This is a request for proposal issued by the Bureau of Reclamation seeking proposals for Upper Rio Grande and Pecos Basin hydrologic model calibration and configuration services. Key details include:

  • The services include compiling necessary data, recalibrating 20 hydrologic model locations in Phase 1, and providing potential additional calibration in Phases 2 through 4. Models include SAC-SMA, SNOW-17, and LAG/K.

  • Proposals are due by March 26, 2021. The period of performance is one base year with three option years to complete subsequent phases.

  • Deliverables consist of compiled calibration data, the calibrated hydrologic model, monthly meeting notes, quarterly reports, and draft and final project reports.

  • The RFP outlines technical evaluation criteria and indicates the technical approach is more important than price in award determination. The final award will be a firm-fixed price contract.

View the file

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

United States Department of the Interior

BUREAU OF RECLAMATION

Upper Colorado Region Albuquerque Area Office

555 Broadway Blvd NE, Suite 100 Albuquerque, NM 87102

Solicitation: 140R4020R0017

Request for Proposal: UCROP ESP Forecasts

This is request for proposal using FAR 12 Acquisition of Commercial Items in conjunction with FAR 13 Simplified Acquisition Procedures. The NAICS Code is 541990 All Other Professional, Scientific and Technical Services.

Proposals Due No-Later-Than: 4:00 pm Mountain Time on Friday, March 26, SOLICITATION # 140R4020R0017

UCROP ESP Forecasts

Table of Contents

SECTIONS A and B - SF 1449 / SCHEDULE OF SERVICES AND PRICES 1- 3

SECTION C – CLAUSES 4 - 15

SECTION D – PERFORMANCE WORK STATEMENT 16 -30

SUB-BASINS LISTING – APPENDIX A-1 ATTACHMENT 1

SECTION E - PROVISIONS 31 - 52

INSTRUCTIONS TO OFFERORS 31 - 32

EVALUATION 33

BASIS OF AWARD 33

ATTACHMENT 1 – APPENDIX A-1 – SUB-BASINS

ATTACHMENT 2- COST PROPOSAL WORKSHEET

ATTACHMENT 3-WAGE DETERMINATION: 2015-5443 Revision 11

SEE ADDENDUMIS CHECKED

CODE 18a. PAYMENT WILL BE MADE BY

CODE

FACILITYCODE

17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT SUCH ADDRESS IN OFFER

OFFEROR

R4Q

555 Broadway Blvd NE, Suite 100 Albuquerque Area Office Upper Colorado Region Bureau of Reclamation

0009909999 CODE 16. ADMINISTERED BYCODE

X

X

541990

SIZE STANDARD:

% FOR:SET ASIDE:UNRESTRICTED ORR43

RFPIFB

10. THIS ACQUISITION ISCODE

RFQ

14. METHOD OF SOLICITATION

13b. RATING

NAICS:

SMALL BUSINESS

03/26/2021 1600 MS

03/05/2021

505-462-3581Mary Maestas (No collect calls)

INFORMATION CALL:

FOR SOLICITATION 8. OFFER DUE DATE/LOCAL TIMEb. TELEPHONE NUMBER a. NAME

4. ORDER NUMBER3. AWARD/ 6. SOLICITATION

140R4020R0017

5. SOLICITATION NUMBER

SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS 1. REQUISITION NUMBER PAGE OF

1 70 0040498227OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, & 30

Albuquerque NM 87102

TELEPHONE NO.

17a. CONTRACTOR/

Albuquerque NM 87102-2352 555 Broadway NE Suite 100 Albuquerque Area Office Bureau of Reclamation-UC-AAO

15. DELIVER TO

87102 See Administered By Office Upper Colorado Region

9. ISSUED BY

7.

2. CONTRACT NO.

EFFECTIVE DATE

$16.50

18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a UNLESS BLOCK BELOW

ISSUE DATE

DELIVERY FOR FOB DESTINA-

TION UNLESS BLOCK IS

MARKED

11.

SEE SCHEDULEX

12. DISCOUNT TERMS

THIS CONTRACT IS A

RATED ORDER UNDER

DPAS (15 CFR 700)

13a.

SERVICE-DISABLED

VETERAN-OWNED

SMALL BUSINESS

HUBZONE SMALL

BUSINESS

8(A)

Bureau of Reclamation

WOMEN-OWNED SMALL BUSINESS

(WOSB) ELIGIBLE UNDER THE WOMEN-OWNED

SMALL BUSINESS PROGRAM

EDWOSB

24.

AMOUNT

23.

UNIT PRICE

22.

UNIT

21.

QUANTITY

20.

SCHEDULE OF SUPPLIES/SERVICES

19.

ITEM NO.

Request for Proposal for UCROP ESP Forecasts - Upper Rio Grande and Pecos Basin Hydrologic Model Calibration and Model Configuration Services.

Legacy Doc #: BOR Period of Performance: 04/26/2021 to 04/25/2025

00001 Hydrologic Model Calibrations - Base Year Product/Service Code: B529 Product/Service Description: SPECIAL Continued ...

(Use Reverse and/or Attach Additional Sheets as Necessary)

HEREIN, IS ACCEPTED AS TO ITEMS:

XX

DATED

Mary B. Maestas

. YOUR OFFER ON SOLICITATION (BLOCK 5),

INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE SET FORTH

COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND DELIVER

ARE

ARE

31c. DATE SIGNED

27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA

31a. UNITED STATES OF AMERICA (SIGNATURE OF CONTRACTING OFFICER)

30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER (Type or print)

ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY ADDITIONAL

SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED.

27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1, 52.212-4. FAR 52.212-3 AND 52.212-5 ARE ATTACHED. ADDENDA

26. TOTAL AWARD AMOUNT (For Govt. Use Only)

OFFER

STANDARD FORM 1449 (REV. 2/2012)

Prescribed by GSA - FAR (48 CFR) 53.212

ARE NOT ATTACHED.

ARE NOT ATTACHED.

AUTHORIZED FOR LOCAL REPRODUCTION

PREVIOUS EDITION IS NOT USABLE

30b. NAME AND TITLE OF SIGNER (Type or print)

30a. SIGNATURE OF OFFEROR/CONTRACTOR

28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN

25. ACCOUNTING AND APPROPRIATION DATA

29. AWARD OF CONTRACT:

REF.

32e. MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE

32c. DATE 32b. SIGNATURE OF AUTHORIZED GOVERNMENT REPRESENTATIVE

ACCEPTED, AND CONFORMS TO THE CONTRACT, EXCEPT AS NOTED:

32a. QUANTITY IN COLUMN 21 HAS BEEN

RECEIVED INSPECTED

40. PAID BY39. S/R VOUCHER NUMBER38. S/R ACCOUNT NUMBER

37. CHECK NUMBER

FINALPARTIAL

36. PAYMENT

FINALPARTIAL

35. AMOUNT VERIFIED

CORRECT FOR

34. VOUCHER NUMBER33. SHIP NUMBER

COMPLETE

32g. E-MAIL OF AUTHORIZED GOVERNMENT REPRESENTATIVE

42d. TOTAL CONTAINERS42c. DATE REC'D (YY/MM/DD)

42b. RECEIVED AT (Location)

42a. RECEIVED BY (Print)

41c. DATE41b. SIGNATURE AND TITLE OF CERTIFYING OFFICER

41a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAYMENT

STANDARD FORM 1449 (REV. 2/2012) BACK

24.

AMOUNT

23.

UNIT PRICE

22.

UNIT

21.

QUANTITY

20.

SCHEDULE OF SUPPLIES/SERVICES

19.

ITEM NO.

STUDIES/ANALYSIS- SCIENTIFIC DATA

Period of Performance: 04/26/2021 to 04/25/2022

00002 Hydrologic Model Calibrations - Option Year One

Product/Service Code: B529

Product/Service Description: SPECIAL

STUDIES/ANALYSIS- SCIENTIFIC DATA

Period of Performance: 04/26/2022 to 04/25/2023

00003 Hydrologic Model Calibrations - Option Year Two

Product/Service Code: B529

Product/Service Description: SPECIAL

STUDIES/ANALYSIS- SCIENTIFIC DATA

Period of Performance: 04/26/2023 to 04/25/2024

00004 Hydrologic Model Calibrations - Option Year Three

Product/Service Code: B529

Product/Service Description: SPECIAL

STUDIES/ANALYSIS- SCIENTIFIC DATA

Period of Performance: 04/26/2024 to 04/25/2025

00005 Six-Month Extension of Services Option per

52.217-8. May be exercised at the discretion of the Government. If exercised in final option

Continued ...

32f. TELEPHONE NUMBER OF AUTHORIZED GOVERNMENT REPRESENTATIVE

32d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT REPRESENTATIVE

70 2 of

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

NAME OF OFFEROR OR CONTRACTOR

3 70

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

(A) (B) (C) (D) (E) (F)

140R4020R0017 period, a six-month extension under FAR 52.217-8 shall be in proportion to the length of time and pricing of the final option period (12 months=1/2 the period price)

Product/Service Code: B529

Product/Service Description: SPECIAL

STUDIES/ANALYSIS- SCIENTIFIC DATA

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

C. Clauses

52.212-4 -- Contract Terms and Conditions -- Commercial Items. (Oct 2018)

52.212-5 Contract Terms and Conditions Required to Implement Statutes or Executive Orders- Commercial Items (Jan 2021)

(a) The Contractor shall comply with the following Federal Acquisition Regulation (FAR) clauses, which are incorporated in this contract by reference, to implement provisions of law or Executive orders applicable to acquisitions of commercial items:

(1) 52.203-19, Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements (Jan 2017) (section 743 of Division E, Title VII, of the Consolidated and Further Continuing Appropriations Act, 2015 (Pub. L. 113-235) and its successor provisions in subsequent appropriations acts (and as extended in continuing resolutions)).

(2) 52.204-23, Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by Kaspersky Lab and Other Covered Entities (Jul 2018) (Section 1634 of Pub. L. 115-91).

(3) 52.204-25, Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment. (Aug 2020) (Section 889(a)(1)(A) of Pub. L. 115-232).

(4) 52.209-10, Prohibition on Contracting with Inverted Domestic Corporations (Nov 2015).

(5) 52.233-3, Protest After Award (Aug 1996) (31 U.S.C. 3553).

(6) 52.233-4, Applicable Law for Breach of Contract Claim (Oct 2004) (Public Laws 108-77 and 108- 78 ( 19 U.S.C. 3805 note)).

(b) The Contractor shall comply with the FAR clauses in this paragraph (b) that the Contracting Officer has indicated as being incorporated in this contract by reference to implement provisions of law or Executive orders applicable to acquisitions of commercial items:

[Contracting Officer check as appropriate.]

__ (1) 52.203-6, Restrictions on Subcontractor Sales to the Government (June 2020), with Alternate I (Oct 1995) (41 U.S.C. 4704 and 10 U.S.C. 2402).

__ (2) 52.203-13, Contractor Code of Business Ethics and Conduct (Jun 2020) (41 U.S.C. 3509)).

__ (3) 52.203-15, Whistleblower Protections under the American Recovery and Reinvestment Act of 2009 (Jun 2010) (Section 1553 of Pub. L. 111-5). (Applies to contracts funded by the American Recovery and Reinvestment Act of 2009.)

_X_ (4) 52.204-10, Reporting Executive Compensation and First-Tier Subcontract Awards (Jun 2020) (Pub. L. 109-282) ( 31 U.S.C. 6101 note).

__ (5) [Reserved].

_X_ (6) 52.204-14, Service Contract Reporting Requirements (Oct 2016) (Pub. L. 111-117, section 743 of Div. C).

__ (7) 52.204-15, Service Contract Reporting Requirements for Indefinite-Delivery Contracts (Oct 2016) (Pub. L. 111-117, section 743 of Div. C).

_X_ (8) 52.209-6, Protecting the Government’s Interest When Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment. (Jun 2020) (31 U.S.C. 6101 note).

_X_ (9) 52.209-9, Updates of Publicly Available Information Regarding Responsibility Matters (Oct 2018) (41 U.S.C. 2313).

__ (10) [Reserved].

__ (11) (i) 52.219-3, Notice of HUBZone Set-Aside or Sole-Source Award (Mar 2020) (15 U.S.C.

657a).

__ (ii) Alternate I (Mar 2020) of 52.219-3.

_X_ (12) (i) 52.219-4, Notice of Price Evaluation Preference for HUBZone Small Business Concerns (Mar 2020) (if the offeror elects to waive the preference, it shall so indicate in its offer) (15 U.S.C. 657a).

__ (ii) Alternate I (Mar 2020) of 52.219-4.

__ (13) [Reserved]

__ (14) (i) 52.219-6, Notice of Total Small Business Set-Aside (Nov 2020) (15 U.S.C. 644).

__ (ii) Alternate I (Mar 2020) of 52.219-6.

__ (15) (i) 52.219-7, Notice of Partial Small Business Set-Aside (Nov 2020) (15 U.S.C. 644).

__ (ii) Alternate I (Mar 2020) of 52.219-7.

_X_ (16) 52.219-8, Utilization of Small Business Concerns (Oct 2018) (15 U.S.C. 637(d)(2) and (3)).

_X_ (17) (i) 52.219-9, Small Business Subcontracting Plan (Jun 2020) (15 U.S.C. 637(d)(4)).

__ (ii) Alternate I (Nov 2016) of 52.219-9.

__ (iii) Alternate II (Nov 2016) of 52.219-9.

__ (iv) Alternate III (Jun 2020) of 52.219-9.

__ (v) Alternate IV (Jun 2020) of 52.219-9

__ (18) (i) 52.219-13, Notice of Set-Aside of Orders (Mar 2020) (15 U.S.C. 644(r)).

__ (ii) Alternate I (Mar 2020) of 52.219-13.

__ (19) 52.219-14, Limitations on Subcontracting (Mar 2020) (15 U.S.C. 637(a)(14)).

_X_ (20) 52.219-16, Liquidated Damages-Subcontracting Plan (Jan 1999) (15 U.S.C.

637(d)(4)(F)(i)).

__ (21) 52.219-27, Notice of Service-Disabled Veteran-Owned Small Business Set-Aside (Mar 2020) (15 U.S.C. 657f).

__ (22) (i) 52.219-28, Post Award Small Business Program Rerepresentation (Nov 2020) (15 U.S.C.

632(a)(2)).

__ (ii) Alternate I (MAR 2020) of 52.219-28.

__ (23) 52.219-29, Notice of Set-Aside for, or Sole Source Award to, Economically Disadvantaged Women-Owned Small Business Concerns (Mar 2020) (15 U.S.C. 637(m)).

__ (24) 52.219-30, Notice of Set-Aside for, or Sole Source Award to, Women-Owned Small Business Concerns Eligible Under the Women-Owned Small Business Program (Mar2020) (15 U.S.C.

637(m)).

__ (25) 52.219-32, Orders Issued Directly Under Small Business Reserves (Mar 2020) (15 U.S.C.

644(r)).

__ (26) 52.219-33, Nonmanufacturer Rule (Mar 2020) (15U.S.C. 637(a)(17)).

_X_ (27) 52.222-3, Convict Labor (Jun 2003) (E.O.11755).

__ (28) 52.222-19, Child Labor-Cooperation with Authorities and Remedies (Jan2020) (E.O.13126).

_X_ (29) 52.222-21, Prohibition of Segregated Facilities (Apr 2015).

__ (30) (i) 52.222-26, Equal Opportunity (Sep 2016) (E.O.11246).

__ (ii) Alternate I (Feb 1999) of 52.222-26.

_X_ (31) (i) 52.222-35, Equal Opportunity for Veterans (Jun 2020) (38 U.S.C. 4212).

__ (ii) Alternate I (Jul 2014) of 52.222-35.

_X_ (32) (i) 52.222-36, Equal Opportunity for Workers with Disabilities (Jun 2020) (29 U.S.C. 793).

__ (ii) Alternate I (Jul 2014) of 52.222-36.

_X_ (33) 52.222-37, Employment Reports on Veterans (Jun 2020) (38 U.S.C. 4212).

_X_ (34) 52.222-40, Notification of Employee Rights Under the National Labor Relations Act (Dec 2010) (E.O. 13496).

_X_ (35) (i) 52.222-50, Combating Trafficking in Persons (Oct 2020) (22 U.S.C. chapter 78 and E.O.

13627).

__ (ii) Alternate I (Mar 2015) of 52.222-50 (22 U.S.C. chapter 78 and E.O. 13627).

_X_ (36) 52.222-54, Employment Eligibility Verification (Oct 2015). (Executive Order 12989). (Not applicable to the acquisition of commercially available off-the-shelf items or certain other types of commercial items as prescribed in 22.1803.)

__ (37) (i) 52.223-9, Estimate of Percentage of Recovered Material Content for EPA–Designated Items (May 2008) ( 42 U.S.C. 6962(c)(3)(A)(ii)). (Not applicable to the acquisition of commercially available off-the-shelf items.)

__ (ii) Alternate I (May 2008) of 52.223-9 (42 U.S.C. 6962(i)(2)(C)). (Not applicable to the acquisition of commercially available off-the-shelf items.)

__ (38) 52.223-11, Ozone-Depleting Substances and High Global Warming Potential Hydrofluorocarbons (Jun 2016) (E.O. 13693).

__ (39) 52.223-12, Maintenance, Service, Repair, or Disposal of Refrigeration Equipment and Air Conditioners (Jun 2016) (E.O. 13693).

__ (40) (i) 52.223-13, Acquisition of EPEAT®-Registered Imaging Equipment (Jun 2014) (E.O.s 13423 and 13514).

__ (ii) Alternate I (Oct 2015) of 52.223-13.

__ (41) (i) 52.223-14, Acquisition of EPEAT®-Registered Televisions (Jun 2014) (E.O.s 13423 and 13514).

__ (ii) Alternate I (Jun2014) of 52.223-14.

__ (42) 52.223-15, Energy Efficiency in Energy-Consuming Products (May 2020) (42 U.S.C.

8259b).

__ (43) (i) 52.223-16, Acquisition of EPEAT®-Registered Personal Computer Products (Oct 2015) (E.O.s 13423 and 13514).

__ (ii) Alternate I (Jun 2014) of 52.223-16.

_X_ (44) 52.223-18, Encouraging Contractor Policies to Ban Text Messaging While Driving (Jun 2020) (E.O. 13513).

__ (45) 52.223-20, Aerosols (Jun 2016) (E.O. 13693).

__ (46) 52.223-21, Foams (Jun2016) (E.O. 13693).

__ (47) (i) 52.224-3 Privacy Training (Jan 2017) (5 U.S.C. 552 a).

__ (ii) Alternate I (Jan 2017) of 52.224-3.

__ (48) 52.225-1, Buy American-Supplies (Jan2021) (41 U.S.C. chapter 83).

_X_ (49) (i) 52.225-3, Buy American-Free Trade Agreements-Israeli Trade Act (Jan 2021)(41 U.S.C.chapter83, 19 U.S.C. 3301 note, 19 U.S.C. 2112 note, 19 U.S.C. 3805 note, 19 U.S.C. 4001 note, Pub.

L. 103-182, 108-77, 108-78, 108-286, 108-302, 109-53, 109-169, 109-283, 110-138, 112-41, 112-42, and 112-43.

__ (ii) Alternate I (Jan 2021) of 52.225-3.

__ (iii) Alternate II (Jan 2021) of 52.225-3.

__ (iv) Alternate III (Jan 2021) of 52.225-3.

__ (50) 52.225-5, Trade Agreements (Oct 2019) (19 U.S.C. 2501, et seq., 19 U.S.C. 3301 note).

__ (51) 52.225-13, Restrictions on Certain Foreign Purchases (Jun 2008) (E.O.’s, proclamations, and statutes administered by the Office of Foreign Assets Control of the Department of the Treasury).

__ (52) 52.225-26, Contractors Performing Private Security Functions Outside the United States (Oct 2016) (Section 862, as amended, of the National Defense Authorization Act for Fiscal Year 2008; 10 U.S.C.

2302Note).

__ (53) 52.226-4, Notice of Disaster or Emergency Area Set-Aside (Nov2007) (42 U.S.C. 5150).

__ (54) 52.226-5, Restrictions on Subcontracting Outside Disaster or Emergency Area (Nov2007) (42 U.S.C. 5150).

__ (55) 52.229-12, Tax on Certain Foreign Procurements (Jun 2020).

__ (56) 52.232-29, Terms for Financing of Purchases of Commercial Items (Feb 2002) (41 U.S.C.

4505, 10 U.S.C. 2307(f)).

__ (57) 52.232-30, Installment Payments for Commercial Items (Jan 2017) (41 U.S.C. 4505, 10 U.S.C. 2307(f)).

_X_ (58) 52.232-33, Payment by Electronic Funds Transfer-System for Award Management (Oct2018) (31 U.S.C. 3332).

__ (59) 52.232-34, Payment by Electronic Funds Transfer-Other than System for Award Management (Jul 2013) (31 U.S.C. 3332).

__ (60) 52.232-36, Payment by Third Party (May 2014) (31 U.S.C. 3332).

__ (61) 52.239-1, Privacy or Security Safeguards (Aug 1996) (5 U.S.C. 552a).

__ (62) 52.242-5, Payments to Small Business Subcontractors (Jan 2017) (15 U.S.C. 637(d)(13)).

__ (63) (i) 52.247-64, Preference for Privately Owned U.S.-Flag Commercial Vessels (Feb 2006) (46 U.S.C. Appx. 1241(b) and 10 U.S.C. 2631).

__ (ii) Alternate I (Apr 2003) of 52.247-64.

__ (iii) Alternate II (Feb 2006) of 52.247-64.

(c) The Contractor shall comply with the FAR clauses in this paragraph (c), applicable to commercial services, that the Contracting Officer has indicated as being incorporated in this contract by reference to implement provisions of law or Executive orders applicable to acquisitions of commercial items:

[Contracting Officer check as appropriate.]

_X_ (1) 52.222-41, Service Contract Labor Standards (Aug 2018) (41 U.S.C. chapter67).

_X_ (2) 52.222-42, Statement of Equivalent Rates for Federal Hires (May 2014) (29 U.S.C. 206 and 41 U.S.C. chapter 67).

_X_ (3) 52.222-43, Fair Labor Standards Act and Service Contract Labor Standards-Price Adjustment (Multiple Year and Option Contracts) (Aug 2018) (29 U.S.C. 206 and 41 U.S.C. chapter 67).

_X_ (4) 52.222-44, Fair Labor Standards Act and Service Contract Labor Standards-Price Adjustment (May 2014) ( 29U.S.C.206 and 41 U.S.C. chapter 67).

__ (5) 52.222-51, Exemption from Application of the Service Contract Labor Standards to Contracts for Maintenance, Calibration, or Repair of Certain Equipment-Requirements (May 2014) (41 U.S.C. chapter 67).

__ (6) 52.222-53, Exemption from Application of the Service Contract Labor Standards to Contracts for Certain Services-Requirements (May 2014) (41 U.S.C. chapter 67).

_X_ (7) 52.222-55, Minimum Wages Under Executive Order 13658 (Nov 2020).

_X_ (8) 52.222-62, Paid Sick Leave Under Executive Order 13706 (Jan 2017) (E.O. 13706).

__ (9) 52.226-6, Promoting Excess Food Donation to Nonprofit Organizations (Jun 2020) (42 U.S.C.

1792).

(d) Comptroller General Examination of Record. The Contractor shall comply with the provisions of this paragraph (d) if this contract was awarded using other than sealed bid, is in excess of the simplified acquisition threshold, as defined in FAR 2.101, on the date of award of this contract, and does not contain the clause at 52.215-2, Audit and Records-Negotiation.

(1) The Comptroller General of the United States, or an authorized representative of the Comptroller General, shall have access to and right to examine any of the Contractor’s directly pertinent records involving transactions related to this contract.

(2) The Contractor shall make available at its offices at all reasonable times the records, materials, and other evidence for examination, audit, or reproduction, until 3 years after final payment under this contract or for any shorter period specified in FAR subpart 4.7, Contractor Records Retention, of the other clauses of this contract. If this contract is completely or partially terminated, the records relating to the work terminated shall be made available for 3 years after any resulting final termination settlement. Records relating to appeals under the disputes clause or to litigation or the settlement of claims arising under or relating to this contract shall be made available until such appeals, litigation, or claims are finally resolved.

(3) As used in this clause, records include books, documents, accounting procedures and practices, and other data, regardless of type and regardless of form. This does not require the Contractor to create or maintain any record that the Contractor does not maintain in the ordinary course of business or pursuant to a provision of law.

(e) (1) Notwithstanding the requirements of the clauses in paragraphs (a), (b), (c), and (d) of this clause, the Contractor is not required to flow down any FAR clause, other than those in this paragraph (e)(1) in a subcontract for commercial items. Unless otherwise indicated below, the extent of the flow down shall be as required by the clause-

(i) 52.203-13, Contractor Code of Business Ethics and Conduct (Jun 2020) (41 U.S.C. 3509).

(ii) 52.203-19, Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements (Jan 2017) (section 743 of Division E, Title VII, of the Consolidated and Further Continuing Appropriations Act, 2015 (Pub. L. 113-235) and its successor provisions in subsequent appropriations acts (and as extended in continuing resolutions)).

(iii) 52.204-23, Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by Kaspersky Lab and Other Covered Entities (Jul 2018) (Section 1634 of Pub. L. 115-91).

(iv) 52.204-25, Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment. (Aug 2020) (Section 889(a)(1)(A) of Pub. L. 115-232).

(v) 52.219-8, Utilization of Small Business Concerns (Oct 2018) (15 U.S.C. 637(d)(2) and (3)), in all subcontracts that offer further subcontracting opportunities. If the subcontract (except subcontracts to small business concerns) exceeds the applicable threshold specified in FAR 19.702(a) on the date of subcontract award, the subcontractor must include 52.219-8 in lower tier subcontracts that offer subcontracting opportunities.

(vi) 52.222-21, Prohibition of Segregated Facilities (Apr 2015).

(vii) 52.222-26, Equal Opportunity (Sep 2015) (E.O.11246).

(viii) 52.222-35, Equal Opportunity for Veterans (Jun 2020) (38 U.S.C. 4212).

(ix) 52.222-36, Equal Opportunity for Workers with Disabilities (Jun 2020) (29 U.S.C. 793).

(x) 52.222-37, Employment Reports on Veterans (Jun 2020) (38 U.S.C. 4212).

(xi) 52.222-40, Notification of Employee Rights Under the National Labor Relations Act (Dec 2010) (E.O. 13496). Flow down required in accordance with paragraph (f) of FAR clause 52.222-40.

(xii) 52.222-41, Service Contract Labor Standards (Aug 2018) (41 U.S.C. chapter 67).

(xiii) (A) 52.222-50, Combating Trafficking in Persons (Oct 2020) (22 U.S.C. chapter 78 and E.O 13627).

(B) Alternate I (Mar 2015) of 52.222-50 (22 U.S.C. chapter 78 and E.O. 13627).

(xiv) 52.222-51, Exemption from Application of the Service Contract Labor Standards to Contracts for Maintenance, Calibration, or Repair of Certain Equipment-Requirements (May2014) (41 U.S.C. chapter 67).

(xv) 52.222-53, Exemption from Application of the Service Contract Labor Standards to Contracts for Certain Services-Requirements (May 2014) (41 U.S.C. chapter 67).

(xvi) 52.222-54, Employment Eligibility Verification (Oct 2015) (E.O. 12989).

(xvii) 52.222-55, Minimum Wages Under Executive Order 13658 (Nov 2020).

(xviii) 52.222-62, Paid Sick Leave Under Executive Order 13706 (Jan 2017) (E.O. 13706).

(xix) (A) 52.224-3, Privacy Training (Jan 2017) (5 U.S.C. 552a).

(B) Alternate I (Jan 2017) of 52.224-3.

(xx) 52.225-26, Contractors Performing Private Security Functions Outside the United States (Oct 2016) (Section 862, as amended, of the National Defense Authorization Act for Fiscal Year 2008; 10 U.S.C.

2302 Note).

(xxi) 52.226-6, Promoting Excess Food Donation to Nonprofit Organizations (Jun 2020) (42 U.S.C. 1792). Flow down required in accordance with paragraph (e) of FAR clause 52.226-6.

(xxii) 52.247-64, Preference for Privately Owned U.S.-Flag Commercial Vessels (Feb 2006) (46 U.S.C. Appx. 1241(b) and 10 U.S.C. 2631). Flow down required in accordance with paragraph (d) of FAR clause 52.247-64.

(2) While not required, the Contractor may include in its subcontracts for commercial items a minimal number of additional clauses necessary to satisfy its contractual obligations.

(End of clause)

ADDENDUM TO 52.212-4

52.204-4 Printed or Copied Double-Sided on Postconsumer Fiber Content Paper (May 2011)

ADDENDUM TO 52.212-4

52.204-13 System for Award Management Maintenance (Oct 2018)

ADDENDUM TO 52.212-4

52.227-14 Rights in Data-General (May 2014)

ADDENDUM TO 52.212-4

52.252-2 -- Clauses Incorporated by Reference. (Feb 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): www.acquisition.gov

(End of Clause)

ADDENDUM TO 52.212-4

52.204-19 – Incorporation by Reference of Representations and Certifications (Dec 2014)

The Contractor’s representations and certifications, including those completed electronically via the System for Award Management (SAM), are incorporated by reference into the contract.

http://www.acquisition.gov/

ADDENDUM TO 52.212-4

52.217-8 Option to Extend Services (Nov 1999)

The Government may require continued performance of any services within the limits and at the rates specified in the contract. These rates may be adjusted only as a result of revisions to prevailing labor rates provided by the Secretary of Labor. The option provision may be exercised more than once, but the total extension of performance hereunder shall not exceed 6 months. The Contracting Officer may exercise the option by written notice to the Contractor within 60 days.

52.217-9 Option to Extend the Term of the Contract. (Mar 2000)

(a) The Government may extend the term of this contract by written notice to the Contractor within 1 day of contract expiration; provided that the Government gives the Contractor a preliminary written notice of its intent to extend at least _60_ days before the contract expires. The preliminary notice does not commit the Government to an extension.

(b)If the Government exercises this option, the extended contract shall be considered to include this option clause.

(c) The total duration of this contract, including the exercise of any options under this clause, shall not exceed 4 years and 6 months.

(End of clause)

ADDENDUM TO 52.212-4

1452.201-70 Authorities and delegations.

AUTHORITIES AND DELEGATIONS (SEP 2011)

(a) The Contracting Officer is the only individual authorized to enter into or terminate this contract, modify any term or condition of this contract, waive any requirement of this contract, or accept nonconforming work.

(b) The Contracting Officer will designate a Contracting Officer's Representative (COR) at time of award. The COR will be responsible for technical monitoring of the contractor's performance and deliveries.

The COR will be appointed in writing, and a copy of the appointment will be furnished to the Contractor.

Changes to this delegation will be made by written changes to the existing appointment or by issuance of a new appointment.

(c) The COR is not authorized to perform, formally or informally, any of the following actions:

(1) Promise, award, agree to award, or execute any contract, contract modification, or notice of intent that changes or may change this contract;

(2) Waive or agree to modification of the delivery schedule;

(3) Make any final decision on any contract matter subject to the Disputes Clause;

(4) Terminate, for any reason, the Contractor's right to proceed;

(5) Obligate in any way, the payment of money by the Government.

(d) The Contractor shall comply with the written or oral direction of the Contracting Officer or authorized representative(s) acting within the scope and authority of the appointment memorandum. The Contractor need not proceed with direction that it considers to have been issued without proper authority.

The Contractor shall notify the Contracting Officer in writing, with as much detail as possible, when the

COR has taken an action or has issued direction (written or oral) that the Contractor considers to exceed the COR's appointment, within 3 days of the occurrence. Unless otherwise provided in this contract, the

Contractor assumes all costs, risks, liabilities, and consequences of performing any work it is directed to perform that falls within any of the categories defined in paragraph (c) prior to receipt of the Contracting

Officer's response issued under paragraph (e) of this clause.

(e) The Contracting Officer shall respond in writing within 30 days to any notice made under paragraph

(d) of this clause. A failure of the parties to agree upon the nature of a direction, or upon the contract action to be taken with respect thereto, shall be subject to the provisions of the Disputes clause of this contract.

(f) The Contractor shall provide copies of all correspondence to the Contracting Officer and the COR.

(g) Any action(s) taken by the Contractor, in response to any direction given by any person acting on behalf of the Government or any Government official other than the Contracting Officer or the COR acting within his or her appointment, shall be at the Contractor's risk.

DOI-AAAP-0028

Electronic Invoicing and Payment Requirements - Invoice Processing Platform (IPP) (April 2013)

Payment requests must be submitted electronically through the U. S. Department of the Treasury's Invoice Processing Platform System (IPP).

"Payment request" means any request for contract financing payment or invoice payment by the Contractor.

To constitute a proper invoice, the payment request must comply with the requirements identified in the applicable Prompt Payment clause included in the contract, or the clause 52.212-4 Contract Terms and Conditions - Commercial Items included in commercial item contracts. The IPP website address is:

https://www.ipp.gov.

The Contractor shall also submit an electronic copy of the IPP invoice to the Contracting Officer Representative, To Be Determined and to the Contract Specialist, Mary B. Maestas at mmaestas@usbr.gov once the invoice has been submitted to IPP. Failure to email the invoice may cause significant delay or possible rejection of your payment request

Under this contract, the following documents are required to be submitted as an attachment to the IPP invoice:

https://www.ipp.gov/ https://www.ipp.gov/ mailto:mmaestas@usbr.gov

FAR 32.905(b) outlines a Proper Invoices to include:

1. Name & address of the Contractor.

2. Invoice date & number.

3. Contract number, contract line item number and, if applicable, the order number.

4. Description, quantity, unit of measure, unit price and extended price of the items delivered.

5. Shipping number and date of shipment including the bill of lading number and weight of shipment if shipped on

Government bill of lading.

6. Terms of any discount for prompt payment offered.

7. Name and address of official to whom payment is to be sent.

8. Name, title, and phone number of person to notify in event of defective invoice.

9. Taxpayer Identification Number (TIN). The Contractor shall include its TIN on the invoice only if required elsewhere in this contract.

Any other information or documentation required by the contract.

The Contractor must use the IPP website to register access and use IPP for submitting requests for payment.

The Contractor Government Business Point of Contact (as listed in SAM) will receive enrollment instructions via email from the Federal Reserve Bank of Boston (FRBB) within 3 - 5 business days of the contract award date. Contractor assistance with enrollment can be obtained by contacting the IPP Production Helpdesk via email ippgroup@bos.frb.org or phone (866) 973-3131.

If the Contractor is unable to comply with the requirement to use IPP for submitting invoices for payment, the Contractor must submit a waiver request in writing to the Contracting Officer with its proposal or quotation.

(End of Local Clause)

WBR 1452.201-80 CONTRACTING OFFICER’S REPRESENTATIVE’S AUTHORITIES AND

LIMITATIONS -- BUREAU OF RECLAMATION (MAY 2018)

(a) Performance of the work under this contract shall be subject to the technical direction of the Reclamation Contracting Officer's Representative (COR). The term “technical direction” is defined to include, without limitation:

(1) Inspecting and accepting or rejecting work performed under the contract.

(2) Representing the Government in technical phases of the work. The COR is responsible for the technical administration of the contract and will provide instructions and interpretations to the Contractor on all technical matters relating to the contract. The COR will supervise or oversee all Government technical and administrative personnel assigned to assist the COR.

(3) Reviewing and, where required by the contract, approving submittals of technical data, shop drawings, samples, literature, plans, or other data required to be delivered by the Contractor to the Government.

(b) The Contractor will receive a copy of the written COR designation from the Contracting Officer. It will specify the extent of the COR's authority to act on behalf of the Contracting Officer.

(c) Technical direction must be within the scope of work stated in the contract. Only the Contracting Officer mailto:ippgroup@bos.frb.org is authorized to determine if a change is within the scope of the contract; therefore, the COR does not have the authority to, and may not, issue any technical direction that -

(1) Constitutes a direction of additional work outside the Contract requirements;

(2) Constitutes a change as defined in the contract clause entitled “Changes;”

(3) In any manner causes an increase or decrease in the total contract cost, or the time required for contract performance;

(4) Changes any of the expressed terms, conditions or specifications of the contract; or

(5) Interferes with the Contractor's right to perform the terms and conditions of the contract.

(d) All technical direction shall be issued in writing by the COR.

(e) The Contractor must proceed promptly with the performance of technical direction duly issued by the COR in the manner prescribed by this clause and within its authority under the provisions of this clause. If, in the opinion of the Contractor, any instruction or direction by the COR falls within one of the categories defined in (c)(1) through (c)(5) of this clause, the Contractor must not proceed and must notify the Contracting Officer in writing within five (5) working days after receipt of any such instruction or direction and must request the Contracting Officer to modify the contract accordingly. Upon receiving the notification from the Contractor, the Contracting Officer must -

(1) Advise the Contractor in writing after receipt of the Contractor's letter that the technical direction is within the scope of the contract effort and does not constitute a change under the Changes clause of the contract; or

(2) Advise the Contractor that the Government will issue a written change order.

(f) A failure of the Contractor and Contracting Officer either to agree that the technical direction is within the scope of the contract or to agree upon the contract action to be taken with respect to the technical direction will be subject to the provisions of the clause entitled “Disputes.”

D. PERFORMANCE WORK STATEMENT (PWS)

Upper Rio Grande and Pecos Basin Hydrologic Model Calibration and

Model Configuration Services

January 15, 2021

1. INTRODUCTION 16

1.1 Acronyms and Abbreviations 17

2. PERIOD OF PERFORMANCE 19

3. PURPOSE, AVAILABLE INFORMATION, AND APPROACH 19

4. SCOPE 24

4.1 Compile necessary data 24

4.2 Recalibrate model locations 24

4.3 Communication 25

4.4 Reporting 25

5. DELIVERABLES 25

5.1 Deliverable 1: Compiled Data 26

5.2 Deliverable 2: Calibrated Model 26

5.3 Deliverable 3: Communication 27

5.4 Deliverable 4: Draft and Final Project Report 27

6. PERSONNEL QUALIFICATIONS 28

7. GOVERNMENT-FURNISHED MATERIALS 28

8. TRAVEL 29

9. TRAINING 29

10. QUALITY 29

10.1 Contractor’s Performance Assessment Reporting System (CPARS) 29

10.2 Performance-Based Contracting 29

11. IDENTIFICATION OF CONTRACTOR EMPLOYEES 30

12. POINTS OF CONTACTS (POCs) 30

1. INTRODUCTION

The National Weather Service (NWS) West Gulf River Forecast Center (WGRFC) provides hydrologic and water supply forecasts for the Rio Grande basin. The WGRFC water supply forecasts are currently used by water managers, including the U.S. Bureau of Reclamation (Reclamation), the Natural Resources Conservation Service (NRCS) and the Colorado Division of Water Resources, to make seasonal water management decisions.

Traditionally, water supply forecasts for the Upper Rio Grande and Pecos basins have been based on regression models of total seasonal supply provided by the NRCS. Recently, through collaboration with the Colorado Basin River Forecast Center (CBRFC), the WGRFC has begun posting model-based forecasts of both supply and timing based on current basin conditions and potential future weather. These seasonal water-supply forecasts are based on a suite, or ensemble, of simulations using the NWS-operated Upper Rio Grande and Pecos basin hydrologic models, which are the basis for the daily Ensemble Streamflow Prediction (ESP) forecasts that the WGRFC publishes for select locations in the basin. The ESP program starts with the current states from the hydrologic models (i.e., soil moisture and snowpack) and generates potential runoff hydrographs assuming the upcoming weather is the same as occurred in historical years. For the Upper Rio Grande Basin, the ESP program generates an ensemble of potential forecast period hydrographs using historical weather data for the period 1980-2007 (see Figure 1). The 28 potential runoff hydrographs are then analyzed using statistics to generate a variety of probabilistic products. The ESP products offer several potential advantages compared to the traditional regression models:

• The daily forecasted streamflow hydrographs contain valuable information about when the runoff is likely to occur, and the associated uncertainty.

• The daily hydrographs allow “what-if” scenario analyses about whether future weather conditions are likely to be similar to a given historical year (i.e., an analog year).

• The ESP products can be run more frequently than monthly (the time step on which the traditional, regression-based water supply forecasts are issued). This feature provides water managers with up-to-date information. The ability to run the model more frequently provides additional information on the relative impact of daily snowfall/snowmelt events that is not available on a monthly timestep.

Figure 1. Example ensemble streamflow prediction (ESP) product

The Upper Rio Grande basin hydrologic model was last calibrated in the 2009-2010 period to a 1980 to 2007/2008 record. The Pecos basin hydrologic model was last calibrated to the 1980- 2011 record. Since the previous calibration periods, approximately 13 years of new climate record has accumulated for the Rio Grande and approximately 9 years has accumulated for the Pecos. The existence of temperature trends and decadal variability in precipitation means that these more recent years are more likely to be similar to a current forecast year than those further back in history. An updated model calibration that includes the new climate record would therefore enhance the accuracy of the underlying hydrologic modeling framework that supports the natural-flow ESP model simulations for water supply volume forecasting.

The WGRFC requires assistance with calibration and configuration for these models.

Reclamation is contributing to the funding of the recalibrations since Reclamation and other water managers could benefit significantly from improved ESP forecasts, for example, to better inform Reclamation’s Rio Grande Annual Operating Plan and other water management decisions.

1.1 Acronyms and Abbreviations

CBRFC Colorado Basin River Forecast Center CHANLOSS Channel Loss model CHPS Community Hydrologic Prediction System CHPS-FEWS Community Hydrologic Prediction System – Flood Early Warning System CO Contracting Officer CONSUSE consumptive use model COR Contracting Officer's Representative

CPARS Contractor’s Performance Assessment Reporting System ESP Ensemble Streamflow Prediction MAP mean areal precipitation MAT mean areal temperature NRCS Natural Resources Conservation Service NWS National Weather Service NWSLID National Weather Service Location Identifier Reclamation U.S. Bureau of Reclamation RSNELEV Rain-Snow Elevation model SAC-SMA Sacramento Soil Moisture Accounting SWE Snow Water Equivalent UHG unit hydrographs WGRFC West Gulf River Forecast Center

2. PERIOD OF PERFORMANCE

This work is scheduled to begin within 60 days from the date of award and continue for one Base Period (Year), with three Option Periods (Years) to complete phases 2, 3, and 4, as described below.

3. PURPOSE, AVAILABLE INFORMATION, AND APPROACH

The purpose of the project is to refine and recalibrate an existing natural-flow hydrologic forecast model, the Upper Rio Grande Hydrologic Model, which is being used by the WGRFC to develop ESP hydrologic forecasts for the Upper Rio Grande. The model includes a total of 107 sub-basins within the Upper Rio Grande watershed. Individual sub-basin model features are identified in Appendix A-1, including parameters supporting the following supplemental models, which feed information into the Upper Rio Grande Hydrologic Model:

• Sacramento Soil Moisture Accounting (SAC-SMA) rainfall-runoff model,

• SNOW-17 snow accumulation/ablation model and

• LAG/K hydraulic routing model.

In addition, Appendix A-1 provides a count of regulation and elevation zones for the 107 sub basins.

The contractor will update the model to include all relevant data through the end of Water Year 2020, and use these data, along with data assembled during the previous calibration, as appropriate, to update the calibration of the model. The duration of the calibration period will span from 1980 to 2020.

The contract will be completed in phases (base period with three option periods), as budget is available to Reclamation. Appendix A-1 contains the list of twenty sub-basins to be calibrated in Phase 1 as well as options for additional calibration in Phases 2, 3, and 4 of the project. Phase 2 includes 22 basins in the Upper Rio Grande, Phase 3 includes the remaining 36 basins in the lower Rio Grande, and Phase 4 includes 29 basins in the Pecos. Figures 2 and 3 show the locations of the basins, and the basins are labeled according to the NWSLID. Figure 4 shows the phase assigned to each basin and is further described in Appendix A-1.

The scope of Phase 1 includes all Phase 1 sub-basins listed in Appendix A-1.

Figure 2. Northern Section of Rio Grande and Pecos Study Area with NWSLIDs Labeled

Figure 3. Southern Section of Rio Grande and Pecos Study Area with NWSLIDs Labeled

Figure 4. Project Calibration Phases 1–4

4. SCOPE

Each option year/phase of the project will include the following four tasks.

4.1 Compile necessary data

Under Task 1, the following activities will be performed:

• Acquisition and analysis of historical streamflow, diversion, return, inter-basin transfer, and reservoir elevation/storage/outflow data as necessary to accommodate the hydrologic model.

• Conversion of these data into a 6-hourly natural flow-based historical time series, if necessary.

• Development of 6-hourly time series of mean aerial precipitation and temperature from observing stations.

For each option year/phase of the contract, the Contractor shall collect the available historical streamflow data and review it for completeness and accuracy. The Contractor shall also collect and review historical data as it applies to reservoir operations, diversions and returns, inter-basin transfers, irrigation practices, etc., as necessary to generate 6-hourly “naturalized” streamflow time series which will be used for hydrologic model calibration.

Flow forecasts based on regulated streamflows will not be an objective of this calibration project as the development of appropriate reservoir models is not covered under this project plan.

The Contractor shall develop historical mean areal temperature (MAT) and precipitation (MAP) 6-hourly time series required to force the hydrologic model. The Contractor shall inventory available temperature and precipitation station data and review it for completeness and accuracy.

Consistency checks will be performed on station data, and corrections made to ensure long-term data consistency. In mountainous areas where elevation has a major influence on temperature and precipitation, the Contractor will calibrate using existing model elevation zones. The required historical data will be developed to allow model calibration for the approximate period of Water Years 1980–2020.

The Contractor shall develop monthly climatological potential evapotranspiration values using the Penman-Monteith method. These are a commonly used static input to the Sac- SMA model.

Data used to calculate the evapotranspiration will be derived from representative weather and climate recording stations in the vicinity of the basin to be calibrated.

The Contractor shall perform a water balance analysis of the basins to identify data quality issues.

4.2 Recalibrate model locations

Under Task 2, the following activities will be performed:

• Calculation of 6-hourly simulated natural flow hydrographs at each location for the appropriate phase of the project.

• Development of model parameters for SAC-SMA, SNOW-17, and UNIT-HG models for the locations appropriate for the phase of the project. To the extent that they are needed, calibration parameters for other necessary supporting (typically minor) NWS-RFS routines such as RSNELEV, CHANLOSS, CONSUSE will also be included here (and in the associated deliverables).

• Development of LAG/K routing parameters for applicable reaches.

• Calibration of all hydrologic model parameters to 6-hourly natural flow at the basin outlets.

The Contractor shall develop 6-hourly unit hydrographs (UHGs) using established GIS methods or observed data, when it is necessary to update existing UHG values. The Contractor shall perform calibration of the SNOW-17 and SAC-SMA model parameters for the headwater sub-basins and local sub-basins as specified in Appendix A-1 for each option year/phase of the project. In addition, LAG/K routing parameters will be calibrated for all downstream locations, identified at Local Areas in Appendix A-1. The unit hydrograph ordinates calculated by the Contractor will also be verified during the calibration process.

4.3 Communication

The contractor will keep Reclamation and the WGRFC abreast of progress on this project through monthly conference calls, as described in more detail in the deliverables section, below.

4.4 Reporting

The Contractor shall provide Quarterly progress reports as well as Draft and Final reports for each option year/phase of the project.

5. DELIVERABLES

For each option year/phase of the project, the contractor will complete all tasks as described above, and provide the following deliverables to Reclamation and the WGRFC:

• Compiled calibration data (any data, such as streamflow or SWE, that was created or compiled during the calibration process and that could be used to recreate or redevelop the calibration).

• final calibrated hydrologic model, and supporting models.

• Notes from monthly progress meetings hosted by the contractor, and quarterly progress reports.

• Draft and final project reports.

The table below provides a listing of deliverables, the media with the number of copies, and the recipients. More details on these deliverables are provided in the sections below

PARA DELIVERABLE DUE DELIVER TO

5.1 Compiled calibration data 1 year from initiating the

contract 1 electronic copy to NWS WGRFC;

1 electronic copy to COR; 1 electronic copy to CO

5.2 Calibrated model 1 year from initiating the

contract

1 electronic copy to NWS WGRFC;

1 electronic copy to COR; 1 electronic copy to CO

5.3 Monthly conference call

meeting notes and quarterly progress reports

1 week after each call and 1 week after the end of each quarter

1 electronic copy to NWS WGRFC;

1 electronic copy to COR; 1 electronic copy to CO

5.4 Draft and final report A Draft report is due at 335 days

and a Final report is due at 365 days from initiating the contract.

1 electronic copy to NWS WGRFC;

1 electronic copy to COR; 1 electronic copy to CO

5.1 Deliverable 1: Compiled Data

For each option year/phase of the project, the contractor shall compile and deliver the following data to Reclamation and the WGRFC:

• A list of the stations used in the MAP/MAT, along with the weights assigned to each station in the calibration process. Data will be delivered in a geospatial format.

• A minimum of 40 years of collected and quality-controlled historical data used to account for any significant regulation and diversions within the study area. Data from water years 1980 to 2020 should be used. Data will be delivered in a 6-hourly time series format.

• A minimum of 40 years of collected and quality-controlled historical and “naturalized” streamflow data for each gauge location to be calibrated. Data from water years 1980 to 2020 should be used. Data will be delivered in a 6-hourly time series format.

• A minimum of 40 years of quality controlled unbiased precipitation and temperature data for continuous reporting stations in the study area. Data from water years 1980 to 2020 should be used.

• A minimum of 40 years of computed Mean Areal Precipitation (MAP) and Mean Areal Temperature (MAT) for each area. Data from water years 1980 to 2020 should be used.

Data will be delivered in a 6-hourly time series format.

The contractor will submit and deliver all data developed for Deliverable 1 in an electronic format. The contractor will document the data collection process, quality control process, changes to the station weighting schema, evapotranspiration data development, water balance, and any pertinent assumptions made in the final report.

5.2 Deliverable 2: Calibrated Model

For each phase of the project, the final calibration will be delivered as a Community Hydrologic Prediction (CHPS) Stand-Alone model, containing fully calibrated supporting hydrologic models, including SNOW-17, SAC-SMA, and UNIT-HG for the sub-basins in Appendix A-1 for the appropriate phase. The final calibration model will be delivered as a CHPS Stand-Alone model including ModuleParFiles, ColdStateFiles, and Forecast and UpdateStates workflows in the same format as delivered to the contractor by WGRFC. Calibrated channel routing parameters will also be provided where appropriate.