SOW - Innovation Lab Renovation.pdf

PDF 934 KB Posted

Attached to
Innovation Lab Renovation Federal contract opportunity
Solicitation number
W50S82-22-R-0007
Issued by
Department of the Army Maryland Army National Guard

About this file

This statement of work outlines requirements for an Innovation Lab Renovation project for the Maryland Air National Guard. The contractor shall provide design and installation services including graphic design, production of signage and wall graphics, custom exhibit elements, and mobile furniture to accommodate six people. The government will provide an existing SMART Board, glass whiteboard, conference camera, and workstation computer. The contractor must conduct design meetings and presentations for approval. The period of performance is 90 days at the contractor's establishment. The solicitation seeks quotes for all work specified to award a firm fixed price purchase order to the best value offeror.

View the file

Other files for this federal contract opportunity

Other files attached to Innovation Lab Renovation, newest first.
File Type Posted
SOW - Innovation Lab Design v3.docx DOCX document
RFP - Innovation Lab Renovation v2.pdf PDF
Innovation Lab - Floor Plan.pdf PDF
SOW - Innovation Lab Design v2.pdf PDF
Innovation Lab Renovation RFI.pdf PDF
RFP - Innovation Lab Renovation.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

Innovation Lab Renovation

MARYLAND AIR NATIONAL GUARD

3 June 2022

1.0 General:

1.1 Scope: The contractor shall provide equipment, tools, materials, supervision, and quality control necessary to perform Design and Installation services specifically targeted for the 175th Innovation lab.

1.2 Background: The 175th Wing established the SPARK Cell: Sprey Innovation Center of Excellence.

The Innovation Center will enable the 175th Wing to connect, empower, and inspire innovators across the Wing to develop solutions for real-world national security problems. This remodeling project is for remodeling the Spark Cell Innovation Lab space. The intended outcome is to implement an innovative space that promotes advancements for Wing and Air Force solutions.

The Spark Cell Innovation Lab space requires furniture, graphics, signage, design, and custom elements to remodel the Innovation Lab room. The Innovation Lab is a 14’ x 11’ room demonstrated under in Appendix I in this document.

1.3 Period of Performance (PoP): The Period of Performance shall be 90 days.

1.4 General Information:

1.4.1 Quality Control (QC): The contractor shall develop and maintain an effective QC Plan (QCP) to ensure services are performed in accordance with this PWS. The contractor shall develop and implement procedures to identify, prevent, and ensure non-recurrence of defective services. The contractor’s QCP is the means by which it assures itself that its work complies with the requirements of the contract. As a minimum, the contractor shall develop QC procedures that address the areas identified in Technical Exhibit 1, Performance Requirements Summary (PRS). A final QCP shall be submitted to the Contracting Officer Representative (COR) NLT 10 days after contract award. After acceptance of the QCP, the contractor shall obtain the Contracting Officer’s (KO’s) acceptance in writing of any proposed changes to its QCP.

1.4.2 Quality Assurance (QA): The Government will evaluate the contractor’s performance under this contract in accordance with the Quality Assurance Surveillance Plan (QASP). This plan is primarily focused on what the Government will do to ensure that the contractor has performed in accordance with the performance standards. It defines how the performance standards will be applied, the frequency of surveillance, and acceptable quality level(s) or defect rate(s).

1.4.3 Recognized Holidays: The following are recognized United States (US) holidays. The contractor shall not perform services on these days:

1.4.3.1 New Year’s Day: January 1st

1.4.3.2 Martin Luther King, Jr.’s Birthday

1.4.3.3 President’s Day

1.4.3.4 Memorial Day

1.4.3.5 Juneteenth

1.4.3.6 Independence Day: July 4th

1.4.3.7 Labor Day

1.4.3.8 Columbus Day

1.4.3.9 Veteran’s Day: November 11th

1.4.3.10 Thanksgiving Day

1.4.3.11 Christmas Day: December 25th

1.4.4 Place and Performance of Services: The contractor shall be able to provide services between the hours of 1000-1900 Monday to Friday, except on recognized US holidays. All services will be provided at the Contractor’s establishment. No portion of this contract will be executed in on-base facilities. Operations Group Pilots will be required to make an appointment with the provider prior to arrival for services. The contractor shall at all times maintain an adequate work force for the uninterrupted performance of all tasks defined within this PWS. When hiring personnel, the contractor shall keep in mind that the stability and continuity of the work force are essential.

1.4.5 Post Award Conference/Periodic Progress Meetings: The contractor agrees to attend any post award conference convened by the KO in accordance with FAR Subpart 42.5. The KO, COR and other Government personnel, as appropriate, may meet periodically with the contractor to review the contactor’s performance. At these meetings, the KO will apprise the contractor of how the Government views the contractor’s performance and the contractor shall apprise the Government of problems, if any, being experienced. The contractor shall resolve outstanding issues raised by the Government. Contractor attendance at these meetings shall be at no additional cost to the Government.

1.4.6 Contract Manager (CM): The contactor shall designate a CM who shall ensure performance under this contract. The name of this person, and an alternate who shall act for the contractor when the CM is absent, shall be designated in writing to the KO. The CM or alternate shall have full authority to act for the contractor on all contract matters relating to daily operation of this contract. The CM shall work through the COR, to resolve issues, receive technical instructions, and ensure adequate performance of services.

The CM shall ensure that contractor employees do not perform any services outside the scope of the contract without an official modification issued by the KO. The CM shall ensure contractor employees understand that services performed outside the scope of the contract are performed wholly at the expense of the contractor.

1.4.7 Identification of Contractor Employees: All contractor personnel attending meetings and working in other situations where their contractor status is not obvious to third parties are required to identify themselves as such to avoid creating an impression that they are Government employees. Contractor Personnel shall wear job-related work clothing and shall be easily identifiable by wearing distinctive clothing bearing the name of the company. Contractor personnel shall wear identification badges distinguishing themselves as such. The badges shall have the company name, employee name and the word “contractor” displayed. The contractor shall retrieve all identification media (including vehicle passes) from its employees who depart employment for any reason. The contractor shall return all identification media (i.e., badges and vehicles passes) to the KO within 14 days of an employee’s departure.

1.4.8 Combating Trafficking in Persons: The United States Government has adopted a zero tolerance policy regarding trafficking in persons. Contractors and contractor employees shall not engage in severe forms of trafficking in persons during the period of performance of the contract; procure commercial sex acts during the period of performance of the contract; or use forced labor in the performance of the contract. The Contractor shall notify its employees of the United States Government’s zero tolerance policy, the actions that will be taken against employees for violations of this policy. The contractor shall take appropriate action, up to and including termination, against employees or subcontractors that violate the US Government policy as described at FAR 22.17.

1.4.9 Organizational Conflicts of Interest (OCI): The contractor and subcontractor personnel performing services under this contract may receive, have access to or participate in the development of proprietary or source selection information (e.g., cost or pricing information, budget information or analyses, specifications or work statements, etc.) or perform evaluation services which may create a current or subsequent OCIs, as defined in FAR Subpart 9.5. The contractor shall notify the KO immediately whenever it becomes aware that such access or participation may result in any actual or potential OCI and shall promptly submit a plan to the KO to avoid or mitigate any such OCI. The contractor’s mitigation plan will be determined to be acceptable solely at the discretion of the KO. In the event the KO unilaterally determines that any such OCI cannot be satisfactorily avoided or mitigated, the KO may impose other remedies as he or she deems necessary, including prohibiting the contractor from participation in subsequent contracted requirements which may be affected by the OCI.

1.5.0 Description of Work: The Contractor shall describe in his or her proposal how they will manage the project. The Contractor shall identify key staff and their abilities to manage projects of this magnitude, including scheduling methods, reporting and execution.

1.5.1 Design Meetings: Conduct the appropriate number of review meetings with the Project Team members during each design phase of the project so they may determine if the project meets their requirements, question any aspect of the contract deliverables, and make changes where appropriate. The Contractor shall describe the philosophy and process used in the development of the design criteria and the various alternatives considered to meet the project objectives. Selected studies, sketches, schedules, submittals, and other relevant information shall be presented to support the design solutions proposed.

1.5.2 Design Presentations: Perform the number of design presentations and drawings as required Final design shall be approved by COR.

2.0 Definitions and Acronyms

2.1 Definitions:

2.1.1 Contractor: A supplier or vendor awarded a contract to provide specific supplies or service to the government. The term used in this contract refers to the prime.

2.1.2 Contracting Officer (KO): A person with authority to enter into, administer, and or terminate contracts, and make related determinations and findings on behalf of the government. Note: The only individual who can legally bind the government.

2.1.3 Contracting Officer Representative (COR): An employee of the U.S. Government designated by the KO to monitor contractor performance. Such appointment will be in writing and will state the scope of authority and limitations. This individual has authority to provide technical direction to the Contractor as long as that direction is within the scope of the contract, does not constitute a change, and has no funding implications. This individual does NOT have authority to change the terms and conditions of the contract.

2.1.4 Defective Service: A service output that does not meet the standard of performance associated with the PWS.

2.1.5 Deliverable: Anything that can be physically delivered and includes non-manufactured things such as meeting minutes or reports.

2.1.6 Key Personnel: Contractor personnel that are evaluated in a source selection process and that may be required to be used in the performance of a contract by the PWS. When key personnel are used as an evaluation factor in best value procurement, an offer can be rejected if it does not have a firm commitment from the persons that are listed in the proposal.

2.1.7 Physical Security: Actions that prevent the loss or damage of Government property.

2.1.8 Quality Assurance: The government procedures to verify that services being performed by the Contractor are performed according to acceptable standards.

2.1.9 Quality Assurance Surveillance Plan (QASP): An organized written document specifying the surveillance methodology to be used for surveillance of contractor performance.

2.1.10 Quality Control: All necessary measures taken by the Contractor to ensure that the quality of an end product or service shall meet contract requirements.

2.1.11 Subcontractor: One that enters into a contract with a prime contractor. The Government does not have privity of contract with the subcontractor.

2.2 Acronyms:

AEI Army Enterprise Infrastructure AR Army Regulation AT/OPSEC Antiterrorism/Operational Security BI Background Investigation CM Contract Manager CMRA Contractor Manpower Reporting Application COR Contracting Officer Representative DA Department of the Army DD254 Department of Defense Contract Security Classification Specification DFARS Defense Federal Acquisition Regulation Supplement DoD Department of Defense FAR Federal Acquisition Regulation GFP/M/E/S Government Furnished Property/Material/Equipment/Services HQDA Headquarters, Department of the Army HSPD Homeland Security Presidential Directive IA Information Assurance IS Information System(s) KO Contracting Officer NGB National Guard Bureau OCI Organizational Conflict of Interest PII Personally Identifiable Information PIPO Phase In/Phase Out POC Point of Contact PRS Performance Requirements Summary PWS Performance Work Statement QA Quality Assurance QASP Quality Assurance Surveillance Plan QC Quality Control QCP Quality Control Program SSN Social Security Number TE Technical Exhibit USD(I) Under Secretary of Defense for Intelligence

3.0 Government Furnished Property, Material, Equipment and Services (GFP/M/E/S): The Government will provide the property, material, equipment, and/or services listed below solely for the purpose of performance under this contract:

3.1 Property: The Government will not provide property for the contractor’s use.

3.2 Materials: None

3.3 Equipment: None

3.4 Services: None

3.5 Utilities: None

4.0 Contractor Furnished Property, Materials, and Equipment (CFP/M/E):

4.1 General: Except for those items specifically stated to be Government-Furnished in Paragraph 3.0, the contractor shall furnish everything required to perform these services as indicated in Paragraph 1.1.

4.1.1 The contractor is responsible to provide necessary equipment to clean, sanitize, and carry out the services required within the SOW.

5.0 Requirements: The contractor shall:

5.1 Provide graphic design and production services to develop room entry signage, wall graphics, and custom exhibit elements.

5.2 Fabricate, deliver and install signage, wall graphics, and custom exhibit elements.

5.3 Provide custom mobile furniture to accomodate at least six (6) people to be seated in the room

5.4 The following items have been purchased by the government and will be installed in the Innovation Lab:

• One (1) SMART Board 6000 Pro Series

• One (1) 4 x 6 Glass White Board

• Owl Lab Conference Room camera

• One (1) workstation computer

APPENDIX I

INNOVATION LAB SPACE

Room Size – 14’ x 11’ **Existing furniture will be removed

3 June 2022