SOW Boiler 2 Repair Tubing_v2.docx
DOCX document 66 KB Posted
- Attached to
- Retubing of Boiler Federal contract opportunity
- Solicitation number
- 12405B24Q0065
About this file
This statement of work and solicitation call for bids to replace boiler tubes in Boiler #2 located at the United States Department of Agriculture Agricultural Research Service facility in Athens, Georgia. The contractor will remove existing fire tubes, clean tube sheets and holes, install new tubes that meet manufacturer specifications, test and inspect the completed work, and provide certification according to NB requirements. Bids are due by February 2, 2024 with work to begin no more than six weeks after award. The contract will be a firm fixed price award made to the technically acceptable bid with the lowest price.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Service Provisions 1117611.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
United States Department of Agriculture Agricultural Research Service
STATEMENT OF WORK
Replace tubes in Boiler #2
U.S. National Poultry Research Center 950 College Station Road Athens, Georgia 30605
1. Scope of Work The contractor shall provide all professional services necessary to complete the removal of the existing tubes and the installation of new tubes in Boiler #2.
The contractor shall include all services and field labor, equipment (including cranes, rigging and material handling equipment), materials, testing and personal protective equipment necessary to perform the work.
Equipment and services provided by the Government for contractor use are listed below:
· None provided
1.1 Base Bid
The contractor shall provide a detailed proposal and cost breakdown for the entire project including submittals for proposed equipment and materials.
Contractor must be registered in System for Award Management, (SAM), prior to submitting a bid.
2. Codes and Standards Applicable Codes and Standards apply and are not limited to the following
| ANSI - | American National Standards Institute. |
| ASME - | American Society of Mechanical Engineers. |
NBBI - National Board of Boiler and Pressure Vessel Inspectors
| NEC - | National Electrical Code, NFPA 72. |
| OSHA - | Occupational Safety and Health Administration |
| ADA – | Americans with Disabilities Act |
All work must meet Local, State and Federal codes, and latest IBC codes.
Project Summary Replacement of all boiler tubes in Boiler #2.
Manufacturer: Cleaver Brooks Boiler model number: CRI-200-350-200 Boiler serial number: OLI07260-2009
1) Remove existing fire tubes.
2) Clean tube sheets and holes.
3) Install 175 2-1/2”, .105 mw sa178 tubes. New tubes must meet or exceed the boiler manufacturer’s code of construction values. New tubes will be rolled, beaded and seal welded in place.
4) Complete tube installation will be tested and inspected and certified in accordance with NB requirements.
5) Boiler will be placed back in service and checked for proper operation.
6) Complete Repair, Testing and Inspection records including Form R-1 will be provided to USDA before final inspection and acceptance.
The facility will be occupied during construction activities. All work shall be scheduled in advance and coordinated with the facility representative to minimize the disruption to traffic, daily operations and research programs.
3. Safety The contractor will submit a Site Safety Specific Plan (SSSP) in industry recognizable format to the Contracting Officer within 14 days of contract award. The Government shall review the SSSP prior to the start any construction activities.
Safety and health matters, as they relate to the work, are the exclusive responsibility of the contractor. The contractor shall furnish, erect, and maintain barricades, warning lights, signs, guards, or take other precautions that may be required by law or local authorities for the protection and security of the grounds, facilities, and personnel.
4. Contractor Requirements The contractor shall provide a complete and functional installation, including all labor, supervision, tools, materials, equipment, apparatus, transportation, rigging and other equipment and services necessary to accomplish the work in accordance with the intent and meaning of this statement of work.
The project work shall be performed per the following guidelines:
1) Contractor will verify all dimensions and site conditions prior to beginning work.
2) The contractor shall always be responsible for protecting his work and ensuring the safety of his crew and ARS employees.
3) Contractor shall remove and dispose of all construction related materials from all work areas daily and remove these waste materials from the site weekly.
4) Contractor is required to manage the project and consult with the Government prior to beginning all work.
5) Contractor shall perform work in a manner that minimizes the impact to daily operations of the facility and its workers. The building will be occupied during construction work.
6) All work is to be performed according with building codes, ordinances and laws of the Authority having jurisdiction on the project. When the requirements of the building codes, ordinances, and laws conflict with any other part of the building codes, ordinances and laws, the most restrictive requirement shall prevail.
5. Material Submittals Submittals and O&M documentation must be provided for all materials used on this project.
6. Damage to Property:
The Contractor shall protect the work, the site, and all existing property and structures within the limits of the construction activities or that may be affected thereby until acceptance of the work. Any damage to property shall be repaired to pre-damaged condition to the satisfaction of the USDA.
7. Inspection and Acceptance A government representative shall inspect and approve the work. The Contractor shall schedule inspection a minimum of 2 days in advance.
8. Period of Performance This boiler repair is extremely urgent and can be detrimental to operations and the mission of this research center. If boiler 1 goes down we will lose the ability to heat the building, operation of autoclaves and other sterilizing equipment. With it being the time of the year, it is this will cause a complete building shut down and all domestic water lines, fire protection and heating water will have to be drained to prevent freezing and rupturing of piping.
Furthermore, the boiler controls are proprietary and obsolete. Procuring new components is almost impossible with months of lead time. Boiler 2 suffered a Modbus control failure prior to the tube rupturing which leads us to believe but not confirmed yet, that the boiler may have run low on water causing the tubes to overheat and crack. Once the tubes are replaced boiler 2 will not run until controls are replaced due to the control failure.
Work must begin no more than 6 weeks after the awarding of the contract.
8.1 Work Hours:
Generally, contractor work hours shall be Monday through Friday, 7:00 A.M. to 4:30 P.M. except on Government holidays for most of the installation work. Tie-in or other work requiring outages will be performed after hours (pre-arranged at least 48 hours in advance).
Any changes to work schedule shall be submitted to Contacting Officer for written approval prior to the schedule change.
9. Guaranty The contractor shall provide and submit a single guarantee stating that all portions of the work are in accordance with Contract requirements. Guarantee all work against faulty and improper material and workmanship for a period of one (1) year from date of final acceptance by the USDA, except where manufacturer guarantees or warranties are for longer terms. The contractor shall correct any deficiencies which occur during the guarantee period within 24 hours after notification.