SOW FGO 46 Repoint Caulk Seal V5_2020.pdf

PDF 715 KB Posted

Attached to
tuck pointing brick exterior facade Federal contract opportunity
Solicitation number
47PJ0020R0094
Issued by
General Services Administration Public Buildings Service Region 8

About this file

This scope of work document outlines a project to repoint caulk and seal windows, associated brick, and cap stone mortar joints on the exterior of a federal building. The General Services Administration is soliciting bids to complete tuckpointing on the east, south, west, and north sides of the building, with options to complete additional sides. Bids should break pricing down by CSI division and include separate line items for materials, labor, equipment, subcontractors, overhead and profit. The selected contractor will have 90 days to complete the base work with 30 additional days for each option. Work must follow all applicable historic preservation standards and receive necessary approvals. The contractor will be responsible for lead and hazardous waste handling procedures, obtaining permits, and providing required submittals, manuals, and as-built drawings upon project completion.

View the file

Other files for this federal contract opportunity

Other files attached to tuck pointing brick exterior facade, newest first.
File Type Posted
WD ND13 1 3 20.pdf PDF
solicitation-tuckpointing.pdf PDF
USR v2 1 6 8 18.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1 | P a g e

CONSTRUCTION SCOPE OF WORK

U.S. GENERAL SERVICES ADMINISTRATION, ROCKY MOUNTAIN REGION 8

Date: 2/19/20 Revision: 5.0

Section 1: REPOINT CAULK AND SEAL

Section 2: Federal Building/Post Office

657 2nd Avenue North, Fargo, ND

Building Number: ND0046ZZ

Section 3: Contact List

Contracting Officer (CO) Name: Pam Burley Email: pam.burley@gsa.gov Address: 657 2nd Ave North, Room 244 Fargo, ND 58102 Phone (O): 701-566-6129

Property Manager Name: David Busching Email: david.busching@gsa.gov Address: 655 1st Ave North, Room 244 Fargo, ND 58102 Phone (O): 701 566-6125

Project Manager Name: Monica Macek Email: monica.macek@gsa.gov Address: 220 East Rosser Ave Bismarck, ND 58501 Phone (O): 701 566-6117 Phone (C): 701 390-8719

Section 4: Project Background & Project Description The intent of this project is to prevent water infiltration and damage from the capstone to the bottom of the second floor on all four sides of building ND0046ZZ. The contractor will repair caulking, repoint and seal windows, associated brick, and cap stone mortar joints. The base bid is the East side of the building, option 1 the South Side, option 2 the West side, option 3 the North side. There is also an option 4 for the contractor to remove rust and possible lead containing paint from the top lintel of all exterior windows and paint with rust inhibiting paint. The Federal Building and Post Office ND0046ZZ building is eligible for historic building listing.

Section 5: Project Objectives The contractor shall provide labor, materials, equipment and supervision necessary to perform:

a) Thoroughly inspect the caulking, mortar joints, control joints and brick at the identified windows and surrounding areas for cracks, open joints, caulk not adhering and any other means for water to infiltrate the building. The infiltration appears to increase with the presence of strong winds driving the rain into the building. The water typically is noticed at or above the lintel height.

b) The contractor shall remove and replace existing cracked and/or damaged caulking on the exterior wall areas (to include lineal areas above and around each side of windows). Sealant is to be polyurethane selected per ASTM C1193 Standard Guide for Use of Joint Sealants and suitable for adhesion to concrete and metal, standing water environment and UV resistant.

c) The windows measure approximately 20” x 72” and there is approximately 36” of masonry between each set of two.

d) There are a total of two hundred twenty eight (228) windows project with locations identified in the drawings.

e) The building cap stone and roof parapet contains several caulked joints that require repair. See drawings for details.

2 | P a g e

f) There are two control joints that run the entire perimeter of the building. The control joints may be either caulk or grout.

Inspect joints and repair as needed.

g) The contractor shall remove existing cracked and/or damaged building and masonry joints. Repair cracked masonry grout joints with new grout on exterior wall areas (to include lineal areas above and around each side of windows) PLEASE NOTE: Area for repointing will be based on inspection of each side of the building (approximate circumference -700 Ln Ft). Mortar used shall be an applicable product for masonry units used in and for North Dakota’s climate. Identify location and area of damaged brick, new replacement brick (if used) shall match existing building brick.

h) Contractor shall provide means for GSA personnel to closely inspect work while in progress.

i) A staging area will be determined by mutual agreement after contract award.

j) This information is provided for bidding purposes only. The contractor is advised to schedule a site visit through GSA

Project Manager or Property Manager. Contractor shall field-verify the exact information and dimensions required for use in completing the specified work and submitting an offer.

k) Work Area is elevated. Contractor shall provide non-penetrating roof anchoring, roof swing lift, scaffolding or lift to access elevation indicated. Lifts must be capable of reaching from the street level. All equipment shall comply with all applicable regulations.

l) Contractor shall confer with City of Fargo for compliance if sidewalk or street access is to be impaired.

APPLICABLE PUBLICATIONS

1. Publications listed below form a part of this specification to extent referenced. Publications are referenced in the text by basic designation only.

a. American Society for Testing and Materials (ASTM):

b. C67-07 ..... Brick and Structural Clay Tile, Sampling and Testing

c. C216-07 .... Facing Brick (Solid Masonry Units Made From Clay or Shale)

d. C270-07 .... Mortar for Unit Masonry

2. International Masonry Institute: Recommended Practices and Guide Specifications for Cold Weather Masonry Construction.

PRODUCTS

REPLACEMENT CAULKING

1. Polyurethane selected per ASTM C1193 Standard Guide for Use of Joint Sealants and suitable for adhesion to concrete and metal, standing water environment and UV resistant.

EXECUTION

REMOVAL OF EXISTING CAULKING

1. Cut out existing damaged or cracked caulking and remove to a depth of 19 mm (3/4-inch), or until sound mortar is reached. Take care to not damage edges of existing masonry units to remain.

2. Remove dust and debris from the joints by brushing, blowing with air or rinsing with water. Do not rinse when temperature is below freezing.

CUT OUT OF EXISTING MORTAR JOINTS

1. Cut out existing mortar joints (both bed and head joints) and remove by means of a toothing chisel or a special pointer's grinder, to a uniform depth of to 19 mm (3/4-inch), or until sound mortar is reached. Take care to not damage edges of existing masonry units to remain.

2. Remove dust and debris from the joints by brushing, blowing with air or rinsing with water. Do not rinse when temperature is below freezing.

JOB CONDITIONS

1. Protection: Protect newly pointed joints from rain, until pointed joints are sufficiently hard enough to prevent damage.

2. Cold Weather Protection:

a. Repointing may be performed in freezing weather when methods of protection are utilized.

b. Comply with applicable sections of "Recommended Practices for Cold Weather Construction" as published by

International Masonry Industry All Weather Council.

3 | P a g e

c. Existing surfaces at temperatures to prevent mortar from freezing or causing other damage to mortar.

INSTALLATION OF REPOINTING MORTAR

1. Immediately prior to application of mortar, dampen joints to be repointed. Prior to application of pointing mortar, allow masonry units to absorb surface water.

2. Tightly pack mortar into joints in thin layers, approximately 6 mm (1/4-inch) thick maximum.

3. Allow layer to become "thumbprint hard" before applying next layer.

4. Pack final layer flush with surfaces of masonry units. When mortar becomes "thumbprint hard", tool joints.

TOOLING OF JOINTS

1. Tool joints with a jointing tool to produce a smooth, compacted, concaved joint.

2. Tool joints in patch work with a jointing tool to match the existing surrounding joints.

REPLACEMENT OF MASONRY UNITS

1. Cut out mortar joints surrounding cracked and/or damaged masonry units that are to be removed and replaced.

a. Units removed may be broken and removed, providing surrounding units to remain are not damaged.

b. Once the units are removed, carefully chisel out the old mortar and remove dust and debris.

c. If units are located in exterior wythe of a cavity or veneer wall, exercise care to prevent debris falling into cavity.

2. Dampen surfaces of the surrounding units before new units are placed.

a. Allow existing masonry to absorb surface moisture prior to starting installation of the new replacement units.

b. Butter contact surfaces of existing masonry and new replacement masonry units with mortar.

c. Center replacement masonry units in opening and press into position.

d. Remove excess mortar with a trowel.

e. Point around replacement masonry units to ensure full head and bed joints.

f. When mortar becomes "thumbprint hard", tool joints.

CLEANING

1. Clean exposed masonry surfaces on completion.

2. Remove mortar droppings and other foreign substances from wall surfaces.

3. First wet surfaces with clean water then wash down with a solution of soap-less detergent specially prepared for cleaning brick.

4. Brush with stiff fiber brushes while washing, and immediately thereafter hose down with clean water.

5. Free clean surfaces from traces of detergent, foreign streaks or stains. Protect materials during cleaning operations including adjoining construction.

6. Use of muriatic acid for cleaning is prohibited.

OPTION 2

1. The contractor will remove rust and paint window lintels above all windows. The paint may contain lead.

Permitting/Regulations/Codes

Contractor shall be responsible for obtaining all necessary local, state, and federal permits and licenses and payment of related fees.

Contractor shall comply with all applicable federal, state, and local regulations, codes, as well as GSA policy, including but not limited to:

1. OSHA Lead Occupational Safety and Health Standards - 29 CFR 1910.1025

2. OSHA Lead Safety and Health Regulations for Construction - OSHA 29 CFR 1926.62

3. EPA Resource Conservation and Recovery Act (RCRA) – 40 CFR 260 et seq.

4. U.S. Department of Transportation Hazardous Material Transportation Regulations – 49 CFR 171 and 172

5. North Dakota Hazardous Waste Law - ND Century Code Chapter 23.1-04

6. North Dakota Hazardous Waste Management Rules - ND Administrative Code Article 33-1.24

7. GSA PBS-P100, current edition.

Lead Work Practices

4 | P a g e

Contractor's OSHA competent person shall determine what work practices, controls, PPE, training, etc. are required to comply with 29 CFR 1926.62.

Contractor shall demarcate the work area and post proper signage in accordance with 29 CFR 1926.62 in all work areas, warning of hazards and restricting access until all lead work is complete.

If work is to occur in the vicinity of any outside air intakes or other HVAC system components, Contractor shall perform work while the HVAC system is off and isolate the intake with a layer of 6-mil poly sheeting to serve as a critical barrier.

Contractor shall lay 6-mil polyethylene (poly) sheeting extending a minimum of 10 feet away from the work area.

Contractor shall stabilize failing paint or remove paint by utilizing lead-safe work practices. Mechanical, dry, media blasting, or other similar high dust and debris generating removal methods shall require greater engineering controls, such as HEPA vacuum attachments and/or full containments. Use of these types of removal methods shall require authorization and approval by GSA’s Regional Industrial Hygienist prior to the commencement of work.

The Contractor shall HEPA vacuum all ground areas to remove all visual debris that is dispersed beyond the 6-mil poly ground cover. The Contractor shall clean by HEPA vacuum at the end of each day and at other times as necessary during work activity to prevent paint chips and debris from being spread beyond the ground cover sheeting.

Waste Disposal

Contractor shall be responsible for the proper characterization and management of lead bearing waste in accordance with applicable federal, state, and local hazardous waste regulations.

All lead containing debris or lead bearing waste shall be double bagged in 6-mil poly, labeled polyethylene bags, containerized, and transported and properly disposed of offsite at an appropriate and permitted/licensed disposal facility.

Lead containing debris and lead bearing waste shall either be assumed to be hazardous waste due to the characteristic of toxicity (Lead, EPA Waste Code D008) or have representative wastestream samples submitted to an accredited analytical laboratory for analysis via EPA Method SW-846 Test Method 1311: Toxicity Characteristic Leaching Procedure (TCLP).

As applicable, the waste characterization and manifest documentation shall be provided to GSA as part of the deliverable.

Deliverables

Lead Pre-Work Submittals

Contractor shall submit a Method of Procedures (MOP) to the Project Manager (PM) for approval prior to the commencement of work. At a minimum the lead MOP shall include:

1. Name and qualifications of Contractor’s lead competent person

2. Description of lead work practices, administrative and engineering controls to be utilized.

3. Name and address of proposed waste disposal facility

4. Copies of safety data sheets (SDSs) for all chemical products to be used

Final Deliverable

Contractor shall submit a written final deliverable including the following:

1. Description of lead work performed including quantity and location of lead paint stabilized or removed.

2. A description of lead work practices, administrative and engineering controls used

3. Lead worker and supervisor training and certification

4. Legible copies of daily logs

5. Legible copies of waste manifests and related waste disposal documentation

5 | P a g e

RUST REMOVAL

1. The recommended method for the removal of the lead base paint is the use of paint stripper. This means and methods decrease the odds of the particles from becoming airborne. Contractor is to submit methods and procedures for the abatement for approval. Sandblasting will not be permitted.

2. The contractor shall comply with the OSHA Lead in Construction Standard at 29 CFR 1926.62.

3. The contractor must have an OSHA defined competent person that will determine what controls and work practices are required to minimize the generation of lead dust, prevent exposure to their workers and the public.

4. The contractor shall have prompt clean up procedures in place and keep the area free of debris.

5. The contractor shall properly dispose of the lead base material considered to be hazardous waste.

6. Most likely the material will be considered hazardous waste due to the characteristics of toxicity (EPA Waste Code D008, Lead) unless a toxicity characteristic leaching procedure (TCLP) test of waste proves otherwise.

7. The contractor shall take extra precaution while preserving lintel, do not damage the existing historical building in any way.

8. The contractor shall prime and paint the metal to match as close to the original color as possible. Paint must be rust and weather resistant.

9. The contractor shall use proper signage to keep the public from entering construction zones.

10. Remove dust or chemical residue and prepare surface for paint.

PAINTING

1. Spot prime bare or rusted spots on metal with a rust inhibitive primer

2. New paint shall match existing paint color.

3. Furnish and install 1-2 coats (top coat) per manufacturer recommendations.

4. Free clean surfaces from traces of remover, primer, paint streaks or stains. Protect existing non-painted surfaces during cleaning operations including adjoining construction.

5. Use of muriatic acid for cleaning is prohibited.

Section 6: Proposal Pricing & Site Walk

2) Pre-proposal Site Visit Meeting:

a) The site visit shall consist of a meeting to review construction requirements followed by a walk-thru of the project site. The meeting shall be attended by the contractor and GSA project personnel, and appropriate sub-contractors.

b) Review existing conditions of the project area including any field verification.

c) Review the solicitation/evaluation requirements.

d) Contact the Program Manager for a site visit.

3) Cost Proposal Requirements:

When submitting a proposal, provide a cost breakdown for each task into the following categories: Materials, equipment, labor hours, subcontractor's quotes, overhead, profit, and bond. Pricing shall be broken down by Construction Specification Institute (CSI) divisions.

a) Base East, West and South Elevations

b) Option 1 – North Elevation

c) Option 2 - Remove Rust and Paint Window Lintels

Section 7: Period of Performance

Once notice to proceed has been issued, the contractor has 90 calendar days to complete the base work plus 30 calendar days for each option to complete the project. The contractor must also promptly begin the badging process at the time of notice to proceed. Extensions will be granted for unforeseen conditions and other factors outside of the contractor’s control at the Contracting Officer’s discretion.

Section 8: Universal Scope Requirements

6 | P a g e

ALL of the requirements in this section are MANDATORY for ALL GSA projects

See the attached Universal Scope Requirements document for the full details outlining each item

Failure to comply with any and all of the requirements will result in the project not being accepted as complete

REQUIREMENTS for ALL Projects (Construction, Design & Design/Build)

a. Safety and Health Program

b. Lead Containing Paint / Lead Based Paint

c. Accessibility

d. Green Purchasing

e. Construction Indoor Air Quality (IAQ) Management Plan

f. Construction Waste Diversion

Section 9: Submittals

1) Contractor shall submit a Method of Procedures (MOP) to the GSA Delivery Project Manager (PM) for approval prior to commencement of work. At a minimum, the MOP shall include:

a) Brief narrative describing method of accomplishment, construction techniques, etc.

b) Project schedule (to include critical path, major milestones, long lead time items, mob & de-mob, inspection dates, substantial completion, and occupancy dates)

c) Phasing schedule (if necessary)

2) Manufacturer's specifications, instructions and material specification sheets in original form

3) Submittal register/ log for all products specified to establish a standard of quality to include. Submittal register response by the government shall be (14) calendar days or less. For pricing purposed please assume 2 hard copies of submittals and 1 electronic copies to be sent to the project manager. Distribution list including final quantities will be finalized after receipt of the submittal log/ register by GSA project manager.

4) If product samples are not submitted in a timely fashion, any delays caused by the contractor will not warrant a time extension.

After completion of all work, the Contractor shall submit to the project manager the manufacturer's specifications, instructions and material specification sheets in original form. Additionally, the Contractor shall submit all inventory changes (removals, additions, upgrades, etc., and new condition codes) to the COR.

5) Submittal response by the government shall be (14) calendar days or less.

6) Submittals required include:

a) Caulk

b) Brick Cleaning Detergent

c) Mortar

d) Replacement Brick

e) Option 2 - Rust Removal and Painting

i. Rust Removal Process or Chemicals

ii. Rust Inhibiting Primer and Paint

iii. Paint Color

Section 10: General Requirements

1) Contractor Use of the Premises

a) During the period of the project, the contractor will have access to the site only during business hours of 7:00 am 6:00

pm. No on-site work shall be performed outside these hours or on holidays unless otherwise directed by the Contracting Officer. The contractor will need to coordinate with the Contracting Officer to arrange access to the parking lot. The contractor shall make every effort to cause a minimum of damage to parking lots, any other paved areas, any items that need to be moved during the course of the project, and any areas not included in this scope of work. Any damage caused will be repaired at the contractor’s expense.

2) Progress Meetings

a) Progress meetings are not required for this project. The project manager and building team representative shall make daily inspections of the work progress.

3) Equipment The contractor shall provide all equipment associated with the entire project, operate in a safe manner and adhere to all OSHA and GSA standards.

7 | P a g e

4) Equipment and Material Storage The contractor shall provide and store all equipment, the materials specified above, and any other materials required completing the project. The materials are required to be kept clean and dry throughout the duration of the project.

Contractor to coordinate with building manager for location of storage sheds.

5) Sanitary Facilities Provide and maintain temporary toilet facilities in accordance with State Health Department and GSA requirements.

6) Electricity, Water, and Gas GSA will pay for electricity, water, and gas during the course of this project. The contractor is responsible for making connections to the existing systems. Temporary electrical work shall meet the requirements of NFPA 70-1996 (NEC), Article

305. When temporary connections are removed, restore existing utility services to their original condition.

7) Protection of Public The building site will continue to be used by tenants. The contractor shall fence, barricade, or otherwise block off the immediate work area to prevent unauthorized entry. The contractor shall illuminate barricades and obstructions at night and maintain safe building access and egress for tenants.

8) Housekeeping The project site shall be kept in a neat, orderly, and safe condition at all times. The contractor shall provide enough containers for collecting construction debris and construction materials to be recycled. The contractor shall wet down dry materials and rubbish to prevent blowing dust and keep volatile wastes in covered containers.

9) Transportation and Deliveries The contractor shall arrange deliveries of materials in accordance with construction schedules; coordinate with COR to avoid conflict with other tenants and other work conditions at the site. Contractor must make GSA PM & CO aware of any lead times that may affect the project schedule.

10) Cleaning Before scheduling the final inspection, the Contractor shall accomplish six items: (1) Remove all tools, equipment, surplus material, and rubbish; (2) Restore or refinish, to original condition, surfaces that are damaged due to the work of this contract; (3) Remove grease, dirt, stains, foreign materials, and labels from finished surfaces; (4) Thoroughly clean building interiors; (5) Pickup all construction debris from the site; and (6) At time of final inspection, project shall be thoroughly cleaned and ready for use.

11) Disruptive Work All painting, staining, or other activity which may cause noxious or undesirable fumes and/ or any noisy work that may be disruptive to the tenants/ public must be performed after normal working hours. The use of paint or stain that does not generate odors is preferred and may be required if the space will be occupied the following day with prior written approval from GSA.

Section 11: Badging & Security

1) Contractor is responsible to follow GSA’s security and badging requirements as detailed in the attached Badging & Security Requirements (Vendor Fitness Determination Training Manual).

2) US Access shared enrollment centers can be found at fedidcard.gov. Travel distances to the nearest center should be accounted for during the badging process.

Section 12: Payments

1) Information regarding payment requests and payment is in the solicitation/ contract. Please contact the CO if you have any questions regarding payments.

Section 13: Substantial Completion & Final Inspection

1) When project, or designated portion of project is complete, request a final inspection. Upon receipt of request that project is substantially complete, the Contracting Officer will proceed with the inspection within ten days of receipt of request or will advise the contractor of items that prevent the project from being designated substantially complete.

2) Red-lined drawings and CAD and/or BIM as-built drawings, and field training for Operations and Maintenance (O&M) personnel shall be provided at completion of project. Maintain one complete set of contract drawings. Clearly mark changes, deletions, and additions using GSA CAD Standards to show actual construction conditions. Show additions in red, deletions in green, and special instructions in blue print. Provide to GSA within timeframe negotiated at time of award.

3) The contractor shall provide O&M manuals. The O&M manuals shall contain the following:

o Executed Warranties (at project completion) http://fedidcard.gov/

8 | P a g e o Maintenance and operation manuals

Section 14: Historic Building: The Federal Building/Courthouse in Fargo, North Dakota has been determined eligible for listing on the National Register of Historic Places. As such, projects in the building are required to follow the guidelines set forth in the following publications.

ADM 1020.2 GSA Procedures for Historic Properties

The National Historic Preservation Act of 1966, as amended and Executive Order 11593.

The Secretary of the Interiors Standards and Illustrated Guidelines for Rehabilitating Historic Buildings, Revised 1992 (36

CFR 67).

GSA Technical Preservation Documents: https://www.gsa.gov/real-estate/historic-preservation/historic-preservation-policy-tools/preservation-tools-resources/technical-documents

National Park Service Preservation Briefs: http://www.nps.gov/tps/how-to-preserve/briefs.htm

National Park Service Preservation Brief No. 2 Repointing Mortar Joints in Historic Buildings:

https://www.nps.gov/tps/how-to-preserve/briefs/2-repoint-mortar-joints.htm

Any work that could alter the building’s historic fabric, character, or appearance, both on the interior and exterior must first be approved by the GSA Historic Preservation Officer/Historic Preservation Specialist and the North Dakota State Historic Preservation Office (SHPO) before any actions are to take place.

No construction work can begin until Section 106 of the National Historic Preservation Act (NHPA) is complete.

Section 15: Attachments

1) Universal Scope requirements

2) Badging & Security requirements (Vendor Fitness Determination & Training Manual)

3) Building drawings, etc.

9 | P a g e

Detail Drawings

INSPECT AND REPAIR MORTOR

JOINTS, REPLACE BRICKS AS

REQUIRED

GROUT

10 | P a g e

Typical Detail of Window and masonry

Pictures

Parapet Cap, Windows, and Masonry Joints Typical

East Side of Building

11 | P a g e

South Side of Building

West Side of Building

12 | P a g e

North Side of Building

Parapet and Cap Stone Joint Inspection Repair Horizontal and Vertical Stone Joints as Required

Remove Rust and Paint Window Lintel