SOLICITATION - SOW and Specifications Rev 2 - Final.docx

DOCX document 1 MB Posted

Attached to
Reprogram Chiller Federal contract opportunity
Solicitation number
12305B24Q0015
Issued by
Department of Agriculture Agricultural Research Service Field Research Implementation and Information Delivery Northeast Area

About this file

This statement of work and specifications document outlines requirements for a federal contract to reprogram one 360-ton Trane chiller at a Department of Agriculture facility. The contractor shall inspect and reprogram the chiller's computer boards according to manufacturer specifications, start up and test the chiller under full load while monitoring operations, and ensure the chiller and work area are clean upon completion. Additional requirements include pre-repair documentation submittals, complying with safety, security, and operations plans, and restoring any areas affected by the work. The solicitation number, agency, and opportunity type are provided for the corresponding federal contract opportunity to reprogram the chiller.

View the file

Other files for this federal contract opportunity

Other files attached to Reprogram Chiller, newest first.
File Type Posted
QA.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

UNITED STATES DEPARTMENT OF AGRICULTURE

BELTSVILLE AGRICULTURAL RESEARCH CENTER

FACILITIES SERVICE

ENGINEERING AND CONSTRUCTION BRANCH

BUILDING 426A, BARC-EAST

10300 BALTIMORE AVENUE

BELTSVILLE, MARYLAND 20705-2350

STATEMENT OF WORK AND SPECIFICATIONS

TO

RE-PROGRAM ONE 360 -TON TRANE CHILLER AT BUILDING 010A

BELTSVILLE AGRICULTURAL RESEARCH CENTER

BELTSVILLE, MARYLAND

April 18, 2023

GENERAL REQUIREMENTS

1.1 GENERAL INTENTION

A.Contractor shall make a complete and proper repair on the Trane 360-ton chiller to include the reprograming of all software.
B.Visits to the site by Bidders may be made only by appointment with the EPM/COR, telephone (301) 504-9817. Alternate – Site visit for all bidders is scheduled for a predetermined time that works for all parties.
C.All employees of general contractor and subcontractors shall comply with ARS security management program, obtain permission of the ARS Location Manager, be identified by project and employer by wearing contractor issued identification badges always on ARS property, and restricted from unauthorized access.
D.Prior to commencing work, the general contractor shall provide proof that an OSHA certified “competent person” (CP) (29 CFR 1926.20(b)(2) will maintain a presence at the work site whenever the general or subcontractors are present.
E.Training:
1.All employees of the general contractor or subcontractors shall have the 10-hour OSHA certified Maintenance Safety course and /or other relevant competency training. Supervisors shall have completed the 30-hour OSHA training.
2.Submit training records of all such employees to the Contracting Officer for approval before the start of work.

1.2 STATEMENT OF BID ITEM(S)

A. ITEM I, GENERAL REPAIRS: Work includes general repairs associated with the reprogramming, start-up, and full operation of the 360-ton Trane chiller.

STATEMENT OF WORK

PROJECT LOCATION: Beltsville Agricultural Research Center (BARC), 10300 Baltimore Avenue, Building 010A, Beltsville, Maryland. 20705-2350

DESCRIPTION OF WORK: The Contractor Shall provide all labor and material to:

Reprogram one Trane 360-ton chiller that has been outfitted with new solid state control boards. The contractor shall ensure to install the proper software for Trane chiller model CVHE 360. The model number for this chiller is CVHE036FC1X03UK2375R1E6S2A000021CPA00000. The serial number for this chiller is L93L11852. The chiller voltage is 460 3PH with a 115-voltage control circuit. The refrigeration system utilizes (800 lbs. of R-123) refrigerant. The contractor shall conduct an overall inspection of the chiller prior to the start of the programming of the chiller to ensure the pressure/temperature transducers are being recognized at the control panel. The contractor shall ensure the compressor oil pressure and temperatures are within range before starting the process of programming the control boards for the chiller. The contractor shall program the new computer boards as per the factory recommendations. Once the programming of the new computer boards has been completed, the contractor shall start the chiller, and place the chiller under a full load while carefully monitoring all operations of the chiller. While the chiller is under full load, the contractor shall perform refrigerant leak detection, and check the accuracy of the pressures and temperatures using refrigeration and thermal testing equipment. The contractor shall record all information in the chiller log book and on the service ticket. The contractor shall take an oil sample from the chiller and have an analysis conducted and report the findings in writing. The contractor shall ensure the chiller and area around the chiller is clean upon the completion of the job.

Picture 1 Trane (360 – Ton) Chiller Data Information for Building 010A.

Picture 2 Trane (360 – Ton) Computer Boards Building 010A

Picture 3 Trane (360 – Ton) Wiring Diagram Building 010A

Picture 4 Trane (360 – Ton) Chiller at Building 010A

Picture 5 Trane (360 – Ton) Chiller with Purge Unit at Building 010A Rear View

1.3 Pre-Repair Documentation: The contractor shall provide all labor and material to:

A. The contractor shall furnish all literature with the sequence of operation for installing the needed software onto the chiller.

1.4 Post Repair Clean-up, final inspection, and meeting: The contractor shall provide all labor and materials to:

A. The contractor shall be sure to remove any trash and they bring and ensure valve caps that cover access ports are re-affixed to the equipment.

1.5 Project Coordination:

A. Construction Project Schedule:

1. The Contractor will submit a repair project schedule to the Contracting Officer for approval within 5 days after receiving the Notice to Proceed. The Contractor will not begin actual work until the maintenance project schedule has been approved by the Contracting Officer.

2. The repair project schedule shall clearly show estimated repair time as well as actual repair time as the work progresses. A Gantt-type chart software shall be used.

3. The Contractor shall submit one electronic copy and one paper copy of the updated repair project schedule with each progress payment request.

B. Contract Inspector’s Daily Report:

The contractor shall submit to the Contracting Officer a daily report listing the names of all those present on the job site each day, along with their Job Classification, hours of work and a brief description of the work performed by each on that day. The Contract Inspector’s Daily Report is to be submitted at the beginning of work each day for the previous day’s work and shall be maintained throughout the term of the contract.

C. Contractor’s Contact Log (Form SF-1413):

The contractor shall provide the Contracting Officer a list of all subcontractors in a table format listing at least the following (which apply): Company Name, Company Address, Name of Contact person(s), Telephone Numbers, Fax Numbers, and E-mail address. The Contractor shall update the list immediately when subcontractors change or are added.

D. Formal Meetings:

Any meeting (deemed formal by the contractor, the COR, or the Contracting Officer) will have the minutes of said meeting prepared by the contractor (and a copy provided to the Contracting Officer). The minutes will include Date, Name of Attendees (with contact info), Old Business, and New Business subjects (or narratives). Regardless of who requests a meeting (the COR or the Contractor or the Contracting Officer) the contractor may be required to provide hard copy pictures of the issues to be discussed. Each issue will be linked to a contract specification section number and/or subject area by page number. Issues discussed will also include an action/completion date.

1.6 SAFETY SUBMITTALS

A. Contractor shall submit a "site specific" Safety Plan to the Contracting Officer that describes how the contractor is to comply with all applicable OSHA standards and NFPA codes pertaining to repair work to include, but not limited to: General Safety and Health Provisions, Occupational Health and Environmental Controls, Personal Protective and Life Saving Equipment, Hand and Power Tools, Welding and Cutting, Electrical, Scaffolds, Fall Protection, Excavations, Demolition, Stairways and Ladders, Toxic and Hazardous Substances, Confined Space Entry, Lockout/Tagout, Respiratory Protection, Hearing Protection. Safety Plan shall identify Contractor and sub-contractor employees who are authorized/qualified to perform electrical work. No work shall proceed until written approval of the Safety Plan by the Contracting Officer. Safety Plan shall describe how the Contractor and/or sub-contractors are to secure equipment, supplies, tools, and chemical products. Contractor and/or sub-contractor equipment, supplies, tools, and chemical products are to be under the control of the Contractor always, equipment, supplies tools, and chemical products found not to be under the control of the Contractor or sub-contractor may be confiscated and delivered to the Contracting Officer.

B. The Contractor shall inspect the entire work site daily, including days without maintenance work if there are NFPA 101 Life Safety Code deficiencies existing while maintenance work is shut down, the results of that inspection shall be documented on the attachment “DAILY INSPECTION FORM”, and the form is to be signed and submitted to the Contracting Officer.

C. Contractors shall provide continuous monitoring for noise, dust, chemical vapor generation, volatile organic compounds, and vibration. At no time, shall noise exposure to any ARS staff exceed 75 db. Contractor shall provide to the Contracting Officer a written weekly update of the all test results and for proposed work for the subsequent two weeks (a two week “look-ahead”) involving any maintenance activity that will produce loud noises, heavy vibrations, strong smells, or significant dust inside ARS staff occupied space.

D. Contractors and sub-contractors shall notify in writing the Contracting Officer at least one week prior to executing high risk work (this may be included in the two week “look-ahead” update). High risk work includes, but is not limited to, tasks requiring Lockout/Tag Out, live electrical work, hot work, work at heights, trenching/ shoring, crane operations, and confined space entry. Contractor’s Competent Person shall provide the Contracting Officer with written weekly documented safety inspection results.

1.7 construction security requiremenets

A.Security Plan:
1.The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.
2.The General Contractor is responsible for assuring that all subcontractors working on the project and their employees also comply with these regulations.
B.Contractor Personnel
1.Upon receipt of the Notice to Proceed, the Contractor shall provide information about every employee including that of all subcontractors who will need access to the repair site.
3.Each employee shall be furnished with a badge by the Government for access to the repair site. This badge must be worn to be clearly visible always while on the work site.
C.Security Procedures:
1.Contractor’s employees shall not enter the project site without appropriate badges. The badges shall be obtained from building 426A prior to reporting to the job site. Each vehicle onsite shall have a vehicle tag for the rear-view mirror during repairs.
2.For working outside the regular working hours (7:00am – 4:00pm) as defined in the contract, The Contractor shall give a ten (10) day notice to the Contracting Officer so that security arrangements can be provided for the employees. This notice is separate from any notices required for utility shutdown described later in this section.
3.No photography of ARS premises is allowed without written permission of the Contracting Officer.
4.ARS reserves the right to close or shut down the project site and order the Contractor’s employees off the premises in the event of a national emergency or Government shutdown. The Contractor may return to the site only with the written approval of the Contracting Officer.
D.Key Control:
1.The Contractor shall provide duplicate keys and lock combinations to the Contracting Officer for the purpose of security inspections of every area of the project including toolboxes and parked machines and take any emergency action.

E. Document Control:

1.The Contractor is responsible for the safekeeping of all drawings, project manuals and other project information. This information shall be shared only with those with a specific need to complete the project.
2.These documents shall not be removed or transmitted from the project site without the written approval of the Contracting Officer.
3.All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the ARS.
F.Motor Vehicle Restrictions
1.Vehicle authorization request shall be required for any vehicle entering the site and such request shall be submitted 24 hours before the date and time of access. Access shall be restricted to picking up and dropping off materials and supplies and Contractor must be on site to receive all deliveries.
2.Separate permits shall be issued for Contractor and its employees for parking in designated areas only.

1.8 OPERATIONS AND STORAGE AREAS

A.The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the Government, its officers, and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.
B.Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the approval of the Contracting Officer and shall be built with labor and materials furnished by the Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the Contractor and shall be removed by the Contractor at its expense upon completion of the work. With the written consent of the Contracting Officer, the buildings and utilities may be abandoned and need not be removed.
C.The Contractor shall, under regulations prescribed by the Contracting Officer, use only established roadways, or use temporary roadways made by the Contractor when and as authorized by the Contracting Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.
D.Working space and space available for storing materials shall be as determined by the Contracting Officer.
E.Workers are subject to the rules of the Location applicable to their conduct which shall be provided by the Contracting Officer.
F.Execute work to interfere as little as possible with the normal functioning of Location including operations of utility services, fire protection systems and any existing equipment, and with work being done by others. Use of equipment and tools that transmit vibrations and noises through the building structure are not permitted in buildings that are occupied during construction except as permitted by the Contracting Officer where required by limited working space.
1.Do not store materials and equipment in other than assigned areas.
2.Schedule delivery of materials and equipment to immediate maintenance working areas within buildings in use by the ARS in quantities sufficient for not more than two workdays.
3.Where access by ARS personnel to vacated portions of buildings is not required, storage of Contractor's materials and equipment may be permitted subject to fire and safety requirements.
G.Contractor shall take all measures and provide all material necessary for protecting existing equipment and property in affected areas of work against dust and debris, so that equipment and affected areas to be used in the ARS operations will not be hindered. Contractors shall permit access to ARS personnel through work areas which serve as routes of access to such affected areas and equipment. Coordinate alteration work in areas occupied by ARS so that operations will continue during the work period.
H.Utilities Services: Maintain existing utility services for ARS always. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services. Where necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems (including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by the Contracting Officer.
1.No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior written approval of the Contracting Officer. Electrical work shall be accomplished with all affected circuits or equipment de-energized. When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without the Contracting Officer’s prior knowledge and written approval.
2.Contractor shall submit a request to interrupt any such services to the Contracting Officer, in writing, Two weeks advanced notice and again 48 hours in advance of proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption.
3.Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of ARS. Interruption time approved by ARS may occur at other than Contractor's normal working hours.
4.Major interruptions of any system must be requested, in writing, at least 21 calendar days prior to the desired time and should be performed as directed by the Contracting Officer. It is the Contractor's responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the mitigating life safety measures to be used during the work, and a schedule defining the duration of the work with milestone subtasks.
5.In case of a contract repair emergency, service will be interrupted on the approval of the Contracting Officer. Such approval will be confirmed in writing as soon as practical.
6.Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the repair project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.
J.To minimize interference of repair activities with flow of ARS traffic, comply with the following:
1.Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of maintenance materials, debris and standing repair equipment and vehicles.
2.Method and scheduling of required cutting, altering and removal of existing roads; walks and entrances must be approved by the Contracting Officer.
K.Coordinate the work for this contract with other construction operations as directed by the Contracting Officer. This includes the scheduling of traffic and the use of roadways, as specified in Article, USE OF ROADWAYS.

1.9 ALTERATIONS

A.Survey: Before any work is started, the Contractor shall make a thorough survey with the Contracting Officer, of areas of the building in which alterations occur and areas which are anticipated routes of access, and furnish a report, signed, to the Contracting Officer.
1.Shall note any discrepancies between drawings and existing conditions at site.
2.Shall designate areas for working space, materials, storage, and routes of access to areas within buildings where alterations occur, and which have been agreed upon by Contractor and Contracting Officer.
B.Any items required by drawings to be either reused or relocated or both, found during this survey to be nonexistent, or in opinion of Contracting Officer, to be in such condition that their use is impossible or impractical, shall be furnished and/or replaced by Contractor with new items in accordance with specifications which will be furnished by Government.
C.ReSurvey: Thirty days before the expected partial or final inspection date, the Contractor and Contracting Officer together shall make a thorough resurvey of the areas of building.
1.Resurvey report shall list any damage caused by Contractor and will form basis for determining extent of repair work required of Contractor to restore damage caused by Contractor's workers in executing work of this contract.
D.Protection: Provide the following protective measures:
1.Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled, and equipment moved and/or relocated.
E.Final Cleanup:
1.Upon completion of project, or as work progresses, remove all repair debris from the site.

2.0 DISPOSAL AND RETENTION

A.Materials and equipment accruing from work removed and from demolition of roadway, or parts thereof, shall be disposed of as follows:
1.Items that remain property of the Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to reinstallation and reuse. Store such items were directed by Contracting Officer.
2.Items not reserved shall become property of the Contractor and be removed by Contractor from ARS property.
3.Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the Government. When rooms and spaces are vacated by the ARS during the alteration period, such items which are NOT required by drawings and specifications to be either relocated or reused will be removed by the Government in advance of work to avoid interfering with Contractor's operation.

2.1 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND IMPROVEMENTS

A.The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work site, which is not to be removed and which does not unreasonably interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workers, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a treepruning compound as directed by the Contracting Officer.
B.The Contractor shall protect from damage all existing improvements and utilities at or near the work site and on adjacent property of a third party, the locations of which are made known to or should be known by the Contractor. The Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the Contractor fails or refuses to repair the damage promptly, the Contracting Officer may have the necessary work performed and charge the cost to the Contractor.

(FAR 52.2369)

2.2 RESTORATION

A.Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter, or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without the approval of the Contracting Officer. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the Contracting Officer before it is disturbed. Materials and workmanship used in restoring work shall conform in type and quality to that of original existing repair, except as otherwise shown or specified.
B.Upon completion of contract, deliver work complete and undamaged. Existing work (mechanical and electrical work, lawns, paving, roads, walks, etc.) disturbed or removed because of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.
C.At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor's workers to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems (including telephone) which are indicated on drawings, and which are not scheduled for discontinuance or abandonment.

2.3 HISTORIC PRESERVATION

Where the Contractor or any of the Contractor's employees, prior to, or during the repair work, are advised of, or discover any possible archeological, historical and/or cultural resources, the Contractor shall immediately notify the Contracting Officer verbally, and then with a written follow up.

DAILY INSPECTION FORM

INSTRUCTIONS: This form is to be utilized when hazards are posed by NFPA 101 deficiencies or construction activities are in progress. Remediation must be implemented upon project start and continuously enforced through project completion to provide a level of life safety comparable to that described in the Life Safety Code. Submit completed forms to the CO & COR weekly.

Project Name:
Project Number:

Construction Location: Affected Areas:

Project COR:
Project Start Date:
Project Competent Person (CP):
Estimated Duration:

Completion Date:

Contractor:

GC Supervisor:
Telephone:

Contractor CP:

Inspection Period: Responses:
SUN
MON
TUE
WED
THR
FRI
SAT

1. Are exits readily accessible and provide unobstructed egress?

2. Have alternate exits been established if required due to inaccessibility of existing exits?

3. If alternate exits have been established, are personnel in the area informed and aware of their relocation?

4. Are the existing and relocated exits clearly marked and able to be seen in the event of a fire or emergency?

5. Are evacuation routes posted with follow-up inspections required by repair impact changes in escape routes?

6. Are written procedures and guidelines posted in the immediate and adjacent areas for what to do and who to call in the event of a fire or emergency?

7. Are personnel in immediate/adjacent areas aware and informed in procedures and guidelines to follow in the event of fire or emergency?

8. Is there free and unobstructed access to services for emergency personnel (e.g., fire, medical, security)?

9. Are fire alarm (e.g., pull station), detection (eg, smoke/heat), suppression (e.g., sprinkler, extinguisher) systems in working order, protected and unobstructed with locations identified?

10. If the fire alarm, detection, suppression systems are impaired or temporarily non-functional, has a fire watch for the area, as required or necessary, been trained and established?

11. If the fire alarm, detection, suppression systems are impaired, have measures been taken to provide temporary equivalent equipment and/or systems for adequate protection? Note date for equivalent measures.

12. If the fire alarm, detection, suppression systems are impaired, are equivalent equipment/systems inspected and tested at least monthly?

13. If temporary fire alarm, detection, suppression systems are installed, are personnel in the area aware and trained on how to operate or utilize them in the event of fire or emergency?

14. Has the “No Smoking” policy been posted, implemented and enforced in the repair area?

15. Are temporary partitions built to be fire/smoke tight with fire retardant noncombustible material and inspected daily for integrity?

16. Ensure that temporary fencing is erected to help secure the site.

17. Is repair site access restricted to authorized personnel only including warning signs and secured at the end of each day?

Page 40 of 114
Page 40 of 114
Inspection Period: Responses:
SUN
MON
TUE
WED
THR
FRI
SAT

17. Is repair area hazard surveillance conducted daily?

18. Is repair area storage, waste, debris and excess materials being daily managed properly to reduce fire or safety hazards?

19. Are repair activities and materials prosecuted, handled, stored, and secured in an orderly and safe manner?

20. Is the generation, spread and exposure of repair dust, fumes, noise, odor, smoke controlled with appropriate fume, odor, vapor ventilation provided to control noxious, infectious, toxic exposure and store/protect flammable/combustible products?

21. Has a GC Safety Manager been designated with routine site safety meetings conducted to ensure awareness of Life Safety Code?

22. Is personnel protective equipment (e.g., safety glasses, ear plugs, hard hats) required and being used?

23. If there are hand/safety rails, scaffolding or ladders required, are they in place, in good condition and being used in a safe manner?

24. Are the repair site (buildings and exterior grounds) hazards (e.g., fall/trip) guarded and free of potential safety violations?

25. Do electrical panels, temporary wiring, extension cords (3 wire grounded type), tools, and equipment appear to be installed, utilized, and functioning in a safe manner?

26. If there are temporary electrical outlets provided, do they have ground fault protection at the receptacle/panel?

27. If hazardous equipment/systems need to be de-energized, are applicable “Lockout/Tagout” procedures being followed?

28. Are utility services (e.g., electrical, steam, water, waste, gas) properly secured at the end of each day?

29. If there is any hot work (welding, soldering, cutting) being performed within the repair site, have additional fire safety precautions been taken and necessary equipment provided?

30. If there is any hot work (welding, soldering, cutting) being performed on the repair site, has the Contracting Officer been notified? Has the Hot Work Permit been approved?

31. If hazardous products are present, are they limited to the amount needed and used daily?

32. Are hazardous products disposed per EPA requirements?

33. Are all hazardous products present or being used (e.g., flammable, combustible, corrosive, noxious) labeled with MSDS information readily available?

34. Are all safety incidents documented and reported to the Contracting Officer?

Contractor CP Initials Performing Daily Inspections:

Inspection Comments/Findings: (PROVIDE DETAILED EXPLAINATION OF EXCEPTIONS/DEFICIENTIES)

Signature/Date: ________________________________________ ___________________ Project CP/ GC Safety Manager Date

END