONTRACTOR SHALL REFILL CYLINDERS AT CONTRACTOR’S LOCATION AND RETURN SAME CYLINDERS BACK TO GOVERNMENT LOCATION WITHIN THREE

(3) DAYS FROM DATE OF PICKUP. The Government tests its own cylinders. If the Contractor discovers that an empty cylinder is "out of test date" then Contractor shall return empty cylinder to Government. BUILDING 3 LOCATION.

$___________ PER REFILL x 160 REFILLS (UN) (ESTIMATED, AS-NEEDED BASIS) =

$ __________________TOTAL PRICE

CLIN 0004 MONTHLY RENTAL CHARGES FOR ONE (1) ACETYLENE CYLINDER (150-300 SOURCE SELECTION INFORMATION SEE FAR 2.101 AND 3.104 CUBIC FOOT) CYLINDER. BUILDING 3 LOCATION.

$__________ PER MONTH x 12 MONTHS (MO) = $__________

CLIN 0005 – CYLINDER EXCHANGE, REPLACE EMPTY ACETYLENE CYLINDER WITH FULL CYLINDER ON AN AS-NEEDED BASIS. BUILDING 3 LOCATION.

$ __________PER EXCHANGE x 1 EXCHANGE (UN) (ESTIMATED, AS-NEEDED BASIS) =

CLIN 0006 – SHIPPING CHARGES. ESTIMATED BREAKDOWN AS FOLLOWS: FIVE (5) HIGH PURITYNITROGEN SHIPMENTS. EIGHT (8) REGULAR NITROGEN SHIPMENTS. ONE (1) ACETYLENE SHIPMENT.

$______________PER SHIPMENT x 14 SHIPMENTS (JB) (ESTIMATED, AS-NEEDED BASIS) =

CLIN 0007 – HAZMAT FEES. ESTIMATED BREAKDOWN AS FOLLOWS: FIVE (5) HIGH PURITY NITROGEN SHIPMENTS. EIGHT (8) REGULAR NITROGEN SHIPMENTS. ONE (1) ACETYLENE SHIPMENT.

$________________PER SHIPMENT x 14 SHIPMENTS (JB) (ESTIMATED, AS-NEEDED BASIS) = $ $_______________

TOTAL AMOUNT FOR CLINS 0001-0007: $ __________________

Option Year One CLINS:

CLIN 1001 – MONTHLY RENTAL CHARGES FOR FOURTEEN (14) HIGH PURITY NITROGEN CYLINDERS. OPEN SHED LOCATION.

$______________ PER MONTH x 12 MONTHS (MO) = $______________

CLIN 1002 – HIGH PURITY NITROGEN CYLINDER EXCHANGE, REPLACE EMPTY CYLINDERS WITH FULL CYLINDERS ON AN AS-NEEDED BASIS. OPEN SHED LOCATION.

CLIN 1003 – GOVERNMENT-OWNED 255 CUBIC FOOT NITROGEN CYLINDERS. CYLINDER REFILL ON AN AS-NEEDED BASIS. CONTRACTOR SHALL REFILL CYLINDERS AT CONTRACTOR’S LOCATION AND RETURN SAME CYLINDERS BACK TO GOVERNMENT LOCATION WITHIN THREE

(3) DAYS FROM DATE OF PICKUP. The Government tests its own cylinders. If the Contractor discovers that an empty cylinder is "out of test date" then Contractor shall return empty cylinder to Government. BUILDING 3 LOCATION.

$___________ PER REFILL x 160 REFILLS (UN) (ESTIMATED, AS-NEEDED BASIS) =

$ __________________TOTAL PRICE

CLIN 1004 MONTHLY RENTAL CHARGES FOR ONE (1) ACETYLENE CYLINDER (150-300 SOURCE SELECTION INFORMATION SEE FAR 2.101 AND 3.104 CUBIC FOOT) CYLINDER. BUILDING 3 LOCATION.

$__________ PER MONTH x 12 MONTHS (MO) = $__________

CLIN 1005 – CYLINDER EXCHANGE, REPLACE EMPTY ACETYLENE CYLINDER WITH FULL CYLINDER ON AN AS-NEEDED BASIS. BUILDING 3 LOCATION.

$ __________PER EXCHANGE x 1 EXCHANGE (UN) (ESTIMATED, AS-NEEDED BASIS) =

CLIN 1006 – SHIPPING CHARGES. ESTIMATED BREAKDOWN AS FOLLOWS: FIVE (5) HIGH PURITYNITROGEN SHIPMENTS. EIGHT (8) REGULAR NITROGEN SHIPMENTS. ONE (1) ACETYLENE SHIPMENT.

$______________PER SHIPMENT x 14 SHIPMENTS (JB) (ESTIMATED, AS-NEEDED BASIS) =

CLIN 1007 – HAZMAT FEES. ESTIMATED BREAKDOWN AS FOLLOWS: FIVE (5) HIGH PURITY NITROGEN SHIPMENTS. EIGHT (8) REGULAR NITROGEN SHIPMENTS. ONE (1) ACETYLENE SHIPMENT.

$________________PER SHIPMENT x 14 SHIPMENTS (JB) (ESTIMATED, AS-NEEDED BASIS) = $ $_______________

TOTAL AMOUNT FOR CLINS 1001-1007:

Option Year Two CLINS:

CLIN 2001 – MONTHLY RENTAL CHARGES FOR FOURTEEN (14) HIGH PURITY NITROGEN CYLINDERS. OPEN SHED LOCATION.

$______________ PER MONTH x 12 MONTHS (MO) = $______________

CLIN 2002 – HIGH PURITY NITROGEN CYLINDER EXCHANGE, REPLACE EMPTY CYLINDERS WITH FULL CYLINDERS ON AN AS-NEEDED BASIS. OPEN SHED LOCATION.

CLIN 2003 – GOVERNMENT-OWNED 255 CUBIC FOOT NITROGEN CYLINDERS. CYLINDER REFILL ON AN AS-NEEDED BASIS. CONTRACTOR SHALL REFILL CYLINDERS AT CONTRACTOR’S LOCATION AND RETURN SAME CYLINDERS BACK TO GOVERNMENT LOCATION WITHIN THREE

(3) DAYS FROM DATE OF PICKUP. The Government tests its own cylinders. If the Contractor discovers that an empty cylinder is "out of test date" then Contractor shall return empty cylinder to Government. BUILDING 3 LOCATION.

$___________ PER REFILL x 160 REFILLS (UN) (ESTIMATED, AS-NEEDED BASIS) =

$ __________________TOTAL PRICE

CLIN 2004 MONTHLY RENTAL CHARGES FOR ONE (1) ACETYLENE CYLINDER (150-300 SOURCE SELECTION INFORMATION SEE FAR 2.101 AND 3.104 CUBIC FOOT) CYLINDER. BUILDING 3 LOCATION.

$__________ PER MONTH x 12 MONTHS (MO) = $__________

CLIN 2005 – CYLINDER EXCHANGE, REPLACE EMPTY ACETYLENE CYLINDER WITH FULL CYLINDER ON AN AS-NEEDED BASIS. BUILDING 3 LOCATION.

$ __________PER EXCHANGE x 1 EXCHANGE (UN) (ESTIMATED, AS-NEEDED BASIS) =

CLIN 2006 – SHIPPING CHARGES. ESTIMATED BREAKDOWN AS FOLLOWS: FIVE (5) HIGH PURITYNITROGEN SHIPMENTS. EIGHT (8) REGULAR NITROGEN SHIPMENTS. ONE (1) ACETYLENE SHIPMENT.

$______________PER SHIPMENT x 14 SHIPMENTS (JB) (ESTIMATED, AS-NEEDED BASIS) =

CLIN 2007 – HAZMAT FEES. ESTIMATED BREAKDOWN AS FOLLOWS: FIVE (5) HIGH PURITY NITROGEN SHIPMENTS. EIGHT (8) REGULAR NITROGEN SHIPMENTS. ONE (1) ACETYLENE SHIPMENT.

$________________PER SHIPMENT x 14 SHIPMENTS (JB) (ESTIMATED, AS-NEEDED BASIS) = $ $_______________

TOTAL AMOUNT FOR CLINS 2001-2007: $_______________ __________________

NOTE:

The nitrogen cylinders that we use at our facility are DOT 3AA 2015 and we have one DOT 3AA 2265 cylinder. These particular cylinders were at one time medical oxygen cylinders and they were downgraded to Nitrogen cylinders. These Nitrogen Cylinders are used to hold the Nitrogen High Purity Grade: 99.995%.

1. The other nitrogen cylinders are DOT 3AA2400C are located in the open storage areas and they are used to hold the Zero Grade: 99.998%.

2. The Nitrogen gas supplier should be able to determine the psi for each cylinders based on the cylinder type, (DOT 3AA2015, DOT 3AA 2265, and DOT 3AA2400C) dimensions and pressure capacities for each high pressure steel cylinders.

3. High Purity Grade : 99.995% Cubic feet : 230

4. Zero Grade : 99.998% Cubic feet: 305

5. Purified Acetylene 99.6% Cubic feet: 300

Source Selection Information See 2.101 and 3.104 For Official Use Only