SOW_-_FPSI.pdf

PDF 620 KB Posted

Attached to
Fire Protection System Inspection Federal contract opportunity
Solicitation number
140P6422Q0100
Issued by
Department of the Interior National Park Service Midwest Region

View the file

Other files for this federal contract opportunity

Other files attached to Fire Protection System Inspection, newest first.
File Type Posted
Technical_Questionnaire.docx DOCX document
Wage_Determination_-_Summit_Co.pdf PDF
Wage_Determination_-_Cuyahoga_Co.pdf PDF
OPTIONAL_-_2021_Inspection_Summary.pdf PDF
Technical_Questionnaire.pdf PDF
Price_Schedule_-_FPSI.xlsx XLSX spreadsheet
Sol_140P6422Q0100.pdf PDF
Price_Schedule_-_FPSI.pdf PDF
Attachment_-_FPS_Inventory_2022.pdf PDF
Attachment_-_FMDS0281.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Cuyahoga Valley National Park Brecksville, Ohio

STATEMENT OF WORK:

Fire Protection System Inspection

DATED:

June 27, 2022

NATIONAL PARK SERVICE

INTERIOR REGION 3/4/5

OHIO MAJOR ACQUISITION BUYING OFFICE

1.0 Description

Cuyahoga Valley National Park, 15610 Vaugh Road, Brecksville Ohio 44141 is 22 miles long with 33,000 acres. The Park stretches north to south and covers two Ohio counties, Cuyahoga County and Summit County. A representative from Cuyahoga Valley National Park will be present with the contractor for the duration of the inspection. The Park representative will guide the contractor through the park. This contract will provide inspection and testing on the following Bosch systems: (2) glycol-based fire protection systems, (2) water-based suppression systems, (1) antifreeze loop, (6) booster pump wet pipe systems, (46) fire alarm panels and associated monitoring systems. This inspection covers

(2) Ohio Counties: Cuyahoga County and Summit County. (9) locations are in Cuyahoga County and (39) locations are in Summit County. Inventory of systems with building addresses are attached.

2.0 Definitions

Approved: Acceptable to the authority having jurisdiction.

Authority having jurisdiction (AHJ): Midwest Regional Office Structural Fire Management Officer, Contractor: as used within this specification refers to the primary contractor and/or subcontractor(s).

Contracting Officer (CO): Government Agent with the authority to approve changes to the terms, conditions or price of the contract. NO OTHER PERSON IS AUTHORIZED to approve changes to the terms, conditions or price of the contract.

Contracting Officers Technical Representative (COTR).

Emergency Impairment: A condition where a fire protection system or portion thereof is out of order due to an unexpected occurrence.

FMSS: Facility Management Software System

Listed: Equipment, materials, or services included in a list published by Underwriters Laboratories (UL) or Factory Mutual (FM), and whose listing states that either the equipment, material, or service meets appropriate designated standards or has been tested and found suitable for a specified purpose.

NFPA: National Fire Protection Association

3.0 General Requirements

3.1 Applicable Codes and Standards

1. NFPA 1: Fire Code, 2018

2. NFPA 13: Standard for the Installation of Sprinkler Systems, 2019

3. NFPA 13R: Standard for the Installation of Sprinkler Systems in Low-Rise Residential Occupancies, 2019

4. NFPA 25: Standard for the Inspection, Testing, and Maintenance of Water-Based Fire Protection Systems, 2020

5. NFPA 72: National Fire Alarm and Signaling Code, 2019

6. NFPA 96: Standard for Ventilation Control and Fire Protection of Commercial Cooking Operations, 2021

7. NFPA 101: Life Safety Code, 2021

8. FM Global Property Loss Prevention Data Sheet 2-81 [October, 2020]

3.2 Qualifications

Contractor: The contractor and proposed sub-contractors must verify that they are licensed in the state of Ohio and must be able to demonstrate they have a minimum of 5-years’ experience completing NFPA compliant inspection testing and maintenance of fire protection systems per the specific requirements of this statement of work.

Technicians: Lead technicians performing fire protection system inspection, testing and maintenance must meet one of the following:

• NICET II or greater certification for Bosch Fire Alarm system..

• Certified by Bosch manufacturer.

3.3 Period of Performance

Project to be completed 120 days after contract award effective date.

3.4 Work Hours

On-site work hours: Work shall be generally performed during normal business working hours of 8 a.m. to 5 p.m., Monday through Friday, except when otherwise indicated.

A. Work on Saturdays, Sundays, Federal holidays, early morning, or at night may not be performed without prior consent from the COR. Submit requests for work outside of the stated normal business hours to the COR for approval at least 48 hours in advance of the work.

3.5 Site Access

A. General: Contractor shall have limited use of the site for operations. Limit use of premises to access of fire suppression and must be accompanied by a park employee. Do not disturb portions of site beyond areas in which the Work is indicated.

3.6 Government Provided Materials and Support

• The Government will assign a point of contact to escort the contractor’s technicians and provide access to buildings.

• The Government will provide staff to reset equipment and systems (elevators, HVAC) interfaced with fire alarm systems.

• The Government will provide an inventory of systems in hardcopy format (see appendix A) and an electronic version in MS Excel format

• The Government will not provide staff to assist with inspection and testing tasks.

4.0 Specific Requirements

4.1 Project Schedule

A kickoff meeting between the contractor and National Park Service must be completed no later than 7 days after the award. During this meeting, the contractor and COR will establish a tentative schedule. The tentative schedule will address any operational concerns between the two different counties. Some of the structures that will be inspected are occupied by private residents and will require a notice before inspection can commence.

Within 5 working days from conclusion of kickoff meeting the Contractor will submit a proposed schedule of work to the

COR.

4.2 Validate Fire Protection System Inventory

The contractor will validate and correct the system inventory provided by the government. The inventory will be provided in an electronic Microsoft Excel format. The corrected inventory will be returned to the Government in the same electronic Microsoft Excel spreadsheet format. All changes to the inventory will be highlighted to indicated the number has changed from the original inventory sheet.

4.3 Inspection and Testing of Fire Alarm Systems

The Contractor shall conduct one inspection and test of each fire alarm system in the inventory. An inspection and test will encompass all quarterly, semiannual, and annual inspection and test requirements as identified in NFPA-72 Chapter

14. 100% of initiating devices shall be tested.

100% of smoke detectors were tested for sensitivity on a 5-year cycle starting FY 2021. Sensitivity testing was conducted in accordance with NFPA-72 Chapter 14 and manufacturer’s instructions. This contract is for FY 2022, NFPA 14.4.4.3.3 applies for smoke detectors.

Inspections and tests for each system will be recorded on inspection report forms that comply with NFPA-72 Chapter 14.

The building FMSS location number and system FMSS asset number must be recorded on the administrative portion of the form. Individual inspection and test reports are required for each system. Reports must be submitted in a type written format. Handwritten reports will not be accepted. Individual reports are due to the COR within 72 hours of the completion of individual inspections.

All impairments and deficiencies must be detailed on the inspection and test forms.

Should an emergency impairment be discovered, the Contractor shall:

• Notify the NPS COTR immediately

• Tag the system with an impairment notice indicating that it is out of service and what caused the impairment.

4.4 Inspection and Testing of Water-Based Fire Sprinkler Systems The Contractor shall conduct one inspection and test of all water-based fire sprinkler systems. An inspection and test shall encompass all quarterly, semiannual, and annual inspection and test requirements as identified in NFPA-25.

Inspection and tests shall be conducted in accordance with methods and procedures as outlined in NFPA-25 and FM Global Property Loss Prevention Data Sheet 2-81 [October, 2020]. See appendix B.

Inspections and tests for each system will be recorded on inspection report forms that comply with NFPA-25 Annex B.

The building FMSS location number and system FMSS asset number must be recorded on the administrative portion of the form (front page). Individual inspection and test reports are required for each system. Reports must be submitted in a type written format. Handwritten reports will not be accepted. Individual reports are due to the COR within 72 hours of the completion of individual inspections.

All impairments and deficiencies must be detailed on the inspection and test forms.

Should an emergency impairment be discovered, the Contractor shall:

• Tag the system with an impairment notice indicating that it is out of service and what caused the impairment.

4.4.1 Antifreeze Sprinkler systems

The concentration of antifreeze solutions shall be tested in accordance with NFPA-25 5.3.4.4.1. Concentrations exceeding limits are to be considered an emergency impairment. The system should be red tagged as impaired and the following notifications made:

• Tag the system with an impairment notice indicating that it is out of service and what caused the impairment.

5.0 Deliverables

5.1 Inspection and Test Reports

• Inspections and tests for each system will be recorded on inspection report forms that comply with requirements of the appropriate NFPA Code or Standard.

• Individual inspection and test reports are required for each system.

• Individual inspection reports are due to the COR within 10 days of the completion of individual inspections.

• Reports must be formatted to 8.5 x 11 inches and submitted electronically in an Adobe PDF file format.

• Reports must be submitted in a type written format. Handwritten reports will not be accepted.

• The building FMSS location number, asset description, and physical address (see appendix A: Inventory of Fire Protection

Systems) must be recorded on the administrative portion of the form.

5.2 Deficiency Cost Summary Report

• Descriptions of all individual deficiencies will be submitted electronically in Microsoft Excel format.

• Individual deficiencies shall be identified by FMSS location number, FMSS asset description as well as the date of inspection

• Report on costs to repair deficiencies shall be broken down by labor and material cost. Labor cost shall be further broken down by labor cost per hour and labor hours.

• The final report is due to the COR 30 days after last inspection.

Appendix A: Inventory of Fire Protection Systems See attached Files

- MS Excel Spreadsheet Labeled: CUVA-FPS-Inventory-2022.xlxs

Appendix B: FM Global Property Loss Prevention Data Sheet 2-81 [October, 2020] See attached File: FMDS0281.pdf

DEVICES

1.0 Description
2.0 Definitions
3.0 General Requirements
3.1 Applicable Codes and Standards
3.2 Qualifications
3.3 Period of Performance
3.4 Work Hours
3.5 Site Access
3.6 Government Provided Materials and Support
4.0 Specific Requirements
4.1 Project Schedule
4.2 Validate Fire Protection System Inventory
4.3 Inspection and Testing of Fire Alarm Systems
4.4 Inspection and Testing of Water-Based Fire Sprinkler Systems
4.4.1 Antifreeze Sprinkler systems
5.0 Deliverables
5.1 Inspection and Test Reports
5.2 Deficiency Cost Summary Report
Appendix A: Inventory of Fire Protection Systems
Appendix B: FM Global Property Loss Prevention Data Sheet 2-81 [October, 2020]