SOW.pdf

PDF 104 KB Posted

Attached to
EAS Generator 1 & 2 Overhaul Federal contract opportunity
Solicitation number
FA521520Q0001
Issued by
Department of the Air Force Pacific Air Forces

About this file

This statement of work outlines the top end overhaul of two CAT C280 generator units at Eareckson Air Station in Alaska. The work includes replacement of cylinder heads, injectors, lifter springs, water pumps, oil filters, temperature regulators and other parts. Inspection of alternator bearings, cylinder blocks, camshafts, lifters, rocker arms, valves, pushrods and other engine components is also required. Testing and adjustment of valves, injectors, engine wiring, gauges and safety systems must be performed. The contractor will provide estimated start and completion dates, personnel details, work days required and a post-inspection report. The Air Force intends to award this sole source purchase order to NC Machinery under FAR 6.302-1 by January 2020 for the overhauls, which must be completed on the first unit by September 2020 and the second unit by March 2020.

View the file

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

EARECKSON AIR STATION

Power Plant Unit 1 & 2

Top End Overhaul

STATEMENT OF WORK

Project Number

VNMH190008

Date: 31 October 2019

BACKGROUND

Eareckson Air Station (EAS) is located on Shemya Island, a windswept island at the Western end of the Aleutian Island chain, approximately 1,500 air miles southwest of Anchorage, Alaska.

Fog, blowing rain and/or snow with temperatures ranging from twenty to forty degrees are common throughout most of the year.

The EAS Power Plant is the sole source of power on the island, with the exception of Emergency Power Units at several of the critical facilities. Power is generated by 4.4 MW Alternators turned by CAT 280 diesel engines. Four units, identically installed in 2013-2014 are available on a rotational basis with two on line at any time. Note: each unit operating alone is capable of carrying the entire load of the island for varying lengths of time and load requirements.

The first and second of the four units are now due for a top end overhaul, measured by 24,000 hours of operation or 4,000,000 gallons of fuel consumed. The second unit is necessary to be complete by March 2020, while the first unit is needed to be complete by September 2020.

SCOPE OF WORK

The Government wants to have a “Top End Overhaul” performed on the CAT C280 Unit 1 & 2:

these units were placed in operation in 2013, in the EAS Power Plant.

Contractor shall provide a written quotation listing the work to be performed, parts and tools required including transportation costs and man-hours required, to include billeting and personnel transportation costs.

SPECIFICS

Work shall include, but not limited to:

REPLACEMENT PARTS

Cylinder Heads Injectors Injector Harness Lifter Springs

TOP END OVERHAUL EAS PP UNIT 1 & 2 VNMH190008

P a g e | 2

Jacket Water Pump Auxiliary Water Pump Turbo Cartridge Oil Filter Breathers Temperature Regulators Priming Pump Fuel Filter Water Separator

INSPECTED ITEMS

Inboard and Outboard Alternator Bearings – Note materials and labor required to correct oil leakage Cylinder Block Deck Spacer Places (Note location if replaced) Cylinder Packs Camshaft Inspect (through cam doors) Lifters (Note location if replaced) Rocker Arms Rocker Shafts (Note location if replaced) Valves Bridges Pushrods Rocker Boxes (Note location if replaced) Valve Covers (Note location if replaced) Front Crankshaft Seal (for leaks) Front Cover Rear Crankshaft Seal (for leaks) Rear Cover Side Covers (and oil gallery covers) Cam Covers Regulator housings Hoses Engine wiring Harness Gauges and Panel Governor Actuator

TESTING-ADJUSTING & SAFETIES

Valve Setting - Intake Valve Setting – Exhaust Injector Setting E-Stop High Water Temp Shutdown Low Oil Pressure Shutdown Low Water Level Alarm

TOP END OVERHAUL EAS PP UNIT 1 & 2 VNMH190008

P a g e | 3

DELIVERABLES

Contractor will provide the Power Plant Operations Contractor (Chugach Federal Solutions Inc.)

the following:

1. Earliest Anticipated Start Date consistent with delivery of materials, tools and personnel to the job site.

2. Estimated completion date.

3. Number of personnel.

4. Number of work days.

5. Written report of inspection findings and any recommendations for best operations.

2019-10-31T08:59:49-0800
LOVE-WATKINS.FRANCESCA.LYNESE.1388014250

File details come from the government source that posted it. Updated .