This is a Statement of Work (SOW) for repair and calibration services of the Joint Combined Aircrew System Tester (JCAST) issued by the National Aeronautics and Space Administration (NASA) Armstrong Flight Research Center in Edwards, California.
The contractor shall perform a complete diagnostic evaluation, repair, and calibration of the JCAST unit and its associated subcomponents (ACAST, Valve Test Accessory, Relief Valve Test Accessory) to Original Equipment Manufacturer (OEM) standards. The JCAST is critical for testing CRU-122 oxygen regulators, pressure suits, g-garments, and integrated aircrew life support systems in support of programs such as the Low Boom Flight Demonstrator. All work must comply with applicable Air Force Technical Orders (T.O. 15X6-4-8-2 and T.O. 33D2-10-141-1), utilize OEM parts and proprietary procedures, and meet Chemring-approved standards with calibration certification traceable to those standards. The contractor must complete repairs within Chemring's standard 14-16 week timeline from equipment receipt and return all equipment in ready-for-use condition with proper packaging for safe transport. The period of performance is 12 months from award date to allow for repair cycles, calibration lead time, shipping, and administrative requirements. Deliverables include inspection and diagnostic reports, calibration certificates, repair summary documentation, verification and functional test results, and all required documentation demonstrating equipment acceptance and work completion. Travel is not applicable. Travel requirements and other special considerations are to be determined individually for each piece of equipment.
View the file
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFP #
STATEMENT OF WORK
Title: Repair and Calibration of Joint Combined Aircrew System Tester (JCAST)
National Aeronautics and Space Administration Armstrong Flight Research Center Edwards, California
Table of Contents
1.0 Background
2.0 Objectives
3.0 Requirements
4.0 Deliverables
5.0 Period of Performance
6.0 Travel
7.0 Other Special Requirements and Considerations
RFP/Contract No. Ordering, receiving and sustaining explosive items 05 June 2024
1.0 Background
AFRC utilizes the Joint Combined Aircrew System Tester (JCAST) to support life support testing requirements for programs such as the Low Boom Flight Demonstrator. The JCAST is used in conjunction with its associated subcomponents (ACAST, Valve Test Accessory, Relief Valve Test Accessory), and is essential for the proper testing of CRU‑122 oxygen regulators, pressure suits, g‑garments, and integrated aircrew life support systems.
2.0 Objectives
The objective of this requirement is to ensure the full restoration, calibration, and verification of the AFRC JCAST system to OEM standards so that accurate, safe, and repeatable life support testing can be performed in support of flight operations
.3.0 Requirements
The contractor shall:
Conduct full diagnostic evaluation of the JCAST unit and all accessories.
Perform all necessary repairs using OEM parts and proprietary procedures.
Calibrate the JCAST and subcomponents using the OEM technical publication Perform functional testing to validate leak rates, pressure profiles, and performance criteria as required for aircrew ensemble testing.
Provide a certification of calibration traceable to Chemring-approved standards.
Ensure all work complies with applicable Air Force Technical Orders (T.O. 15X6‑4‑8‑2, T.O.
33D2‑10‑141‑1). 2 Return equipment in ready‑for‑use condition, packaged for safe transport.
Complete repairs within Chemring’s standard 14–16 week timeline from receipt of equipment.
4.0 Deliverables
Contractor shall provide:
Inspection results and diagnostic report Calibration certificate(s) Repair summary documentation Verification and functional test results Proper packaging and shipment back to AFRC All required documentation demonstrating equipment acceptance and completion of work
RFP/Contract No Ordering, receiving and sustaining explosive items
5.0 Period of Performance
The period of performance is 12 months from award date. This allows for repair cycles, calibration lead time, shipping, and administrative requirements.
6.0 Travel
Not applicable
7.0 Other Special Requirements and Considerations
To be determined individually for each piece of equipment.
RFP/Contract No Ordering, receiving and sustaining explosive items
REVISIONS
Revision Number Date Brief Summary of Changes
Base
File details come from the government source that posted it. Updated .