SOW092222fdBoilerTubes.doc
DOC document 35 KB Posted
- Attached to
- REPLACE BOILER TUBES INSIDE STEAM BOILER Federal contract opportunity
- Solicitation number
- 140A0923Q0012
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Attachment_No_6___Boiler_Serial_and_Model_No__0001.docx | DOCX document | |
| Sol_140A0923Q0012_Amd_0001.pdf | ||
| Location_plan_for_boiler_retube_11_21_11.pdf | ||
| CombinedSynopsis_BoilerTube_Replacement.doc | DOC document | |
| BuyIndianRepresentation_081922.pdf | ||
| WageRates_Apache_Boilers.pdf | ||
| Sol_140A0923Q0012.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BIE, Navajo District Office of Facility Management Scope of Work Boiler Tube Replacement for Williams & Davis Boiler # 6791
Building #501, Ft. Defiance, Arizona Contact:
David Allison, Facility Operation Specialist BIE, Navajo District P.O. Box 110, Ft. Defiance, Arizona, 86504 Office: (928) 729-7309 Cell: (928) 206-7669 Fax: (928) 729-7313 Overview:
Facility maintenance crew discovered a leak on our Williams & Davis steam boiler located in Ft. Defiance, Arizona. Upon inspection of the boiler, we have determined that all seventy-six (76) fire tubes within the boiler need replacement.
Scope of Work:
The contractor shall furnish all supervision, labor, materials, equipment and transportation to replace seventy-six (76) 2-1/2” x 96” boiler tubes on one Williams and Davis boiler. Contractor shall comply with all manufacturer’s installation specifications.
Work Requirements:
· Contractor shall notify the agency facility management office of overall project schedule.
· Contractor shall supply and install seventy-six (76) 2-1/2” OD x 96”, 0.105 ml (12 Ga.) SA-178-A boiler tubes on one Williams and Davis boiler.
· Contractor shall perform a hydrostatic test upon installing all fire tubes.
· Contractor shall close the boiler, fire the boiler and check the boiler/burner operation.
· Contractor will be required to work during the week Monday through Friday, with the option to work longer hours per day.
· Agency local maintenance staff will open the boiler front and back, and drain the boiler
· If additional deficiencies are found, an additional quote will be required for additional repair work.