SOW-Replace Boiler Vent Piping at Bldg. 24; Lubbock Tx_.docx

DOCX document 77 KB Posted

Attached to
Replace Boiler Vent Piping Federal contract opportunity
Solicitation number
12744L20Q0001
Issued by
Department of Agriculture Agricultural Research Service

View the file

Other files for this federal contract opportunity

Other files attached to Replace Boiler Vent Piping, newest first.
File Type Posted
Clauses and Provisions - Replace Boiler Vent Pipe.docx DOCX document
ARS-371.pdf PDF
Wage Rates 05-21-2020.pdf PDF
SF 1442 - Replace Boiler Vent Piping.pdf PDF
ARS-372.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

United States Department of Agriculture Agricultural Research Service

STATEMENT OF WORK

“REPLACE BOILER VENT PIPING at Bldg. 24”

Cropping Systems Research Laboratory (CSRL)

USDA-ARS, LUBBOCK, TX

March 11, 2020

STATEMENT OF WORK

Construction

1.0 CONTRACT PROJECT:

A. Project Title: “Replace Boiler Vent Piping at Bldg. 24”, Cropping Systems Research Laboratory), Lubbock, TX 79415

2.0 PROJECT CONTACT PERSONS:

a. CONTRACTING OFFICER / CONTRACTING SPECIALIST:

Kelly Wright (CS)
USDA, ARS, PA, NBAF
1880 Kimball Ave Suite 300
Manhattan, KS 66502
Email: kelly.wright@usda.gov
Phone: (785) 712-3226
Jennifer Busbea (CO)
USDA, ARS, PA
3810 4th St.
Lubbock, TX 7915
Email: jennifer.busbea@usda.gov
Phone: (806) 723-5211FAX: (806) 723-5272

b. RESEARCH PROGRAM REPRESENTATIVES (RPR):

Dr. Alejandro Rooney
USDA, ARS, PA
3810 4th St.

Lubbock, TX 79415

Email: alejandro.rooney@usda.gov
Phone: (806) 749-5560

c. LOCATION ADMINISTRATIVE OFFICER (AO):

Harrison Axum
USDA, ARS, PA
3810 4th St.
Lubbock, TX 79415
Email: Harrison.axum@usda.gov
Phone: (806) 723-5213

d. FACILITIES MANAGER/ LOCATION MONITOR (LM) Shane Wludyka Facility Operations Specialists

USDA/ARS/PA/CSRL

3810 4th St.

Lubbock, Texas 79415 Email: shane.wludyka@usda.gov Phone: (806) 723-5210

e. AREA REALTY SPECIALIST / USDA LEASE CONTRACTING OFFICER (RS):

Lisa Baete
USDA, ARS, PA
2150 Centre Avenue, Bldg. D, Suite 330
Fort Collins, CO 80526-8119
Email: lisa.baete@usda.gov
Phone: (970) 492-7071

f. AREA SAFETY AND HEALTH MANAGER (ASHM):

Dwayne Cordray
USDA, ARS, PA
2775 F & B Road
College Station, TX 77840
Email: dwayne.cordray@usda.gov
Phone: (979) 260-9663

g. ENGINEERING PROJECT MANAGER (EPM)

Brian Dean
USDA, ARS, PA
2150 Centre Avenue, Bldg. D, Suite 330
Fort Collins, CO 80526-8119
Email: brian.dean@usda.gov
Phone: (970) 492-7026

2.1 CSRL Mission Statement

The mission of the Cropping Systems Research Laboratory is to develop fundamental, long-range research programs in Plant Stress and Germplasm Development, Wind Erosion and Water Conservation, Cotton Production and Processing, and Livestock Issues. The overall mission is subdivided among four multidisciplinary research units. All major crops and soil types, and significant animal production exist within a 50-mile radius of the Laboratory. This diversity of cropping systems, soil types, and livestock industries allows Laboratory scientists the opportunity to relay their fundamental information directly to their applied counterparts in State Agricultural Experiment Stations, private industry, commodity organizations, and other user groups.

3.0 SCOPE OF SERVICES:

The Contractor shall provide all professional services necessary for the accomplishment of the contract project and such required services shall be in accordance with requirements as described herein.

1. The Contractor shall provide services for the following tasks marked by an “X”:

[X] Provide a detailed technical proposal and detailed cost proposal to complete the project as per project requirements.

[X] Provide and install all material to complete the project as per project requirements.

Cont. on next page

4.0 PROJECT REQUIREMENTS:

The Contractor shall furnish a detailed technical proposal and detailed cost proposal to provide material and services to “Replace Boiler Vent Pipping” at the CSRL in a correct and proper manner.

The contractor will provide a turnkey product to include, but not limited to, all materials as specified and the correct and proper installation of all material. Contractor will provide all permits as required.

1. The Contractor will work with Facility personnel to ensure project is accomplished in a timely manner.

1. The Contractor’s work shall adhere to the criteria stated within these project requirements and specifications.

1. Materials and Installation shall meet the applicable sections of the Uniform Federal Guide Specifications (UFGS). The UFGS specifications can be found listed on the Whole Building Design Guide Construction Criteria Base UFGS page at: https://www.wbdg.org/ccb/browse_cat.php?c=3.

1. The Contractor’s work shall adhere to the criteria stated within these project requirements, drawings, and specifications. All construction shall comply with applicable federal, state, and local code requirements as well as current industry standards, (i.e.: UBC, NFPA, UL, ACI, ANSI, FCC, ASTM, NEC, NEMA, etc.) and health and safety codes, in effect at the time of contract award.

1. All codes and standards referenced in this specification will be to the edition of the references as detailed in this section. All materials and Work and Services to be performed under these specifications shall be in compliance with the Codes listed in this section or as determined by the authority having jurisdiction.

1. Davis Bacon Wage Rates apply to all construction contracts in excess of $2,000. Employee payroll logs for the project will be required to verify wage rates are being adhered to.

1. Payment bid or other bonds may be required per the Contracting Officer’s bid package. Obtaining and the cost of these bonds is the responsibility of the Contractor. Proof of Insurance may also be required.

1. Shutoff of utilities, if required, shall be scheduled no less than ten (10) working days in advance.

1. The Contractor is responsible for visiting the site prior to submitting a bid to observe existing conditions. No compensation will be provided for conditions that would be visible during an on-site visit for persons experienced performing this type of work.

1. Clean up and removal of all debris from construction site once job is completed.

1. Building(s) will be occupied while construction is ongoing. Contractor will schedule work with location in order to allow location to meet current research needs. See also 6.0 Schedule.

4.1 Bid Schedule:

1. Base Bid: Base bid shall include all work described in section 4.2 Description of Work and comply with section 5.10 Warranty. In summary, contractor to:

0. Remove and dispose old vent piping from five (5) hot water boilers.

0. Install new Category IV appliance double wall Stainless Steel vent piping (AL29-4C or equivalent) through roof.

0. Install a condensate tee with drain for moisture removal at each boiler (at 90 degree elbow).

0. Install one condensate drain manifold (all 5 boilers tied together) with an in-line acid neutralization collector (removable lid and limestone) that drains to the mechanical tunnel.

0. Completed project shall be weather tight.

4.2 Description of Work:

4.2.1 Pre-Construction Services

Prior to Construction Notice to Proceed (NTP) the following submittals must be submitted to the Contracting Officer (CO) for approval, unless otherwise determined by CO that submittals may be provided after NTP:

a. Submittals for all Material used on the project and per Section 5.4.

b. Work Hours, per Section H.30 entitled, MAXIMUM WORKWEEK – CONSTRUCTION SCHEDULE. The work hours will include the daily starting and stopping time, and days of the week the Contractor proposes to carry out the work.

c. Accident Prevention Plan/Site Specific Safety Plan.

1. Contractor shall submit a "site specific" Safety Plan to the Contracting Officer that describes how the contractor is to comply with all applicable OSHA standards and NFPA codes pertaining to construction work to include, but not limited to: General Safety and Health Provisions, Occupational Health and Environmental Controls, Personal Protective and Life Saving Equipment, Hand and Power Tools, Welding and Cutting, Electrical, Scaffolds, Fall Protection, Excavations, Demolition, Stairways and Ladders, Toxic and Hazardous Substances, Confined Space Entry, Lockout/Tagout, Respiratory Protection, Hearing Protection. Safety Plan shall identify Contractor and sub-contractor employees who are authorized/qualified to perform electrical work. No work shall proceed until written approval of the Safety Plan by the Contracting Officer. Safety Plan shall describe how the Contractor and/or sub-contractors are to secure equipment, supplies, tools, and chemical products. Contractor and/or sub-contractor equipment, supplies, tools, and chemical products are always to be under the control of the Contractor. Equipment, supplies, tools, and chemical products found not to be under the control of the Contractor or sub-contractor may be confiscated and delivered to the Contracting Officer.

d. Construction Cost Proposal presented in a cost break-out format resembling a Schedule of Values.

e. CPM Scheduling.

f. Individual Quality Control Plan is required on this project.

g. Individual Environmental Protection Plan is required on this project.

h. The Contractor shall provide to the CO a list of contract personnel of the general and subcontractors, who will be emergency contacts, including address, and telephone numbers for use in an emergency. As changes occur and additional information becomes available, the Contractor shall update the list.

i. Completion of all necessary Code reviews from all applicable City, Local, State and Federal entities.

4.2.2 Construction Services

The Scope of this project includes the following:

4.2.2.1 Base Bid

a. The Contractor will provide a turn-key project satisfying all Local, State, and Federal requirements.

1. Remove and dispose old vent piping from five (5) hot water boilers.

2. Install new Category IV appliance double wall Stainless Steel vent piping (AL29-4C or equivalent) through roof.

3. Install a condensate tee with drain for moisture removal at each boiler (at 90 degree elbow).

4. Install one condensate drain manifold (all 5 boilers tied together) with an in-line acid neutralization collector (removable lid and limestone) that drains to the mechanical tunnel.

5. Completed project shall be weather tight.

b. The Contractor is responsible for providing any required alternations of mechanical, electrical, plumbing, pipe-fitting, etc. to provide a turnkey installation.

c. The Contractor is responsible for any damage to adjacent equipment that may become damaged during installation. The Contractor is responsible for making repairs to meet or exceed conditions prior to damage.

d. The Contractor is responsible for visiting the site prior to submitting a bid to observe existing conditions. No compensation will be provided for conditions that would be visible during an on-site visit for persons experienced in performing this type of work.

4.3 Government Furnished Equipment\Services

1. The Government will be available to assist with the identification of possible other above ceiling or underground utilities but does not guarantee location of all utilities.

1. The Government will furnish a reasonable amount of electricity and water.

5.0 GENERAL REQUIREMENTS:

5.1Permits:
Where governing regulations and imposed codes and standards require notices, permits, licenses, inspections, tests, and similar items or actions in order to lawfully proceed with the required work, the Contractor shall obtain items and take those actions in accordance with the regulations of the governing authority. The costs of such permits, licenses, inspections, etc., are the obligation of the Contractor.

5.2 Existing Installations / Demolition:

a. Contractor shall modify existing installations as needed to accommodate the new installation. Contractor shall coordinate demolition / modification of existing installations with Owner. All disturbances of existing systems shall be thoroughly coordinated with the Owner to prevent disconnecting equipment that might jeopardize on-going research.

b. Owner typically reserves the right to retain any equipment / materials removed as part of the scope of work. Contractor shall coordinate any equipment / materials to be retained with Owner prior to starting demolition operations. Contractor shall legally dispose all equipment / materials removed that will not be retained.

c. Contractor shall divert project waste to recycle where practical. The Contractor shall track and document the amount of waste diverted to recycle. The Contractor shall submit diversion documentation as part of closeout. If no waste is diverted to recycle, the Contractor shall submit a letter stating this and why diversion was not practical. Reference the remaining Contracting Package for more information.

5.3Installation:
It shall be the responsibility of the Contractor to complete work in accordance with the manufacturer’s recommendations, Industry Standards, ARS standards, and Local, State and Federal codes and standards. Additional procedures and materials may be required than is indicated herein. If any item specified herein conflicts with the applicable codes and recommendations, the Contractor shall bring it to the attention of the Contracting Officer Representative for immediate resolution.

5.4 Submittals:

a. Provide all per 4.2.1.

b. Provide manufacturer’s descriptive literature/shop drawings for all materials to the COR for review. The descriptive literature shall be annotated/ highlighted to show its conformance with contract requirements. Submittals are required for all building materials and equipment and will be stamped and/or signed by the general contractor prior to submission to the Government. Contractor is responsible for any costs incurred for equipment ordered without prior approval.

5.5Quality Control:
The work performed under this contract shall be subject to continuous audit by the CO/COR/LM. Quality control is the exclusive responsibility of the Contractor.

5.6 Protection of Work and Property/Safety Requirements:

1. The Contractor shall protect the work, the site, and all existing property and structures within the limits of the construction activities or that may be affected thereby until acceptance of the work. Any damage to property shall be repaired at the Contractor’s expense, to pre-damaged condition to the satisfaction of the COR.

1. Safety and health matters, as they relate to the work, are the exclusive responsibility of the Contractor. The Contractor shall furnish, erect, and maintain barricades, warning lights, signs, guards, or take other precautions as may be required by law or local authorities for protection and security.

1. Contractor is responsible for verifying location of any underground utility and is responsible for any damaged caused to such utilities. The Contractor shall inspect the entire construction site daily, including days without construction work if there are NFPA 101 Life Safety Code deficiencies existing while construction work is shut down, the results of that inspection shall be documented on a “DAILY INSPECTION FORM”, and the form is to be signed and submitted to the Contracting Officer.

1. Contractor shall provide continuous monitoring for noise, dust, silica, chemical vapor generation, volatile organic compounds, and vibration. At no time shall noise exposure to any anyone at CNRC exceed 75 db. Contractor shall provide to the Contracting Officer a written weekly update of the all test results and for proposed work for the subsequent two weeks (a two week “look-ahead”) involving any construction activity that will produce loud noises, heavy vibrations, strong smells, or significant dust inside occupied space.

1. Contractor and sub-contractors shall notify in writing the Contracting Officer at least one week prior to executing high risk work (this may be included in the two week “look-ahead” update). High risk work includes, but is not limited to, tasks requiring Lockout/Tag Out, live electrical work, hot work, work at heights, trenching/ shoring, crane operations, and confined space entry. Contractor’s Competent Person shall provide the Contracting Officer written weekly documented safety inspection results.

1. Contractor shall provide to the Contracting Officer for approval, copies of Safety Data Sheets (SDS) for EVERY CHEMICAL WITHOUT EXCEPTION prior to bringing such chemical on the work site.

1. HOT WORK PERMITS: The Contractor will not be permitted to work without this permit when performing hot work.

6. A Hot Work Permit is required when cutting torch, welding, soldering and/or any other spark or heat producing equipment is to be used. A Hot Work Permit will be requested at least ten (10) working day in advance of the proposed work and will be issued only for the period necessary to perform such work. Hot Work Permit request form will be supplied by Owner during pre-construction meeting for this project.

5.7 Temporary Facilities:

1. Temporary utilities (water and electricity) may be furnished to the Contractor by the Government, if so requested. The Contractor shall maintain and protect all such utilities during the course of construction and shall repair or replace any items damaged through its own negligence.

1. Should the Contractor require any power or utility shutdowns during construction, the Contractor shall obtain approval for such shutdown from the COR ten (10) working days prior to the need.

1. Contractor to provide its own toilet facilities unless otherwise approved by CO and location during pre-bid site visit.

5.8 Materials and Equipment:

1. The material and equipment to be furnished under these contract documents shall be the standard products of manufacturers regularly engaged in the production of such materials and equipment and shall be the manufacturer’s latest standard design.

1. All materials and equipment to be incorporated in the work shall be handled and stored by the manufacturer, fabricator, supplier and Contractor before, during, and after shipment in a manner to prevent warping, twisting, breaking, chipping, rusting, personal injury, theft or damage of any kind to the materials and equipment. All materials and equipment furnished by the Contractor shall be subject to inspection and approval by the CO/COR or their designee.

5.9Cleanup:
The construction site shall be kept clean and free of debris at all times. Disposal of the old equipment is required. Restore areas disturbed as nearly as possible to the original appearance and condition. Upon completion of the project, and prior to final inspection, the Contractor shall remove from the premises all unused material, trash, and debris resulting from the work to the satisfaction of the COR.

5.10 Warranty:

1. Submit data concerning the warranty, including the warranty periods (dates), and warranty contacts with names, addresses and telephone numbers.

1. Extended Equipment/Product Warranties: Obtain and furnish to the Contracting Officer all written warranties for equipment/products that have extended warranties (warranty periods exceeding the standard one-year warranty) furnished under the contract. The warranty period shall begin on the same date as project acceptance and shall continue for the full/product warranty period. The warranties shall be fully executed and delivered to the Contracting Officer prior to final acceptance of the facility.

5.11 Final Payment/Contract Closeout: The following documents are REQUIRED PRIOR TO FINAL PAYMENT (other documents may also be required):

a. General contractors one (1) year warranty on workmanship.

b. Extended equipment warranty(s), if required above or in Specs and Drawings.

c. Operation and maintenance data. Include the following, if applicable:

1. Operation and maintenance instructions.

2. Parts list, with recommended parts inventory.

3. Legible schematic of all wiring diagrams of installed electrical equipment, including control equipment, and changes made in the work including any in field modifications,

4. Copy of field pull sheet wiring as built notes. Pull sheets to include wire numbers and colors.

5. Submit parts catalog and show evidence of local parts inventory with complete list of recommended spare parts. Manufacturer of original equipment shall produce parts.

d. Release of liens.

e. Employee payroll\time sheets

f. Invoice

6.0 Project Schedule: The Contract time for this project is 60 days from Construction Notice to Proceed issued by Contracting Officer.