This document is a Solicitation for a single-ply cutting machine. The key details are:
The solicitation is for a brand name item, the Eastman Machine Company C135 single-ply cutting machine. The contract will be awarded on a best value basis considering price and delivery, to the responsible offeror. The delivery date is estimated but the Government reserves the right to award to other than the lowest price or earliest delivery bidder. Offers for used or refurbished equipment are unacceptable.
The solicitation includes detailed requirements for the cutting machine, including minimum specifications for cut speed, cutting area, cutting head, conveyor system, vacuum table, control system, and safety features. Installation, acceptance testing, and training are also required. The machine must be delivered within 120 days of award and installed within 15 days after delivery. There is a 1-year warranty on parts and labor. The Government is the end user and the Tobyhanna Army Depot is the procuring activity.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Redacted Brand Name Form-SinglePlyCuttingMach-signed - Copy_Redacted.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SEE ADDENDUM
(No Collect Calls)
W51AA125Q0003 17-Oct-2024
b. TELEPHONE NUMBER
570-615-8742
8. OFFER DUE DATE/LOCAL TIME
12:00 PM 06 Nov 2024
5. SOLICITATION NUMBER 6. SOLICITATION ISSUE DATE
AUTHORIZED FOR LOCAL REPRODUCTION
PREVIOUS EDITION IS NOT USABLE
STANDARD FORM 1449 (REV. 2/2012)
Prescribed by GSA – FAR (48 CFR) 53.212
(TYPE OR PRINT)
(SIGNATURE OF CONTRACTING OFFICER)
ADDENDA X ARE
26. TOTAL AWARD AMOUNT (For Gov t. Use Only )
23.
CODE 10. THIS ACQUISITION IS
SUCH ADDRESS IN OFFER
17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT
BELOW IS CHECKED
TELEPHONE NO.
W51AA19. ISSUED BY
18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a. UNLESS BLOCK
7. FOR SOLICITATION
INFORMATION CALL:
a. NAME
MELISSA HOFFMAN
2. CONTRACT NO. 3. AWARD/EFFECTIVE DATE 4. ORDER NUMBER
(TYPE OR PRINT)
30b. NAME AND TITLE OF SIGNER 30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER
30a. SIGNATURE OF OFFEROR/CONTRACTOR 31a.UNITED STATES OF AMERICA
1 27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1. 52.212-4. FAR 52.212-3. 52.212-5 ARE ATTACHED.X
25. ACCOUNTING AND APPROPRIATION DATA
1. REQUISITION NUMBER
20.
ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED.
OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, AND 30
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS
W25G1V423300PO
ARE NOT ATTACHED
27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA ARE ARE NOT ATTACHED
(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE
SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:
. YOUR OFFER ON SOLICITATION
28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN
% FOR:SET ASIDE:UNRESTRICTED ORX
SMALL BUSINESS
17a.CONTRACTOR/ CODE FACILITY
OFFEROR CODE
ACC-APG TOBYHANNA DIVISION (W51AA1)
11 HAP ARNOLD BLVD
TOBYHANNA PA 18466
18a. PAYMENT WILL BE MADE BY CODE
RATED ORDER UNDER
DPAS (15 CFR 700)
13a. THIS CONTRACT IS A
13b. RATING
CODE15. DELIVER TO CODE W25G1V 16. ADMINISTERED BY
12. DISCOUNT TERMS11. DELIVERY FOR FOB DESTINA-
TION UNLESS BLOCK IS
MARKED
SEE SCHEDULE
14. METHOD OF SOLICITATION
RFQ IFB RFPX
TOBYHANNA ARMY DEPOT
ASARS RECEIVING
BUILDING 1 C 6
INSERT PO NUMBER
11 HAP ARNOLD BLVD
TOBYHANNA PA 18466-5091
TEL: FAX:
FAX:
TEL: SERVICE-DISABLED
VETERAN-OWNED
SMALL BUSINESS
8(A)
HUBZONE SMALL
BUSINESS
SIZE STANDARD:
NAICS:
333248
X
OFFER DATED
29. AWARD OF CONTRACT: REF.
DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY
COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND
EMAIL:
TEL:
31c. DATE SIGNED
SEE SCHEDULE
SCHEDULE OF SUPPLIES/ SERVICESITEM NO. QUANTITY UNIT UNIT PRICE AMOUNT
24.22.21.19.
WOMEN-OWNED SMALL BUSINESS (WOSB)
ELIGIBLE UNDER THE WOMEN-OWNED
SMALL BUSINESS PROGRAM
EDWOSB
32g. E-MAIL OF AUTHORIZED GOVERNMENT REPRESENTATIVE
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS
(CONTINUED)
PAGE 2 OF57
ACCEPTED, AND CONFORMS TO THE CONTRACT, EXCEPT AS NOTED: ______________________________________________________
32a. QUANTITY IN COLUMN 21 HAS BEEN
RECEIVED INSPECTED
32b. SIGNATURE OF AUTHORIZED GOVERNMENT
REPRESENTATIVE
32c. DATE 32d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT
REPRESENTATIVE
32e. MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE 32f . TELEPHONE NUMBER OF AUTHORIZED GOVERNMENT REPRESENTATIVE
37. CHECK NUMBER
FINALPARTIALCOMPLETE
36. PAYMENT35. AMOUNT VERIFIED
CORRECT FOR
34. VOUCHER NUMBER
FINAL
33. SHIP NUMBER
PARTIAL
38. S/R ACCOUNT NUMBER 39. S/R VOUCHER NUMBER 40. PAID BY
41a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAYMENT
41b. SIGNATURE AND TITLE OF CERTIFYING OFFICER 41c. DATE
42a. RECEIVED BY (Print)
42b. RECEIVED AT (Location)
42c. DATE REC'D (YY/MM/DD) 42d. TOTAL CONTAINERS
STANDARD FORM 1449 (REV. 2/2012) BACK
Prescribed by GSA – FAR (48 CFR) 53.212
AUTHORIZED FOR LOCAL REPRODUCTION
PREVIOUS EDITION IS NOT USABLE
SEE SCHEDULE
20.
SCHEDULE OF SUPPLIES/ SERVICES
21.
QUANTITY UNIT
22. 23.
UNIT PRICE
24.
AMOUNT
19.
ITEM NO.
W51AA125Q0003
Section SF 1449 - CONTINUATION SHEET
BASIS OF AWARD
ITEM IS BRAND NAME ONLY: Eastman Machine Company
The award will be based on best value to the Government, considering price and delivery, to the responsible offeror otherwise conforming to all solicitation requirements. The Government reserves the right to award to other than the lowest price bidder or the earliest delivery bidder.
The delivery date specified in this solicitation is only an estimate.
OFFEROR MUST COMPLETE FAR PROVISIONS 52.204-24, 52.204-26, 52.209-11, 52.212-3, 52.219-1, 52.219- 28 and 52.225-18 AND SUBMIT WITH THEIR QUOTE.
The Offeror shall supply new equipment only. Offers for refurbished, remanufactured, reconditioned, overhauled, grey market, or used equipment are unacceptable and will not be considered.
To be considered for award, offerors must propose their pricing for CLIN 0001 listed in the SF1449. The company must also have an active registration in the System for Award Management (SAM) https://www.sam.gov. Offerors must be found to be responsible in accordance with FAR 9.1 and have no delinquent federal debt.
All submissions shall be submitted to the buyer via email: melissa.hoffman4.civ@army.mil by the date and time specified in the solicitation. Submissions shall include a signed copy of the SF 1449 solicitation (by a company representative authorized to bind the company) filled in with pricing for the CLINs, delivery date and all other items listed above. Submissions not including all of these items may not be accepted.
Submissions not received by the date and time specified in the solicitation or not providing all of the required documentation, may not be considered for award. It is the responsibility of the Offeror to verify that their submission, to include all attachments, was received by the date and time specified in the solicitation.
Offerors are advised to submit any questions regarding this solicitation in writing to the buyer via email:
melissa.hoffman4.civ@army.mil. Questions will not be accepted within five (5) business days of the solicitation close date.
ACWS WRITING SYSTEM LANGUAGE
Army Contract Writing System (ACWS) Transition Information for Contractors
a. The Army Contracting Enterprise (ACE) is in the process of deploying new solicitation and contract writing software to Army contracting offices worldwide. Known as the Army Contract Writing System (ACWS), this modern software suite will soon replace most existing Army contract writing systems, including the system used to create and release this Contract.
b. During this transition period, Contractors are hereby advised:
1. The Contracting Office may use any combination of contract writing systems to generate distributable copies of this contract during its period of performance, as well as any subsequent modifications or orders (if applicable). As a result:
i. Subsequent documents you receive may appear noticeably different than the original award or previous contractual documents from the same Contracting Office.
ii. A change between contract writing systems may cause important information concerning contract terms and conditions to take on different formatting or appear in different parts of later documents issued.
iii. Contractors shall ensure Customer Relationship Management (CRM) systems and personnel interacting with this contract are prepared to identify and respond appropriately to differences between document versions.
2. The Government does not intend to use the shift between contract writing systems to effect any changes to Contract terms and conditions. Therefore:
i. Contractors should view changes to terms or conditions between document versions as system-generated and potentially erroneous unless accompanied by narrative(s) designating such changes as deliberate and desired.
ii. Contractors shall inform the Contracting Officer listed on the first page of the most recent document issued for guidance regarding any suspected or observed inadvertent or system-generated changes (e.g. noticing something missing in a new conformed copy).
iii. The Government will correct any inadvertent or system-generated changes, additions, or omissions discovered by either party, via bilateral modification, at no cost to the Contractor.
iv. The terms and conditions contained in the latest document reflecting deliberate action by the Contracting Officer (e.g. the last conformed copy of the award not affected by the observed issue) will take precedence until these problems are corrected.
3. In the unlikely event award information is corrupted or mutilated during system migration and replacement or re-issuance of this contract is necessary for continued contract administration, the Contracting Officer will:
i. Issue a continuation contract in accordance with DFARS 204.1601(c) and DFARS PGI 204.1601(c), carrying over all terms and conditions from the last-known version of this contract accurately reflecting mutual agreement of the parties.
ii. Incorporate the last-known version of this contract accurately reflecting mutual agreement of the parties as an attachment to the replacement or continuation contract for future reference.
iii. Ensure any such reissuance or continuance is properly reported to preserve the integrity of Contractor performance measurement data, if any (e.g. FAPIIS, CPARS).
STATEMENT OF WORK (SOW)
Statement of Work (SOW) For Single-Ply Cutting Machine
1.0 Scope
1.1 Removal of Existing Multi-Ply Cutting Machine
The removal of the existing multi-ply cutting machine shall be performed by Tobyhanna Army Depot Production Equipment personnel.
2.0 Functional Requirements of New Single-Ply Cutting Machine
2.1 General Requirements
This specification/Statement of Work (SOW) sets forth the general system requirements for the purchase, installation and training of shop personnel on the proper operation and preventative maintenance of a new single-ply cutting machine. Used or refurbished equipment is NOT acceptable. For the purpose of this specification, the single-ply cutting machine will be referred to as the single-ply cutting machine, cutting machine and machine.
2.2 Requirements Overview
The single-ply cutting machine obtained as a result of this solicitation shall provide a conveyorized automatic means of cutting various fabrics. The fabrics to be cut range from nylon, vinyl, and up to 1” thick foam minimum.
2.3 Cut Speed
The cutting machine shall be capable of a minimum of 60 inches per second cut speed. (It is understood that actual cutting speeds vary based on the material being processed and patterns being cut.)
2.4 Cutting Area
The cutting machine shall have a minimum of a 72” by 144” cutting area.
2.5 Cutting Head
The cutting head shall employ a pneumatically oscillating tool knife head with a depth limiting function. In addition to the knife the cutting head shall have two each 7/8” diameter heavy duty spindles as a minimum. The tool head shall also be equipped with a marking/labeling assembly such that material being processed can be marked.
2.6 Cutting Parameters
Cutting machine operators shall be capable of adjusting cutting parameters such as the cutting tool pressure, vacuum levels and cutting speed on the machine’s touch screen control.
2.7 Conveyor System
The cutting machine shall have the ability to continuously convey rolled material at a consistent speed. The conveyor shall employ a bristle type conveyor belt with replaceable blocks/sections.
2.8 Vacuum Table
The cutting machine shall have a vacuum table for holding material down during the cutting process. The vacuum table shall have a minimum of 10 horsepower, variable-frequency drive (VFD) controlled vacuum blower. The vacuum pressure shall be variable and programmable for processing different materials. The vacuum table shall provide the appropriate vacuum while the material is being conveyed from the cutting area to the pickup area.
2.9 Control
The cutting machine shall have a sealed control cabinet to protect against particulates from the fabric cutting area.
The cabinet shall be fan-cooled for optimal computer performance. The control shall employ an industrial computer for multi-axis motion. The cutting machine shall have a minimum of a 7” LCD touchscreen, color control panel for inputting commands mounted on the traveling bridge/gantry. The gantry shall also have a joystick for positioning the gantry and the control head. In addition to the touchscreen control on the gantry the machine shall have a kiosk type control cabinet on wheels that can be positioned on either side or end of machine. Programs for the cutting machine shall be accomplished via a personal computer (PC) with Windows based software. (The PC shall be provided by the government per requirements identified by the contractor.) Programs shall then be transferred to the machine controller via memory stick. The control system shall employ cutting software that provides the following functions as a minimum: allows operators or programmers to define patterns to be cut, allows the machine to cut and convey at the same time, stores multiple programs/recipes and allows user to switch between cut program to go from one cutting job to another. (It must be understood that due to security issues and concerns vendors will NOT be permitted to remotely access the cutting machine via a network or internet for troubleshooting or any other purposes.)
2.10 Software
The cutting machine software shall be user friendly, prompting users for necessary parameters and input. The software features shall include but not be limited to being capable of uploading and converting various types of Computer Aided Manufacturing (CAD) files such as DXF and other major CAD formats. Software shall also include pattern and nesting functions. The cutting machine shall come with lifetime software key and updates.
2.11 Safety Features
The cutting machine shall be provided with the following safety systems, as a minimum:
2.11.1 Emergency Stop Buttons
The cutting machine shall have emergency stop buttons provided to immediately stop motion of the cutting machine.
The buttons shall be bright red in color and located such that it is easily accessible and noticeable in the case of an emergency situation. Emergency stop switches shall be provided at various locations around the cutting machine, on the traveling bridge/gantry and at the control cabinet/kiosk as a minimum. The E-stop buttons shall immediately stop all motion of the cutting machine. The gantry/traveling bridge shall also have bump stops or some form of stopping switch such that if the bridge comes in contact with a person or object in the path of the gantry the bridge travel is disabled until the person or object is clear of the area and an operator resets and restarts the machine.
2.11.2 Service Door Interlocks
Service Door interlock switches immediately stop and prevent motion when opened.
2.11.3 Bump Stops/Light Beams
The cutting machine shall employ bump type stops on both sides of the gantry or an infrared light beams/light curtain at operator station to protect the operators from being exposed to hazards associated with moving parts.
2.11.4 Status Lights
The cutting machine shall employ status lights to provide operator with a visual indicator of when it is safe and not safe to reach into the cutting area. Status lights shall display red when it is not safe to reach into access opening and green when it is safe to reach into access opening.
2.12 Accessories
The following accessories shall be provided with the cutting machine as a minimum.
2.12.1 Pneumatic Air Booster System: A pneumatic air booster system or similar type system shall be provided with the cutting machine to provide for fluctuations in compressed air pressure from the shop air system. The air booster system shall not serve as the primary source of compressed air but balance the compressed air flow to prevent inconsistencies in the pressure from negatively impacting the cutting process.
2.12.2 Plastic Roll Holder: A plastic roll holder shall be provided with the cutting machine to dispense plastic for holding fabric down on the cutting surface.
2.12.3 Spare Oscillating Tools: Three spare oscillating tools shall be provided with the cutting machine to allow for quick tool changes when changing from one material to another.
2.12.4 Blades: The cutting machine shall include a minimum of 5 each oscillating cutting blades in each of the appropriate sizes for cutting a minimum of 1” thick foam, nylon, vinyl. The following size blades shall be provided as a minimum:
- OSC Blade, 0.63 mm Thick, 31.0 mm cutting height, 86°, Pointed Tip
- OSC Blade, 0.63 mm Thick, 12.0 mm cutting height, 65°, Pointed Tip
- OSC Blade, 1.50 mm Thick, 16.5 mm cutting height, 81°, Pointed Tip
- OSC Blade, 1.50 mm Thick, 35.0 mm cutting height, 83°, Flat Tip
- OSC Blade, 1.50 mm Thick, 70.0 mm cutting height, 89°, Pointed Tip
- Tungsten Carbide 50 x 5 x 1 x 30
2.16 Power Requirements
The cutting machine and its accessories provided shall operate on a 208 VAC, 3-phase, grounded, 60 cycle electrical service. Control power and computers associated with the machine may be 120 VAC. Power required to include voltage and amperage shall be stated in proposal.
2.17 Physical Size/Footprint
The cutting machine shall not require a footprint greater than 12’ x 18’ when installation is complete and machine is ready for operation. It is acceptable to provide the equipment in a disassembled condition but the government will not assemble the equipment. This will be considered part of the contractor’s installation. Cargo door entrances to Building 10A where machine will be installed are 14’ wide by 12’ high nominal. Machine shall be cable of going through existing doorways without modification to the building or doorways.
3.0 Safety
The cutting machine shall be UL listed and meet all requirements set forth in OSHA General Industry Standards 29 CFR 1910, dated 1 July 1996 or CE listed. In addition it shall meet or exceed the National Fire Protection Association (NFPA) requirements of NFPA 79-1994, "Electrical Standards for Industrial Machinery." All energy control sources shall have the capability of being locked out and tagged out. The contractor's manuals shall detail the lockout/tagout procedures which are required to bring the cutting machine to a zero mechanical state for maintenance or service procedures. If the machine has a power switch and plugs into a receptacle such that the switch maybe turned off and the machine can be unplugged from the power source, that is sufficient to comply with zero mechanical state requirement. Start-up procedures to return from the zero mechanical state to full operational capability shall also be provided.
3.1 ISO 45001
Tobyhanna Army Depot is an ISO 45001 certified site; therefore, Tobyhanna Army Depot complies with Occupational Safety and Health Administration (OSHA) standards. Accordingly, Tobyhanna Army Depot expects and requires full contractor compliance with all applicable safety regulations and standards. The Contractor is responsible for maintaining, monitoring and enforcing full compliance.
3.2 OSHA Rules and Regulations
Contractors must comply with all Department of Labor and OSHA Rules and Regulations, 29 CFR 1910 (General Industries) and/or 1926 (Construction), and all applicable sections of the National Fire Protection Association (NFPA) Codes.
3.3 Standards for Electrical Safety
Particular attention is directed to NFPA 70E, Standard for Electrical Safety Requirements for Employee Workplaces. Contractor shall fully comply with all sections of this standard, including but not limited to; PART I, Chapter 2 - Ground Fault Protection for Personnel on Construction Sites, PART I, Chapter 3-7.1 - Use of Flexible Cords and Cables, PART II, Chapter 2-3 - Working On or Near Electrical Conductors or Circuit Parts, PART II, Chapter 5 - Lockout/Tagout Practices and Devices.
4.0 Delivery
a. Delivery of the cutting machine shall be within 120 days of contract award. Installation shall be performed by the contractor not later than 15 working days after delivery of the equipment and shall be completed within 10 working days of start date. Acceptance testing shall be performed not later than 15 working days after installation.
b. Training shall be completed not later than 10 working days after Acceptance testing.
c. Contractor shall coordinate delivery with the Contracting Officer or Contracting Officer’s Representative
(COR), to include a pre-delivery notification at least 10 days prior to shipment of equipment.
5.0 Installation
Installation responsibilities shall be shared between the Government and the contractor. The Government will unload the equipment from the truck, move it to the shop area, rough level the equipment, and connect the utilities (electricity and compressed air). Government personnel will not assemble the machine. This will be considered part of the contractor’s installation. The contractor shall then complete any incidental installation processes in order to place the cutting machine into service and ready for demonstration/acceptance testing. All installation procedures shall be coordinated with the Contracting Officer (KO) or the Contracting Officer's Representative (COR). All installation shall be performed by English speaking U.S. citizens. All work shall be performed during normal working hours: Monday through Friday from 7:30 am to 4:00 pm Eastern Standard Time, excluding Federal Holidays, unless special arrangements are made with the KO or COR.
5.1 Installation Requirements
Installation shall be completed by trained authorized system support personnel. The installation including assembly, wiring and testing shall be in accordance with the manufacturer’s installation instructions. The contractor shall provide all tools, material movement equipment and lift equipment necessary to assemble and install the machine in its predefined location.
5.2 Requirement to Use Electric Powered Vehicles
In accordance with Tobyhanna Army Depot’s policy to eliminate the use of fossil fuel vehicles within depot buildings, only electric-powered material movement equipment (to include forklifts, high-reach equipment, etc.)
shall be allowed in any depot building. Additionally, the Contractor will provide any battery recharging units required for operation of this material movement equipment.
6.0 Acceptance Testing
Operational Acceptance Testing for the cutting machine shall be performed following installation of the machine at Tobyhanna Army Depot and prior to training. Acceptance Testing will consist of the Contractor's technical representative demonstrating the ability to perform to the standard specified in the Requirements section of this specification. The material to be used for the Acceptance Testing shall be provided by the Government. In the event that the machine fails the acceptance test or fails to comply with any other aspect of this specification, the Contractor shall correct any deficiencies within 15 working days of the acceptance test, at which time the machine will be retested for compliance. It shall be at the discretion of the Contracting Officer as to whether all, part, or none of the acceptance test procedure shall be performed again. For the purpose of re-testing required due to the failure of the system to pass the initial testing, it shall be the responsibility of the Contractor to provide the material required for any re-testing, inclusive of any shipping costs, and such material shall be per the specification provided by the Government.
7.0 Training
Training shall begin within 10 working days of installation, set-up, and successful acceptance testing of the cutting machine. The contractor shall provide training for a maximum of 3 shop personnel and 2 Engineering personnel in the proper set-up, operation, and calibration of the machine. The contractor shall also provide instruction for 2 equipment mechanics on the proper preventative maintenance and troubleshooting techniques for the cutting machine. Instruction shall be performed at the Depot during normal Depot working hours (Monday thru Friday 7:30 AM to 4:00 PM) excluding Federal Holidays. The start-up and instruction shall be structured to be completed within two days (sixteen hours) and have sufficient time for a question and answer session. Training will take place after installation and acceptance testing but prior to final acceptance by the Contracting Officer (KO) or her Representative (COR). The contractor shall supply all training materials necessary to complete the training requirement.
7.1 Documentation
The single-ply cutting machine shall be provided with a comprehensive Operator’s Manual. A minimum of one hard copy and one electronic copy on CD/DVD of the manual shall be provided at the same time as machine delivery.
Department of Defense Item Unique Identification Code(DOD IUID) is Not required.
8.0 Warranty
8.1 Warranty Requirement
Contractor warrants that, at the time of delivery, the cutting machine shall conform to the requirements of the contract and be free from all defects in material and workmanship at the time of acceptance for a minimum of one
(1) year from date of final acceptance by the Government.
8.2 Warranty Coverage
The Contractor shall provide a minimum of a one (1) year warranty on parts and labor for all performance requirements. This warranty excludes any damage caused by the customer through misuse or abuse. Warranty service does not cover repairs required because of accidents, fire, water, abuse, misuse or conditions resulting from an act of nature. There shall be no cost to the Government for repairs to include parts, shipping, labor, and travel required to return the system to full operation during the one-year warranty period. The equipment furnished under this specification shall be warranted for parts and labor for a period of 1 year from the date of final acceptance. IN
THE CASE OF ANY COMPONENTS OR SUBSYSTEMS WHICH COME WITH A WARRANTY FROM THE
MANUFACTURE THAT IS LONGER THAN A YEAR, THAT WARRANTY WILL BE PROVIDED TO THE
GOVERNMENT WITH THE OTHER REQUIRED DOCUMENTATION. THE EXISTANCE OF WARRANTIES
FOR COMPONENTS OR SUBSYSTEMS WHICH HAVE A DURATION OF LONGER THAN ONE YEAR IN
NO WAY NEGATES OR DIMINISHES THE RESPONSIBILITY OF THE CONTRACTOR FOR PROVIDING
WARRANTY OF THOSE COMPONENTS OR SUBSYSTEMS FOR A PERIOD OF ONE YEAR AFTER THE
DATE OF FINAL ACCEPTANCE. There shall be single contractor accountability to prevent confusion of responsibility if a problem or breakdown occurs.
Cyber Requirements Applicable Publications
The Vendor, and all sub-contractors, must abide by all applicable regulations, publications, manuals, and local policies and procedures. This includes, but is not limited to; AR 25-1 as well as STIGs and SRGs as published on https://public.cyber.mil.
Acronyms
AO Approving Official AR Army Regulation APMS Army Portfolio Management System ARCYBER United States Army Cyber Command ASB Automation Support Branch ATO Authority to Operate CCB Configuration Control Board CD Compact Disc CMVP Cryptographic Module Validation Program COOP Continuity of Operations COR Contracting Officer Representative COTR Contracting Officer’s Technical Representative CPLD Complex Programmable Logic Device CSR Certificate Signing Request DISA Defense Information Systems Agency DOD United States Depart of Defense ELTY Electronic Tobyhanna Army Depot Form eMASS Enterprise Mission Assurance Support Service EULA End User License Agreement FIPS Federal Information Processing Standard FPGA Field Programmable Gate Array GIG Government Information Grid HBSS Host Based Security System IAVA Information Assurance Vulnerability Alert IAVB Information Assurance Vulnerability Bulletin ICAN Internal Campus Area Network IMD Information Management Division IRB Industrial Review Board IS Information System IT Information Technology NETCOM United States Army Network Enterprise Technology Command NIST National Institute of Standards and Technology OEM Original Equipment Manufacturer PKI Public Key Infrastructure PLC Programmable Logic Controller RMF Risk Management Framework SD Secure Digital
SME Subject Matter Expert SOW Statement of Work SRG Security Requirements Guide STIG Security Technical Implementation Guide TRC Technical Review Cell USB Universal Serial Bus USCYBERCOM United States Cyber Command
Definitions
This section contains explanations of terms used in this document. They are taken from, and not to supersede, those definitions given in Army Regulation (AR) 25-1. All terms used in this document are in accordance with AR 25-1.
This section shall be considered the authoritative source for definitions of terms not contained within AR 25-1 and/or its supporting documents.
Automation Support Branch The Automation Support Branch (ASB), under the Mission Support Division, under the Directorate of Production Engineering, is the single point of contact for all mission-related IT equipment at TYAD. The ASB develops, protects, and maintains specialty IT equipment, both networked and standalone, in support of unique workloads across TYAD.
Configuration Control Board
The Configuration Control Board (CCB) is the local approving authority, composed of Supervisory personnel, for all actions regarding IT equipment at TYAD. Receiving an ATO for an IT equipment, from NETCOM, does not automatically guarantee that the system can be utilized at TYAD. The IT equipment must also obtain approval from the TYAD CCB, before it may be used with Army ISs at TYAD. The CCB is the local entity responsible for approving the STIGs and SRGs deemed applicable by the TRC, before the ATO accreditation package is submitted to NETCOM for approval.
Government
Any federal civilian, or military personnel employed by the United States Department of Defense (DOD), United States Army (Army), and/or Tobyhanna Army Depot (TYAD).
Industrial Review Board The Industrial Review Board (IRB) is the local governing body that oversees all industrial mission assets to ensure compliance with TYAD production requirements. Composed of SMEs from the Directorates of Production Engineering (D/PE) and Systems Integration and Support (D/SIS), the IRB collects requirements, reviews contracting documents, plans industrial capabilities, and oversees contract implementation in alignment with current and future production needs. The three voting members of the IRB are the Division Chiefs for the Mission Support Division, Design, Development and Fabrication Division, and Command, Control, Communications, Computers, Intelligence, Surveillance and Reconnaissance (C4ISR) Finishing Division.
Information Management Division
Part of the Directorate of Installation Services, the Information Management Division (IMD) is responsible for the development, protection, and maintenance of the TYAD SBU LAN. The IMD operates all critical infrastructure upon which TYAD’s IT equipment operate.
Information System Information System (IS) is defined as the organized collection, processing, transmission, and dissemination of information in accordance with defined procedures, whether automated or manual. For the purposes of Army Portfolio Management System (APMS), the terms "application" and "information system" are both IT investments describing a discrete set of information resources organized for the collection, processing, maintenance, use, sharing, dissemination, or disposition of information (see JP 1–02).The application of IT to solve a business or operational (tactical) problem creates an information system.
Information Technology Information technology (IT) is any equipment or interconnected system or subsystem of equipment that is used in the automatic acquisition, storage, manipulation, management, movement, control, display, switching, interchange, transmission, or reception of data or information by the executive agency. For purposes of the preceding sentence, equipment is used by an executive agency if the equipment is used directly or is used by a contractor under a contract with the executive agency, which 1) requires the use of such equipment; or 2) requires the use, to a significant extent, of such equipment in the performance of a service or the furnishing of a product. The term "information technology" also includes computers, ancillary equipment, software, firmware, and similar procedures, services (including support services), and related resources. The term "information technology" does not include any equipment that is acquired by a Federal contractor incidental to a Federal contract. (Reference 40 USC Subtitle III (Clinger-Cohen Act of 1996).)
Technical Review Cell Composed of technical experts from both the ASB, and IMD, the Technical Review Cell (TRC) conducts the preliminary review of all actions, related to IT equipment at TYAD, prior to either ATO submission, or CCB approval. The TRC is responsible for determining which security technical implementation guides (STIGs), and security requirements guides (SRGs) are applicable to a given system, based on the direction given by NETCOM, and higher headquarters.
Tobyhanna Army Depot
Tobyhanna Army Depot (TYAD) is responsible for the development, and protection of the TYAD Internal Campus Area Network (TYAD-ICAN). To obtain an ATO, all IT equipment Vendors will provide the resources necessary to obtain an ATO to TYAD, so that the TYAD entities, named in this sub-section, can assemble, and submit, the information to NETCOM for consideration. In addition to approval from NETCOM, local approvals must be obtained, from the entities named in this sub-section, for an IT equipment to operate both on the TYAD-ICAN, and standalone.
United States Army Network Enterprise Technology Command
The 9th Army Signal Command, otherwise known as United States Army Network Enterprise Technology Command (NETCOM), is responsible for all Army network development, and protection. In accordance with AR 25-1, all ISs must obtain an Authority to Operate (ATO) from NETCOM, before being permitted to communicate with any Army system. It is the responsibility of the Vendor, of any IT equipment, to provide all requested documentation, software, hardware, and licenses to the Tobyhanna Army Depot (TYAD) for ATO submission.
Vendor Any non-Government personnel, whether the original equipment manufacturer (OEM), reseller, or third-party personnel involved in the procurement, installation, and/or maintenance of the IT equipment.
Hardware Requirements Without exception, all IT equipment shall comply with any, and all, applicable security technical implementation guides (STIGs) and security requirement guides (SRGs) as published by the Defense Information Systems Agency (DISA). This includes STIGs and SRGs regarding physical security. In addition, all IT equipment will comply with relevant Department of Defense (DOD) guidance, and mandates regarding hardware lifecycle upgrades. Without exception, all hardware must come from sources approved by the DOD, abide by all current restrictions, and be able to obtain and maintain an ATO throughout planned life cycle.
Communication Interfaces All IT equipment must utilize at least RS-232 serial, or Universal Serial Bus (USB) communication methods. USB connections are to function as a peripheral device only, such as a printer. USB Mass Storage Devices are strictly prohibited. Additional communication interfaces, such as Ethernet, or RS-485, are acceptable, but cannot be in lieu of an RS-232, or USB interface. Full system functionality must be provided via all communication methods present in the IT equipment. All communication interfaces must be enabled, and available for use by the Government, upon delivery of the IT equipment to the Government. This is to ensure continuity of operations (COOP) should a communication interface become either inoperable, or prohibited for security, or technical reasons.
Cryptographic Devices
Any, and all, hardware implementing cryptographic functionality must utilize a Federal Information Processing Standard (FIPS) 140-2 Level 1, or better, compliant device, certified by the National Institute of Standards and Technology (NIST) Cryptographic Module Validation Program (CMVP).
Workstations and Servers
Only standardized, Government owned, managed, and maintained computing hardware shall be utilized.
Removable Storage Media The use of removable storage media, including, but not limited to, Universal Serial Bus (USB) flash drives, CompactFlash cards, and Secure Digital (SD) cards is prohibited, except by authorized Government personnel.
Neither the Vendor, nor their sub-contractors, shall utilize such devices, and will provide data via optical media, such as a compact disc (CD) or the DOD SAFE available at https://safe.apps.mil/.
Memory Contents
In the event of main, and backup power failure, it is preferred that the IT equipment shall not utilize volatile memory to store information including, but not limited to, parameters, configurations, or passwords. Upon restoration of power, the IT equipment must return to a state such that the Government can continue to use the IT equipment without requiring service by either the Vendor, or any of their sub-contractors. The Vendor must state which form of memory (volatile or non-volatile) they will be using for which system functionalities. Further demonstration of memory is required in section 3.8.2.
Smart Card Readers
DOD personnel utilize a smartcard, called a Common Access Card (CAC) to access IT equipment. All user identification, and authentication, is to be accomplished with a FIPS 201 compliant smartcard reader.
Testing Hardware
The Vendor, and all of their sub-contractors, shall provide additional hardware, and licenses to simulate all electronic system functionality in a laboratory environment. These assets are to be used for TYAD DNC integration testing and cyber security purposes only, and will not be deployed for production use. In order to ensure that security updates, and configurations do not interfere with IT equipment in production use, the Government requires the ability to test a representative system in a controlled, laboratory environment.
Registration and Licensing
Sensitive information shall not be provided by the Government to the Vendor, or any sub-contractors. This information includes, but is not limited to; computer hostnames, IP addresses, usernames, or passwords. All products shall be registered to:
Commander Tobyhanna Army Depot 11 Hap Arnold Boulevard Tobyhanna, PA 18466
Unless approved by the TYAD CCB, physical security tokens are restricted to server use only, and prohibited in end-user IT equipment. No licensing terms between the Vendor, or any sub-contractors, may supersede any requirements from either TYAD, or higher DOD headquarters.
Software Requirements
Without exception, all IT equipment shall comply with any, and all, applicable STIGs, and SRGs developed by DISA, as well as relevant Army guidance, and mandates. Any, and all software, firmware, or operating systems intended to be used on, with, or in support of any IT equipment is required to have a current, and valid, ATO, approval from the TYAD CCB, a unique name to identify the product, and employ a version numbering system to enable tracking of outdated software. All data delivered to TYAD will be provided with FIPS 140-2 compliant cryptographic hashes to enable TYAD to verify the integrity of the received files. The provided hashes shall not reside solely on the same physical media as the associated data. Without exception, all software, firmware, and data must come from sources approved by the DOD, and abide by all current restrictions. Without exception, all software, firmware, data, and/or operating systems must come from sources approved by the DOD, abide by all current restrictions, and be able to obtain and maintain an ATO throughout planned life cycle.
Operating Systems
All IT equipment shall utilize only operating systems, approved by the Army, and configured according to applicable STIGs, SRGs, Army, and local TYAD guidance, and mandates. All operating system installations must be protected by the DOD’s Host Based Security System (HBSS) software suite.
Install Location
Unless authorized by the TYAD CCB, all software, firmware, and data provided the Vendor, and all sub-contractors, must be installed within, and provide full system functionality while running from, standard locations appropriate for the particular operating system on which it is installed (e.g., Program Files, Program Files (x86), etc.)
Account Credentials
The IT equipment must integrate with TYAD’s Active Directory infrastructure in order to utilize the existing public key infrastructure (PKI), operated by the Army, for user, service, and machine accounts. In addition, the Government must have the ability to change and/or disable, any, and all, built-in administrative, user, and service accounts in the system, including those in embedded sub-systems (e.g., microcontrollers, FPGAs, PLCs, CPLDs, etc.).
Cryptographic Functionality
All cryptographic functions must be FIPS 140-2 Level 1 compliant, or better, and utilize an implementation certified by the NIST CMVP.
Encryption Certificates
For cryptographic functionality, requiring use of a certificate, the system must be able to generate a certificate signing request (CSR) for submission to a DOD Certificate Authority. The CSR must be in a FIPS 140-2 Public Key Cryptography Standards (PKCS) #10 format of at least 2048 bits.
Connections to Outside Systems
All data shall remain within the bounds of the DOD Global Information Grid (GIG). Connections to outside entities for purposes including, but not limited to, performance metric reporting, or remote support are prohibited.
Support Requirements All IT equipment are required to have a valid support contract for at least the software, and firmware. While a support contract is in effect, the following requirements, and all those listed in applicable STIGs, and SRGs from DISA, as well as relevant DOD guidance, and mandates shall apply in order for the system to maintain the ATO.
The information contained within the Acceptance section 3.8 of this document shall also apply for the duration of the support contract. In addition an upgrade path for the system for its planned life cycle must be outlined by the vendor. The upgrade path must be able to address all potential issues discussed under heading 3.6 and its subheadings.
Response Time
The Government will receive a response from either the Vendor, or one of their sub-contractors, no later than 24 hours after the Government initiated a service request with either the Vendor, or one of their sub-contractors.
Replacement Hardware
Any, and all, replacement hardware shall be new, or functionally, and aesthetically, equivalent to new, in performance, and appearance.
Software Updates Software support will include software updates and enhancements on covered software products. Covered software products is defined as any software, or firmware provided, by the Vendor and/or any subcontractors, to the Government.
Operating System Compatibility
The IT equipment must remain compatible with future updated operating systems in accordance with DOD migration schedules during the entirety of the system’s planned lifecycle. Delivery, to the Government, of all materials required to perform upgrades for compatibility must be completed within the timelines set by DISA, NETCOM, U.S. Army Cyber Command (ARCYBER), U.S. Cyber Command (USCYBERCOM), and any additional DOD organizations tasked with the security of the GIG.
Security Updates
The Vendor, and all of their sub-contractors, shall address all security-related issues for the duration of the support contract. Delivery, to the Government, of all materials required to perform mitigation, and/or remediation of Information Assurance Vulnerability Alerts and Bulletins (IAVAs and IAVBs) must be completed within the timelines set by DISA, NETCOM, ARCYBER, USCYBERCOM, and any additional DOD organizations tasked with the security of the GIG.
Safety Issues
The Vendor, and all of their sub-contractors, shall address all safety-related issues, as identified by the TYAD Safety Office, for the duration of the support contract. Delivery of all materials required to perform mitigation and/or remediation of safety hazards must be completed within the timelines set by the TYAD Safety Office.
Cyber Documentation
The Vendor, and all sub-contractors, shall provide at least a digital copy of the following information, in a file format to be approved by the TYAD CCB. All the following information must be delivered with a valid cryptographic hash using an approved method. The cryptographic hashes of any products built using the information provided by the Vendor, and all sub-contractors, must match the cryptographic hashes of the compiled data provided to the Government.
Manuals The Vendor, and all sub-contractors, shall provide a complete set of instruction manuals containing all information necessary to operate, maintain, administer, and reinstall software and hardware contained within the system.
Disaster Recovery The vendor shall also provide step-by-step instructions to facilitate a complete restoration of the system, to the state in which it was initially accepted by TYAD, in the event of a fatal system error.
System Backups The Vendor, and all sub-contractors, shall also provide a backup copy of all configuration settings in effect at the time of successful demonstration of system functionality.
Source Code If any software, firmware, or data has been customized for use by the Government, the Vendor, and all sub-contractors shall provide the associated source code, firmware, build environment, and build instructions to the Government. If any software, firmware, or data, governed by an open source license has been provided for use by the Government, the Vendor, and all sub-contractors shall provide the associated source code, firmware, build environment, and build instructions to the Government.
Calibrations and Certifications The vendor and all sub-contractors must provide a digital copy of any documentation related to certifications received by the system or information of calibrations performed on the system.
Implementation Plan The Vendor will submit a written implementation plan for review and acceptance by the TYAD CCB. This plan will include, but is not limited to, detailed information of all IT equipment, components, software, firmware, and data to be delivered to TYAD. All IT IT equipment, components, software, and firmware must have an associated version number.
Digital Copies of Paper Deliverables In addition all documentation requested in section 7.0 Documentation must be provided digitally.
Acceptance
The following criteria must be met before any IT equipment can be accepted, and put into use, by TYAD. Upon acceptance, all assets provided to TYAD by the Vendor, and all sub-contractors, shall become the sole property of the Government. All data delivered to TYAD shall be provided with FIPS 140-2 compliant cryptographic hashes to enable TYAD to verify the integrity of the received files. The provided hashes shall not reside solely on the same physical media as the associated data, and must not be initially provided after receipt of the data by TYAD. Data received by TYAD which does not match the associated cryptographic hashes shall not be considered valid, and will not be accepted.
Proof of Implementation
Upon solicitation, the Vendor will submit a written implementation plan for review and acceptance by the TYAD CCB. This plan will include, but is not limited to, detailed information of all IT equipment, components, software, firmware, and data to be delivered to TYAD. This plan, and the associated list of components will be verified by TYAD personnel to ensure the promised assets have not been tampered with prior to system delivery at TYAD. The same component list will be used to verify that no assets are tampered with during the install phase, after delivery, but prior to acceptance by TYAD. The component list will continue to be used to verify system integrity, and track changes made, after acceptance by TYAD.
Proof of COOP A successful demonstration of disaster recovery is required. The demonstration must include removing any power or backup power, battery or otherwise, from the system followed by the return of a state such that the Government can continue to use the IT equipment without requiring service by either the Vendor, or any of their sub-contractors.
Any files and/or passwords used in the disaster recovery demonstration must be provided to TYAD by the vendor.
This demonstration must be carried out in accordance with demonstration guidelines defined in section 3.6.3.
Proof of Functionality The IS must obtain written confirmation, from the Contracting Office Representative (COR), of successful demonstration of full system functionality, a demonstration of COOP (section 3.8.2), and any demonstrations agreed to by the vendor during the solicitation or performance periods. The demonstration must occur at TYAD, in the presence of either the COR, or the Contracting Office Technical Representative (COTR) and at least one TYAD subject matter expert (SME). The COTR cannot serve as the only SME, at least one SME shall be from the Cost Center where the asset is to be utilized. Full system functionality demonstrations shall only be performed on the fully installed IT equipment. The written confirmation, from the COR, will contain an itemized list of checks performed during the demonstration. Each check will detail the steps taken, inputs/commands given, and results received. The TYAD COR/COTR and TYAD SMEs shall sign and date the verified component list, previously provided as Proof of Implementation, as well as the completed system functionality demonstration checklist. End-user license agreements (EULA) and similar documents will be signed by the TYAD COR/COTR and TYAD SMEs, after signing both the verified component list, and completed system functionality demonstration checklist. If the COTR is present for the full system functionality demonstration test, and signs on behalf of the COR, then the COR must sign and date the same documents, upon receipt from the COTR.