SOW_Replace_Generator_and_UPS_at_FR_Headquarters_11_pgs.pdf
PDF 1 MB Posted
- Attached to
- REPLACE GENERATOR AND UPS AT FR HQ Federal contract opportunity
- Solicitation number
- 140P5323Q0037
About this file
This statement of work outlines requirements for replacing a generator, fuel tank, and uninterruptible power supply at the Fort Raleigh National Historic Site headquarters building. The project involves removing the existing 31-year-old generator and 1991 fuel tank, installing a new 100KW generator, 2,000 gallon double-walled fuel tank, and similar tower-style UPS. Additional tasks include electrical connections, testing, fencing, and ensuring compliance with applicable codes. The performance period is within normal business hours under the oversight of the contracting officer representative. Bidders must demonstrate at least five years of relevant experience and submit qualifications, schedules, and product data for review prior to contract award under the related solicitation for this work issued by the National Park Service Southeast Region.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| corrected_Price_Schedule_1_page_0002.pdf | ||
| Sol_140P5323Q0037_Amd_0002.pdf | ||
| Price_Schedule_1_page_0001.pdf | ||
| Sol_140P5323Q0037_Amd_0001.pdf | ||
| dba_wages_4_pages.pdf | ||
| Price_Schedule_1_page.pdf | ||
| 003_Form_2_pges_3_.pdf | ||
| 002_Form_1___Past_Performance_Quesionnaire_1_page.pdf | ||
| Sol_140P5323Q0037.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CAPE HATTERAS NATIONAL SEASHORE
Fort Raleigh North Carolina
STATEMENT OF WORK:
Replace Generator and UPS at Fort Raleigh Headquarters Building
NATIONAL PARK SERVICE
Southeast Region
2 | P a g e
TABLE OF CONTENTS
TABLE OF CONTENTS
1.0 BACKGROUND/ EXISTING CONDITIONS..…………………………………………………..………………3
2.0 OBJECTIVES………………………………………………………………………………….…….…………….3
3.0 PLACE OF PERFORMANCE
4.0 TASKS/SPECIFICATIONS ..…………………………………...…………………….………………...………3,4
5.0 WARRANTIES………………………………………………………………….……………..………………….5
6.0 DELIVERARY
7.0 GOVERNMENT FURNISHED EQUIPMENT
8.0 SECURITY
9.0 SPECIAL MATERIAL REQUIREMENTS
10.0 OTHER UNIQUE REQUIREMENTS…...…………………………………………...………...………...……6,7
11.0 QUALITY ASSURANCE………………………………………………………..…………...…………….……7
12.0 SUBMITTALS ....……………………………………………………………………………….……….………7
13.0 BARRIERS & RESOURCE PROTECTION MEASURES……………………...………………………….…..8
14.0 PICTURES & DRAWINGS………………………………………….…………………………………8,9,10,11
3 | P a g e
1.0 BACKGROUND AND EXISTING CONDITIONS:
Fort Raleigh Headquarters building is used daily for permanent, term and seasonal employees and is the primary building for operations and management of the Cape Hatteras National Seashore, Fort Raleigh National Historic Site and The Wright Brothers National Monument. This project will replace a generator, fuel tank and Uninterruptible Power Supply (UPS) for the headquarters building. The generator is used as backup power for all power outages at Fort Raleigh National Historic Site to maintain operational capabilities of the headquarters offices. The existing generator was installed in 1991 and has an estimated design life of 20 years; this unit is 31 years old. The existing generator is a diesel 90KW Three Phase generator with and automatic switching unit that powers a specific portion of the headquarters building.
The existing generator is currently located inside of an outbuilding that houses the generator and the fuel tank that supports this generator. This existing fuel tank is not double walled or properly insulated.
2.0 OBJECTIVE:
Replace the current 31-year-old Three Phase 90 KW diesel generator with a new Three phase 100 KW diesel generator that includes an enclosed overcurrent protection device in the same location, install a new 2,000 gallon, double walled and insulated above ground fuel storage tank on a concrete pad in the designated space, replace the existing Uninterruptable Power Supply (UPS) with a new UPS, and perform all operation and functional testing for the new generator and the new UPS. The replacement includes all required electrical connections, disconnects, exhaust for the generator and multiple operational checks for the newly installed generator and UPS.
3.0 PLACE OF PERFORMANCE:
Fort Raleigh Headquarters Building – 1401 National Park Drive, Manteo, NC 27954
4.0 TASKS/SPECIFICATIONS:
4.1 Remove existing 90KW generator
4.1.1 Disconnect old 90KW generator from existing fuel tank.
4.1.2 Disconnect old 90KW generator from existing power connection to headquarters building.
4.1.3 Remove and dispose the currently used 90KW generator offsite. Do not abandon in place any portion on the existing generator.
4.1.4 Clean the floor of outbuilding and surrounding area to prepare for installation of new generator.
4.2 Remove existing fuel tank.
4.2.1 Recover fuel from existing fuel tank.
4.2.2 Remove and dispose the currently used fuel tank and system offsite. Do not abandon in place any portion of the existing fuel tank.
4.2.3 Clean the floor of outbuilding and surrounding area to prepare for installation of new generator.
4.3 Install new 12x10 concrete pad adjacent to existing outbuilding.
4 | P a g e
4.3.1 Install a new concrete 12’ X 10’ X 6” thick fiber reinforced concrete pad in location identified in the drawing.
4.3.1.1 Concrete pad shall be 4,000 PSI strength with fiber reinforcement
4.3.1.2 Concrete pad shall have a 5 LB/CY CNI admixture
4.3.1.3 Reinforcement shall be 1.6 mix welded wire fabric (WWF)
4.4 Install new 2,000 gallon above ground fuel storage tank on new concrete pad adjacent to existing outbuilding.
4.4.1 Install new 2,000 gallon double walled above ground metal or concrete fuel storage tank with approximate dimensions of 10’ X 8’ on the newly installed concrete pad adjacent to existing outbuilding.
4.4.1.1 Tank shall have all required overfill prevention and alarms.
4.4.2 Trench and bury all required new cabling and fuel lines leading from the new tank to the new generator in the existing outbuilding.
4.4.2.1 The buried fuel lines shall be double walled fuel piping with secondary containment and be buried at least 1 foot deep.
4.4.2.1.1 Approximately 1 inch below the surface a detectable fuel line marker tape that is APWA approved (yellow) shall be buried following the exact path of the newly installed fuel line.
4.4.3 Connect all fuel lines and cabling to the new generator.
4.4.3.1 Install new quarter turn valves on both the fuel supply and return lines at the tank and at the generator.
4.4.4 Activate and test the newly installed fuel lines for leaks and proper operation.
4.4.5 Reseed the grass where the cables were buried using preapproved grass seed mixture.
4.4.6 Fill new fuel tank – use existing reclaimed fuel from the old fuel tank and then top off with new fuel.
4.5 Install new Three Phase 100 KW diesel generator
4.5.1 Install new Three Phase 100 KW generator in existing outbuilding in the same general location where the old generator was installed.
4.5.1.1 The generator radiator shall be connected by sheet metal to the existing load bank.
4.5.2 Connect new generator to fuel tank.
4.5.3 Connect all required attachments for proper operation of the new generator.
4.5.3.1 Fasten the generator to the concrete floor using a minimum of 6 each ½ red head wedge type concrete bolts.
4.5.4 Connect the new generator to the power connection for the headquarters building.
4.5.5 Clean the floor of outbuilding and surrounding area.
4.6 Install a new transfer switch that is compatible with the newly installed generator.
4.6.1 This automatic switching unit must be capable of handling all load requirements and be 100% compatible with the newly installed generator.
4.7 Test New Generator
5 | P a g e
4.7.1 Perform initial generator installation operational testing to include startup and shutdown under normal load conditions.
4.7.1.1 Provide load readings and operational status checks to COR
4.7.1.2 Provide a date and time for generator testing to the COR. COR
(and/or designated representative(s) by the COR shall be present for initial generator testing.
4.7.1.3 Perform a 1-hour long load test on the new generator to ensure there are no issues.
4.7.1.4 Resolve any startup or shutdown issues.
4.7.2 Provide all operational manuals, parts manuals, instructions, and manufacturing specifications upon completion to the COR
4.8 Remove Uninterrupted Power Supply- (UPS)
4.8.1 Remove the current Eaton 9355-30 UPS system inside the mailroom of the Fort
Raleigh Headquarters building
4.9 Install a new similar tower style UPS with the same capabilities as the existing unit. (See attached photos)
4.9.1 After installing new UPS, perform at least 3 full operational checks to ensure proper operation and functionality as described in the product specifications.
4.9.1.1 The COR or designated representative must be present and notified 24 hours in advance of planned operational tests.
4.9.2 Record the # of Amps per leg on each test and provide these readings to the COR
4.9.3 Provide all UPS operational manuals, instructions, and manufacturing specifications upon completion to the COR
4.10 Install new permanent wood fencing
4.10.1 Install new Western Red Cedar wood fence to match the existing vertical plank fencing around 3 sides (two sides will be new and one side will use existing fence) of the new 12’ X 10’ concrete pad that matches the current style, size, and materials of the nearby existing fence. (See Pictures on section 14.3)
4.10.2 Ensure the new fence is the same height, shape, style and is permanently installed in a way that it’s enclosing (on three sides) the new concrete pad and fuel tank to help obscure viewing of the new tank and concrete pad as indicated in the provided drawing.
4.10.2.1 The open end of this fence will be the end facing the generator building.
4.10.3 Stain the fence to match the current color and style of the surrounding neighboring fence.
5.0 WARRANTIES
5.1 A One-Year warranty is required on all contractor and sub-contractor labor, which does not include the individual manufacturer’s part or product implied warranties.
6 | P a g e
5.2 At least a One-Year manufacturer’s warranty is required on all parts installed. All generator and UPS parts will be installed and applied in accordance with the manufacturer’s instructions/specifications to obtain full manufacturer’s warranty
6.0 DELIVERY:
6.1 Deliver materials to the project site in original containers with seals unbroken and labeled with manufacturer's name, product brand name and type, date of manufacture, approval or listing agency markings, and directions for storing and installation
6.2 Delivery of materials to the park will be brought in when needed. Items stored outside will be done at the Contractor’s own risk. Use and storage of a work trailer may be coordinated with the COR.
7.0 GOVERNMENT-FURNISHED EQUIPMENT:
7.1 No Government equipment will be provided. Water is available at the headquarters building via exterior hose bibs. Electricity is also available via exterior receptacles.
8.0 SECURITY:
8.1 All access to the site will be during normal business hours (M-F 7:00 to 5:00 PM) unless temporarily approved by the COR. An escort will be provided during any necessary entry into non-public or secure areas. No work will be accomplished during federal holidays, during inclement weather, in advent of an emergency or during planned park events.
9.0 SPECIAL MATERIAL REQUIREMENTS:
9.1 The Contractor must submit for the government approval all products to be used on this project prior to purchase or installation.
10.0 OTHER UNIQUE REQUIREMENTS:
10.1 This work is to be conducted with preservation of current storage unit in mind. Care must be used when demolishing, removing, repairing, and replacing building materials so as not to cause damage to building fabric.
10.2 This site is part of the Fort Raleigh National Historic Site. Therefore, additional care must be taken while working around visitor areas. No obscene language on clothing will be allowed. Appropriate clothing and shoe wear must be worn inside of the park’s areas.
No smoking or tobacco products in or around the buildings (within 50 feet of buildings or entrances). The COR will show the crew members where the established smoking areas are located. No inside lunch areas are available. Clean-up will be accomplished 45 minutes prior to schedule closing time. No trash or debris will remain in the work site overnight. Dumpster locations if needed will be coordinated by the COR and is the sole responsibility of the contractor. Contractor’s vehicles will be parked at the discretion and coordination of the COR to prevent impact on the visiting public.
7 | P a g e
10.3 During the demolition and construction phases of the project, work will be done to prevent the greatest impact on the visiting public and occupants. Areas that need to be closed will be coordinated with the COR.
10.4 The contractor will provide all technical support, materials, tools, equipment, and manpower required complete the project. The contractor is responsible for verifying existing conditions and ensuring that all parts used are correct. Refer to the Technical Evaluation Statement.
10.5 All conductors must be copper, and the entire installation shall meet all requirements of the 2023 NEC (National Electric Code).
11.0 QUALITY ASSURANCE:
11.1 Contractor shall maintain a qualified crew throughout the duration of the project and ensure quality control. Only qualified journeypersons shall be engaged in work.
Apprentices may be used provided they work under the direct supervision of a qualified journeyperson. A qualified crew will consist of the project manager, journeymen, and apprentices.
11.2 The services to be performed by the contractor shall be inspected by the Contracting
Officer Representative, the COR.
11.3 All work shall comply with the policies and standards of the governing bodies and applicable regulations, which include but are not limited to:
11.3.1 State and Local Codes (latest addition)
11.3.2 International Building Code (IBC, latest addition)
11.3.3 Occupational Safety and Health Act (OSHA, latest addition)
11.4 The contractor shall have a minimum of 5 years’ experience and expertise of successfully completed projects in:
11.4.1 Generator Repairs and Replacements
11.4.2 Uninterruptible Power Supplies
11.5 The Contractor must submit proof of experience by providing a list of references for projects completed on generators, uninterrupted power supplies or other related work like this project.
12.0 SUBMITTALS:
Submittals shall be submitted to the CO/COR and approved prior to contract award.
12.1 Work schedule delineating the various stages of work by phase (milestones).
12.2 Submit the manufacturer’s available colors/styles and specifications for approval by the
CO/COR for all products.
12.2 Contractor shall provide copies of product specifications, manufacturer’s literature and installation instructions of materials and products to be furnished and installed.
8 | P a g e
12.3 The Contractor must submit for the government approval all products to be used on this project.
12.5 The following submittals will-be required to-be submitted before final payment is made:
12.5.1 All Work Warranties and Product Guarantees.
12.5.2 Manufacturers recommended care, Operation Manuals, and recurring maintenance requirements.
13.0 BARRIERS & RESOURCE PROTECTION MEASURES:
13.1 Protect all exterior/interior surfaces of the building and adjacent landscaping, walks, drives, walls, signage, all adjacent buildings, and Government equipment from damage by project operations. Use suitable protective means. Protect glass windowpanes, and metal hinges and other features from breakage or other damage during project work.
13.2 Erect temporary construction barriers to protect visitors, employees and restrict pedestrian access. The contractor shall work with the CO/COR to avoid or minimize interruptions to general visitor access. Minimum is OSHA standards.
14.0 PICTURES AND DRAWINGS:
14.1 Pictures of current generator and switching unit inside shed:
9 | P a g e
10 | P a g e
14.2 Pictures of current UPS inside headquarters building:
14.3 Location of new above ground storage tank
11 | P a g e
14.4 Image of existing wood fencing
| 1.0 BACKGROUND and existing conditions: |
| 2.0 OBJECTIVE: |
| 3.0 PLACE of Performance: |
| 4.7.1.2 Provide a date and time for generator testing to the COR. COR (and/or designated representative(s) by the COR shall be present for initial generator testing. |
| 4.7.1.3 Perform a 1-hour long load test on the new generator to ensure there are no issues. |
| 4.7.1.4 Resolve any startup or shutdown issues. |
| 7.0 Government-Furnished EQUIPMENT: |
| 8.0 SECURITY: |
| 9.0 SPECIAL Material Requirements: |
| 10.0 OTHER Unique Requirements: |
| 10.1 This work is to be conducted with preservation of current storage unit in mind. Care must be used when demolishing, removing, repairing, and replacing building materials so as not to cause damage to building fabric. |