SOW Pump House VFDs.pdf
PDF 378 KB Posted
- Attached to
- Furnish and Install Pump House Variable Frequency Drive (VFD) Federal contract opportunity
- Solicitation number
- 1333M2-21-Q-00076
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 1333M2-21-Q-00076 VFD Installation.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work Installation of Two Variable Frequency Drives (VFD’s) and Associated Equipment in Pump House
NOAA/NCCOS Oxford Laboratory
1.0 GENERAL
1.1 BACKGROUND
The NOAA, National Ocean Service, National Centers for Coastal Ocean Science (NCCOS), Cooperative Oxford Laboratory (COL) located at 904 South Morris Street, Oxford, MD has a requirement for the delivery and installation of two Variable Frequency Drives (VFD’s) and associated equipment and hardware in Building # 9 (Pump House) located on the facility campus at 904 S. Morris Street, Oxford, Maryland.
For technical information or questions for this Statement of Work, please contact the Government
Point of Contact, Mr. Greg Wilson at cell 410-473-3717 or greg.wilson@noaa.gov
Contractors are encouraged to visit the facility to ensure completeness of their quote submission.
Visits must be pre-arranged with Greg Wilson.
1.2 SCOPE
The requirement is for a vendor to furnish and install two (2) VFD’s, two starters, associated equipment and hardware in building #9 located on the COL property at 904 South Morris Street, Oxford MD 21654.
1.3 OBJECTIVE
This installation is to be performed by factory-trained technicians in accordance with manufacturer’s guidelines and recognized “Best Industry Practices.” The four pumps located in building #9 will be able to provide lead lag operations for alike pumps, speed control of pumps, and send alarms through current seawater alarming system. This system will provide the appropriate amount of seawater to various locations based upon demand.
2.0 SPECIFIC REQUIREMENTS/TASKS
2.1 Purchase and install two 7.5 Horse Power VFD’s for two Pacer Pump Pedestal Mounted
Pumps (already installed). Pump Models # TE3MBBCTSS. Pump Motors are Baldor /
Reliance 7.5 HP, 3 Phase, 230/460 Volt, 16.8/8.4 Amps, 3450 RPM. The VFD’s need to be programmed to do the following:
2.1.1 Provide lead lag operations to all four pumps. The Baldor / Reliance Pumps need to be able to lead / lag in tandem with each other and the Gould CentriPro
Pumps need to lead/lag in tandem with each other.
2.1.2 Control the speed of all four pumps located in the pump house.
2.1.3 Send alarm via current Sea Water Monitoring System connected to Honeywell controls operating on a Back Net platform to notify end users when there is an issue.
2.1.4 Provide a low level shutoff.
mailto:greg.wilson@noaa.gov file:///C:/Users/mark.t.molloy/Documents/PMO/SCOPE%20PARAGRAPHS.doc
2.2 Purchase and install pressure transducer on common discharge header.
2.3 Purchase and install fuse disconnect and three contactor bypasses for each VFD allowing
VFD’s to be bypassed in the event of VFD failure.
2.4 Purchase and install two starters for two Gould CentriPro Pumps (already installed), 3 HP, 3450 RPM, 230 Volts, 60 HZ, and 12 F.L.A.
2.5 Purchase and install one controller, and all required conduit and wiring to take control of all four pumps as outlined above.
2.6 Provide training to end users on how to program all installed equipment and basic trouble shooting techniques.
3.0 CONTRACTOR PERSONNEL
3.1 QUALIFIED PERSONNEL
The Contractor shall provide qualified personnel to perform all requirements specified in this
SOW.
All contractor employees must sign in at the front desk, sign a visitor’s log, and wear a NOAA issued visitor’s badge at all times.
3.2 EMPLOYEE CONDUCT
Contractor’s employees shall comply with all applicable Government regulations, policies and procedures (e.g., fire, safety, sanitation, environmental protection, security, “off limits” areas, etc.)
when visiting or working at Government facilities.
4.2 PERIOD OF PERFORMANCE
All work shall be completed by the vendor within 30 days of the vendor’s receipt of all required/ordered parts, and no later than January 30, 2021.
4.3 PLACE OF PERFORMANCE
904 South Morris Street
Oxford, MD 21654
4.4 HOURS OF OPERATION
Contractor employees shall generally perform all work between the hours of 8:00am and 4:30pm
EST, Monday through Friday (except Federal holidays). However, there may be occasions when
Contractor employees shall be required to work other than normal business hours, including weekends and holidays, to fulfill requirements under this SOW.
5.0 GOVERNMENT FURNISHED RESOURCES
The Government will not furnish any resources to the Contractor in support of this contract.
6.0 CONTRACTOR FURNISHED ITEMS
The Contractor shall furnish all materials, parts, equipment and labor necessary to fulfill the requirements of this contract, except for the Government Furnished Resources specified in SOW 2.0.