This solicitation requests proposals for a fixed-price construction contract to install fixed emergency generators at the Federal Prison Camp in Bryan, Texas. The selected contractor must provide all materials, labor, and equipment to complete the project in accordance with the attached specifications and drawings by August 10, 2023. The magnitude of the project is estimated between $1,000,000 and $5,000,000. The contractor must submit performance and payment bonds within 10 days of award and carry workers' compensation, general liability, and automobile insurance. The pre-construction conference will cover labor standards, prevailing wage requirements, and institution procedures. The contractor must make submittals, coordinate inspections, and participate in monthly progress meetings over the 364-day performance period.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Bid Abstract.pdf | ||
| Amendment 00002- Bid Submission Extension.pdf | ||
| Amendment 0001- Pre-Bid Site Visit Minutes.pdf | ||
| Wage Determination TX20230234 Modification 3.pdf | ||
| Attachment 5 - Criminal History Check Form.pdf | ||
| Instruction to Bidders.pdf | ||
| Attachment 4 - SF-24 Bid Bond Form.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
15BFA023B00000013 Page 1 of 55
SOLICITATION,OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NUMBER
15BFA023B00000013
X SEALED BID (IFB)
INVITATION FOR BID
NEGOTIATED (RFP)
REQUEST FOR PROPOSAL
2. TYPE OF SOLICITATION 3. DATE ISSUED
06/29/2023
PAGE OF PAGES
1 55
IMPORTANT -The "offer" section on the reverse must be fully completed by offeror.
4. CONTRACT NUMBER 5. REQUISITION/PURCHASE REQUEST NUMBER
15B50423PR000119
6. PROJECT NUMBER
23Z5AM4
CODE BFAO
Federal Bureau of Prisons Field Acquisition Office U.S. Armed Forces Reserve Complex 346 Marine Forces Drive Grand Prairie, TX 75051
7. ISSUED BY 8. ADDRESS OFFER TO
9. FOR
INFORMATION CALL:
a. NAME
Patrick Ford pford@bop.gov
b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)
202-913-1665
SOLICITATION
NOTE: In sealed bid solicitations "offer" and "offeror" means "bid" and "bidder".
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)
The selected contractor shall provide all materials, labor, and equipment to complete the project Install Fixed Emergency Generators at the Federal Prison Camp located in Bryan, TX in accordance with the attached Specifications and Drawings. PLEASE COMPLETE
THE FOLLOWING ITEMS:
UNIQUE ENTITY IDENTIFIER (FORMERLY DUNS):_____________________________
TAX IDENTIFICATION NUMBER: ____________________________
CAGE CODE:________________________________
CONTRACTOR EMAIL:_______________________________
11. The Contractor shall begin performance within calendar days and complete it within calendar days after receiving10 364 award, X notice to proceed. This performance period is X mandatory negotiable. (See __________________________.)
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS? (If "YES," indicate within how many calendar days after award in Item 12b).
X YES NO
12b. CALENDAR DAYS
Sealed offers in original and copies to perform the work required are due at the place specified in item 8 by (hour) local time (date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
13:00US/
Pacific a.
08/10/2023
b. An offer guarantee X is, is not required.
All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.c.
90d. Offers providing less than calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
13. ADDITIONAL SOLICITATION REQUIREMENTS:
STANDARD FORM 1442 (REV. 12/2022)
Prescribed by GSA - FAR (48 CFR) 53.236-1(d)
Bidders shall upload all documents identified in the Instructions to Bidders to the following
URL:
https://jefs.app.box.com/f/9d556ec12dac4a34afb98485f2dcd7b6 bop37133 Highlight
15BFA023B00000013 Page 2 of 55
OFFER (Must be fully completed by offeror)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NUMBER (Include area code)
16. REMITTANCE ADDRESS (Include only if different than Item 14.)
CODE FACILITY CODE
The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ___________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
17.
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT
NUMBER
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)
20b. SIGNATURE 20c. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified) 27
ITEM
10 U.S.C. 3204(a) ( ) 41 U.S.C. 3304(a) ( )
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO THE
UNITED STATES CODE AT
26. ADMINISTERED BY 15B504
Federal Bureau of Prisons FPC Bryan 1100 Ursuline Bryan, TX 77803
Federal Bureau of Prisons FPC Bryan 1100 Ursuline Bryan, TX 77803
27. PAYMENT WILL BE MADE BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return __________ copies to issuing office.) Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.
30a.NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)
Patrick R Ford
31a. NAME OF CONTRACTING OFFICER (Type or print)
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA
BY
31c. DATE
STANDARD FORM 1442 (REV. 12/2022) BACK
bop37133 Highlight bop37133 Highlight bop37133 Highlight bop37133 Highlight
15BFA023B00000013 Page 3 of 55
Table of Contents
Section Description Page Number
1 Solicitation, Offer and Award 2 Commodity or Services Schedule 3 Special Contract Requirements
FAO-0001 Bonds FAO-0002 Magnitude FAO-0003 Required Insurance FAO-0004 Pre-Construction Conference FAO-0005 Submittals FAO-0006 Contractor Use of Premises FAO-0007 Payment Services FAO-0008 Request for Final Inspection FAO-0009(a) Construction Contract Security FAO-0010 Assignment of Contract Administration Office and Functions FAO-0011 Schedule of Values FAO-0012 Progress Meetings FAO-0013 Contract Closeout Procedures (for construction contracts exceeding $150,000)
4 Contract Clauses 52.246-12 Inspection of Construction (Aug 1996) 52.236-15 Schedules for Construction Contracts (Apr 1984) 52.242-14 Suspension of Work (Apr 1984) 52.204-23 Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by Kaspersky Lab and Other Covered Entities (Nov 2021) 52.204-25 Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment (Nov 2021) 52.202-1 Definitions (Jun 2020) 52.203-3 Gratuities (Apr 1984) 52.203-5 Covenant Against Contingent Fees (May 2014) 52.203-6 Restrictions on Subcontractor Sales to the Government (Jun 2020) 52.203-7 Anti-Kickback Procedures (Jun 2020) 52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity (May 2014) 52.203-10 Price or Fee Adjustment for Illegal or Improper Activity (May 2014) 52.203-12 Limitation On Payments to Influence Certain Federal Transactions (Jun 2020) 52.203-17 Contractor Employee Whistleblower Rights and Requirement To Inform Employees of Whistleblower Rights (Jun 2020) 52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements (Jan 2017) 52.204-4 Printed or Copied Double-Sided on Postconsumer Fiber Content Paper (May 2011) 52.204-9 Personal Identity Verification of Contractor Personnel (Jan 2011) 52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards (Jun 2020) 52.204-13 System for Award Management Maintenance (Oct 2018) 52.204-14 Service Contract Reporting Requirements (Oct 2016) 52.204-18 Commercial and Government Entity Code Maintenance (Aug 2020) 52.204-27 Prohibition on a ByteDance Covered Application (Jun 2023) 52.209-6 Protecting the Government's Interest When Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment (Nov 2021) 52.209-9 Updates of Publicly Available Information Regarding Responsibility Matters (Oct 2018) 52.209-10 Prohibition on Contracting with Inverted Domestic Corporations (Nov 2015) 52.219-6 Notice of Total Small Business Set-Aside (Nov 2020) 52.219-8 Utilization of Small Business Concerns (Oct 2022) 52.219-28 Post-Award Small Business Program Rerepresentation (Mar 2023) 52.222-1 Notice to the Government of Labor Disputes (Feb 1997) 52.222-3 Convict Labor (June 2003) 52.222-4 Contract Work Hours and Safety Standards--Overtime Compensation (May 2018) 52.222-12 Contract Termination - Debarment (May 2014)
15BFA023B00000013 Page 4 of 55
52.222-7 Withholding of Funds (May 2014) 52.222-14 Disputes Concerning Labor Standards (Feb 1988) 52.222-13 Compliance with Construction Wage Rate Requirements and Related Regulations (May 2014) 52.222-8 Payrolls and Basic Records (Jul 2021) 52.222-9 Apprentices and Trainees (July 2005) 52.222-6 Construction Wage Rate Requirements (Aug 2018) 52.222-11 Subcontracts (Labor Standards) (May 2014) 52.222-15 Certification of Eligibility (May 2014) 52.222-10 Compliance with Copeland Act Requirements (Feb 1988) 52.222-21 Prohibition of Segregated Facilities (Apr 2015) 52.222-26 Equal Opportunity (Sept 2016) 52.222-27 Affirmative Action Compliance Requirements for Construction (Apr 2015) 52.222-37 Employment Reports on Veterans (Jun 2020) 52.222-40 Notification of Employee Rights Under the National Labor Relations Act (Dec 2010) 52.222-50 Combating Trafficking in Persons (Nov 2021) 52.222-54 Employment Eligibility Verification (May 2022) 52.222-55 Minimum Wages for Contractor Workers Under Executive Order 14026 (Jan 2022) 52.222-62 Paid Sick Leave Under Executive Order 13706 (Jan 2022) 52.223-2 Affirmative Procurement of Biobased Products Under Service and Construction Contracts (Sep 2013) 52.223-3 Alt I Hazardous Material Identification and Material Safety Data (Feb 2021) - Alternate I (July 1995) 52.223-5 Pollution Prevention and Right-to-Know Information (May 2011) 52.223-11 Ozone-Depleting Substances and High Global Warming Potential Hydrofluorocarbons (Jun 2016) 52.223-17 Affirmative Procurement of EPA-designated Items in Service and Construction Contracts (Aug 2018) 52.223-18 Encouraging Contractor Policies to Ban Text Messaging While Driving (Jun 2020) 52.223-21 Foams (Jun 2016) 52.223-20 Aerosols (Jun 2016) 52.225-13 Restrictions on Certain Foreign Purchases (Feb 2021) 52.227-1 Authorization and Consent (Jun 2020) 52.227-2 Notice and Assistance Regarding Patent and Copyright Infringement (Jun 2020) 52.227-4 Patent Indemnity-Construction Contracts (Dec 2007) 52.228-2 Additional Bond Security (Oct 1997) 52.228-5 Insurance-Work on a Government Installation (Jan 1997) 52.228-11 Individual Surety-Pledge of Assets (Feb 2021) 52.228-12 Prospective Subcontractor Requests for Bonds (Dec 2022) 52.228-14 Irrevocable Letter of Credit (Nov 2014) 52.228-15 Performance and Payment Bonds-Construction (Jun 2020) 52.229-3 Federal, State and Local Taxes (Feb 2013) 52.229-12 Tax on Certain Foreign Procurements (Feb 2021) 52.232-5 Payments under Fixed-Price Construction Contracts (May 2014) 52.232-17 Interest (May 2014) 52.232-23 Assignment of Claims (May 2014) 52.232-27 Prompt Payment for Construction Contracts (Jan 2017) 52.232-33 Payment by Electronic Funds Transfer-System for Award Management (Oct 2018) 52.232-39 Unenforceability of Unauthorized Obligations (Jun 2013) 52.232-40 Providing Accelerated Payments to Small Business Subcontractors (Mar 2023) 52.233-1 Alt I Disputes (May 2014) - Alternate I (Dec 1991) 52.233-3 Protest after Award (Aug 1996) 52.233-4 Applicable Law for Breach of Contract Claim (Oct 2004) 52.236-2 Differing Site Conditions (Apr 1984) 52.236-3 Site Investigation and Conditions Affecting the Work (Apr 1984) 52.236-5 Material and Workmanship (Apr 1984) 52.236-6 Superintendence by the Contractor (Apr 1984) 52.236-7 Permits and Responsibilities (Nov 1991) 52.236-8 Other Contracts (Apr 1984)
15BFA023B00000013 Page 5 of 55
52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements (Apr 1984) 52.236-10 Operations and Storage Areas (Apr 1984) 52.236-11 Use and Possession Prior to Completion (Apr 1984) 52.236-12 Cleaning Up (Apr 1984) 52.236-13 Alt I Accident Prevention (Nov 1991) - Alternate I (Nov 1991) 52.236-14 Availability and Use of Utility Services (Apr 1984) 52.236-26 Preconstruction Conference (Feb 1995) 52.242-13 Bankruptcy (July 1995) 52.243-4 Changes (June 2007) 52.244-6 Subcontracts for Commercial Products and Commercial Services (Mar 2023) 52.246-21 Warranty of Construction (Mar 1994) 52.248-3 Value Engineering-Construction (Oct 2020) 52.249-2 Alt I Termination for Convenience of the Government (Fixed-Price) (Apr 2012) - Alternate I (Sept 1996) 52.249-10 Default (Fixed-Price Construction) (Apr 1984) 52.204-2 Alt II Security Requirements (Mar 2021) - Alternate II (Apr 1984) 52.219-14 Limitations on Subcontracting (Oct 2022) 52.223-6 Drug-Free Workplace (May 2001) 52.236-17 Layout of Work (Apr 1984) 52.236-21 Alt II Specifications and Drawings for Construction (Feb 1997) - Alternate II (Apr 1984) 52.253-1 Computer Generated Forms (Jan 1991) 52.204-19 Incorporation by Reference of Representations and Certifications (Dec 2014) 52.211-12 Liquidated Damages-Construction (Sept 2000) 52.211-10 Commencement, Prosecution, and Completion of Work (Apr 1984) 2852.223-70 Unsafe Conditions Due to the Presence of Hazardous Material (NOV 2020) FAO-0015 Changes FAO-0016 Equitable Adjustments: Waiver and Release of Claims 52.204-21 Basic Safeguarding of Covered Contractor Information Systems (Nov 2021) 52.215-21 Alt IV Requirements for Certified Cost or Pricing Data and Data Other Than Certified Cost or Pricing Data-Modifications (Nov 2021) - Alternate IV (Oct 2010) 52.222-35 Equal Opportunity for Veterans (Jun 2020) 52.222-36 Equal Opportunity for Workers with Disabilities (Jun 2020) 52.225-9 Buy American-Construction Materials (Oct 2022) BOP 2852.201-71 Contracting Officer's Representative (COR) (June 2012) 52.24-403-70 Notice of Contractor Personnel Security Requirements (OCT 2005)
BOP 2852.242-71 EVALUATION OF CONTRACTOR PERFORMANCE UTILIZING CPARS (APR
2011) DOJ-01 Whistleblower Information Distribution (Oct 2021) DOJ-02 Contractor Privacy Requirements (JAN 2022) DOJ-03 Personnel Security Requirements For Contractor Employees (Nov 2021) DOJ-08 Continuing Contract Performance During a Pandemic Influenza or other National Emergency
(OCT 2007)
5 Attachments 6 Solicitation Provisions
52.204-20 Predecessor of Offeror (Aug 2020) 52.204-17 Ownership or Control of Offeror (Aug 2020) 52.214-5 Submission of Bids (Dec 2016) 52.214-6 Explanation to Prospective Bidders (Apr 1984) 52.214-7 Late Submissions, Modifications, and Withdrawals of Bids (Nov 1999) 52.214-19 Contract Award-Sealed Bidding-Construction (Aug 1996) 52.228-1 Bid Guarantee (Sept 1996) 52.228-17 Individual Surety-Pledge of Assets (Bid Guarantee) (Feb 2021) 52.214-18 Preparation of Bids-Construction (Apr 1984) 52.214-34 Submission of Offers in the English Language (Apr 1991) 52.214-35 Submission of Offers in U.S. Currency (Apr 1991) 52.204-7 System for Award Management (Oct 2018) 52.204-16 Commercial and Government Entity Code Reporting (Aug 2020) 52.204-22 Alternative Line Item Proposal (Jan 2017)
15BFA023B00000013 Page 6 of 55
52.214-3 Amendments to Invitations for Bids (Dec 2016) 52.214-4 False Statements in Bids (Apr 1984) 52.222-23 Notice of Requirement for Affirmative Action to Ensure Equal Employment Opportunity for Construction (Feb 1999) 52.225-10 Notice of Buy American Requirement-Construction Materials (May 2014) 52.236-27 Alt I Site Visit (Construction) (Feb 1995) - Alternate I (Feb 1995) 2852.233-70 Protests Filed Directly with the Department of Justice (NOV 2020) 52.216-1 Type of Contract (Apr 1984) 52.222-5 Construction Wage Rate Requirements - Secondary Site of the Work (May 2014) 52.233-2 Service of Protest (Sept 2006) 52.211-6 Brand Name or Equal (Aug 1999)
7 Representations and Certifications FAO-0022 List of References and Bank Information 52.204-8 Annual Representations and Certifications (Mar 2023) 52.204-24 Representation Regarding Certain Telecommunications and Video Surveillance Services or Equipment (Nov 2021) 52.209-7 Information Regarding Responsibility Matters (Oct 2018) 52.209-13 Violation of Arms Control Treaties or Agreements-Certification (Nov 2021) 52.229-11 Tax on Certain Foreign Procurements--Notice and Representation (Jun 2020)
15BFA023B00000013 Page 7 of 55
Section 2 - Commodity or Services Schedule
Firm Fixed Price
SCHEDULE OF SUPPLIES/SERVICES
CONTINUATION SHEET
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 The selected contractor shall provide all materials, labor, and equipment to complete the project "Install Fixed Emergency Generators” at FPC Bryan, TX in accordance with the attached Specifications and Drawings.
PSC: Z2FF
1 JB $________ $_________________
NOTE: The successful contractor shall be responsible for all applicable federal, state, and local taxes. No tax exemption certification will be issued by the Federal Bureau of Prisons. THE TOTAL PRICE SHALL BE WRITTEN ON LINE ITEM 17 OF THE
STANDARD FORM
15BFA023B00000013 Page 8 of 55
Section 3 - Special Contract Requirements
Clauses By Full Text
FAO-0001 Bonds
(a) Bid Guarantee. Each bidder shall submit with his bid a Bid Bond (Standard Form 24) with good and sufficient surety or sureties acceptable to the Government, or other security as provided in provision 52.228-1, in the form of twenty percent (20) of the bid price or not to exceed $3,000,000. The bid bond penalty may be expressed in terms of a percentage of the bid price or may be expressed in dollars and cents. A bid bond is not required for bids of $150,000 or less. (FAR 28.102-1)
(b) Performance and Payment Bonds. Within 10 days after award the contractor shall execute and submit to the Contracting Officer two bonds, each with good and sufficient surety or sureties acceptable to the Government, as follows; a Performance Bond (Standard Form 25) and a Payment Bond (Standard Form 25A). The penal sums of such bonds will be as follows: (Not required for contracts of $150,000 or less)
(1) Performance Bond: The penal sum of performance bonds at the time of contract award shall be 100 percent of the original contract price.
(2) Payment Bond: The penal amount of payment bonds at the time of contract award shall be 100 percent of the original contract price.
(c) For construction contracts greater than $35,000 but not greater than $150,000, the Contracting Officer shall select two or more of the following payment protections, giving particular consideration to inclusion of an irrevocable letter of credit as one of the selected alternatives (FAR 28.102-1(b)(1)):
(1) A Payment Bond;
(2) An irrevocable letter of credit (ILC);
(3) A tripartite escrow agreement;
(4) A Certificate of Deposit; or
(5) A deposit of the types of security listed in 28.204-1 and 28.204-2.
(d) Individual Sureties.
(1) Bidders may elect to furnish individual surety bonds. If individual surety bonds are furnished for bid guarantees, payment or performance bonds, the individual sureties must submit their bonds proof of ownership and value of the assets which they claim in their net worth at time of bid opening. The Government's preferred method of proof is to have a statement of net worth prepared by a Certified Public Accountant (CPA) in accordance with Generally Accepted Accounting Principles (GAAP). Statements from a CPA that contain disclaimers are not acceptable. The statement of net worth on the Standard Form 28, Affidavit of Individual Surety, is insufficient and will not be accepted without additional proof of value and ownership.
(2) Bidders are cautioned that individual sureties must provide complete and detailed information in Block 9 of Standard Form 28 concerning other contracts on which they have provided bonds. This information shall include contract number, contract location, amount, and type of bond and telephone number of the involved contracting office. Failure to provide the proof and information required may result in rejection of the bid or termination of the contract for failure to provide adequate bonds.
FAO-0002 Magnitude
The magnitude of this project is between $1,000,000.00 and $5,000,000.00.
FAO-0003 Required Insurance
15BFA023B00000013 Page 9 of 55
See FAR 52.228-5, Insurance - Work on a Government Installation.
The Contractor shall, at its own expense, provide and maintain during the entire performance period of this contract, at least the kinds and minimum amounts of insurance required in the
Schedule or elsewhere in the contract.
TYPE AMOUNT
(1) WORKERS COMPENSATION & EMPLOYER'S LIABILITY $100,000
The required Workmen's Compensation Insurance shall extend to cover employee's liability for accidental bodily injury or death and for occupational disease with a minimum liability of $100,000.
(2) COMPREHENSIVE GENERAL LIABILITY with a minimum limit of:
PER ACCIDENT OR
OCCURRENCE FOR BODILY INJURY $500,000
This insurance shall include contractor's protective and contractual liability.
(3) COMPREHENSIVE AUTOMOBILE LIABILITY with the following minimum limits:
PER PERSON $200,000
PER OCCURRENCE FOR BODILY INJURY $500,000
PER OCCURRENCE FOR PROPERTY DAMAGE $ 20,000
FAO-0004 Pre-Construction Conference
(a) Prior to the start of construction, Contracting Officers shall call a conference with the contractor, subcontractor(s), Warden, Controller/Business Administrator, Safety Manager, Facilities Administrator, Project Representative, A&E firm, Captain and other interested personnel to discuss the statutory labor standards, prevailing wage requirements, submission of the contractor's payrolls, subcontractor's responsibilities, institution work schedules, local policies, contraband, parking, storage of vehicles and equipment, etc.
15BFA023B00000013 Page 10 of 55
Minutes of the conference shall be recorded, listing the names and titles of all attendees, and the subject matter of all items covered.
The minutes shall be signed by the contractor and the Contracting Officer, and a signed copy placed in the contract file.
(b) The Contractor shall familiarize himself/herself with all procedures involved in normal institution routines. Any requirements which may constitute a problem or result in conflict, will be brought to the attention of the Contracting Officer or his representative for determination.
FAO-0005 Submittals
Within 10 calendar days after commencement of work or as otherwise established by the Contracting Officer, all materials and articles requiring approval, as contemplated by the Materials and Workmanship clause, shall be submitted by the contractor.
The submittal process is in place to allow the Government the opportunity to determine whether materials or procedures used by the contractor are in accordance with contract requirements. It is ultimately the Contractor's responsibility via the quality control process to ensure submittal items installed under the contract and work performed on site are in accordance with industry standards and general practices.
(a) The types of submittal requirements specified in this contract may include, but is not limited to; shop drawings, product data, samples, certificates of conformance or compliance, certified test or inspection reports, equipment, materials, and miscellaneous work related submittals for construction. Individual submittal requirements are generally specified in applicable sections for each unit of work in the specifications and/or as a whole in one section in the statement of work.
(b) The Bureau of Prisons (BOP) Contracting Officer’s Representative (COR) shall act for the Contracting Officer in the review and acceptance of all submittals. The Contractor shall submit submittals as required by the contract/specifications to the COR for transmittal to the Contracting Officer. Fabrication of any work or purchase or use of any submittals (such as materials for which samples are required or equipment, etc.) shall not take place until written acceptance is given by the COR, except at the Contractor's own risk.
(c) The Contractor shall submit all shop drawings and submittals sufficiently in advance (unless otherwise specified in the specifications) of the construction requirements to allow ample time for checking, re-submitting, and re-checking.
(d) Failure of any materials to pass their specified tests shall be sufficient cause for refusal to consider, under this contract, any further samples of the same brand or make of that material. The Government reserves the right to disapprove any material or equipment which has previously proven unsatisfactory in service.
(e) The Contracting Officer’s or designee’s approval or acceptance of submittals is not to be construed as a complete check.
Approval or acceptance will not relieve the Contractor of the responsibility for any error which may exist, as the Contractor is responsible for the satisfactory construction of all work. The Contractor is responsible for delivering a final product/system that is operational as intended by the contract requirements, regardless of any Government approvals or acceptance of submittals. The Government assumes no liability during the submittal approval/acceptance process. It is the sole responsibility of the Contractor to deliver a properly functioning product or system.
FAO-0006 Contractor Use of Premises
Work Hours The project schedule is based on a normal forty (40) hour work week, eight (8) hours per day, Monday through Friday, excluding Federal holidays. The Contracting Officer’s Representative (COR) shall establish the work hour time frames for the duration of the project, subject to the approval of the Contracting Officer. Work hours and work days may be altered only with a 48 hour advance approval of the Contracting Officer.
NOTE: Access to the site will be available during normal working hours except during emergencies. It shall be the responsibility of the Contractor to familiarize himself, his employees, and his subcontractors of the working hours and conditions in the correctional facility, as working hours may not constitute a full eight hour day. The Government assumes no responsibility to the Contractor, nor to any of his subcontractors, for shorter hours due to institutional emergencies or entry and/or exit of workers necessitated by normal institution routines. The procedures and institutional entrance/exit routines applicable to this project will be explained at both the pre-bid conference/site visit and the pre-construction meeting.
Contraband
15BFA023B00000013 Page 11 of 55
The Contractor shall inform his employees that intoxicating beverages, drugs, weapons, etc., will not be allowed on the site.
Introduction of contraband shall be subject to the penalties prescribed by Title 18 USC-1791.
Explosives The use of explosives is absolutely forbidden without written authorization from the Contracting Officer.
Parking and Temporary Office Parking will be available at the site to the extent it does not interfere with construction activities. Otherwise, parking shall be provided for by the Contractor, at his expense, off the site for workmen employed on the project. Any temporary field office used by the Contractor shall be located in an area approved by the COR.
Safety and Accident Prevention In performing work under this contract the contractor shall:
(a) Conform to the specific safety requirements established by this contract;
(b) Comply with the safety rules of the Government institution that concern related activities not directly addressed in this contract;
(c) Take all reasonable steps and precautions to prevent accidents and preserve the life and health of contractor and Government personnel performing or in any way coming in contact with the performance of this contract; and
(d) Take such additional immediate precautions as the Contracting Officer and/or COR may reasonably require for safety and accident prevention purposes.
FAO-0007 Payment Services
(a) Original application for payment shall be prepared on AIA (American Institute of Architects) Form G-702 "Application and Certificate for Payment" and submitted to the Contracting Officer. The contractor may use another form; however, it shall contain similar information as the AIA Form G-702. The Contracting Officer’s Representative (COR) will approve the amount of payment by signing. The approved application for payment shall be forwarded as follows: Original to Accounting; Copy for Contract Award File.
(b) All small business contractors are required to self-certify on all invoices their small business status.
(c) The following information is required with each application for payment:
• Name and address of contractor
• Contract number
• Contractor invoice/application for payment number
• Description, price, and quantity of construction completed/rendered
• Payment terms (reference the contract payment clause)
• Other substantiating documentation or information required by the contract
• Name, title, and phone number of official to be notified in the event of a defective invoice
• Contractor TIN (Tax ID Number)
FAO-0008 Request for Final Inspection
The Contractor shall give the Contracting Officer’s Representative (COR) a minimum of ten (10) working days advanced written notice of the date on which the work will be fully completed and ready for the Government’s final inspection.
FAO-0009(a) Construction Contract Security
FAO-0009(a) Construction Contract Security (Program Statement 3732.01 BOP Identifications and Background Investigation)
In addition to the information contained in clause “DOJ-03 Personnel Security Requirements For Contractor Employees (Nov 2021);
(Alt. I) -- Classified Information – Cleared Contractors”, the following additional security is required to be completed and submitted for all contract employees who will be working under the terms of the contract:
Criminal History Check – BP-A0660 (May 2018)
15BFA023B00000013 Page 12 of 55
CJIS Name Check Request Form BOP Contractor Pre-employment Questionnaire BOP Authority for Release of Information The contactor should be aware that the time required for contractor security clearances to be completed may vary. For the purposes of this solicitation, ____ calendar days [contracting officer to insert the number of days based on performance period memo] have been included in the performance period specified in FAR clause 52.211-10. The number of days listed above is contingent upon the contractor providing completed clearance packages for their employees within 10 calendar days of the Notice to Proceed. For any subsequently awarded subcontract, completed security clearance packages for subcontractor workers shall be submitted in conjunction with the completed SF-1413.
**A form package will be issued by the Administrative Contracting Officer or Contracting Officer's Representative (COR) at the institution upon contract award. Completed packages shall be submitted by the PRIME CONTRACTOR ONLY to obtain clearance for each prime and sub-contract employee. Security Clearance packages will NOT be accepted from sub-contractors. Upon clearance being obtained the contractor will be notified. Should a contract employee NOT be cleared to enter the facility for this project, the contractor will be notified immediately. The contractor will be responsible to submit another contract employee as soon as possible for clearance. Be advised, the Federal Bureau of Prisons cannot disclose why an individual does not pass the security clearance process, as it is a violation of law.**
FAO-0010 Assignment of Contract Administration Office and Functions
Pursuant to FAR 42.201 and 42.202, the assigned Contract Administration Office is listed in Block 26 of the Standard Form 1442 Back. This assignment carries with it the authority to perform all of the contract administration functions listed in FAR 42.302(a) and 42.302(b) to the extent that those functions apply to the contract.
FAO-0011 Schedule of Values
The Contractor shall prepare a Schedule of Values (SOV) for the project and submit to the Contracting Officer for approval prior to submitting the first application for payment. The SOV shall be correlated with the construction schedule. The SOV shall be formatted per the Construction Specification Institute Master Format structure. The Contractor may propose an alternate organizational format to the Contracting Officer for approval.
(a) The SOV shall include:
(1) Project name, location, and contract number;
(2) Contractor’s name and address;
(3) Date of submittal.
(b) The SOV shall be arranged in a tabular form with separate columns to indicate the following for each item listed:
(1) Description of Work or Material;
(2) Related specification section, if applicable;
(3) Name of subcontractor, if applicable;
(4) Name of manufacturer or fabricator, if applicable;
(5) Name of supplier, if applicable;
(6) Change orders (modifications) that have affected value, if applicable;
(7) Dollar value;
(8) Percentage of Contract sum rounded to the nearest percent, adjusted to total 100 percent.
(c) The SOV shall breakdown the contract sum in sufficient detail to facilitate continued evaluation of applications for payment and progress reports. The contractor should separate principal subcontract amounts down into several line items.
(d) SOV amounts shall be rounded to the nearest whole dollar. The total of all SOV amounts shall equal the total contract amount.
15BFA023B00000013 Page 13 of 55
(e) The contractor shall progress the percentage of completion, with the concurrence of the Contracting Officer’s Representative, for each value in conjunction with the preparation of each monthly application for payment. The progressed value percentages shall directly correlate to the calculated total amount due for each monthly progress payment.
(f) The SOV shall remain fixed for the duration of contract performance. Any revisions to the SOV must be requested in writing, with justification, for approval by the Contracting Officer.
FAO-0012 Progress Meetings
The Administrative Contracting Officer (ACO) shall conduct progress meetings at the project site on a monthly basis, or at intervals as determined by the ACO.
(a) At a minimum, the attendees shall include but is not limited to:
(1) FBOP: Administrative Contracting Officer, Contracting Officer’s Representative (COR), Facility Administrator/ Manager, Architect/Engineer (if applicable), Other Personnel (Executive Staff, Captain, Safety Manager, etc.).
(2) Contractor: Project Manager, Superintendent, and technical support disciplines as appropriate (Subcontractors, Manufacturers, Suppliers, etc.).
(b) The meeting should include, but is not limited to issues such as:
Administrative Contracting Officer:
(1) Old business from previous progress meeting(s);
(2) Status of modifications, certified payrolls, submittals, requests for information (RFI);
(3) Review of payments made to date and review/approve current payment request;
(4) Status of modification proposal requests;
(5) Discuss new business.
COR:
(1) Status of escort coverage;
(2) Review gate or sallyport entrance/exit issues;
(3) Discuss other delays contractor may be experiencing;
(4) Discuss performance/quality issues.
Contractor:
(1) Review/discuss updated progress schedule;
(2) Provide 30 day outlook;
(3) Discuss other issues affecting performance.
FAO-0013 Contract Closeout Procedures (for construction contracts exceeding $150,000)
Contract Closeout must be completed within six (6) months of physical completion of the work.
Prior to payment of final invoice:
The contractor shall submit the following documents:
15BFA023B00000013 Page 14 of 55
(1) Contractor’s Affidavit of Release of Liens (AIA Document G706A);
(2) Contractor’s Affidavit of Payment of Debts and Claims (AIA Document G706);
(3) All as-built drawings/shop drawings, if applicable;
(4) Contractor’s final invoice;
(5) Release of Claims (GSA Form 1142);
(6) Consent of Surety to Final Payment (AIA Document G707);
(7) Letter establishing warranty dates;
(8) Complete list of subcontractors with telephone numbers and points of contact;
(9) Guarantees and warranties;
(10) All balance and test reports;
(11) All operation/maintenance manuals;
(12) All permits and certifications.
AIA forms can be obtained from The American Institute of Architects at www.aiabookstore.com.
GSA forms can be obtained from the General Services Administration at www.gsa.gov (click on the “Forms Library” link).
15BFA023B00000013 Page 15 of 55
Section 4 - Contract Clauses
Clauses By Reference
52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): www.acquisition.gov
Clause Title Fill-ins (if applicable)
52.246-12 Inspection of Construction (Aug 1996)
52.236-15 Schedules for Construction Contracts (Apr 1984)
52.242-14 Suspension of Work (Apr 1984)
52.204-23 Prohibition on Contracting for Hardware, Software, and Services
Developed or Provided by Kaspersky Lab and Other Covered Entities
(Nov 2021)
52.204-25 Prohibition on Contracting for Certain Telecommunications and Video
Surveillance Services or Equipment (Nov 2021)
52.202-1 Definitions (Jun 2020)
52.203-3 Gratuities (Apr 1984)
52.203-5 Covenant Against Contingent Fees (May 2014)
52.203-6 Restrictions on Subcontractor Sales to the Government (Jun 2020)
52.203-7 Anti-Kickback Procedures (Jun 2020)
52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or
Improper Activity (May 2014)
52.203-10 Price or Fee Adjustment for Illegal or Improper Activity (May 2014)
52.203-12 Limitation On Payments to Influence Certain Federal Transactions
(Jun 2020)
52.203-17 Contractor Employee Whistleblower Rights and Requirement To
Inform Employees of Whistleblower Rights (Jun 2020)
52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or
Statements (Jan 2017)
15BFA023B00000013 Page 16 of 55
Clause Title Fill-ins (if applicable)
52.204-4 Printed or Copied Double-Sided on Postconsumer Fiber Content
Paper (May 2011)
52.204-9 Personal Identity Verification of Contractor Personnel (Jan 2011)
52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards
(Jun 2020)
52.204-13 System for Award Management Maintenance (Oct 2018)
52.204-14 Service Contract Reporting Requirements (Oct 2016)
52.204-18 Commercial and Government Entity Code Maintenance (Aug 2020)
52.204-27 Prohibition on a ByteDance Covered Application (Jun 2023)
52.209-6 Protecting the Government's Interest When Subcontracting with
Contractors Debarred, Suspended, or Proposed for Debarment (Nov
2021)
52.209-9 Updates of Publicly Available Information Regarding Responsibility
Matters (Oct 2018)
52.209-10 Prohibition on Contracting with Inverted Domestic Corporations (Nov
2015)
52.219-6 Notice of Total Small Business Set-Aside (Nov 2020)
52.219-8 Utilization of Small Business Concerns (Oct 2022)
52.219-28 Post-Award Small Business Program Rerepresentation (Mar 2023) (h)(1) NAICS Code: "238210"
52.222-1 Notice to the Government of Labor Disputes (Feb 1997)
52.222-3 Convict Labor (June 2003)
52.222-4 Contract Work Hours and Safety Standards--Overtime Compensation
(May 2018)
52.222-12 Contract Termination - Debarment (May 2014)
52.222-7 Withholding of Funds (May 2014)
52.222-14 Disputes Concerning Labor Standards (Feb 1988)
52.222-13 Compliance with Construction Wage Rate Requirements and Related
Regulations (May 2014)
52.222-8 Payrolls and Basic Records (Jul 2021)
52.222-9 Apprentices and Trainees (July 2005)
15BFA023B00000013 Page 17 of 55
52.222-6 Construction Wage Rate Requirements (Aug 2018)
52.222-11 Subcontracts (Labor Standards) (May 2014)
52.222-15 Certification of Eligibility (May 2014)
52.222-10 Compliance with Copeland Act Requirements (Feb 1988)
52.222-21 Prohibition of Segregated Facilities (Apr 2015)
52.222-26 Equal Opportunity (Sept 2016)
52.222-27 Affirmative Action Compliance Requirements for Construction (Apr
2015)
52.222-37 Employment Reports on Veterans (Jun 2020)
52.222-40 Notification of Employee Rights Under the National Labor Relations
Act (Dec 2010)
52.222-50 Combating Trafficking in Persons (Nov 2021)
52.222-54 Employment Eligibility Verification (May 2022)
52.222-55 Minimum Wages for Contractor Workers Under Executive Order 14026
(Jan 2022)
52.222-62 Paid Sick Leave Under Executive Order 13706 (Jan 2022)
52.223-2 Affirmative Procurement of Biobased Products Under Service and
Construction Contracts (Sep 2013)
52.223-3 Alt I Hazardous Material Identification and Material Safety Data (Feb 2021)
- Alternate I (July 1995)
52.223-5 Pollution Prevention and Right-to-Know Information (May 2011)
52.223-11 Ozone-Depleting Substances and High Global Warming Potential
Hydrofluorocarbons (Jun 2016)
52.223-17 Affirmative Procurement of EPA-designated Items in Service and
Construction Contracts (Aug 2018)
52.223-18 Encouraging Contractor Policies to Ban Text Messaging While Driving
(Jun 2020)
52.223-21 Foams (Jun 2016)
52.223-20 Aerosols (Jun 2016)
52.225-13 Restrictions on Certain Foreign Purchases (Feb 2021)
15BFA023B00000013 Page 18 of 55
52.227-1 Authorization and Consent (Jun 2020)
52.227-2 Notice and Assistance Regarding Patent and Copyright Infringement
(Jun 2020)
52.227-4 Patent Indemnity-Construction Contracts (Dec 2007)
52.228-2 Additional Bond Security (Oct 1997)
52.228-5 Insurance-Work on a Government Installation (Jan 1997)
52.228-11 Individual Surety-Pledge of Assets (Feb 2021)
52.228-12 Prospective Subcontractor Requests for Bonds (Dec 2022)
52.228-14 Irrevocable Letter of Credit (Nov 2014)
52.228-15 Performance and Payment Bonds-Construction (Jun 2020)
52.229-3 Federal, State and Local Taxes (Feb 2013)
52.229-12 Tax on Certain Foreign Procurements (Feb 2021)
52.232-5 Payments under Fixed-Price Construction Contracts (May 2014)
52.232-17 Interest (May 2014)
52.232-23 Assignment of Claims (May 2014)
52.232-27 Prompt Payment for Construction Contracts (Jan 2017)
52.232-33 Payment by Electronic Funds Transfer-System for Award Management
(Oct 2018)
52.232-39 Unenforceability of Unauthorized Obligations (Jun 2013)
52.232-40 Providing Accelerated Payments to Small Business Subcontractors
(Mar 2023)
52.233-1 Alt I Disputes (May 2014) - Alternate I (Dec 1991)
52.233-3 Protest after Award (Aug 1996)
52.233-4 Applicable Law for Breach of Contract Claim (Oct 2004)
52.236-2 Differing Site Conditions (Apr 1984)
52.236-3 Site Investigation and Conditions Affecting the Work (Apr 1984)
52.236-5 Material and Workmanship (Apr 1984)
52.236-6 Superintendence by the Contractor (Apr 1984)
52.236-7 Permits and Responsibilities (Nov 1991)
52.236-8 Other Contracts (Apr 1984)
15BFA023B00000013 Page 19 of 55
52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and
Improvements (Apr 1984)
52.236-10 Operations and Storage Areas (Apr 1984)
52.236-11 Use and Possession Prior to Completion (Apr 1984)
52.236-12 Cleaning Up (Apr 1984)
52.236-13 Alt I Accident Prevention (Nov 1991) - Alternate I (Nov 1991)
52.236-14 Availability and Use of Utility Services (Apr 1984)
52.236-26 Preconstruction Conference (Feb 1995)
52.242-13 Bankruptcy (July 1995)
52.243-4 Changes (June 2007)
52.244-6 Subcontracts for Commercial Products and Commercial Services (Mar
2023)
52.246-21 Warranty of Construction (Mar 1994)
52.248-3 Value Engineering-Construction (Oct 2020)
52.249-2 Alt I Termination for Convenience of the Government (Fixed-Price) (Apr
2012) - Alternate I (Sept 1996)
52.249-10 Default (Fixed-Price Construction) (Apr 1984)
52.204-2 Alt II Security Requirements (Mar 2021) - Alternate II (Apr 1984)
52.219-14 Limitations on Subcontracting (Oct 2022)
52.223-6 Drug-Free Workplace (May 2001)
52.236-17 Layout of Work (Apr 1984)
52.236-21 Alt II Specifications and Drawings for Construction (Feb 1997) - Alternate II
(Apr 1984)
(g) desired amount: "two"
52.253-1 Computer Generated Forms (Jan 1991)
52.204-19 Incorporation by Reference of Representations and Certifications (Dec
2014)
Clauses By Full Text
52.211-12 Liquidated Damages-Construction (Sept 2000)
15BFA023B00000013 Page 20 of 55
(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of $904.46 [Contracting Officer insert amount] for each calendar day of delay until the work is completed or accepted.
(b) If the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.
(End of clause)
52.211-10 Commencement, Prosecution, and Completion of Work (Apr 1984)
The Contractor shall be required to (a) commence work under this contract within 10 [Contracting Officer insert number] calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 364 calendar days.* The time stated for completion shall include final cleanup of the premises.
* The Contracting Officer shall specify either a number of days after the date the contractor receives the notice to proceed, or a calendar date.
(End of clause)
2852.223-70 Unsafe Conditions Due to the Presence of Hazardous Material (NOV 2020)
(a) “Unsafe condition” as used in this clause means the actual or potential exposure of Contractor or Government employees to a hazardous material.
(b) “Hazardous Material” as used in this clause includes any material defined as hazardous under the latest version of Federal Standard No. 313 (including revisions adopted during the term of the contract), any other potentially hazardous material requiring safety controls, or any other material or working condition designated as hazardous by the Contracting Officer's Representative (COR).
(c) The Occupational Safety and Health Administration (OSHA) is responsible for issuing and administering regulations that require Contractors to apprise its employees of all hazards to which they may be exposed in the course of their employment; proper conditions and precautions for safe use and exposure; and related symptoms and emergency treatment in the event of exposure.
(d) Prior to commencement of work, Contractors are required to inspect for and report to the Contracting Officer the presence of, or suspected presence of, any unsafe condition including asbestos or other hazardous materials or working conditions in areas in which they will be working.
(e) If during the performance of the work under this contract, the Contractor or any of its employees, or subcontractor employees, discovers the existence of an unsafe condition, the Contractor shall immediately notify the Contracting Officer, or designee (with written notice provided not later than three (3) working days thereafter), of the existence of an unsafe condition. Such notice shall include the Contractor's recommendations for the protection and the safety of Government, Contractor and subcontractor personnel and property that may be exposed to the unsafe condition.
(f) When the Government receives notice of an unsafe condition from the Contractor, the parties will agree on a course of action to mitigate the effects of that condition and, if necessary, the contract will be amended. Failure to agree on a course of action will constitute a dispute under the Disputes clause of this contract.
(g) Nothing contained in this clause shall relieve the Contractor or subcontractors from complying with applicable Federal, State, and local laws, codes, ordinances and regulations (including the obtaining of licenses and permits) in connection with hazardous material including but not limited to the use, disturbance, or disposal of such material.
(End of Clause)
FAO-0015 Changes
(a) Unilateral changes (Change Orders) will be in accordance with the Changes clause 52.243-4 or Changes and Changed Conditions clause 52.243-5 whichever applies to this contract. Additionally, the parties may enter into bi-lateral supplemental agreements based on mutual agreement between the parties.
(b) In the case of either a unilateral change order or bi-lateral supplemental agreement, the Contractor shall submit to the Contracting Officer, through the Contracting Officer’s Representative (COR), a written proposal for adjustment of the amount of increase or decrease. With the proposal, the Contractor shall submit an itemized breakdown in at least the following detail:
(1) Material quantities and unit cost
(2) Labor costs by material item
(3) Construction equipment cost
15BFA023B00000013 Page 21 of 55
(4) Workmen's compensation and public liability insurance
(5) Overhead
(6) Profit or commission
(7) Employment taxes (FICA and FUTA)
(8) Performance and payment bonds increase
(c) For either unilateral change orders or bi-lateral supplemental agreements, the maximum allowable overhead, profit and commission percentages are contained below. The percentages for overhead, profit and commission shall be negotiated and may vary according to the nature, extent and complexity of the work involved, but in no case shall exceed the following:
(1) To the Contractor (Prime), on work performed by other than his own forces. The commission is 10% in the first $20,000, 7 1/2% on the next $30,000, 5% on the balance over $50,000.
(2) To the Contractor, and/or the Subcontractors for that portion of the work performed with their respective forces. The percentage is 10% overhead and 10% profit on the first $20,000, 7 1/2% overhead and 7 1/2% profit on the next $30,000, and 5% overhead and 5% profit on the balance over $50,000.
Not more than three (3) percentages, not to exceed the maximum percentage amounts shown above, will be allowed regardless of the number of…