SOW_Transformer_Installation.pdf
PDF 150 KB Posted
- Attached to
- ND GARRISON DAM INSTALLATION OF TWO TRANSFORMERS Federal contract opportunity
- Solicitation number
- 140FS225Q0033
About this file
This is a Statement of Work (SOW) for the removal and installation of two electrical transformers at the Garrison Dam National Fish Hatchery in Riverdale, ND, due to a lightning strike. The contractor must remove existing transformers and install two reconditioned transformers behind the shop building, with work to be completed prior to March 21, 2025, subject to transformer delivery.
Key requirements include: contractor must be licensed and certified in North Dakota to install electrical transformers; must follow all municipal, federal, state and county regulations; must conduct a site visit prior to installation; and provide all equipment and materials needed for installation. Work hours are Monday through Friday 8:00 AM to 4:30 PM. The government will provide restrooms, electricity, and water during the work. Quality control must meet industry standards, and acceptance is contingent upon U.S. Fish and Wildlife Service representatives determining the work to be acceptable and in good working order.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140FS225Q0033.pdf | ||
| Wage_Determination_2015-5383_Revision_23_2024-07-22_McLean_County_North_Dakota.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
140FS225Q0033 Removal and Installation of Transformers Page 1 of 3 Garrison Dam National Fish Hatchery
1. General:
1.1 Garrison Dam National Fish Hatchery (NFH), 530 Hatchery Rd, Riverdale, ND 58565. Service, has a requirement to replace and install two electrical transformers behind shop building due to lightning strike.
1.2 Purpose/End Application: This project is to remove the existing two transformers and install two reconditioned electrical transformers for the shop building.
1.3 Contractor Qualifications: The contractor must be appropriately licensed and certified within the state of North Dakota to install electrical transformers.
1.4 Other: The contractor must follow all associated regulations and laws including: Municiple, Federal, State, and County.
2. Place of Performance and Period of Performance
2.1 Work is to be performed at Garrison Dam National Fish Hatchery, 530 Hatchery Rd, Riverdale, ND
58565.
2.2 This project needs to be completed prior to March 21, 2025, subject to the delivery of the two transformers.
2.3 Normal duty hours Monday thru Friday 8:00 a.m. - 4:30 p.m. In the event of emergencies, Contractor shall provide contact information.
2.4 Non-duty hours include week nights, weekends, and Government holidays (New Year’s Day, Martin
Luther King JR.s’s Birthday, Memorial Day, Juneteenth, Independence Day, Labor Day, Columbus Day, Veteran’s Day, Thanksgiving Day, Christmas Day).
3. Scope
3.1 Contractor shall remove existing transformers and install two reconditioned transformers.
3.2 Contractor shall install two new electrical transformers that will be delivered to the station prior to installation. These transformers must meet all Municiple, Federal, State, and County regulations and laws.
3.3 The contractor must visit the site prior to installation.
4. Deliverables and/or Delivery Schedule:
4.1 The contractor shall provide all equipment and materials required for installation and functionality of the two transformers.
140FS225Q0033 Removal and Installation of Transformers Page 2 of 3
5. Data Management Plan (DMP) N/A
6. Government-Furnished Equipment (GFE) / Government-Furnished Information (GFI)
6.1 Garrison Dam NFH will provide restrooms, electricity, and water for the contractor to using while the contracted work is being completed.
6.2 Identify any limitations. N/A
7. Evaluation and Acceptance
7.1 The contractor will be evaluated as detailed herein. Government acceptance is contingent upon:
designated U.S. Fish and Wildlife Service representative(s) determining the work to be acceptable and in good working order.
8. Quality Control/Quality Assurance:
8.1 For commercial supplies reference clauses for inspection and acceptance. Where appropriate, QC will be maintained according to industry standards and made available to the agency with the contractor’s proposal.
8.2 Identify and detail measures for assessing quality control and acceptance; each requirement is unique and a table format is visually friendly and may be desirable.
9. Technical Coordinator:
9.1 Primary Technical Point of Contact:
Aaron Von Eschen
Project Leader
Garrison Dam National Fish Hatchery Complex
530 Hatchery Rd
Riverdale, ND 58565.
Office: 701-654-7451 aaron_voneschen@fws.gov
9.2 Alternate Technical Point of Contact:
Kristopher “Kris” Johnson
Facility Management Coordinator (FMC)
Asset Management Coordinator (AMC)
U.S. Fish and Wildlife Service
Fish and Aquatic Conservation (FAC) mailto:aaron_voneschen@fws.gov
140FS225Q0033 Removal and Installation of Transformers Page 3 of 3
1380 South 2350 West
Vernal, UT 84078
Cell: 435-299-5150
Office: 435-789-0351 ext. 16 kristopher_b_johnson@fws.gov mailto:kristopher_b_johnson@fws.gov