SOW MS State Energy Savings Project 2025.docx

DOCX document 987 KB Posted

Attached to
Replace Lighting with Energy Efficient LED's Federal contract opportunity
Solicitation number
1232SA25Q0214
Issued by
Department of Agriculture Agricultural Research Service

View the file

Other files for this federal contract opportunity

Other files attached to Replace Lighting with Energy Efficient LED's, newest first.
File Type Posted
Site visit sign in sheet.jpg JPG image
LED Lighting spreadsheet MS State.xlsx XLSX spreadsheet
FAR-13--Brand-Name-Justification-Less-Than-SAT-Nov-2024 1148617 KM LH.pdf PDF
Service Wage Rates.pdf PDF
Service Provisions 1148617.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Agricultural Research Service

U.S. DEPARTMENT OF AGRICULTURE

Install LED Lighting Page 2 of 2

STATEMENT OF WORK

Install Energy Efficient LED Lighting

Harned Building 150 Twelve Lane MS State, Mississippi 39762 Asset ID: 640600B001

Poultry Research Unit 606 Spring Street MS State, Mississippi 39762 Asset ID: 640600B012

1. PROJECT INTRODUCTION

1.1. PROJECT TITLE

Install Energy Efficient LED Lighting, Buildings 1 & 12.

1.2. PROJECT BACKGROUND AND PURPOSE

The USDA, Agricultural Research Service (ARS), Mississippi State houses various agricultural research units at the Building 1, Harned Building at 150 Twelve Lane and houses Poultry Research unit at Building 12, 606 Spring Street, MS State, MS 39762. Both of these buildings were built in the 1960’s and originally contained a mixture of incandescent and florescent lighting fixtures. There is an aggregate total of approximately 735 interior, exterior, and parking lot lighting fixtures at the two buildings. In the following years, lighting updates on approximately 100 fixtures have been made at various locations throughout both buildings therefore there is currently a mix of LED lighting is scattered throughout. The purpose of this project is to perform a comprehensive LED lighting update on all fixtures (approximately 635) that aren’t already converted to LED lighting and install occupancy sensors in selected rooms. Additionally, there are low mast pole mounted roadway lighting fixtures that are already LED but need replacement as a part of this project so that the lighting color is consistent with the rest of the USDA campus as well as the Mississippi State University campus.

1.3. PROJECT CONTACT PERSONS

CONTRACTING OFFICER (CO)

Lynn Hults Contract Specialist USDA, ARS, ARM, Southeast Area 912-464-9723 lynn.hults@usda.gov

2. SCOPE AND OBJECTIVES

2.1. DESCRIPTION OF WORK

Provide all materials, labor, and equipment to install approximately 635 LED lighting fixtures at Building 1, Building 12, occupancy sensors, and 5 low mast pole mounted lights at designated locations. Contractor must dispose of the old equipment at an off-site disposal area in a proper, legal, and environmentally responsible manner. Contractor services must be performed by a licensed Contractor. All outdoor lights to be 4000K. All roadway/parking lot lighting shall be AEL Autobahn, ATB2 60BLEDE13 Mvolt RS 4K BZ SXL PCLL. Interior lights to be 5000K. Requisite work is outlined as follows:

2.1.1. Location, existing fixture, proposed fixture, and quantity are to be completed according to the following:

The University requires that we work to maintain consistency with the visual aesthetics. The specified American Electric Lighting Autobahn series is the roadway and parking lot lighting unit that is used throughout the entire Mississippi State Campus. Specifying these units will provide visual consistency in aesthetics, lighting intensity, and light color with the rest of campus. The Green Creative numbers are there for information only to ensure that products provided will be similar to these items.

2.2. The Contractor will verify all dimensions and site conditions prior to beginning work. No Government equipment will be available for use by the Contractor. The Contractor must provide their own restroom facility.

2.3. LOCATION OF WORK

The project is located at Building 1, 150 Twelve Lane, and Building 12, 606 Spring Street, MS State, Mississippi 39762.

2.4. PRE-BID SITE VISIT

Interested vendors are encouraged to visit the site and be escorted by a government representative to confirm locations, dimensions, and conditions of the project before a quote is submitted. The purpose of a site visit is to observe conditions relevant to the completion of this project. No consideration will be given to claims based on lack of knowledge of existing conditions, except where contract documents detail definite provisions for adjustment in cost or extension due to existing conditions not readily foreseeable.

3. PROJECT SCHEDULE

3.1. The completion of the project must not exceed ninety(90) calendar days from the date of the Notice to Proceed (NTP).

3.2. The Contractor must prepare an overall project schedule including milestone dates for all phases of work and completion date; submit to the COR for approval. This schedule is due fourteen (14) days after contract award. The Contractor must track all work progress to ensure that the project is completed according to the schedule. Include work week schedule with daily starting and stopping time.

3.3. The Contractor must coordinate and confirm the dates for all work with the COR. If necessary, any request for a time extension must be submitted to the Contracting Specialist in writing before the expiration of the Period of Performance. Each request must include specific and detailed reasons in support of the schedule alteration and provide an updated schedule for completion. No extension of the period of performance may be given without the written authority of the CO.

3.4. Project work hours are 7:00 am and 4:30 pm, local time, Monday through Friday; federal holidays excluded. The contractor is not required to provide services on recognized Federal holidays established by Federal law (5 U.S.C. 6103). Any changes to work schedule must be submitted to CO for written approval prior to any schedule change.

3.5. This work location is inside of a locked compound that houses animal research, therefore site security and animal welfare are serious concerns due to disease transmission, etc. All work must be coordinated with the LPOC and RL to ensure that safety and health protocols are observed and the research animals as well as workers are protected.

4. GENERAL REQUIREEMENTS

4.1. PERMITS

The Contractor must obtain all building and trade permits necessary to include any drawings, plans, permit and inspection fees, utility location, site surveys, and any other items necessary for compliance with state, local, and federal building authorities.

4.2. SAFETY

The Contractor must submit a Site Safety Specific Plan/Accident Prevention Plan (Plan) in industry recognizable format to the COR within Fourteen (14) days of contract award. The Plan must include phone numbers and maps to local physician offices and the nearest hospital. The Government will review and approve the Plan before issuance of the NTP.

4.3. EXISTING INSTALLATIONS/DEMOLITION

Coordinate all activities with COR. All disruptions of existing systems must be coordinated with the COR to prevent disconnecting equipment that may jeopardize on-going research.

4.4. QUALITY CONTROL

Provide quality control to ensure that all components of project work meet the requirements of the contract specifications. Ensure that all work not acceptable or compliant with the specifications is corrected prior to inspection or review by the COR. Quality control is the exclusive responsibility of the Contractor.

4.5. PROTECTION OF WORK AND PROPERTY/SAFETY REQUIREMENTS

4.5.1. The Contractor must protect the work, the site, and all existing property and structures within the limits of the construction activities or that may be affected thereby until acceptance of the work. Any damage to property must be repaired at the Contractor’s expense to pre-damaged condition to the satisfaction of the COR.

4.5.2. Safety and health matters, as they relate to the work, are the exclusive responsibility of the Contractor. The Contractor must furnish, erect, and maintain barricades, warning lights, signs, guards, or take other precautions as may be required by law or local authorities of the protection and security.

4.5.3. The contract documents may not represent all surface conditions at the site and adjoining areas. The known surface conditions are as indicated and must be compared with actual conditions before commencement of work and the cost must be included in the Contractor’s quote.

4.5.4. The Government will not furnish any labor or equipment to unload or move materials or supplies.

5. UTILIZATION OF BIOBASED PRODUCTS

The Contractor must make every effort to utilize products and material based from bio-based materials as applicable, (e.g. bio-based greases; bio-based hydraulic fluids, bio-based absorbents), to the maximum extent possible without jeopardizing the intended end use or detracting from the overall quality delivered to the Government. All supplies and materials must be of a type and quality that conform to the applicable federal specifications and standards. All supplies and materials to be used in the performance of work described herein are subject to the approval of the Contracting Officer Representative (COR). Products can be found at: www.biopreferred.gov.

6. HAZARDOUS MATERIAL

This work is not expected to disturb areas that involve asbestos containing materials or lead based paint. Existing conditions are reflected correctly to the best of USDA’s knowledge. The USDA makes no representation, warranty, or guaranty that the conditions indicated either are representative of those conditions existing throughout the area, or that unforeseen developments may not occur, or that materials other than, or proportions different from those indicated may not exist. If hazardous materials are found to be present, it must be reported to the CO & COR for further action.

7. DISPOSAL OF REMOVED MATERIALS AND DEBRIS

7.1. The Contractor must dispose of removed, materials, waste, trash, and debris in a safe, acceptable manner, in accordance with applicable laws and ordinances and as prescribed by authorities having jurisdiction.

7.2. Burying of trash and debris on the site is prohibited. Burning of trash and debris at the site is prohibited.

7.3. Remove trash and debris from the site at frequent intervals so that its presence will not delay the progress of the work or cause hazardous conditions for workers and the public.

7.4. Removed materials, trash, and debris must become the property of the Contractor and must be removed from the project site and be disposed of in a legal manner. Location of disposal site and length of haul are the Contractor's responsibility.

7.5. The contractor should make every effort to recycle as much of the construction debris as possible.

7.6. Any waste materials encountered during the demolition that are found to contain lead, asbestos, polychlorinated biphenyls (PCB), fluorescent lamps, or any hazardous substances are to be handled and removed in accordance with local, state, and federal laws and requirements concerning hazardous waste as well as any specific hazardous waste requirements stated in different sections.

7.7. Comply with hauling and disposal regulations of authorities having jurisdiction, per federal, state, and local requirements.

8. TEMPORARY FACILITIES

Temporary utilities (water and electricity) may be furnished to the Contractor by the Government, if so requested. The Contractor must maintain and protect all such utilities during the course of construction and must repair or replace any items damaged through its own actions. Should the Contractor require any power or utility shutdowns during construction, the Contractor must obtain approval for such shutdown from the COR three (3) working days prior to the need.

9. CLEANUP

The construction site must be kept clean and free of debris at all times. Restore areas disturbed as nearly as possible to the original appearance and condition. Upon completion of the project, and prior to final inspection, the Contractor must remove from the premises all unused material, trash, and debris resulting from the work to the satisfaction of the COR.

10. SUBMITTALS

Submittals on all material incorporated into the work, including shop drawings and specifications, used on this project must be submitted to the EPM, COR, and Contracting Specialist. Electronic submittals are acceptable, otherwise three (3) written submittals are required.

10.1. Project Schedule within fourteen (14) calendar days of award (see Section 3.2).

10.2. Safety Plan within fourteen (14) days of award (see Section 4.2).

10.3. Any additional material submittals, including shop drawings and specifications, used on this project.

11. INSPECTION AND ACCEPTANCE

A government representative will inspect and approve the work performed on this project. The Contractor must schedule inspection a minimum of three (3) days in advance, in writing, to the COR and CO.

12. FINAL PAYMENT/CONTRACT CLOSEOUT

The following documents are required prior to final payment (other documents may also be required): Release of Liens, Release of Claims, Employee Payroll\Timesheets, and Invoice.