Solicitation W912BV20Q0134.pdf

PDF 1 MB Posted

Attached to
Snake Creek Gate Shack Federal contract opportunity
Solicitation number
W912BV20Q0134
Issued by
Department of the Army Corps of Engineers Engineering District Tulsa

View the file

Other files for this federal contract opportunity

Other files attached to Snake Creek Gate Shack, newest first.
File Type Posted
Amendment 0002.pdf PDF
W912BV20Q0134 Amend 0001.pdf PDF
Appendex A.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SEE ADDENDUM

(No Collect Calls)

W912BV20Q0134 17-Jul-2020

b. TELEPHONE NUMBER

918.669.7173

8. OFFER DUE DATE/LOCAL TIME

02:00 PM 14 Aug 2020

5. SOLICITATION NUMBER 6. SOLICITATION ISSUE DATE

AUTHORIZED FOR LOCAL REPRODUCTION

PREVIOUS EDITION IS NOT USABLE

STANDARD FORM 1449 (REV. 2/2012)

Prescribed by GSA – FAR (48 CFR) 53.212

(TYPE OR PRINT)

(SIGNATURE OF CONTRACTING OFFICER)

ADDENDA X ARE

26. TOTAL AWARD AMOUNT (For Gov t. Use Only )

23.

CODE 10. THIS ACQUISITION IS

SUCH ADDRESS IN OFFER

17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT

BELOW IS CHECKED

TELEPHONE NO.

W912BV9. ISSUED BY

18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a. UNLESS BLOCK

7. FOR SOLICITATION

INFORMATION CALL:

a. NAME

AMY C FEEMSTER

2. CONTRACT NO. 3. AWARD/EFFECTIVE DATE 4. ORDER NUMBER

(TYPE OR PRINT)

30b. NAME AND TITLE OF SIGNER 30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER

30a. SIGNATURE OF OFFEROR/CONTRACTOR 31a.UNITED STATES OF AMERICA

1 27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1. 52.212-4. FAR 52.212-3. 52.212-5 ARE ATTACHED.X

25. ACCOUNTING AND APPROPRIATION DATA

1. REQUISITION NUMBER

20.

ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED.

OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, AND 30

SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS

ARE NOT ATTACHED

27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA ARE ARE NOT ATTACHED

(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE

SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:

. YOUR OFFER ON SOLICITATION

28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN

% FOR:SET ASIDE:UNRESTRICTED OR X

SMALL BUSINESSX

17a.CONTRACTOR/ CODE FACILITY

OFFEROR CODE

CONTRACTING DIV

US ARMY CORPS OF ENGINEERS, TULSA DISTRICT

2488 E. 81ST STREET

TULSA OK 74137-4290

18a. PAYMENT WILL BE MADE BY CODE

RATED ORDER UNDER

DPAS (15 CFR 700)

13a. THIS CONTRACT IS A

13b. RATING

CODE15. DELIVER TO CODE 16. ADMINISTERED BY

SEE SCHEDULE

12. DISCOUNT TERMS11. DELIVERY FOR FOB DESTINA-

TION UNLESS BLOCK IS

MARKED

SEE SCHEDULE

14. METHOD OF SOLICITATION

RFQ IFB RFPX

918-669-7436FAX:

TEL: SERVICE-DISABLED

VETERAN-OWNED

SMALL BUSINESS

8(A)

HUBZONE SMALL

BUSINESS

SIZE STANDARD:

NAICS:

321992

X

OFFER DATED

29. AWARD OF CONTRACT: REF.

DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY

COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND

EMAIL:

TEL:

31c. DATE SIGNED

SEE SCHEDULE

SCHEDULE OF SUPPLIES/ SERVICESITEM NO. QUANTITY UNIT UNIT PRICE AMOUNT

24.22.21.19.

WOMEN-OWNED SMALL BUSINESS (WOSB)

ELIGIBLE UNDER THE WOMEN-OWNED

SMALL BUSINESS PROGRAM

EDWOSB

32g. E-MAIL OF AUTHORIZED GOVERNMENT REPRESENTATIVE

SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS

(CONTINUED)

PAGE 2 OF55

ACCEPTED, AND CONFORMS TO THE CONTRACT, EXCEPT AS NOTED: ______________________________________________________

32a. QUANTITY IN COLUMN 21 HAS BEEN

RECEIVED INSPECTED

32b. SIGNATURE OF AUTHORIZED GOVERNMENT

REPRESENTATIVE

32c. DATE 32d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT

REPRESENTATIVE

32e. MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE 32f . TELEPHONE NUMBER OF AUTHORIZED GOVERNMENT REPRESENTATIVE

37. CHECK NUMBER

FINALPARTIALCOMPLETE

36. PAYMENT35. AMOUNT VERIFIED

CORRECT FOR

34. VOUCHER NUMBER

FINAL

33. SHIP NUMBER

PARTIAL

38. S/R ACCOUNT NUMBER 39. S/R VOUCHER NUMBER 40. PAID BY

41a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAYMENT

41b. SIGNATURE AND TITLE OF CERTIFYING OFFICER 41c. DATE

42a. RECEIVED BY (Print)

42b. RECEIVED AT (Location)

42c. DATE REC'D (YY/MM/DD) 42d. TOTAL CONTAINERS

STANDARD FORM 1449 (REV. 2/2012) BACK

Prescribed by GSA – FAR (48 CFR) 53.212

AUTHORIZED FOR LOCAL REPRODUCTION

PREVIOUS EDITION IS NOT USABLE

SEE SCHEDULE

20.

SCHEDULE OF SUPPLIES/ SERVICES

21.

QUANTITY UNIT

22. 23.

UNIT PRICE

24.

AMOUNT

19.

ITEM NO.

W912BV20Q0134

Section SF 30 - BLOCK 14 CONTINUATION PAGE

INSTRUCTIONS TO OFFERORS

Instructions to Offerors

MAIL, FAX, EMAIL or HAND DELIVER YOUR DOCUMENTS

Do not include excess information, to include audio-visual materials, electronic media, CD’s, thumbdrives, etc. or pages of the solicitation that do not contain information provided by the perspective offeror. NO cross outs or strike through marks. Submit a legible quote with no correction marks.

EMAIL

Emailed quotes must be received in a supported Adobe or Microsoft Office file format. These formats are the only acceptable methods of submitting a quote electronically. Cloud storage providers, google docs, web based drop boxes, OneNote/OneDrive, URLs, web-based format, or any other virtual/web-based memory service are NOT acceptable methods of submitting a quote electronically. All documents must be attached in one file. Reference the solicitation in the subject line. Send quotes to E-mail address CESWT‐CT‐SS‐Quotes@usace.army.mil and copy Amy.c.feemster@USACE.Army.mil. Ensure your quote is received before the due date and time. In order for your quote to be considered responsive, all required materials must be received before the due date and time. If all required materials are not received your quote will not be considered.

FAX or MAIL

Include a cover sheet that references the Contract Specialist – Amy C. Feemster and the solicitation number. When submitting through mail ensure you clearly mark the envelope to:

US Army Corps of Engineers, Tulsa District Amy C. Feemster, CECT-SWT-CT 2488 E. 81st Street Tulsa, OK 74137-4290

Clearly mark the envelope in the lower left hand corner with the solicitation number. All pages should be numbered.

Use only 8 ½ by 11 inch paper for fax or mail submissions. Do not use fold-outs (e.g., 11” x 14” or 11” x 17” sheets). Do not use a font size smaller than 10, or condensed print for any submission. Time New Roman or Arial Font are the only acceptable fonts. All page margins must be at least 1 inch wide, but may include headers and footers. Illegible handwritten quotes will not be considered. Typed quotes are highly encouraged and the preferred method. Do not use spring clamps, staples, or exceed the recommended capacity of the fastener or binder. Do not use plastic multi-hole/spiral binding systems, heat binding systems, or other systems which do not facilitate the ready insertion of additional pages or removal of pages. DO NOT use tabbed dividers, flagged tabs, or any divider that extends beyond the paper size to separate sections. The pages must be able to be removed from their binding without ripping or tearing. Ensure to allow enough time to submit your quote before the due date and time.

HAND DELIVER

If your submission will be hand-carried, please provide notification to the Contract Specialist at least one working day in advance (918-669-7173) or Amy.c.feemster@USACE.Army.mil, as unescorted visitors are not allowed in the Contracting Division offices. Please consider in your arrival that visitors must go through security check points on the 16th floor of the 20 story Building. Offerors can only submit their documents to the Contract Specialist or a Contracting Officer of the Tulsa District Office. The address of the Tulsa District Office is below:

US Army Corps of Engineers, Tulsa District 2488 E. 81st Street Tulsa, OK 74137-4290

Please submit the following documents:

1) A signed copy of the 1st page of the solicitation and all amendments

2) The pricing schedule provided in the solicitation.

3) Your quote must identify the business size of the prime contractor and the business name and address of any subcontractors, if applicable, based on the NAICS code identified. Offerors must clearly identify whether a subcontractor(s) will be performing work, the percentage of work to be performed by each subcontractor, and the socio-economic category into which each identified subcontractor falls. (FAR

52.219-14 LIMITATIONS ON SUBCONTRACTING (DEVIATION 2019-O0003) (JAN 2019))

4) Complete and return the Representations and Certifications in Section K unless already completed in the System for Awards Management at www.sam.gov.

Funds are not presently available for this acquisition. No contract award will be made until appropriated funds are made available.

Please see clause clause 52.251-1 where the Government will provide an authorization letter to the awardee to procure the supply item via GSA.

BIDDERS INQUIRY

INQUIRIES – OFFEROR’S QUESTIONS AND COMMENTS

USE OF BIDDER’S INQUIRY

Prospective offerors shall submit questions and inquiries related to this solicitation in accordance with the following (no other means of questions or inquiries will be answered except through Bidder Inquiry):

a. For information related to amendments, and the dates set for receipt of proposals, please check http://www.fedbizopps.gov

b. Contractual and Technical inquiries and questions relating to proposal procedures are to be submitted via Bidder Inquiry in ProjNet at https://www.projnet.org/projnet.

1. To submit and review bid inquiry items, offerors will need to be a current registered user or self-register into the system. To self-register go to the aforementioned web page and click on the BID tab. Select Bidder Inquiry, select agency USACE, and enter the Bidder Inquiry Key for this solicitation listed below, your e-mail address, and then click login. Fill in all required information and click create user. Verify that information on next screen is correct and click continue.

2. From this page you may view all bidder inquiries or add an inquiry.

3. Bidders will receive an acknowledgement of their question via e-mail, followed by an answer to their question after it has been processed.

4. The Solicitation Numbers are: W912BV20Q0134

The Bidder Inquiry Key is: 8M73AZ-37VBZV

c. The Bidder Inquiry System will be unavailable for new inquiries after Tuesday, 4 August 2020 in order to ensure adequate time is allotted to form an appropriate response and amend the solicitation, if necessary.

d. Offerors are requested to review the specification in its entirety, and review the Bidder Inquiry System for answers to questions prior to submission of a new inquiry.

e. The call center operates weekdays from 8AM to 5PM U.S. Central Time Zone (Chicago). The telephone number for the Call Center is 800-428-HELP.

f. Offers will NOT be publicly opened. Information concerning the status of the evaluation and/or award will NOT be available after receipt of proposals.

g. The point of contact for this solicitation is:

Contract Specialist: Amy C. Feemster Telephone: 918-669-7173 E-MAIL: Amy.c.feemster@usace.army.mil

Section B - Supplies or Services and Prices

PRICING SCHEDULE

CLIN Description QTY Unit Total 0001 Removal of Gate Shack and Flower Bed, Installation of New Gate Shack 1 Job

Subcontracting Information: All offerors must fill out this section Self Performing:

Prime Contractor Business Size of Prime contractor Percentage of work to be completed by Prime Contractor

Subcontractor (if applicable):

Name of Subcontractor Address Percentage to be completed by the Subcontractor

Business size and socioeconomic category

Section C - Descriptions and Specifications

SCOPE OF WORK

Specifications of Work

Snake Creek Campground and Recreation Area Tenkiller Lake, Oklahoma

PART 1 – GENERAL

1.1 Scope of Work. The contractor shall provide all labor, materials, tools, equipment, CXT pre-manufactured structure and other items required to install (1) granular (gravel) sub-base pad which will be built for the purpose of installing one CXT Prefabricated Gate Shack, The Contractor shall perform to the standards and specifications in this contract. The Tenkiller Lake Dam and Snake Creek is located in Cherokee County, Oklahoma.

1.1.2 Location of Work. Located at the Snake Creek Campground Facility in the Tenkiller Lake Area.

1.1.3 Site Conditions. A site visit by prospective bidders is encouraged to determine exact site conditions and work requirements. Work will be in a campground. Care will be taken to prevent damage to riprap, utilities, and roads.

1.2.1 Pre-Proposal Conference. A pre-proposal conference will be scheduled and coordinated by the Tenkiller Lake Office personnel and held at the lake office on Tuesday, July 28, 2020 at 10:00am Central Time.

1.2.2 The purpose of the site visit will be to familiarize prospective bidders with the extent and nature of the requirement and location of performance. Oral questions pertaining to the Scope of Work or other contractual matters will not be answered during the tour of the performance work areas. Any questions of any nature must be prepared in writing submitted through Bidders Inquiry no later than Wednesday, July 8, 2020 by 4:00pm Central Time (see Instructions to Offerors for Bidders Inquiry information). If questions are received after this time the Government may not be able to respond to your question before the solicitation closing date.

1.2.3 After Tuesday, August 4, 2020 answers to all questions will be available to potential offers. These questions and answers will be posted on Bidders Inquiry and constitute the official Corps answer.

1.2.4 This conference is not mandatory for prospective bidders. All prospective bidders are strongly urged to attend the pre-proposal conference and to satisfy themselves as to all general conditions that may affect the cost and schedule of performance of this contract.

1.2.5 Any questions pertaining to past or current contract information for any of the past or current construction contracts should be submitted to the Office of Counsel, Tulsa District Office in the form of a FOIA (Freedom of Information Act) request. Below is the contact information for the Office of Counsel, Tulsa District.

US Army Corps of Engineers, Tulsa District Attn: CESWT-OC 2488 E.81st Street Tulsa, OK 74137-4290 foia-swt@usace.army.mil Phone: 918-669-7593/7178 Fax: 918-669-7576

1.2.6 Guidance on how to submit a FOIA request can be found at http://www.usace.army.mii/FOIA.aspx.

Please ensure your request is submitted in a timely matter to receive feedback before the solicitation closing date.

1.3 References. All work will be accomplished in accordance with standard work practices.

1.4 Basis of Payment. The contractor may invoice for payment after all work has been completed, inspected and accepted by the Government. Invoice shall have as a minimum: Contractor's company name, contract number, invoice number, and date. Mail, email, fax, or hand deliver invoice and other required forms to: Corps of Engineers, Tenkiller Project Office, 446977 E. 980 Rd. Gore, OK 74435.

1.5 Work Hours. The contractor may work between the hours of 7:00 a.m. to 5:00 p.m., Monday through Friday, excluding federal holidays. Any proposed changes to the work hours must be approved by the Contracting Officer Representative (COR).

1.6 Completion Time. Work shall be completed within 90 calendar days.

1.7 Safety Requirements. The contractor shall comply with the Corps of Engineers Safety and Health Requirements Manual, EM 385-1-1 dated 30 November 2014, and all applicable Federal, State, and local safety codes and practices. Matters of interpretation of the standards shall be submitted to the Contracting Officer for resolution before starting work. Where the regulations conflict, the most stringent requirements shall apply. It is the contractor’s responsibility to insure public safety during the entire duration of the contract. Necessary signs, barriers, warning devices, etc. shall be operated and maintained by the contractor at contractor expense. Contractor employees shall comply with the minimum dress requirements as stated in Chapter 7 of EM 385-1-1. A copy of this manual is available from the Contracting Officer.

1.7.1 The following sections of the manual are particularly applicable to the work under these specifications. Section 14 – Material Handling, Storage, and Disposal; Section 18 - Vehicles, Machinery, and Equipment. Workers shall be required to comply with the minimum clothing requirements for field work which includes short sleeve shirt, long pants, leather or protective work boots, hard hat, and proper ear, hand, and eye protection as necessary. Persons exposed to vehicular traffic shall wear reflective vests or high visibility apparel. Traffic warning signs will be required when equipment is parked on the roadway and a flagman present to direct traffic anytime equipment and personnel are working from or on the roadway. The work plan shall include procedures to follow in case of injury accidents. The Contractor shall review the safety requirements with all workers prior to any work under this Contract.

1.8 Equipment. All equipment used to perform work under this contract shall be in good operating and mechanical condition and shall comply with Section 18 of EM 385-1-1 (30 NOV 2014). Equipment shall be inspected by the contractor and the inspection reports shall be submitted to the Contracting Officer prior to utilization of such equipment to accomplish work on this contract.

1.9 Environmental Cleanup. The contractor shall maintain a clean work area at all times. The contractor shall be responsible for the protection of the environment and will be required to restore all damages subject to the approval of the contracting officer. The contractor shall remove and dispose of all debris off Government property in a state approved disposal site unless specified otherwise. The contractor will be required to comply with Federal and State environmental requirements.

1.9.1 Quality Control. The contractor is responsible for all actions necessary to allow for successful completion of this contract. Plumbing work shall comply with the National Plumbing Code. Electrical work shall comply with the National Electrical Code. Concrete work shall comply with American Concrete Institute.

1.9.2 Warranties. The contractor shall warranty all work for one year from the date of acceptance.

1.10 Weather Delays. TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER (OCT 1989) (ER 415-1-15).

1.10.1 This provision specifies the procedure for determination of time extensions for unusually severe weather in accordance with the contract clause entitled “Default: (Fixed Price Construction)”. In order for the Contracting Officer to award a time extension under this clause, the following conditions must be satisfied:

a. The weather experienced at the project site during the contract period must be found to be unusually severe, that is, more severe than the adverse weather anticipated for the project location during any given month.

b. The unusually severe weather must actually cause a delay to the completion of the project.

The delay must be beyond the control and without the fault or negligence of the contractor.

1.10.2 The following schedule of monthly anticipated adverse weather delays is based on National Oceanic and Atmospheric Administration (NOAA) or similar data for the project location and will constitute the base line for monthly weather time evaluations. The contractor’s progress schedule must reflect these anticipated adverse weather delays in all-weather dependent activities.

MONTHLY ANTICIPATED ADVERSE WEATHER DELAY

WORK DAYS BASED ON (5) DAY WORK WEEK

JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC

4 4 4 5 5 4 4 4 4 3 4 4

1.10.3 Upon acknowledgment of the Notice to Proceed (NTP) and continuing throughout the contract, the contractor will record on the daily Contractor Quality Control (CQC) report, the occurrence of adverse weather and resultant impact to normally scheduled work. Actual adverse weather delay days must prevent work on critical activities for 50 percent of more of the contractor’s scheduled work day. The number of actual adverse weather delay days shall include days impacted by actual adverse weather (even if adverse weather occurred in previous month), be calculated chronologically from the first to the last day of each month, and be recorded as full days. If the number of actual adverse weather delay days exceeds the number of days anticipated in paragraph 1.10.2, above, the contracting officer will convert any qualifying delays to calendar days, giving full consideration for equivalent fair weather work day, and issue a modification in accordance with the contract clause entitled “Default (Fixed Price Construction)”.

1.11 Submittals. The contractor may be required to furnish certain submittals. These submittals may be certifications of materials, safety plans, drawings, training certifications, work plans, etc. These will be specifically listed and shall be furnished to the Contracting Officer. Submittals requiring Government approval shall be formally prepared and approval granted prior to proceeding with work involving these submittals. FIO (For Information Only) submittals do not require Government approval.

1.11.1 Work Plan. The Contractor’s work plan shall be submitted to the Contracting Officer or Contracting Officer’s Representative (COR) for approval prior to the beginning of work. The work plan shall provide detailed procedures defining the Contractor’s provisions for utility and equipment installation activities.

1.11.2 Safety Plan. A Safety plan for work procedures and safety and health protection shall be approved prior to beginning work. This plan shall include the procedures for equipment operation, chainsaw operation, public safety precautions, and traffic control if applicable. The safety plan shall include procedures to follow in case of injury accidents. The Contractor shall review the safety requirements with all workers prior to any work. Contractor Job Hazard Analysis shall be provided for each type of work.

1.11.3 Utilities. Care shall be taken not to cut nor damage overhead and underground utilities. The contractor will be responsible for all damages. Depth of existing utilities shall be verified by the contractor prior to construction. Extreme care will be taken to prevent damage to riprap, utilities, roads, and parking lot. The contractor will be responsible for all damages.

1.11.4 Release Claim. The release is to have contractor’s original signature and notarized.

1.11.5 Payrolls. Contractor and subcontractor payrolls shall be submitted weekly and directly to USAED, Tulsa District, Attn: Labor Relations Contracting Div, 1645 S. 101st East Avenue, Tulsa, OK 74128-4609.

The contractor shall submit DD Form 879, Statement of Compliance with payrolls. If there are subcontractors, the contractor shall submit Standard Form 1413, Statement of Acknowledgment signed by both the contractor and subcontractor.

1.11.6 Other submittals shall include but not limited to 1) safety meeting records and 2) monthly exposure reports.

1.12 Pre-Work Conference. A pre-work conference will be held with the Contracting Officer and contractor prior to the commencement of any work at Tenkiller Lake. The contractor’s responsible person and necessary administrative staff will be required to attend this meeting. Procedures for proper invoicing and payment, schedule, etc., shall be covered at this time.

1.13 Coordination of Work. The Contractor will be required to complete the work, within the recommended time frame without impacting the day to day operations. Pete Theodos the Technical Point of Contract (POC) and Contracting Officer’s Representative (COR). He may be reached from 7:30 a.m.

through 3:30 p.m., Monday through Friday excluding Federal Holidays. Mr. Theodos phone number is

(918) 489-5541, ext. 6414,.

1.14 Antiterrorism and Operations Security Requirements. The Contractor shall be responsible for ensuring all personnel, to include sub-contractor personnel, comply with the training requirements and procedures identified on the document titled “Antiterrorism/Operations Security Requirements” in Section H, Special Contract Requirements. When items for which training is identified, the Contractor shall ensure that all personnel complete acknowledgement for the specified training; the Contractor is responsible for ensuring all training acknowledgments, when applicable, are submitted to the COR or Contracting Officer within 10 calendar days of contract award (or NTP for construction contracts). In no event shall any contractor or sub-contractor personnel be onsite prior to completion of any applicable training and submission of training verification. Training materials and verification forms will be provided by the Contracting Officer upon written request.

1.15 Discrepancies. The contractor shall notify the government of any discrepancies discovered in prior work or in work under contract that are not readily explainable and in such time that they may be resolved prior to completion of the work. If, at the discretion of the contracting officer, work is found to be in error after the assignment is completed, the contractor shall be liable for all costs in connection with correcting the work.

PART 2 – PRODUCTS

2.1 Materials. The Contractor shall furnish all materials and supplies required to complete this task.

2.2 CXT Gate Attendant Building. Specifications for a Gate Shack can be found in Appendix A. The Gate Shack must fit manufacturer’s specifications while incorporating notes in Appendix A. Contractor must contact manufacturer to ensure building is “square” as annotated in Appendix A. The Gate Shack shall be a CXT or equal as approved by the COR.

2.2.1 CXT Contact Information.

CXT, Incorporated Spokane Industrial Park 3808 North Sullivan Road, Building 7 Spokane , WA 99216 Phone: 800 - 696 - 5766

2.5 Delivery and Storage. Materials shall be delivered to the site undamaged and stored in an area approved by the COR. Materials that are damaged during the delivery shall be replaced at no cost to the Government.

PART 3 - EXECUTION

3.0 Execution. The contractor shall furnish all labor, fuel, tools, materials, supplies and equipment to complete the tasks listed below. Construction area shall be flagged or caution taped around the entire worksite at the end of each day's work and at the final completion of each project. All work shall be accomplished in a safe manner and in accordance with standard industry practices.

3.1 Snake Creek Recreation Area and Campground (Base Bid).

3.1.1 Description of Work. The contractor shall remove a gate attendant shack measuring approximately 14’ x 8’, preparing a site and installing a CXT Inc. concrete pre-fabricated Gate Attendant Building measuring approximately 20’ x 10’ or equal as approved by the COR, emplacing two new concrete camping pads with utility connections, installing a septic tank and sewage line for the pads, and installing an ADA accessible playground area.

3.1.2 Accomplishment of Work.

A. Gate Attendant Building.

1. Demolition. The contractor shall demolish the old gate attendant building. The current gate attendant building measures approximately 14’ x 8’ x 8’. Work is to include removing the structure, preserving utility connections (telephone and electric) for future use, and removing the old foundation. All debris to include, but not limited to roofing material, rock siding, wood, electrical wiring or components, plumbing fixtures and components, or insulation shall be disposed of off government property in accordance with state and local law. Refer to 4.2.1 Gate Building and exit gate.

2. Installation. Installation of the CXT gate shack shall be completed as specified in manufacturer’s instructions and Appendix A.

Section E - Inspection and Acceptance

Section F - Deliveries or Performance

DELIVERY INFORMATION

CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /

CAGE

CLAUSES INCORPORATED BY REFERENCE

52.211-17 Delivery of Excess Quantities SEP 1989 52.242-15 Stop-Work Order AUG 1989 52.246-1 Contractor Inspection Requirements APR 1984 52.247-34 F.O.B. Destination NOV 1991

Section G - Contract Administration Data

252.201-7000 Contracting Officer's Representative DEC 1991 252.204-7006 Billing Instructions OCT 2005

Section H - Special Contract Requirements

WAGE DETERMINATIONS

"General Decision Number: OK20200067 03/06/2020

Superseded General Decision Number: OK20190067

State: Oklahoma

Construction Type: Building Building Construction -does not include residential construction consisting of single family homes and apartments up to and including 4 stories.

Counties: Adair and Cherokee Counties in Oklahoma.

Note: Under Executive Order (EO) 13658, an hourly minimum wage of $10.80 for calendar year 2020 applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2015. If this contract is covered by the EO, the contractor must pay all workers in any classification listed on this wage determination at least $10.80 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract in calendar year 2020. If this contract is covered by the EO and a classification considered necessary for performance of work on the contract does not appear on this wage determination, the contractor must pay workers in that classification at least the wage rate determined through the conformance process set forth in 29 CFR 5.5(a)(1)(ii) (or the EO minimum wage rate,if it is higher than the conformed wage rate). The EO minimum wage rate will be adjusted annually. Please note that this EO applies to the above-mentioned types of contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but it does not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(2)-(60). Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.

Modification Number Publication Date 0 01/03/2020 1 03/06/2020

BOIL0592-001 01/01/2017

Rates Fringes

BOILERMAKER......................$ 28.47 21.88

ELEC0584-006 05/28/2018

Rates Fringes

ELECTRICIAN (Excludes Low Voltage Wiring and Installation of Alarms and Sound and Communication Systems).........................$ 30.43 7%+9.70

* ELEV0083-003 01/01/2020

Rates Fringes

ELEVATOR MECHANIC................$ 42.02 34.765+a+b

PAID HOLIDAYS:

a. New Year's Day, Memorial Day, Independence Day, Labor Day, Veteran's Day, Thanksgiving Day, the Friday after Thanksgiving, and Christmas Day.

b. Employer contributes 8% of regular hourly rate to vacation pay credit for employee who has worked in business more than 5 years; 6% for less than 5 years' service.

ENGI0627-022 06/01/2019

Rates Fringes

POWER EQUIPMENT OPERATOR:

Group 1.....................$ 31.05 13.75 Group 2.....................$ 29.35 13.75 Group 3.....................$ 28.80 13.75 Group 4.....................$ 28.00 13.75 Group 5.....................$ 26.90 13.75 Group 8.....................$ 23.65 13.75 Group10.....................$ 22.20 13.75

POWER EQUIPMENT OPERATOR

GROUP 1: All Crane Type Equipment 200 ton and larger and including 400 ton capacity cranes. All Tower Cranes.

GROUP 2: All Crane Type Equipment 100 ton capacity and larger cranes, and less than 200 ton capacity.

GROUP 3: All Crane Type Equipment 50 ton capacity and larger cranes, and less than 100 ton capacity. Crane Equipment (as rated by mfg.) 3 cu. yd and over Guy derrick Whirley Power Driven Hole Digger (with 30' and longer mast).

GROUP 4: CRANES with Boom Incl. Jib less than 100 ft and less than 3 cu. Yd.; Overhead Monorail Crane; BACKHOE; TRACKHOE;

EXCAVATOR

GROUP 5: BULLDOZER

GROUP 8: FORK-LIFT

GROUP 10:OILER

IRON0584-010 06/01/2019

Rates Fringes

IRONWORKER, STRUCTURAL...........$ 26.00 15.35

PLUM0430-022 07/01/2018

Rates Fringes

PIPEFITTER (Including HVAC Pipe and Unit Installation)......$ 31.50 13.88

SHEE0270-009 06/01/2017

Rates Fringes

SHEET METAL WORKER (Including HVAC Duct Installation)..........$ 31.89 14.31

SUOK2012-047 06/18/2012

Rates Fringes

BRICKLAYER.......................$ 20.00 0.00

CARPENTER........................$ 13.42 0.00

CAULKER..........................$ 20.00 1.61

CEMENT MASON/CONCRETE FINISHER...$ 16.91 0.61

ELECTRICIAN (Alarm Installation)....................$ 20.47 4.52

ELECTRICIAN (Low Voltage Wiring)..........................$ 21.14 4.96

ELECTRICIAN (Sound and Communications Systems Installation)....................$ 22.10 5.76

LABORER: Common or General......$ 11.51 0.00

LABORER: Mason Tender - Brick...$ 10.25 0.00

LABORER: Mason Tender - Cement/Concrete..................$ 13.04 0.00

LABORER: Pipelayer..............$ 12.93 0.00

PAINTER: Brush, Roller and Spray............................$ 13.56 0.00

PLUMBER, Excludes HVAC Pipe Installation.....................$ 24.66 10.36

ROOFER...........................$ 15.00 0.29

SPRINKLER FITTER (Fire Sprinklers)......................$ 39.95 0.38

WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.

Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.

Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.

Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).

The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of ""identifiers"" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate (weighted union average rate).

Union Rate Identifiers

A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than ""SU"" or ""UAVG"" denotes that the union classification and rate were prevailing for that classification in the survey. Example:

PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, 2014.

Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate.

Survey Rate Identifiers

Classifications listed under the ""SU"" identifier indicate that no one rate prevailed for this classification in the survey and the published rate is derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As this weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SULA2012-007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana. 2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. 5/13/2014 indicates the survey completion date for the classifications and rates under that identifier.

Survey wage rates are not updated and remain in effect until a new survey is conducted.

Union Average Rate Identifiers

Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those classifications; however, 100% of the data reported for the classifications was union data. EXAMPLE: UAVG-OH-0010 08/29/2014. UAVG indicates that the rate is a weighted union average rate. OH indicates the state. The next number, 0010 in the example, is an internal number used in producing the wage determination. 08/29/2014 indicates the survey completion date for the classifications and rates under that identifier.

A UAVG rate will be updated once a year, usually in January of each year, to reflect a weighted average of the current negotiated/CBA rate of the union locals from which the rate is based.

WAGE DETERMINATION APPEALS PROCESS

1.) Has there been an initial decision in the matter? This can be:

* an existing published wage determination

* a survey underlying a wage determination

* a Wage and Hour Division letter setting forth a position on a wage determination matter

* a conformance (additional classification and rate) ruling

On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.)

and 3.) should be followed.

With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:

Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:

Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.

3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:

Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

4.) All decisions by the Administrative Review Board are final.

END OF GENERAL DECISION"

CLAUSES INCORPORATED BY FULL TEXT

ANTITERRORISM/OPERATIONS SECURITY REQUIREMENTS, Jun 2015

The Contractor shall comply with the following requirements marked with an “X”.

1. AT Level I Training. This provision/contract text is for contractor employees with an area of performance within an Army controlled installation, facility or area. Proposed language: "All contractor employees, to include subcontractor employees, requiring access to Army installations, facilities, controlled access areas, or require network access, shall complete AT Level I awareness training within 30 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. Upon request, the contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee, to the COR or to the contracting officer (if a COR is not assigned), within 5 calendar days after completion of training by all employees and subcontractor personnel. AT Level I awareness training is available at the following website:

http://jko.jten.mil/courses/atl1/launch.html; or it can be provided by the RA ATO in presentation form which will be documented via memorandum."

X

2. Access and General Protection/Security Policy and Procedures. This standard language text is for contractor employees with an area of performance within an Army controlled installation, facility or area.

Proposed language: "All contractor and all associated sub-contractors employees shall comply with applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative). The contractor shall also provide all information required for background checks to meet installation/facility access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. Contractor workforce must comply with all personal identity verification requirements (FAR clause 52.204-9, Personal Identity Verification of Contractor Personnel) as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any installation or facility change, the Government may require changes in contractor security matters or processes."

2a. For contractors requiring Common Access Card (CAC). Before CAC issuance, the contractor employee requires, at a minimum, a favorably adjudicated National Agency Check with Inquiries (NACI) or an equivalent or higher investigation in accordance with Army Directive 2014-05 and Homeland Security Presidential Directive-12 (HSPD-12). Proposed language: “The contractor and all sub-contractors employees will be issued a CAC only if duties involve one of the following: (1) Both physical access to a DoD facility and access, via logon, to DoD networks on-site or remotely; (2) Remote access, via logon, to a DoD network using DoD-approved remote access procedures; or (3) Physical access to multiple DoD facilities or multiple non-DoD federally controlled facilities on behalf of the DoD on a recurring basis for a period of 6 months or more. At the discretion of the sponsoring activity, an interim CAC may be issued based on a favorable review of the FBI fingerprint check and a successfully scheduled NACI at the Office of Personnel Management.”

X

2b. For contractors who do not require CAC, but require access to a DoD facility or installation.

Proposed language: Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014-05 / AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative, as NCIC and TSDB are available), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.

3. AT Awareness Training for Contractor Personnel Traveling Overseas. This standard language text required US based contractor employees and associated sub-contractor employees to make available and to receive government provided area of responsibility (AOR) specific AT awareness training as directed by AR 525-13 (Antiterrorism). Specific AOR training content is directed by the combatant commander with the unit ATO being the local point of contact. Proposed language: "All US based contractor employees and associated sub-contractor employees traveling overseas will receive the government provided AOR specific AT awareness training. The documentation of training completion must be provided to the COR prior to departure.”

X

4. Suspicious Activity Reporting Training (e.g. iWATCH, CorpsWatch, or See Something, Say Something). This standard language is for contractor employees with an area of performance within an Army controlled installation, facility or area. Proposed language: "The contractor and all associated sub-contractors shall receive a brief/training (provided by the RA) on the local suspicious activity reporting program. This locally developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the project manager, security representative or law enforcement entity. This training shall be completed within 30 calendar days of contract award and within 30 calendar days of new employees commencing performance with the results reported to the COR NLT 5 calendar days after the completion of the training."

5. Contractor Employees Who Require Access to Government Information Systems. This standard language text is for contractor employees with access to government info system. Proposed language: "All contractor employees with access to a government info system must be registered in the Army Training Certification Tracking System (ATCTS) at commencement of services, and must successfully complete the DOD information Assurance Awareness prior to access to the information systems and then annually thereafter in accordance with personnel security standards listed in AR 25-2 (Information Assurance), an appropriate background investigation will be conducted prior to accessing the government information systems."

6. For Contracts that Require an OPSEC Standing Operating Procedure/Plan. This standard language text is for contractor employees with an area of performance for classified contracts or if the contract employee has access or responsibility to protect critical information. The Contractor, in collaboration with RA OPSEC Officer, shall develop an OPSEC Standard Operating Procedure (SOP)/Plan within 90 calendar days of contract award per AR 530-1 (Operations Security). Proposed language: "The Contractor shall develop an OPSEC SOP/Plan within 90 days of contract award. The OPSEC SOP/Plan must be reviewed and approved by the RA OPSEC Officer. The SOP/Plan will include the government's critical information, why it needs to be protected, where it is located, who is responsible for it and how to protect it. In addition, the contractor shall identify an individual who will be an OPSEC Coordinator."

7. For Contracts that Require OPSEC Training. Per AR 530-1, (Operations Security) contractor employees must complete Level I OPSEC Training within 30 calendar days of contract award. Proposed language: "All new contractor employees will complete Level I OPSEC Training within 30 calendar days of their reporting for duty. Additionally, all contractor employees must complete annual OPSEC awareness training. The contractor shall submit certificates of completion for each affected contractor and subcontractor employee, to the COR or to the contracting officer (if a COR is not assigned), within 5 calendar days after completion of training. OPSEC awareness training is available at the following websites:

https://www.iad.gov/ioss/ or http://www.cdse.edu/catalog/operations-security.html; or it can be provided by the RA OPSEC Officer in presentation form which will be documented via memorandum."

8. For Information assurance (IA)/information technology (IT) training. This standard language text is for contract employees who need network access and/or working IA/IT functions. Proposed language: "All contractor employees and associated sub-contractor employees must complete the DoD IA awareness training before issuance of network access and annually thereafter. All contractor employees working IA/IT functions must comply with DoD and Army training requirements in DoDD 8570.01, DoD 8570.01-M and AR 25-2 within six months of employment."

9. For information assurance (IA)/information technology (IT) certification. Per DoD 8570.01-M , DFARS 252.239.7001 and AR 25-2, the contractor employees supporting IA/IT functions shall be appropriately certified upon contract award. The baseline certification as stipulated in DoD 8570.01-M must be completed upon contract award. Proposed language: "All contractor employees supporting IA/IT functions shall be appropriately certified upon contract IAW DoD 8570.01-M, DFARS 252.239-7001 and AR 25-2. The baseline certification as stipulated in DoD 8570.01-M must be completed upon contract award."

10. For Contractors Authorized to Accompany the Force. DFARS Clause 252.225-7040, Contractor Personnel Authorized to Accompany U.S. Armed Forces Deployed Outside the United States. The clause shall be used in solicitations and contracts that authorize contractor personnel to accompany US Armed Forces deployed outside the US in contingency operations; humanitarian or peacekeeping operations; or other military operations or exercises, when designated by the combatant commander. Proposed language:

"All contractor employees shall ensure the following AT/OPSEC requirements are met prior to deploying personnel authorized to accompany U.S. Armed Forces outside the United States; to include compliance with laws, regulations, pre-deployment requirements, and required training in accordance with combatant command guidance."

11. For Contracts Requiring Performance or Delivery in a Foreign Country. DFARS Clause 252.225- 7043, Antiterrorism/Force Protection for Defense Contractors Outside the US. The clause shall be used in solicitations and contracts that require performance or delivery in a foreign country. This clause applies to both contingencies and non-contingency support. Proposed language: "All non-local contracting personnel will comply with theater clearance requirements and allows the combatant commander to exercise oversight to ensure the contractor's compliance with combatant commander and subordinate task force commander policies and directives."

12. For Contracts That Require Handling or Access to Classified Information. This clause involves access to classified information, i.e. “Confidential,” “Secret,” or “Top Secret”. Proposed language:

"Contractor shall comply with AR 380-67 (Personnel Security Program) and Homeland Security Presidential Directive 12 (Policy for a Common Identification Standard for Federal Employees and Contractors) as well as FAR 52.204-2, Security Requirements.

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .