Sol_140L1724Q0048.pdf
PDF 399 KB Posted
- Attached to
- TRFO CHUTES LADDERS TRAILHEAD Federal contract opportunity
- Solicitation number
- 140L1724Q0048
About this file
This document is a Request for Quotation (RFQ) for the construction of the TRFO Chutes Ladders Trailhead project near Cortez, Colorado. The Bureau of Land Management (BLM) Colorado Region is the issuing agency.
The RFQ provides details on the project, including a pre-bid site tour on July 31, 2024, a period of performance from September 3, 2024 to February 7, 2025, and a fixed-price contract type. Key requirements include submitting quotes by August 19, 2024, providing a payment bond, and adhering to the limitations on subcontracting. The RFQ incorporates various FAR clauses and outlines the proposal submission instructions, including the required volumes and page limitations. The contract will be awarded using the lowest price technically acceptable source selection process.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| B11_-140L1724Q0048-_Pre-bid_Site_Visit_Attendees_0002.pdf | ||
| Sol_140L1724Q0048_Amd_0002.pdf | ||
| Sol_140L1724Q0048_Amd_0001.pdf | ||
| A06_-_140L1724Q0048-Revised_Drawings_0001.pdf | ||
| A06_-_140L1724Q0048-Drawings.pdf | ||
| B03-_140L1724Q0048-Wage_Rate.pdf | ||
| A04_-_140L1724Q0048-_Bid_Schedule.pdf | ||
| B13_-_140L1724Q0048_-Past_Performance_Questionnaire.doc | DOC document | |
| A06_-_140L1724Q0048-Specifications.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
140L1724Q0048
1. REQUEST NO.
5a. ISSUED BY
NAME
a. NAME
c. STREET ADDRESS
d. CITY
10. PLEASE FURNISH QUOTATIONS TO
THE ISSUING OFFICE IN BLOCK 5a ON
OR BEFORE CLOSE OF BUSINESS (Date)
2. DATE ISSUED 3. REQUISITION/PURCHASE REQUEST NO. 4. CERT. FOR NAT. DEF.
UNDER BDSA REG. 2
AND/OR DMS REG.1
RATING
6. DELIVERY BY (Date)
7. DELIVERY
9. DESTINATION
a. NAME OF CONSIGNEE
b. STREET ADDRESS
PAGE OF PAGES
5b. FOR INFORMATION CALL: (No collect calls)
TELEPHONE NUMBER
AREA CODE NUMBER
8. TO:
b. COMPANY
e. STATE f. ZIP CODE
c. CITY
d. STATE e. ZIP CODE
IMPORTANT: This is a request for information, and quotations furnished are not offers. If you are unable to quote, please so indicate on this form and return it to the address in Block 5a. This request does not commit the Government to pay any costs incurred in the preparation of the submission of this quotation or to contract for supplies or services. Supplies are of domestic origin unless otherwise indicated by quoter. Any representations and/or certifications attached to this Request for Quotations must be completed by the quoter.
11. SCHEDULE (Include applicable Federal, State and local taxes)
THIS RFQ
REQUEST FOR QUOTATION
(THIS IS NOT AN ORDER)
IS IS NOT A SMALL BUSINESS SET ASIDEX
07/22/2024 0040670296
1 36
Denver Federal Center Building 40 Lakewood CO 80225
COLORADO STATE OFF
02/07/2025
BLM-CO GUNNISON GORGE NCA
2465 S TOWNSEND AVE
MONTROSE
CO 81401
303 239-3678Chau Nguyen
08/19/2024 1700 MD
FOB DESTINATION
OTHER
(See Schedule)X
ITEM NO.
(a)
SUPPLIES/SERVICES
(b)
QUANTITY
(c)
UNIT
(d)
UNIT PRICE
(e)
AMOUNT
(f)
A pre-bid site tour will be provided on July 31, 2024 at 11 AM local time. The project locations are near Cortez, CO. From Cortez, Colorado, travel east on highway 160 for approximately 9 miles. Turn north on Montezuma County road 34.
Travel north approximately 0.5 miles. The trailhead is on the right.
For questions regarding to site tour, please contact COR: Peter Russell, 970-240-5433, prussell@blm.gov Period of Performance: 09/03/2024 to 02/07/2025
00010 TRFO Chutes Ladders Trailhead Product/Service Code: Y1PZ Continued ...
12. DISCOUNT FOR PROMPT PAYMENT
a. 10 CALENDAR DAYS (%) b. 20 CALENDAR DAYS (%) c. 30 CALENDAR DAYS (%) d. CALENDAR DAYS
NUMBER PERCENTAGE
NOTE: Additional provisions and representations
13. NAME AND ADDRESS OF QUOTER
b. STREET ADDRESS
c. COUNTY
d. CITY e. STATE f. ZIP CODE
14. SIGNATURE OF PERSON AUTHORIZED TO
SIGN QUOTATION
16. SIGNER
a. NAME (Type or print)
c. TITLE (Type or print)
a. NAME OF QUOTER
AREA CODE
NUMBER
15. DATE OF QUOTATION
b. TELEPHONE are are not attached
AUTHORIZED FOR LOCAL REPRODUCTION
Previous edition not usable
STANDARD FORM 18 (REV. 6-95)
Prescribed by GSA - FAR (48 CFR) 53.215-1(a)
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
2 36
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
140L1724Q0048
Product/Service Description: CONSTRUCTION OF
OTHER NON-BUILDING FACILITIES
Delivery: 02/07/2025
Invoicing is through ipp.gov- 30 day prompt.
Matching invoice is required to be uploaded to avoid payment delays.
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
PART I - THE SCHEDULE
SECTION B – SUPPLIES OR SERVICES AND PRICES/COSTS
SCHEDULE OF ITEMS
Please see attached document.
SECTION C - DESCRIPTION/SPECIFICATION/STATEMENT OF WORK
SPECIFICATIONS AND PLANS ARE ATTACHED AND INCORPORATED HEREIN BY REFERENCE, SEE
SECTION J, AND ATTACHMENT(S)
SECTION D--PACKAGING AND MARKING
Not applicable
SECTION E--INSPECTION AND ACCEPTANCE
FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):
https://www.acquisition.gov/browse/index/far
FULL-TEXT CLAUSES
SECTION F--DELIVERIES OR PERFORMANCE
FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text.
Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):
https://www.acquisition.gov/browse/index/far
FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES
52.242-14 Suspension of Work (APR 1984)
FAR 52.211-10 Commencement, Prosecution, and Completion of Work (APR 1984)
The Contractor shall be required to (a) commence work under this contract within ten (10) calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 150 days after Notice to Proceed date. The time stated for completion shall include final cleanup of the premises.
F.1 NOTICE TO PROCEED
A Notice to Proceed will be issued in writing by the Contracting Officer. No work shall begin until receipt of this notice.
https://www.acquisition.gov/browse/index/far https://www.acquisition.gov/browse/index/far
Contract time shall commence on the day indicated on the Notice to Proceed. Notice to Proceed will be approved once all submittals have been approved by Government.
F.2 Suspension of Work
52.242-14 Suspension of Work April 1984
SECTION G - CONTRACT ADMINISTRATION DATA
G.1 DESIGNATION OF CONTRACTING OFFICERS REPRESENTATIVE (COR)
A. The Contracting Officer will designate an individual as Contracting Officer's Representative (COR) at time of award.
The name will be designated on a letter or form.
B. The Contracting Officer’s Representative is responsible for administering the performance of work under this contract.
In no event, however, will any understanding, agreement, modification, change order, or other matter deviating from the terms of this contract be effective or binding upon the Government unless formalized by a proper contractual documents executed by the Contracting Officer prior to completion of the contract.
C. The Contracting Officer should be informed as soon as possible of any actions or inactions by the Contractor or the Government which will change the required delivery or completion times stated in the contract, and the contract will be modified accordingly. (This does not apply to individual assignments which were issued by the Contracting Officer’s Representative provided they do not affect the delivery schedule or performance period stated in the contract.)
D. On all matters that pertain to the contract terms the Contractor must communicate with the Contracting Officer.
Whenever, in the opinion of the Contractor, the Contracting Officer’s Representative requests effort outside the scope of the contract, the Contractor should so advise the Contracting Officer’s Representative. If the Contracting Officer’s Representative persists and there still exists a disagreement as to proper contractual coverage, the Contracting Officer should be notified immediately, preferably in writing if time permits. Proceeding with work without proper contractual coverage could result in nonpayment or necessitate submittal of a contract claim.
G.2 DIARS 1452.201-70 AUTHORITIES AND DELEGATIONS September 2011
(a) The Contracting Officer is the only individual authorized to enter into or terminate this contract, modify any term or condition of this contract, waive any requirement of this contract, or accept nonconforming work.
(b) The Contracting Officer will designate a Contracting Officer's Representative (COR) at time of award. The COR will be responsible for technical monitoring of the contractor's performance and deliveries. The COR will be appointed in writing, and a copy of the appointment will be furnished to the Contractor. Changes to this delegation will be made by written changes to the existing appointment or by issuance of a new appointment.
(c) The COR is not authorized to perform, formally or informally, any of the following actions:
(1) Promise, award, agree to award, or execute any contract, contract modification, or notice of intent that changes or may change this contract;
(2) Waive or agree to modification of the delivery schedule;
(3) Make any final decision on any contract matter subject to the Disputes Clause;
(4) Terminate, for any reason, the Contractor's right to proceed;
(5) Obligate in any way, the payment of money by the Government.
(d) The Contractor shall comply with the written or oral direction of the Contracting Officer or authorized representative(s) acting within the scope and authority of the appointment memorandum. The Contractor need not proceed with direction that it considers to have been issued without proper authority. The Contractor shall notify the Contracting Officer in writing, with as much detail as possible, when the COR has taken an action or has issued direction (written or oral) that the Contractor considers to exceed the COR's appointment, within 3 days of the occurrence. Unless otherwise provided in this contract, the Contractor assumes all costs, risks, liabilities, and consequences of performing any work it is directed to perform that falls within any of the categories defined in paragraph
(c) prior to receipt of the Contracting Officer's response issued under paragraph (e) of this clause.
(e) The Contracting Officer shall respond in writing within 30 days to any notice made under paragraph (d) of this clause.
A failure of the parties to agree upon the nature of a direction, or upon the contract action to be taken with respect thereto, shall be subject to the provisions of the Disputes clause of this contract.
(f) The Contractor shall provide copies of all correspondence to the Contracting Officer and the COR.
(g) Any action(s) taken by the Contractor, in response to any direction given by any person acting on behalf of the Government or any Government official other than the Contracting Officer or the COR acting within his or her appointment, shall be at the Contractor's risk.
(End of clause)
G-3 NOTICE TO CONTRACTORS - CONTRACTOR PERFORMANCE ASSESSMENT REPORTING
SYSTEM (DEC 2015)
1. FAR 42.1502 directs all Federal agencies to collect past performance information on contracts. The Department of the Interior (DOI) has implemented the Contractor Performance Assessment Reporting System (CPARS) to comply with this regulation. One or more past performance evaluations will be conducted in order to record your contract performance as required by FAR 42.15.
2. The past performance evaluation process is a totally paperless process using CPARS. CPARS is a web-based system that allows for electronic processing of the performance evaluation report. Once the report is processed, it is available in the Past Performance Information Retrieval System (PPIRS) for Government use in evaluating past performance as part of a source selection action.
3. We request that you furnish the Contracting Officer (CO) with the name, position title, phone number, and email address for each person designated to have access to your firm's past performance evaluation(s) for the contract no later than 30 days after award. Each person granted access will have the ability to provide comments in the Contractor portion of the report and state whether or not the Contractor agrees with the evaluation, before returning the report to the Assessing Official (AO). Information in the report must be protected as source selection sensitive information not releasable to the public.
4. When your Contractor Representative(s) are registered in CPARS, they will receive an automatically generated email with detailed login instructions. Further details, systems requirements, and training information for CPARS is available at https://www.cpars.gov/.
5. Within 60 days after the end of a performance period, the AO will complete an interim or final past performance evaluation, and the report will be accessible at https://www.cpars.gov/.
a. Contractor Representatives may then provide comments in response to the evaluation, or return the evaluation without comment.
b. Your comments should focus on objective facts in the AO's narrative and should provide your views on the causes and ramifications of the assessed performance.
c. All information provided should be reviewed for accuracy prior to submission.
d. If you elect not to provide comments, please acknowledge receipt of the evaluation by indicating "No comment" in the space provided, and then selecting “Accept the Ratings and Close the Evaluation”.
e. Your response is due within 60 calendar days after receipt of the CPAR. On day 15, the evaluation will become available in PPIRS-RC marked as “Pending” with or without comments and whether or not it has been closed.
f. If you do not sign and submit the CPAR within 60 days, it will automatically be returned to the Government and will be annotated: "The report was delivered/received by the contractor on (date). The contractor neither signed nor offered comment in response to this assessment."
6. The following guidelines apply concerning your use of the past performance evaluation:
a. Protect the evaluation as source selection information. After review, transmit the evaluation by completing and submitting the form through CPARS. If for some reason you are unable to view and/or submit the form through CPARS, contact the CO for instructions.
b. Strictly control access to the evaluation within your organization. Ensure the evaluation is never released to persons or entities outside of your control.
c. Prohibit the use of or reference to evaluation data for advertising, promotional material, pre-award surveys, responsibility determinations, production readiness reviews, or other similar purposes.
7. If you wish to discuss a past performance evaluation, you should request a meeting in writing to the CO no later than seven days following your receipt of the evaluation. The meeting will be held in person or via telephone or other means during your 60-day review period.
https://www.cpars.gov/ https://www.cpars.gov/
8. A copy of the completed past performance evaluation will be available in CPARS for your viewing and for Government use supporting source selection actions after it has been finalized.
(End of Notice)
G.4 ELECTRONIC INVOICING AND PAYMENT REQUIREMENTS – INTERNET PAYMENT PLATFORM (IPP) (April 2013)
Payment requests must be submitted electronically through the U. S. Department of the Treasury's Invoice Processing Platform System (IPP).
"Payment request" means any request for contract financing payment or invoice payment by the Contractor. To constitute a proper invoice, the payment request must comply with the requirements identified in the applicable Prompt Payment clause included in the contract. The IPP website address is: https://www.ipp.gov.
The contractor shall submit a draft Invoice Package, including copies of the following documents, to the National Park Service’s (NPS) Construction Management Representative (CMR) a minimum of 5 working days prior to submittal of the formal Invoice through IPP. Within 5 working days of receipt, the CMR shall provide an acceptability recommendation to both the NPS Contracting Officer’s Representative (COR) and the contractor. If the CMR recommends acceptance, the contractor shall submit a copy of the final version of the CMR’s checklist and the Invoice Package to the NPS through IPP.
1. Completed copy of the CMR’s final Construction Payment Request Checklist (Submit only with the formal submittal to IPP)
2. Completed copy of the Pay Estimate Form (including signed certification of subcontractor payments)
3. Completed copy of the Limitations on Subcontracting Report
4. Certified copies of Payroll Reports per Contract clause 52.222-8 Payrolls and Basic Records.
5. Completed copy of the Payroll Report PII Certification
6. Information required by contract clause 52.232-27, Prompt Payment for Construction Contracts
7. A copy of the currently accepted construction schedule (refer to project specification section 013216)
8. A copy of the currently accepted Schedule of Values. (refer to project specification section 013216)
9. Other documents required by Division 1 of the construction specifications.
The Contractor must use the IPP website to register access and use IPP for submitting requests for payment. The Contractor Government Business Point of Contact (as listed in SAM) will receive enrollment instructions via email from the Federal Reserve Bank of Boston (FRBB) within 3 - 5 business days of the contract award date. Contractor assistance with enrollment can be obtained by contacting the IPP Production Helpdesk via email ippgroup@bos.frb.org or phone (866) 973-3131.
If the Contractor is unable to comply with the requirement to use IPP for submitting invoices for payment, the Contractor must submit a waiver request in writing to the Contracting Officer with its proposal or quotation.
(End of Local Clause)
G.5 LOCAL INTERNET PAYMENT PLATFORM (IPP) HOTLINE
To check payment status, contact the Payment Hotline at 877-480-9724 or 303-236-2850. You will need to leave a message with the following information:
1. Company Name
2. Contract Number
3. Invoice Number
4. Invoice Amount
5. A brief description of why you are calling
6. Your contact information
If you do not receive a callback from the Payment Hotline within 72 hours, please contact the Contract Officer with the day and time you contacted the Payment Hotline.
G.6 GOVERNMENT POINTS OF CONTACT
Chau Nguyen (Contracting Officer) cnguyen@blm.gov
(END OF SECTION)
SECTION H -- SPECIAL CONTRACT REQUIREMENTS
https://www.ipp.gov/ mailto:ippgroup@bos.frb.org mailto:cnguyen@blm.gov
H-1 WORK HOURS
The performance period established for this contract is based upon all work being conducted during regular working hours between 7:30am and 5:30pm, Monday through Friday, excluding government holidays. If the Contractor desires to carry on work outside regular hours, including Saturdays, Sundays, and government holidays, a request must be submitted to the Contracting Officer in sufficient time to allow satisfactory arrangements to be made by the Government for access to the work site and inspection.
H-2 FIRE DANGER SEASON
If the Contracting Officer Representative (COR) allows the Contractor to continue work during periods of declared fire danger or season, the Contractor shall comply with all applicable state laws relating to fire prevention and with all special conditions of work as directed by the COR.
H-3 DRAWINGS
(a) Typical Drawings. Any drawings titled typical are general only and dimensions of each structure will be fixed by the Contracting Officer to adapt the design to existing conditions at the structure location.
(b) Reduced Size Drawings. Any drawings identified as "REDUCED SIZE DRAWINGS" appearing in the solicitation are photographically reduced in size. Accordingly, measurements and dimensions should not be taken or be based on any numerical scales shown. Prospective bidders desiring to review a copy of the full size drawings may contact the Contracting Officer identified in the solicitation.
H-4 PRESERVATION OF HISTORICAL AND ARCHEOLOGICAL DATA
(a) The Historic and Archeological Data Preservation Act of 1974, provides for the preservation of historical and archeological data that might otherwise be lost as the result of alterations to the terrain caused by a federal or federally licensed activity or program.
(b) If, in connection with operations under this contract, the Contractor, subcontractors, or the employees of any of them, discovers, encounters or becomes aware of any possible historical or archeological data, objects or sites of cultural value on the project area, such as historical ruins, graves or grave markers, fossils, or artifacts, the Contractor shall immediately suspend all operations in the vicinity of the cultural value and shall notify the Contracting Officer in writing, giving the location and nature of the findings. No objects of cultural resource value may be removed.
(c) Where appropriate by reason of discovery, the Contracting Officer may order delays in the time of performance and/or changes in the work. If such delays and/or changes are ordered, the time of performance and contract price shall be adjusted in accordance with the Changes clause.
(d) The Contractor will be responsible for protecting the cultural resources within the effected area from damage. In addition, the contractor will be liable for all damage to the identified cultural resources caused by their actions or the actions of their agents or representatives. The Contractor shall immediately notify the Contracting Officer or his representative if any damage occurs to any cultural resource and immediately suspend work in the area in which damage has occurred until authorized to proceed.
H-5 SAFETY AND QUALITY CONTROL PLAN
Following contract award, the contractor must provide effective quality assurance and safety plans for acceptance by the Government.
H-6 FEDERAL HOLIDAYS
The following Federal Legal Holidays are observed:
New Year’s Day Martin Luther King, Jr.
Day President’s Day Memorial Day Independence Day Labor Day Columbus Day Veterans Day Thanksgiving Day Christmas Juneteenth
H-7 52.219-14 Limitations on Subcontracting.
As prescribed in 19.507(e), insert the following clause:
https://www.acquisition.gov/far/19.507#FAR_19_507
LIMITATIONS ON SUBCONTRACTING (OCT 2022)
(a) This clause does not apply to the unrestricted portion of a partial set-aside.
(b) Definition. Similarly situated entity, as used in this clause, means a first-tier subcontractor, including an independent contractor, that—
(1) Has the same small business program status as that which qualified the prime contractor for the award (e.g., for a small business set-aside contract, any small business concern, without regard to its socioeconomic status); and
(2) Is considered small for the size standard under the North American Industry Classification System (NAICS) code the prime contractor assigned to the subcontract.
(c) Applicability. This clause applies only to—
(1) Contracts that have been set aside for any of the small business concerns identified in 19.000(a)(3);
(2) Part or parts of a multiple-award contract that have been set aside for any of the small business concerns identified in 19.000(a)(3);
(3) Contracts that have been awarded on a sole-source basis in accordance with subparts 19.8, 19.13, 19.14, and 19.15;
(4) Orders expected to exceed the simplified acquisition threshold and that are—
(i) Set aside for small business concerns under multiple-award contracts, as described in 8.405- 5 and 16.505(b)(2)(i)(F); or
(ii) Issued directly to small business concerns under multiple-award contracts as described in 19.504(c)(1)(ii);
(5) Orders, regardless of dollar value, that are—
(i) Set aside in accordance with subparts 19.8, 19.13, 19.14, or 19.15 under multiple-award contracts, as described in 8.405-5 and 16.505(b)(2)(i)(F); or
(ii) Issued directly to concerns that qualify for the programs described in subparts 19.8, 19.13, 19.14, or 19.15 under multiple-award contracts, as described in 19.504(c)(1)(ii); and
(6) Contracts using the HUBZone price evaluation preference to award to a HUBZone small business concern unless the concern waived the evaluation preference.
(d) Independent contractors. An independent contractor shall be considered a subcontractor.
(e) Limitations on subcontracting. By submission of an offer and execution of a contract, the Contractor agrees that in performance of a contract assigned a North American Industry Classification System (NAICS) code for—
(1) Services (except construction), it will not pay more than 50 percent of the amount paid by the Government for contract performance to subcontractors that are not similarly situated entities. Any work that a similarly situated entity further subcontracts will count towards the prime contractor's 50 percent subcontract amount that cannot be exceeded. When a contract includes both services and supplies, the 50 percent limitation shall apply only to the service portion of the contract;
(2) Supplies (other than procurement from a nonmanufacturer of such supplies), it will not pay more than 50 percent of the amount paid by the Government for contract performance, excluding the cost of materials, to subcontractors that are not similarly situated entities. Any work that a similarly situated entity further subcontracts will count towards the prime contractor's 50 percent subcontract amount that cannot be exceeded. When a contract includes both supplies and services, the 50 percent limitation shall apply only to the supply portion of the contract;
https://www.acquisition.gov/far/19.000#FAR_19_000 https://www.acquisition.gov/far/19.000#FAR_19_000 https://www.acquisition.gov/far/subpart-19.8#FAR_Subpart_19_8 https://www.acquisition.gov/far/subpart-19.13#FAR_Subpart_19_13 https://www.acquisition.gov/far/subpart-19.14#FAR_Subpart_19_14 https://www.acquisition.gov/far/subpart-19.15#FAR_Subpart_19_15 https://www.acquisition.gov/far/8.405-5#FAR_8_405_5 https://www.acquisition.gov/far/8.405-5#FAR_8_405_5 https://www.acquisition.gov/far/16.505#FAR_16_505 https://www.acquisition.gov/far/19.504#FAR_19_504 https://www.acquisition.gov/far/subpart-19.8#FAR_Subpart_19_8 https://www.acquisition.gov/far/subpart-19.13#FAR_Subpart_19_13 https://www.acquisition.gov/far/subpart-19.14#FAR_Subpart_19_14 https://www.acquisition.gov/far/subpart-19.15#FAR_Subpart_19_15 https://www.acquisition.gov/far/8.405-5#FAR_8_405_5 https://www.acquisition.gov/far/16.505#FAR_16_505 https://www.acquisition.gov/far/subpart-19.8#FAR_Subpart_19_8 https://www.acquisition.gov/far/subpart-19.13#FAR_Subpart_19_13 https://www.acquisition.gov/far/subpart-19.14#FAR_Subpart_19_14 https://www.acquisition.gov/far/subpart-19.15#FAR_Subpart_19_15 https://www.acquisition.gov/far/19.504#FAR_19_504
(3) General construction, it will not pay more than 85 percent of the amount paid by the Government for contract performance, excluding the cost of materials, to subcontractors that are not similarly situated entities. Any work that a similarly situated entity further subcontracts will count towards the prime contractor's 85 percent subcontract amount that cannot be exceeded; or
(4) Construction by special trade contractors, it will not pay more than 75 percent of the amount paid by the Government for contract performance, excluding the cost of materials, to subcontractors that are not similarly situated entities. Any work that a similarly situated entity further subcontracts will count towards the prime contractor's 75 percent subcontract amount that cannot be exceeded.
(f) The Contractor shall comply with the limitations on subcontracting as follows:
(1) For contracts, in accordance with paragraphs (c)(1), (2), (3) and (6) of this clause—
[Contracting Officer check as appropriate.]
□ By the end of the base term of the contract and then by the end of each subsequent option period; or
□ By the end of the performance period for each order issued under the contract.
(2) For orders, in accordance with paragraphs (c)(4) and (5) of this clause, by the end of the performance period for the order.
(g) A joint venture agrees that, in the performance of the contract, the applicable percentage specified in paragraph (e) of this clause will be performed by the aggregate of the joint venture participants.
(1) In a joint venture comprised of a small business protégé and its mentor approved by the Small Business Administration, the small business protégé shall perform at least 40 percent of the work performed by the joint venture. Work performed by the small business protégé in the joint venture must be more than administrative functions.
(2) In an 8(a) joint venture, the 8(a) participant(s) shall perform at least 40 percent of the work performed by the joint venture. Work performed by the 8(a) participants in the joint venture must be more than administrative functions.
(End of clause)
SPECIAL CLAUSE 1: OPTION FOR ADDITIONAL SERVICES—SEPARATELY PRICED LINE ITEMS
The Government may require the delivery of the numbered line items identified in the Schedule as option items at the price stated in the Schedule. The Contracting Officer may unilaterally exercise the option by written notice to the Contractor within 150 days after contract award. Performance of added line item tasks shall be at the price negotiated in the contract Schedule.
(End of clause)
SPECIAL CLAUSE 2: KEY PERSONNEL
(a) The Contractor shall assign to this contract the following key personnel: Project Manager and/or Site Forman or equivalent positions
(b) During the first 30 days of performance, the Contractor shall make no substitutions of key personnel unless the substitution is necessitated by illness, death, or termination of employment. The Contractor shall notify the Contracting Officer within 15 calendar days after the occurrence of any of these events and provide the information required by paragraph (c) below. After the initial 30-day period, the Contractor shall submit the information required by paragraph (c) to the Contracting Officer at least 7 calendar days prior to making any permanent substitutions.
(c) The Contractor shall provide a detailed explanation of the circumstances necessitating the proposed substitutions, complete resumes for the proposed substitutes, and any additional information requested by the Contracting Officer.
Proposed substitutes should have comparable qualifications to those of the persons being replaced. The Contracting Officer will notify the Contractor within 7 calendar days after receipt of all required information of the decision on substitutions.
(End of clause)
PART II--CONTRACT CLAUSES
SECTION I--CONTRACT CLAUSES
52.252-2 CLAUSES INCORPORATED BY REFERENCE February 1998
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address (es): http://acquisition.gov/far/index.html .
Claus e
Title Date
52.202-1 Definitions June 2020
52.203-3 Gratuities April 1984
52.203-5 Covenant Against Contingent Fees May 2014
52.203-7 Anti-Kickback Procedures June 2020
52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity
May 2014
52.203-10 Price Or Fee Adjustment For Illegal Or Improper Activity May 2014
52.203-12 Limitation On Payments To Influence Certain Federal Transactions June 2020 52.203-17 Contractor Employee Whistleblower Rights and Requirement to Inform
Employees of Whistleblower Rights
June 2020
52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements
January 2017
52.204-4 Printed or Copied Double-Sided on Postconsumer Fiber Content Paper May 2011
52.204-9 Personal Verification Contractor Personnel January 2011
52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards June 2020
52.204-13 System for Award Management Maintenance October 2018
52.204-14 Service Contract Reporting Requirements October 2016
52.209-6 Protecting the Government's Interest When Subcontracting With Contractors Debarred, Suspended, or Proposed for Debarment
November
52.209-9 Updates of Publicly Available Information Regarding Responsibility Matters October 2018
52.209-10 Prohibition on Contracting with Inverted Domestic Corporations November
52.215-2 Audit and Records – Negotiation June 2020
52.215-8 Order of Precedence- Uniform Contract Format October 1997
52.215-21 Requirements for Certified Cost or Pricing Data and Data Other than Certified Cost or Pricing Data – Modifications Alternate III
November http://acquisition.gov/far/index.html
52.219-6 Notice of Total Small Business Set-Aside November
52.219-8 Utilization of Small Business Concerns October 2022
52.219-14 Limitations on Subcontracting October 2022
52.219-28 Post-Award Small Business Program Representation March 2023
52.222-1 Notice To The Government Of Labor Disputes February 1997
52.222-3 Convict Labor June 2003
52.222-4 Contract Work Hours and Safety Standards Act - Overtime Compensation May 2018
52.222-6 Construction Wage Requirements August 2018
52.222-7 Withholding of Funds May 2014
52.222-8 Payrolls and Basic Records July 2021
52.222-9 Apprentices and Trainees July 2005
52.222-10 Compliance with Copeland Act Requirements February 1988
52.222-11 Subcontracts (Labor Standards) May 2014
52.222-12 Contract Termination-Debarment May 2014
52.222-13 Compliance with Construction Wage Rate Requirements and Related Act Regulations
May 2014
52.222-14 Disputes Concerning Labor Standards February 1988
52.222-15 Certification of Eligibility May 2014
52.222-21 Prohibition of Segregated Facilities April 2015
52.222-26 Equal Opportunity September
52.222-27 Affirmative Action Compliance Requirements for Construction April 2015
52.222-35 Equal Opportunity for Veterans June 2020
52.222-36 Equal Opportunity for Workers with Disabilities June 2020
52.222-37 Employment Reports Veterans June 2020
52.222-40 Notification of Employee Rights Under the National Labor Relations Act December
52.222-50 Combating Trafficking in Persons November
52.222-54 Employment Eligibility Verification May 2022
52.222-55 Establishing a Minimum Wage for Contractors 13658 January 2022
52.223-2 Affirmative Procurement of Biobased Products Under Service and Construction Contracts
September
52.223-3 Hazardous Material Identification and Material Safety Data February 2021
52.223-5 Pollution Prevention and Right-to-Know Information May 2011
52.223-6 Drug Free Workplace May 2001
52.223-15 Energy Efficiency in Energy-Consuming Products May 2020
52.223-17 Affirmative Procurement of EPA-designated Items in Service and Construction Contracts
August 2018
52.223-18 Encouraging Contractor Policy to Ban Text Messaging While Driving June 2020
52.223-21 Foams June 2016
52.225-13 Restrictions on Certain Foreign Purchases February 2021
52.227-1 Authorization and Consent June 2020
52.227-4 Patent Indemnity – Construction Contracts December
52.228-5 Insurance – Work on a Government Installation January 1997
52.228-11 Pledges of Assets February 2021
52.228-12 Prospective Subcontractor Requests for Bonds December
52.229-3 Federal, State And Local Taxes February 2013
52.232-5 Payments under Fixed-Price Construction Contracts May 2014
52.232-17 Interest May 2014
52.232-23 Assignment Of Claims May 2014
52.232-27 Prompt Payment for Construction Contracts January 2017
52.232-33 Payment by Electronic Funds Transfer-- System for Award Management October 2018
52.232-39 Unenforceability of Unauthorized Obligations June 2013
52.232-40 Providing Accelerated Payments to Small Business Subcontractors March 2023
52.233-1, Alt 1 Disputes December
52.233-3 Protest After Award August 1996
52.233-4 Applicable Law for Breach of Contract Claim October 2004
52.236-2 Differing Site Conditions April 1984
52.236-3 Site Investigation and Conditions Affecting the Work April 1984
52.236-5 Material and Workmanship April 1984
52.236-6 Superintendence by the Contractor April 1984
52.236-7 Permits and Responsibilities November
52.236-8 Other Contracts April 1984
52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and April 1984
52.236-10 Operations and Storage Areas April 1984
52.236-11 Use and Possession Prior to Completion April 1984
52.236-12 Cleaning up April 1984
52.236-13 Accident Prevention November
52.236-14 Availability and Use of Utility Services April 1984
52.236-15 Schedules for Construction Contracts April 1984
52.236-17 Layout of Work April 1984
52.236-21 Alt 1 Specifications and Drawings for Construction April 1984
52.236-26 Preconstruction Conference February 1995
52.242-13 Bankruptcy July 1995
52.243-4 Changes June 2007
52.244-6 Subcontracts for Commercial Items March 2023
52.246-12 Inspection of Construction August 1996
52.246-13 Inspection-Dismantling, Demolition, or Removal of Improvements August 1996
52.246-21 Warranty of Construction March 1994
52.248-3 Value Engineering – Construction October 2020
52.249-2, Alt 1 Termination for Convenience of the Government (Fixed-Price), Alternate 1 September
52.249-3 Termination for Convenience of the Government (Dismantling, Demolition, or Removal of Improvements
April 2012
52.249-10, Alt I Default (Fixed-Price Construction) April 1984
52.253-1 Computer Generated Forms January 1991
DIAR 1452.201-70 Authorities and Delegations September
DIAR 1452.203-70 Restrictions on Endorsements – Department of the Interior July 1996
DIAR 1452.204-70 Release of Claims – Department of the Interior July 1996
DIAR 1452.215-70 Examination of Records – Department of the Interior April 1984
DIAR 1452.236-70 Prohibition Against Use of Lead-Based Paint – Department of the Interior July 1996
DIAR 1452.237-70 Information Collection – Department of the Interior July 1996
52.252-6 Authorized Deviations in Clauses.
As prescribed in 52.107(f), insert the following clause in solicitations and contracts that include any FAR or supplemental clause with an authorized deviation. Whenever any FAR or supplemental clause is used with an authorized deviation, the contracting officer shall identify it by the same number, title, and date assigned to the clause when it is used without deviation, include regulation name for any supplemental clause, except that the contracting officer shall insert "(DEVIATION)" after the date of the clause.
Authorized Deviations in Clauses (Nov 2020)
(a) The use in this solicitation or contract of any Federal Acquisition Regulation (48 CFR Chapter 1) clause with an authorized deviation is indicated by the addition of "(DEVIATION)" after the date of the clause.
(b) The use in this solicitation or contract of any 48 CFR Chapter 1 clause with an authorized deviation is indicated by the addition of "(DEVIATION)" after the name of the regulation.
(End of clause)
CLAUSES INCORPORATED BY FULL TEXT
52.225-9 Buy American-Construction Materials.
As prescribed in 25.1102(a), insert the following clause:
BUY AMERICAN-CONSTRUCTION MATERIALS (OCT 2022)
(a) Definitions. As used in this clause—
Commercially available off-the-shelf (COTS) item— https://www.acquisition.gov/far/52.107#FAR_52_107 https://www.acquisition.gov/far/25.1102#FAR_25_1102
(1) Means any item of supply (including construction material) that is–
(i) A commercial product (as defined in paragraph (1) of the definition of “commercial product” at Federal Acquisition Regulation (FAR) 2.101);
(ii) Sold in substantial quantities in the commercial marketplace; and
(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and
(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.
"Construction material" means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.
Cost of components means—
(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or
(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit.
Cost of components does not include any costs associated with the manufacture of the construction material.
Critical component means a component that is mined, produced, or manufactured in the United States and deemed critical to the U.S. supply chain. The list of critical components is at FAR 25.105.
Critical item means a domestic construction material or domestic end product that is deemed critical to U.S. supply chain resiliency. The list of critical items is at FAR 25.105.
Domestic construction material means—
(1) For construction material that does not consist wholly or predominantly of iron or steel or a combination of both-
(i) An unmanufactured construction material mined or produced in the United States; or
(ii) A construction material manufactured in the United States, if–
(A)The cost of its components mined, produced, or manufactured in the United States exceeds 60 percent of the cost of all its components, except that the percentage will be 65 percent for items delivered in calendar years 2024 through 2028 and 75 percent for items delivered starting in calendar year 2029. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic. Components of unknown origin are treated as foreign; or
(B) The construction material is a COTS item; or
(2) For construction material that consists wholly or predominantly of iron or steel or a combination of both, a construction material manufactured in the United States if the cost of foreign iron and steel constitutes less than 5 percent of the cost of all components used in such construction material. The cost of foreign iron and steel includes but is not limited to the cost https://www.acquisition.gov/far/2.101#FAR_2_101 https://www.acquisition.gov/far/25.105#FAR_25_105 of foreign iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the construction material and a good faith estimate of the cost of all foreign iron or steel components excluding COTS fasteners. Iron or steel components of unknown origin are treated as foreign. If the construction material contains multiple components, the cost of all the materials used in such construction material is calculated in accordance with the definition of "cost of components".
Fastener means a hardware device that mechanically joins or affixes two or more objects together. Examples of fasteners are nuts, bolts, pins, rivets, nails, clips, and screws.
Foreign construction material means a construction material other than a domestic construction material.
Foreign iron and steel means iron or steel products not produced in the United States. Produced in the United States means that all manufacturing processes of the iron or steel must take place in the United States, from the initial melting stage through the application of coatings, except metallurgical processes involving refinement of steel additives. The origin of the elements of the iron or steel is not relevant to the determination of whether it is domestic or foreign.
Predominantly of iron or steel or a combination of both means that the cost of the iron and steel content exceeds 50 percent of the total cost of all its components. The cost of iron and steel is the cost of the iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the product and a good faith estimate of the cost of iron or steel components excluding COTS fasteners.
Steel means an alloy that includes at least 50 percent iron, between 0.02 and 2 percent carbon, and may include other elements.
"United States" means the 50 States, the District of Columbia, and outlying areas.
(b) Domestic preference.
(1) This clause implements 41 U.S.C.chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the domestic content test of the Buy American statute is waived for construction material that is a COTS item, except that for construction material that consists wholly or predominantly of iron or steel or a combination of both, the domestic content test is applied only to the iron and steel content of the construction materials, excluding COTS fasteners. (See FAR 12.505(a)(2)). The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.
(2) This requirement does not apply to information technology that is a commercial product or to the construction materials or components listed by the Government as follows:
________________________________________________[Contracting Officer to list applicable excepted materials or indicate "none"]
(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that-
(i)The cost of domestic construction material would be unreasonable.
(A) For domestic construction material that is not a critical item or does not contain critical components.
(1)The cost of a particular domestic construction material subject to the requirements of the Buy American statute is unreasonable when the cost of such material exceeds the cost of foreign material by more than 20 percent;
(2)For construction material that is not a COTS item and does not consist wholly or predominantly of iron or steel or a combination of both, if the cost of a particular domestic construction material is determined to be unreasonable or there is no domestic offer received, and the low offer is for foreign construction material that is manufactured in the United States and does not exceed 55 percent domestic content, the Contracting Officer will treat the lowest offer of foreign construction http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 https://www.acquisition.gov/far/12.505#FAR_12_505 material that exceeds 55 percent domestic content as a domestic offer and determine whether the cost of that offer is unreasonable by applying the evaluation factor listed in paragraph (b)(3)(i)(A)(1) of this clause.
(3)The procedures in paragraph (b)(3)(i)(A)(2) of this clause will no longer apply as of January 1, 2030.
(B) For domestic construction material that is a critical item or contains critical components.
(1)The cost of a particular domestic construction material that is a critical item or contains critical components, subject to the requirements of the Buy American statute, is unreasonable when the cost of such material exceeds the cost of foreign material by more than 20 percent plus the additional preference factor identified for the critical item or construction material containing critical components listed at FAR 25.105.
(2)For construction material that does not consist wholly or predominantly of iron or steel or a combination of both, if the cost of a particular domestic construction material is determined to be unreasonable or there is no domestic offer received, and the low offer is for foreign construction material that does not exceed 55 percent domestic content, the Contracting Officer will treat the lowest foreign offer of construction material that is manufactured in the United States and exceeds 55 percent domestic content as a domestic offer, and determine whether the cost of that offer is unreasonable by applying the evaluation factor listed in paragraph (b)(3)(i)(B)(1) of this clause.
(3)The procedures in paragraph (b)(3)(i)(B)(2) of this clause will no longer apply as of January 1, 2030.
(ii) The application of the restriction of the Buy American statute to a particular construction material would be impracticable or inconsistent with the public interest; or
(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.
(c) Request for determination of inapplicability of the Buy American statute.
(1)
(i) Any Contractor request to use foreign construction material in accordance with paragraph (b)(3) of this clause shall include adequate information for Government evaluation of the request, including-
(A) A description of the foreign and domestic construction materials;
(B) Unit of measure;
(C) Quantity;
(D) Price;
(E) Time of delivery or availability;
(F) Location of the construction project;
(G) Name and address of the proposed supplier; and
(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.
(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.
(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).
(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.
(2) If the Government determines after contract award that an exception to the Buy American statute applies and the Contracting Officer and the Contractor negotiate adequate consideration, the Contracting Officer will modify the contract to allow use of the foreign construction material. However, when the basis for the exception is the unreasonable price of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(3)(i) of this clause.
(3) Unless the Government determines that an exception to the Buy…