- BLM-CO HILL 71 TOWER REINFORCEMENT Federal contract opportunity
- Solicitation number
- 140L1722Q0009
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140L1722Q0009_Amd_0002.pdf | ||
| Sol_140L1722Q0009_Amd_0001.pdf | ||
| Attachment_1_-_SOW.pdf | ||
| Attachment_5_-_Site_Location.pdf | ||
| Attachment_4_-_Wage_Determination.pdf | ||
| Attachment_3_-_Engineering_Reports.zip | ZIP file | |
| Attachment_2_-_Drawings_and_Specs.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOLICITATION, OFFER,
AND AWARD
2. TYPE OF SOLICITATION
6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.
PAGE OF PAGES
7. ISSUED BY CODE 8. ADDRESS OFFER TO
SOLICITATION
(Construction, Alteration, or Repair)
1. SOLICITATION NO. 3. DATE ISSUED
IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.
9.
INFORMATION
a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."
CALL:
FOR
SEALED BID (IFB)
NEGOTIATED (RFP)
0040567410
COLORADO STATE OFFICE
2850 YOUNGFIELD STREET
LAKEWOOD CO 80215
LRA
Robert Hall 9708769038
105/12/2022
140L1722Q0009
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)
BLM-CO Communications Tower Reinforcement
This is a solicitation to reinforce tower footings on Hill 71 (elevation 12000 feet) located near Lake City, Colorado . The tower was studied last year with the recommended and designer stamped reinforcement procedures described in the attachments. The work may required specialized skills and equipment. Access to the site is limited to high clearance 4WD with several steep water bars to cross. The
Government estimates the rough order of magnitude for this project to between
$25,000 and $100,000 with a budget toward the upper end of the scale.
Site Visit: 3 June 2022 - 11:00 - at the site.
11. The Contractor shall begin performance
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and is not required.is, b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
d. Offers providing less than
12b. CALENDAR DAYSYES NO
(If "YES", indicate within how many calendar days after award in Item 12b.)
10 75 calendar days and complete it within ________________ ________________ calendar days after receiving
06/13/2022
NSN 7540-01-155-3212
x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________
STANDARD FORM 1442 (Rev. 4-85)
Prescribed by GSA
FAR(48 CFR) 53.236-1(d)
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)
16. REMITTANCE ADDRESS (Include only if different than item 14.)
CODE FACILITY CODE
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGEMENT OF AMENDMENTS
OFFER (Must be fully completed by offeror)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this document and return (Contractor is not required to sign this document.)
Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award.
No further contractual document is necessary.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE
BY
2PAGE OF
Upper Colorado River District
2815 H. ROAD
GRAND JUNCTION CO 81506
LRL
Robert Hall
28. NEGOTIATED AGREEMENT 29. AWARD
Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, copies to issuing office.)
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
STANDARD FORM 1442 (REV. 4-85) BACK
Continued...
ITEM NO.
(A)
SUPPLIES/SERVICES
(B)
QUANTITY
(C)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
NAME OF OFFEROR OR CONTRACTOR
3 32
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
140L1722Q0009
BLM-CO Communications Tower Reinforcement
Basic Contracting Requirements:
1. Active Registration -www.sam.gov
2. Invoicing and Payment - www.ipp.gov
3. FAR Part 12 - Construction Provisions and
Clauses
4. FAR Part 13 - Simplified Acquisition Procedures
5. Construction Wages for Hinsdale County, CO
6. Bonding - 20% bid bond, 100% performance and payment
7. Total Small Business Set Aside
8. Award Basis - Low Price Technically Acceptable
Instructions: Please update your marketing literature with your new SAM Unique Entity
Identifier (UEI). It has already been assigned to you if you had an existing registration in
SAM.Gov. To find it just log in to SAM and note your new 12 alpha-numeric ID. Starting from
April 4th, the SAM UEI is the ONLY identifier the
Federal Government uses to identify you in our systems. Your DUNS number was deleted from our systems and is no longer used for Federal
Business. Contact me if you have questions about that or anything else related to the Federal
Procurement process or setting up your filters and notifications in www.sam.gov to get first hand info on contracting opportunities.
Minimum Requirements for a Responsive Quote:
1. Signed, dated and filled out SF1442 with your prices filled in and on Schedule B. Acknowledge all amendments.
2. Technical response detailing your plan of actions, resources, capabilities, supervision, personnel, equipment and safety plan for accomplishing this work. A generic response without details will most likely be deemed technically unacceptable. Include at least three recent and relevant contactable references who are willing to attest to your technical capability in performing this work.
3. Bid Bond - 20% of quote
4. Email the above items to the POC no later than
Continued ...
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
ITEM NO.
(A)
SUPPLIES/SERVICES
(B)
QUANTITY
(C)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
NAME OF OFFEROR OR CONTRACTOR
4 32
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
140L1722Q0009 than the solicitation response date.
POC: Contracting Officer Robert Hall -rhall@blm.gov - 970-876-9038
Delivery: 09/30/2022
Delivery Location Code: 0004276316
BLM-CO COLORADO STATE OFFICE*
2850 YOUNGFIELD STREET
LAKEWOOD CO 80215 US
Period of Performance: 07/18/2022 to 09/30/2022
00010 Hill 71 Tower Footings
Product/Service Code: Y1PZ
Product/Service Description: CONSTRUCTION OF
OTHER NON-BUILDING FACILITIES
REMINDER: All invoices must be submitted directly to www.ipp.gov and include an itemized matching attachment, certified payroll, certification for progress payments and a release of claims for the final invoice. The attached invoice must display the Purchase Order number, your invoice number, vendor name and address and the overall invoice amount.
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
140L1722Q0009 Hill 71 Tower Reinforcement Page 6 of 32
Contents
B - SCHEDULE OF ITEMS
C- STATEMENT OF WORK/DESCRIPTION/SPECIFICATIONS
E - INSPECTION AND ACCEPTANCE
J – LIST OF DOCUMENTS AND ATTACHMENTS
L – INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS OR RESPONDENTS
M - EVALUATION FACTORS FOR AWARD
140L1722Q0009 Hill 71 Tower Reinforcement Page 7 of 32
B - SCHEDULE OF ITEMS
B-1. Schedule of Items
The Government intends to evaluate bids and award contract without discussions with offerors.
Job Title: GAOA Hill 71 Tower Reinforcement
Furnish necessary labor, equipment, supervision, supplies and materials to provide items listed below in accordance with the specifications in Section C and all other provisions contained herein.
Estimated Start Date: July 18, 2022
Period of performance 75 days
Line Pay Item Description Quantity Unit Unit Price Total Price
10 01009(10) Strengthen Tower Footings 1 LS
Total ________________
(All or None)
To be eligible for award, contractors MUST be registered in the System for Award Management (SAM), https://www.sam.gov/SAM/
B-2 NOTE: Payment for bond premiums in accordance with Clause 52.232-5, Payments under Fixed-Price
Construction Contracts, shall not be in addition to the contract price. Include your costs for bond payments in the
Mobilization line.
https://www.sam.gov/SAM/
140L1722Q0009 Hill 71 Tower Reinforcement Page 8 of 32
C- STATEMENT OF WORK/DESCRIPTION/SPECIFICATIONS
C-1. Description of Work
1.01 SUMMARY:
A. Description of Work: Furnish labor, equipment, supplies and materials to strengthen the footing for the radio tower at Hill 71. All work shall be in accordance with the attachments listed in Section J.
B. Location: Work under this Contract is near Lake City in Hinsdale County, Colorado.
E - INSPECTION AND ACCEPTANCE
52.246-12 Inspection of Construction. (APR 1996) – IBR
52.232-5 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS (MAY 2014)
(a) Payment of price. The Government shall pay the Contractor the contract price as provided in this contract .
(b) Progress payments. The Government shall make progress payments monthly as the work proceeds, or at more frequent intervals as determined by the Contracting Officer , on estimates of work accomplished which meets the standards of quality established under the contract , as approved by the Contracting Officer .
(1) The Contractor ’s request for progress payments shall include the following substantiation:
(i) An itemization of the amounts requested, related to the various elements of work required by the contract covered by the payment requested.
(ii) A listing of the amount included for work performed by each subcontractor under the contract .
(iii) A listing of the total amount of each subcontract under the contract .
(iv) A listing of the amounts previously paid to each such subcontractor under the contract .
(v) Additional supporting data in a form and detail required by the Contracting Officer .
(2) In the preparation of estimates, the Contracting Officer may authorize material delivered on the site and preparatory work done to be taken into consideration. Material delivered to the Contractor at locations other than the site also may be taken into consideration if-
(i) Consideration is specifically authorized by this contract ; and
(ii) The Contractor furnishes satisfactory evidence that it has acquired title to such material and that the material will be used to perform this contract .
140L1722Q0009 Hill 71 Tower Reinforcement Page 9 of 32
(c) Contractor certification. Along with each request for progress payments, the Contractor shall furnish the following certification, or payment shall not be made : (However, if the Contractor elects to delete paragraph (c)(4) from the certification, the certification is still acceptable.)
I hereby certify, to the best of my knowledge and belief, that-
(1) The amounts requested are only for performance in accordance with the specifications, terms, and conditions of the contract ;
(2) All payments due to subcontractors and suppliers from previous payments received under the contract have been made , and timely payments will be made from the proceeds of the payment covered by this certification, in accordance with subcontract agreements and the requirements of Chapter 39 of Title 31, United States Code;
(3) This request for progress payments does not include any amounts which the prime contractor intends to withhold or retain from a subcontractor or supplier in accordance with the terms and conditions of the subcontract ; and
(4) This certification is not to be construed as final acceptance of a subcontractor ’s performance.
__________________________________________________ (Name)
__________________________________________________ (Title)
__________________________________________________ (Date)
(d) Refund of unearned amounts. If the Contractor , after making a certified request for progress payments, discovers that a portion or all of such request constitutes a payment for performance by the Contractor that fails to conform to the specifications, terms, and conditions of this contract (hereinafter referred to as the "unearned amount"), the Contractor shall -
(1) Notify the Contracting Officer of such performance deficiency; and
(2) Be obligated to pay the Government an amount (computed by the Contracting Officer in the manner provided in paragraph (j) of this clause) equal to interest on the unearned amount from the 8 thday after the date of receipt of the unearned amount until-
(i) The date the Contractor notifies the Contracting Officer that the performance deficiency has been corrected; or
(ii) The date the Contractor reduces the amount of any subsequent certified request for progress payments by an amount equal to the unearned amount.
(e) Retainage. If the Contracting Officer finds that satisfactory progress was achieved during any period for which a progress payment is to be made , the Contracting Officer shall authorize payment to be made in full. However, if satisfactory progress has not been made , the Contracting Officer may retain a maximum of 10 percent of the amount of the payment until satisfactory progress is achieved. When the work is substantially complete, the Contracting Officer may retain from previously withheld funds and future progress payments that amount the Contracting Officer considers adequate for protection of the Government and shall release to the Contractor all the remaining withheld funds. Also, on completion and acceptance of each
140L1722Q0009 Hill 71 Tower Reinforcement Page 10 of 32 separate building, public work, or other division of the contract , for which the price is stated separately in the contract , payment shall be made for the completed work without retention of a percentage.
(f) Title, liability, and reservation of rights. All material and work covered by progress payments made shall , at the time of payment, become the sole property of the Government, but this shall not be construed as-
(1) Relieving the Contractor from the sole responsibility for all material and work upon which payments have been made or the restoration of any damaged work; or
(2) Waiving the right of the Government to require the fulfillment of all of the terms of the contract .
(g) Reimbursement for bond premiums. In making these progress payments, the Government shall , upon request, reimburse the Contractor for the amount of premiums paid for performance and payment bonds (including coinsurance and reinsurance agreements, when applicable) after the Contractor has furnished evidence of full payment to the surety . The retainage provisions in paragraph (e) of this clause shall not apply to that portion of progress payments attributable to bond premiums.
(h) Final payment. The Government shall pay the amount due the Contractor under this contract after-
(1) Completion and acceptance of all work;
(2) Presentation of a properly executed voucher; and
(3) Presentation of release of all claims against the Government arising by virtue of this contract , other than claims, in stated amounts, that the Contractor has specifically excepted from the operation of the release. A release may also be required of the assignee if the Contractor ’s claim to amounts payable under this contract has been assigned under the Assignment of Claims Act of1940 ( 31 U.S.C.3727 and 41 U.S.C.6305).
(i) Limitation because of undefinitized work. Notwithstanding any provision of this contract , progress payments shall not exceed 80 percent on work accomplished on undefinitized contract actions. A "contract action" is any action resulting in a contract , as defined in FAR subpart 2.1, including contract modifications for additional supplies or services, but not including contract modifications that are within the scope and under the terms of the contract , such as contract modifications issued pursuant to the Changes clause, or funding and other administrative changes.
(j) Interest computation on unearned amounts. In accordance with 31 U.S.C.3903(c)(1), the amount payable under paragraph (d)(2) of this clause shall be-
(1) Computed at the rate of average bond equivalent rates of 91-day Treasury bills auctioned at the most recent auction of such bills prior to the date the Contractor receives the unearned amount; and
(2) Deducted from the next available payment to the Contractor .
(End of clause) http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 https://www.acquisition.gov/far/part-2#FAR_Subpart_2_1 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3
140L1722Q0009 Hill 71 Tower Reinforcement Page 11 of 32
F - DELIVERIES AND PERFORMANCE
52.211-10 Commencement, Prosecution, and Completion of Work. (APR 1984)
The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than Sept 30, 2022. The time stated for completion shall include final cleanup of the premises.
(End of clause)
52.242-14 Suspension of Work. (APR 1984) – IBR
52.228-1 -- Bid Guarantee (Sep 1996)
(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.
(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier’s check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds --
(1) To unsuccessful bidders as soon as practicable after the opening of bids; and
(2) To the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.
(c) The amount of the bid guarantee shall be 20% percent of the bid price or $N/A, whichever is less.
(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.
(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.
140L1722Q0009 Hill 71 Tower Reinforcement Page 12 of 32
(End of Provision) (End of Clause)
52.236-27 -- Site Visit (Construction) (Feb 1995)
(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the
Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.
(b) An organized site visit has been scheduled for
Site visit : 3 June 2022 – 11:00 AM
Participants will meet at – work site
52.252-2 Clauses Incorporated by Reference. (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this address: www.aquistions.gov .
52.216-1 Type of Contract. (APR 1984)
The Government contemplates award of a Firm-Fixed Price contract resulting from this solicitation. (End of provision)
52.219-6 Notice of Total Small Business Set-Aside. (NOV 2020) - IBR
52.219-14 Limitations on Subcontracting. (SEP 2021) - IBR
52.222-3 Convict Labor. (JUN 2003) - IBR
52.222-6 Construction Wage Rate Requirements. (Aug 2018) - IBR
52.222-7 Withholding of Funds. (MAY 2014) - IBR
52.222-8 Payrolls and Basic Records. (JUL 2021) - IBR
52.222-9 Apprentices and Trainees. (JUL 2005) - IBR
52.222-10 Compliance with Copeland Act Requirements. (FEB 1988) - IBR
52.222-11 Subcontracts (Labor Standards). (MAY 2014) - IBR
52.222-12 Contract Termination - Debarment. (MAY 2014) - IBR
52.222-13 Compliance with Construction Wage Rate Requirements and Related Regulations. (MAY 2014) http://www.aquistions.gov/
140L1722Q0009 Hill 71 Tower Reinforcement Page 13 of 32
All rulings and interpretations of the Construction Wage Rate Requirements and related statutes contained in 29 CFR parts 1, 3, and 5 are hereby incorporated by reference in this contract.
52.222-14 Disputes Concerning Labor Standards. (FEB 1988) - IBR
52.222-15 Certification of Eligibility. (MAY 2014) – IBR
52.222-16 Approval of Wage Rates (May 2014) – IBR
52.222-20 Contracts for Materials, Supplies, Articles, and Equipment (June 2020) - IBR
52.222-21 Prohibition of segregated facilities. (APR 2015)
52.222-26 Equal Opportunity. (SEP 2016)
52.223-1 -- Biobased Product Certification. (May 2012)
As required by the Farm Security and Rural Investment Act of 2002 and the Energy Policy Act of 2005 (7 U.S.C.
8102(c)(3)), the offeror certifies, by signing this offer, that biobased products (within categories of products listed by the
United States Department of Agriculture in 7 CFR part 3201, subpart B) to be used or delivered in the performance of the contract, other than biobased products that are not purchased by the offeror as a direct result of this contract, will comply with the applicable specifications or other contractual requirements.
(End of provision)
52.223-2 -- Affirmative Procurement of Biobased Products Under Service And Construction Contracts. (Sep 2013)
(a) In the performance of this contract, the contractor shall make maximum use of biobased products that are United
States Department of Agriculture (USDA)-designated items unless—
(1) The product cannot be acquired—
(i) Competitively within a time frame providing for compliance with the contract performance schedule;
(ii) Meeting contract performance requirements; or
(iii) At a reasonable price.
(2) The product is to be used in an application covered by a USDA categorical exemption (see 7 CFR 3201.3(e)). For example, all USDA-designated items are exempt from the preferred procurement requirement for the following:
(i) Spacecraft system and launch support equipment.
(ii) Military equipment, i.e., a product or system designed or procured for combat or combat-related missions.
(b) Information about this requirement and these products is available at http://www.biopreferred.gov .
(c) In the performance of this contract, the Contractor shall—
(1) Report to http://www.sam.gov , with a copy to the Contracting Officer, on the product types and dollar value of any
USDA-designated biobased products purchased by the Contractor during the previous Government fiscal year, between
October 1 and September 30; and http://www.biopreferred.gov/ http://www.sam.gov/
140L1722Q0009 Hill 71 Tower Reinforcement Page 14 of 32
(2) Submit this report not later than—
(i) October 31 of each year during contract performance; and
(ii) At the end of contract performance.
52.223-6 Drug-Free Workplace. (MAY 2001) - IBR
52.225-9 Buy American - Construction Materials. (Feb 2021)
Definitions. As used in this clause—
Commercially available off-the-shelf (COTS) item—
(1) Means any item of supply (including construction material) that is–
(i) A commercial item (as defined in paragraph (1) of the definition at Federal Acquisition
Regulation (FAR) 2.101);
(ii) Sold in substantial quantities in the commercial marketplace; and
(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and
(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.
"Construction material" means an article, material, or supply brought to the construction site by the
Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.
Cost of components means—
(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or
(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.
Domestic construction material means—
(1) For construction material that does not consist wholly or predominantly of iron or steel or a combination of both-
(i) An unmanufactured construction material mined or produced in the United States; or https://www.acquisition.gov/far/part-2#FAR_2_101
140L1722Q0009 Hill 71 Tower Reinforcement Page 15 of 32
(ii) A construction material manufactured in the United States, if–
(A) The cost of its components mined, produced, or manufactured in the United States exceeds
55 percent of the cost of all its components. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic. Components of unknown origin are treated as foreign; or
(B) The construction material is a COTS item; or
(2) For construction material that consists wholly or predominantly of iron or steel or a combination of both, a construction material manufactured in the United States if the cost of foreign iron and steel constitutes less than 5 percent of the cost of all components used in such construction material. The cost of foreign iron and steel includes but is not limited to the cost of foreign iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the construction material and a good faith estimate of the cost of all foreign iron or steel components excluding COTS fasteners. Iron or steel components of unknown origin are treated as foreign. If the construction material contains multiple components, the cost of all the materials used in such construction material is calculated in accordance with the definition of "cost of components".
Fastener means a hardware device that mechanically joins or affixes two or more objects together.
Examples of fasteners are nuts, bolts, pins, rivets, nails, clips, and screws.
Foreign construction material means a construction material other than a domestic construction material.
Foreign iron and steel means iron or steel products not produced in the United States. Produced in the
United States means that all manufacturing processes of the iron or steel must take place in the United States, from the initial melting stage through the application of coatings, except metallurgical processes involving refinement of steel additives. The origin of the elements of the iron or steel is not relevant to the determination of whether it is domestic or foreign.
Predominantly of iron or steel or a combination of both means that the cost of the iron and steel content exceeds 50 percent of the total cost of all its components. The cost of iron and steel is the cost of the iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the product and a good faith estimate of the cost of iron or steel components excluding COTS fasteners.
Steel means an alloy that includes at least 50 percent iron, between 0.02 and 2 percent carbon, and may include other elements.
"United States" means the 50 States, the District of Columbia, and outlying areas.
(b) Domestic preference.
(1) This clause implements 41 U.S.C.chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the domestic content test of the Buy American statute is waived for construction material that is a COTS item, except that for construction material that consists wholly or predominantly of iron or steel or a combination of both, the domestic content test is applied only to the iron and steel content of the construction materials, excluding COTS fasteners. (See FAR 12.505(a)(2)). The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.
(2) This requirement does not apply to information technology that is a commercial item or to the construction materials or components listed by the Government as follows:
http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 https://www.acquisition.gov/far/part-12#FAR_12_505
140L1722Q0009 Hill 71 Tower Reinforcement Page 16 of 32
________________________________________________[Contracting Officer to list applicable excepted materials or indicate "none"]
(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that-
(i) The cost of domestic construction material would be unreasonable. The cost of a particular domestic construction material subject to the requirements of the Buy American statute is unreasonable when the cost of such material exceeds the cost of foreign material by more than 20 percent;
(ii) The application of the restriction of the Buy American statute to a particular construction material would be impracticable or inconsistent with the public interest; or
(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.
(c) Request for determination of inapplicability of the Buy American statute.
(1)
(i) Any Contractor request to use foreign construction material in accordance with paragraph (b)(3) of this clause shall include adequate information for Government evaluation of the request, including-
(A) A description of the foreign and domestic construction materials;
(B) Unit of measure;
(C) Quantity;
(D) Price;
(E) Time of delivery or availability;
(F) Location of the construction project;
(G) Name and address of the proposed supplier; and
(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.
(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.
(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).
(iv) Any Contractor request for a determination submitted after contract award shall explain why the
Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the Contracting
Officer need not make a determination.
140L1722Q0009 Hill 71 Tower Reinforcement Page 17 of 32
(2) If the Government determines after contract award that an exception to the Buy American statute applies and the Contracting Officer and the Contractor negotiate adequate consideration, the Contracting Officer will modify the contract to allow use of the foreign construction material. However, when the basis for the exception is the unreasonable price of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(3)(i) of this clause.
(3) Unless the Government determines that an exception to the Buy American statute applies, use of foreign construction material is noncompliant with the Buy American statute.
(d) Data. To permit evaluation of requests under paragraph (c) of this clause based on unreasonable cost, the Contractor shall include the following information and any applicable supporting data based on the survey of suppliers:
Foreign and Domestic Construction Materials Price Comparison
Construction Material
Description Unit of
Measure Quantity Price
(dollars)*
Item1:
Foreign construction material
Domestic construction
Item2:
Foreign construction
Domestic construction
140L1722Q0009 Hill 71 Tower Reinforcement Page 18 of 32
[* Include all delivery costs to the construction site and any applicable duty (whether or not a duty-free entry certificate is issued)].
[List name, address, telephone number, and contact for suppliers surveyed. Attach copy of response; if oral, attach summary.]
[Include other applicable supporting information.]
52.225-10 Notice of Buy American Requirement - Construction Materials. (MAY 2014)
(a) Definitions. "Commercially available off-the-shelf (COTS) item," "construction material," "domestic construction material," and "foreign construction material," as used in this provision, are defined in the clause of this solicitation entitled "Buy American-Construction Materials" (Federal Acquisition Regulation (FAR) clause 52.225-9).
(b) Requests for determinations of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of the clause at FAR 52.225-9 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American statute before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.
140L1722Q0009 Hill 71 Tower Reinforcement Page 19 of 32
(c) Evaluation of offers. (1) The Government will evaluate an offer requesting exception to the requirements of the Buy
American statute, based on claimed unreasonable cost of domestic construction material, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(3)(i) of the clause at FAR 52.225-9.
(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.
(d) Alternate offers. (1) When an offer includes foreign construction material not listed by the Government in this solicitation in paragraph (b)(2) of the clause at FAR 52.225-9, the offeror also may submit an alternate offer based on use of equivalent domestic construction material.
(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of the clause at FAR
52.225-9 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.
(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of the clause at FAR 52.225-9 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic construction material, and the offeror shall be required to furnish such domestic construction material. An offer based on use of the foreign construction material for which an exception was requested-
(i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or
(ii) May be accepted if revised during negotiations.
52.225-13 - Restrictions on Certain Foreign Purchases. (FEB 2021) - IBR
52.227-4 - Patent Indemnity--Construction Contracts. (DEC 2007) - IBR
52.228-15 - Performance and Payment Bonds – Construction (June 2020) - IBR
52.232-23 Assignment of Claims. (MAY 2014) - IBR
52.232-27 Prompt payment for construction contracts. (Jan 2017) - IBR
52.232-33 Payment by Electronic Funds Transfer - System for Award Management. (Oct 2018) - IBR
52.233-1 Disputes. (MAY 2014) - IBR
52.233-3 Protest after Award. (AUG 1996) - IBR
52.236-2 Differing Site Conditions. (APR 1984) - IBR
52.-236-3 – Site Investigations and Conditions Affecting Work – (Apr 1984) - IBR
52.236-5 Material and Workmanship. (APR 1984)
(a) All equipment, material, and articles incorporated into the work covered by this contract shall be new and of the most suitable grade for the purpose intended, unless otherwise specifically provided in this contract. References in the
140L1722Q0009 Hill 71 Tower Reinforcement Page 20 of 32 specifications to equipment, material, articles, or patented processes by trade name, make, or catalog number, shall be regarded as establishing a standard of quality and shall not be construed as limiting competition. The Contractor may, at its option, use any equipment, material, article, or process that, in the judgment of the Contracting Officer, is equal to that named in the specifications, unless otherwise specifically provided in this contract.
(b) The Contractor shall obtain the Contracting Officer's approval of the machinery and mechanical and other equipment to be incorporated into the work. When requesting approval, the Contractor shall furnish to the Contracting
Officer the name of the manufacturer, the model number, and other information concerning the performance, capacity, nature, and rating of the machinery and mechanical and other equipment. When required by this contract or by the
Contracting Officer, the Contractor shall also obtain the Contracting Officer's approval of the material or articles which the Contractor contemplates incorporating into the work. When requesting approval, the Contractor shall provide full information concerning the material or articles. When directed to do so, the Contractor shall submit samples for approval at the Contractor's expense, with all shipping charges prepaid. Machinery, equipment, material, and articles that do not have the required approval shall be installed or used at the risk of subsequent rejection.
(c) All work under this contract shall be performed in a skillful and workmanlike manner. The Contracting Officer may require, in writing, that the Contractor remove from the work any employee the Contracting Officer deems incompetent, careless, or otherwise objectionable.
52.236-7 Permits and Responsibilities. (NOV 1991)
The Contractor shall, without additional expense to the Government, be responsible for obtaining any necessary licenses and permits, and for complying with any Federal, State, and municipal laws, codes, and regulations applicable to the performance of the work. The Contractor shall also be responsible for all damages to persons or property that occur as a result of the Contractor's fault or negligence. The Contractor shall also be responsible for all materials delivered and work performed until completion and acceptance of the entire work, except for any completed unit of work which may have been accepted under the contract.
52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements. (APR 1984)
(a) The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work site, which are not to be removed and which do not unreasonably interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so, and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workmen, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by the Contracting Officer.
(b) The Contractor shall protect from damage all existing improvements and utilities (1) at or near the work site, and (2) on adjacent property of a third party, the locations of which are made known to or should be known by the Contractor.
The Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work.
If the Contractor fails or refuses to repair the damage promptly, the Contracting Officer may have the necessary work performed and charge the cost to the Contractor.
52.236-10 Operations and Storage Areas. (APR 1984)
(a) The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.
140L1722Q0009 Hill 71 Tower Reinforcement Page 21 of 32
(b) Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the approval of the Contracting Officer and shall be built with labor and materials furnished by the Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the Contractor and shall be removed by the Contractor at its expense upon completion of the work. With the written consent of the Contracting
Officer, the buildings and utilities may be abandoned and need not be removed.
(c) The Contractor shall, under regulations prescribed by the Contracting Officer, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the Contracting Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.
52.236-12 Cleaning Up. (APR 1984)
The Contractor shall at all times keep the work area, including storage areas, free from accumulations of waste materials.
Before completing the work, the Contractor shall remove from the work and premises any rubbish, tools, scaffolding, equipment, and materials that are not the property of the Government. Upon completing the work, the Contractor shall leave the work area in a clean, neat, and orderly condition satisfactory to the Contracting Officer.
52.236-13 Accident Prevention. (NOV 1991) - IBR
52.236-17 Layout of Work (Apr 1984) - IBR
52.236-26 Preconstruction Conference. (FEB 1995) - IBR
52.236-27 Site Visit (Construction) Feb 1995)
(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the
Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.
52.243-5 Changes and Changed Conditions. (APR 1984) – IBR
52.243-7 Notification of Changes. (JAN 2017)
(a) Definitions. "Contracting Officer," as used in this clause, does not include any representative of the Contracting Officer.
"Specifically Authorized Representative (SAR)," as used in this clause, means any person the Contracting Officer has so designated by written notice (a copy of which shall be provided to the Contractor) which shall refer to this paragraph and shall be issued to the designated representative before the SAR exercises such authority.
(b) Notice. The primary purpose of this clause is to obtain prompt reporting of Government conduct that the Contractor considers to constitute a change to this contract. Except for changes identified as such in writing and signed by the Contracting Officer, the Contractor shall notify the Administrative Contracting Officer in writing promptly, within ______ (to be negotiated) calendar days from the date that the Contractor identifies any Government conduct (including actions, inactions, and written or oral communications) that the Contractor regards as a change to the contract terms and conditions. On the basis of the most accurate information available to the Contractor, the notice shall state-
(1) The date, nature, and circumstances of the conduct regarded as a change;
140L1722Q0009 Hill 71 Tower Reinforcement Page 22 of 32
(2) The name, function, and activity of each Government individual and Contractor official or employee involved in or knowledgeable about such conduct;
(3) The identification of any documents and the substance of any oral communication involved in such conduct;
(4) In the instance of alleged acceleration of scheduled performance or delivery, the basis upon which it arose;
(5) The particular elements of contract performance for which the Contractor may seek an equitable adjustment under this clause, including-
(i) What line items have been or may be affected by the alleged change;
(ii) What labor or materials or both have been or may be added, deleted, or wasted by the alleged change;
(iii) To the extent practicable, what delay and disruption in the manner and sequence of performance and effect on continued performance have been or may be caused by the alleged change;
(iv) What adjustments to contract price, delivery schedule, and other provisions affected by the alleged change are estimated; and
(6) The Contractor’s estimate of the time by which the Government must respond to the Contractor’s notice to minimize cost, delay or disruption of performance.
(c) Continued performance. Following submission of the notice required by paragraph (b) of this clause, the Contractor shall diligently continue performance of this contract to the maximum extent possible in accordance with its terms and conditions as construed by the Contractor, unless the notice reports a direction of the Contracting Officer or a communication from a SAR of the Contracting Officer, in either of which events the Contractor shall continue performance; provided, however, that if the Contractor regards the direction or communication as a change as described in paragraph (b) of this clause, notice shall be given in the manner provided. All directions, communications, interpretations, orders and similar actions of the SAR shall be reduced to writing promptly and copies furnished to the Contractor and to the Contracting Officer. The Contracting Officer shall promptly countermand any action which exceeds the authority of the SAR.
(d) Government response. The Contracting Officer shall promptly, within _____ (to be negotiated) calendar days after receipt of notice, respond to the notice in writing. In responding, the Contracting Officer shall either-
(1) Confirm that the conduct of which the Contractor gave notice constitutes a change and when necessary direct the mode of further performance;
(2) Countermand any communication regarded as a change;
(3) Deny that the conduct of which the Contractor gave notice constitutes a change and when necessary direct the mode of further performance; or
(4) In the event the Contractor’s notice information is inadequate to make a decision under paragraphs (d)(1), (2), or (3) of this clause, advise the Contractor what additional information is required, and establish the date by which it should be furnished and the date thereafter by which the Government will respond.
(e) Equitable adjustments.
(1) If the Contracting Officer confirms that Government conduct effected a change as alleged by the Contractor, and the conduct causes an increase or decrease in the Contractor’s cost of, or the time required for, performance of any part of…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .