SOW_for_Radon_Mitigation.pdf
PDF 260 KB Posted
- Attached to
- TX INKS DAM NFH RADON MITIGATION for QUARTERS Federal contract opportunity
- Solicitation number
- 140FS224Q0097
About this file
This statement of work outlines requirements for a radon mitigation project at a national fish hatchery. The contractor will be responsible for reducing radon levels in Quarters 2 and 3, which tested above EPA standards at 6.0 pCi/L and 8.0 pCi/L respectively, through installation of mitigation systems guaranteed to lower levels below 4 pico curies. The contractor must conduct pre- and post-mitigation radon tests, with the post-test occurring within 30 days of system installation by a state-certified technician. The attached site plan shows the locations of the affected quarters.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140FS224Q0097.pdf | ||
| Wage_Determination_2015-5287_Revision_25_2023-12-26_Burnet_County_Texas.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
140FS224Q0097 Radon Mitigation for Two Buildings Page 1 of 2
FWS Inks Dam National Fish Hatchery
Statement of Work
INKS DAM NATIONAL FISH HATCHERY RADON MITIGATION FOR QUARTERS 2 AND 3.
General Information
Radon testing of Quarters 2 and 3 resulted in elevated levels above EPA standards. Tests concluded
Quarters 3 at an elevated level of 8.0 pCi/L and Quarters 2 at an elevated level of 6 pCi.L.
Radon mitigation work to be performed (in accordance with industry standards)
1. Perform work for the purpose of reducing radon in air in accordance with industry standards.
All Mitigation Systems guaranteed to bring Radon levels to below 4 Pico curies.
2. Conduct radon test to verify the validity of the radon mitigation system and warranty. You must wait for at least 24 hours to run a retest for radon levels after radon mitigation. After 24 hours testing, retest within 30 days of the new mitigation system’s installation. Radon Testing
Report shall be conducted by State certified technician. Contractor shall include the certification with the radon testing report.
Attached is a reference site plan showing proposed Quarters 2 and 3.
140FS224Q0097 Radon Mitigation for Two Buildings Page 2 of 2
FWS Inks Dam National Fish Hatchery