This solicitation is for a 2023 USFO Conifer Mastication project requiring mastication services to treat 463 acres across two units located in Fremont County, Idaho. Services include complete removal of juniper and lodgepole pine trees from designated treatment areas using a tracked excavator or similar equipment. The contractor must furnish all labor, equipment, supervision and incidentals to treat areas in accordance with detailed specifications by December 31, 2023. Quotes are due by July 5 and the contract is set-aside for small business. The Bureau of Land Management Upper Snake Field Office will administer the contract.

View the file

Other files for this federal contract opportunity

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SEE ADDENDUMIS CHECKED

CODE 18a. PAYMENT WILL BE MADE BY

CODE

FACILITYCODE

17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT SUCH ADDRESS IN OFFER

OFFEROR

LDF

IDAHO FALLS ID 83401

1405 HOLLIPARK DR.

BLM ID IDAHO FALLS DO (IDI00)

0004276376 CODE 16. ADMINISTERED BYCODE

X

X

X

115310

SIZE STANDARD:

100.00 % FOR:SET ASIDE:UNRESTRICTED ORLDB

RFPIFB

10. THIS ACQUISITION ISCODE

RFQ

14. METHOD OF SOLICITATION

13b. RATING

NAICS:

SMALL BUSINESS

07/05/2023 1500 MD

06/06/2023

2083843317Nikki Bachman (No collect calls)

INFORMATION CALL:

FOR SOLICITATION 8. OFFER DUE DATE/LOCAL TIMEb. TELEPHONE NUMBER a. NAME

4. ORDER NUMBER3. AWARD/ 6. SOLICITATION

140L0723Q0007

5. SOLICITATION NUMBER

SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS 1. REQUISITION NUMBER PAGE OF

1 46 0040608760OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, & 30

TELEPHONE NO.

17a. CONTRACTOR/

IDAHO FALLS ID 83401

1405 HOLLIPARK DRIVE

BLM-ID UPPER SNAKE FIELD OFFICE (ID

15. DELIVER TO

BOISE ID 83705

3948 DEVELOPMENT AVE

9. ISSUED BY

7.

2. CONTRACT NO.

EFFECTIVE DATE

$11.5

18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a UNLESS BLOCK BELOW

ISSUE DATE

DELIVERY FOR FOB DESTINA-

TION UNLESS BLOCK IS

MARKED

11.

SEE SCHEDULEX

12. DISCOUNT TERMS

THIS CONTRACT IS A

RATED ORDER UNDER

DPAS (15 CFR 700)

13a.

SERVICE-DISABLED

VETERAN-OWNED

SMALL BUSINESS

HUBZONE SMALL

BUSINESS

8(A)

BLM ID-BOISE DIST OFC(IDB00)

WOMEN-OWNED SMALL BUSINESS

(WOSB) ELIGIBLE UNDER THE WOMEN-OWNED

SMALL BUSINESS PROGRAM

EDWOSB

24.

AMOUNT

23.

UNIT PRICE

22.

UNIT

21.

QUANTITY

20.

SCHEDULE OF SUPPLIES/SERVICES

19.

ITEM NO.

Delivery: 12/31/2023 Period of Performance: 09/25/2023 to 12/31/2023

00010 2023 USFO CONIFER MASTICATION

Product/Service Code: F006 Product/Service Description: NATURAL

RESOURCES/CONSERVATION- LAND TREATMENT PRACTICES

Continued ...

(Use Reverse and/or Attach Additional Sheets as Necessary)

HEREIN, IS ACCEPTED AS TO ITEMS:

DATED

Nikki Bachman

. YOUR OFFER ON SOLICITATION (BLOCK 5),

INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE SET FORTH

COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND DELIVER

ARE

ARE

31c. DATE SIGNED

27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA

31a. UNITED STATES OF AMERICA (SIGNATURE OF CONTRACTING OFFICER)

30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER (Type or print)

ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY ADDITIONAL

SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED.

27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1, 52.212-4. FAR 52.212-3 AND 52.212-5 ARE ATTACHED. ADDENDA

26. TOTAL AWARD AMOUNT (For Govt. Use Only)

OFFER

STANDARD FORM 1449 (REV. 2/2012)

Prescribed by GSA - FAR (48 CFR) 53.212

ARE NOT ATTACHED.

ARE NOT ATTACHED.

AUTHORIZED FOR LOCAL REPRODUCTION

PREVIOUS EDITION IS NOT USABLE

30b. NAME AND TITLE OF SIGNER (Type or print)

30a. SIGNATURE OF OFFEROR/CONTRACTOR

28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN

25. ACCOUNTING AND APPROPRIATION DATA

29. AWARD OF CONTRACT:

REF.

32e. MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE

32c. DATE 32b. SIGNATURE OF AUTHORIZED GOVERNMENT REPRESENTATIVE

ACCEPTED, AND CONFORMS TO THE CONTRACT, EXCEPT AS NOTED:

32a. QUANTITY IN COLUMN 21 HAS BEEN

RECEIVED INSPECTED

40. PAID BY39. S/R VOUCHER NUMBER38. S/R ACCOUNT NUMBER

37. CHECK NUMBER

FINALPARTIAL

36. PAYMENT

FINALPARTIAL

35. AMOUNT VERIFIED

CORRECT FOR

34. VOUCHER NUMBER33. SHIP NUMBER

COMPLETE

32g. E-MAIL OF AUTHORIZED GOVERNMENT REPRESENTATIVE

42d. TOTAL CONTAINERS42c. DATE REC'D (YY/MM/DD)

42b. RECEIVED AT (Location)

42a. RECEIVED BY (Print)

41c. DATE41b. SIGNATURE AND TITLE OF CERTIFYING OFFICER

41a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAYMENT

STANDARD FORM 1449 (REV. 2/2012) BACK

24.

AMOUNT

23.

UNIT PRICE

22.

UNIT

21.

QUANTITY

20.

SCHEDULE OF SUPPLIES/SERVICES

19.

ITEM NO.

32f. TELEPHONE NUMBER OF AUTHORIZED GOVERNMENT REPRESENTATIVE

32d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT REPRESENTATIVE

46 2 of

SOLICITATION NO: 140L0723Q0007

TITLE: USFO Conifer Mastication Page 3

INFORMATION TO PROSPECTIVE QUOTERS

This is a combined Synopsis/Solicitation for commercial items prepared in accordance with the format in Subpart 12.6, as supplemented with additional information included in this notice. This announcement constitutes the only solicitation; proposals are being requested and a written solicitation will not be issued. Firm, fixed-price quotes are requested under Request for Quotation (RFQ) Solicitation number 140L0723Q0007. This document incorporates provisions and clauses which are in effect through Federal Acquisition Regulations 2022-08. This solicitation is set-aside for small business under North American Industry Classification System (NAICS) code 115310. The Small Business Annual Receipts for the preceding three (3) fiscal years does not exceed $34 Million.

Site Visit:

(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.

(b) An organized site visit has been scheduled for--

Date: June 21, 2023 Time: 10:00 am Meeting Place: Island Park Ranger Station (3726 US-20, Island Park, ID

83429) Meet in the parking lot. Tour will consist of visiting both treatment areas, please allow for up to three hours of travel and discussions.

Point of Contact for Site Visit: Ben Dyer, 208-524-7534 or bdyer@blm.gov

Questions Due Date: June 27, 2023 by 3:00 pm, Mountain Time

Due Date: July 5, 3:00 pm Mountain Time. Quotes will be accepted via Email at nbachman@blm.gov .

Offerors must be registered and active in the System for Award Management (SAM) database found at https://www.sam.gov.

In accordance with this Solicitation Section 4 - Solicitation Provisions

See FAR 52.212-2 Evaluation - Commercial Items

The overall proposal shall consist of a completed Standard Form 1449, completed Bid Schedule, and a detailed work plan that demonstrates the capability to meet the technical aptitude of the Statement of work.

To expedite the handling of your quotation, please check the following items:

❏ Is the unit price legible?

❏ Is the extended price correct?

❏ Have you initialed any changes or erasures?

NOTE: SUBMIT ONLY REQUESTED ITEMS ABOVE, NOT THE ENTIRE SOLICITATION

mailto:bdyer@blm.gov mailto:nbachman@blm.gov https://www.sam.gov/

TITLE: USFO Conifer Mastication Page 4

TABLE OF CONTENTS

Section 1: Solicitation/Contract Form See Standard Form 1449

Section 2: Contract Clauses 16

Section 3: List of Documents, Exhibits, and Other Attachments 30

Section 4: Solicitation Provisions 31

TITLE: USFO Conifer Mastication Page 5

SECTION 1: BID SCHEDULE

Offerors are to complete Block 17a and blocks 30 - 31 of the SF-1449.

BID SCHEDULE

2023 USFO CONIFER MASTICATION

Item

no. Item Description

Estimated Quantity*

Unit of Measure

Unit Price Total

0001 Cedar Hollow Juniper Mastication 326 Ac. $ $

0002 Boundary Lodgepole Mastication 137 Ac. $ $

TOTAL (ALL OR NONE) $

*GIS Calculated Quantity

PERIOD OF PERFORMANCE: 92 working days ESTIMATED START DATE: September 25, 2023 TOTAL ESTIMATED ACRES: 463 ac.

• The treatment may coincide with early snow fall which may result in roads becoming impassable and the backcountry inaccessible due to muddy, wet, or snow-covered conditions.

• Contractor will be required to start work within three days after being notified by the Contracting Officer Representative (COR).

Note: This Solicitation is “All or None”

TITLE: USFO Conifer Mastication Page 6

DESCRIPTION/SPECIFICATIONS/WORK STATEMENT

See Section J for additional attachments to include project specifications and drawings.

DETAILED SPECIFICATIONS

(MASTICATION/GRINDING)

Item 0001 – Cedar Hollow Juniper Mastication

1. Approximate Acreage: 326 acres

2. Location of Work Site as shown on Work Location Maps: Project area is located in Fremont County, Idaho approximately four miles northwest of Ashton, Idaho (T9N R42E Sec. 17, 18, 20 & 21). Access is made by way of the US 20 Frontage Road and unimproved two-track roads (see Location Map). The treatment will be implemented on federal land administered by the Bureau of Land Management’s (BLM) Idaho Falls District (IFD), Upper Snake Field Office (USFO) (see Unit Maps); however, private land is adjacent to but outside the treatment area and must be traversed to access the treatment unit. Elevations at the treatment site range from 5,200 feet to 5,400 feet above sea level.

3. Scope of Work: The objective of the treatment is to completely remove juniper from within the designated treatment unit that has encroached into the sagebrush steppe.

4. Detailed Unit Information: Species of trees to be cut within the Cedar Hollow unit include Utah juniper (Juniperus osteosperma), Rocky Mountain juniper (Juniperus scopulorum) and western juniper (Juniperus occidentalis). Juniper density in the area ranges from 22 stems/acre to 47 stems/acre, while the diameter at breast height (DBH) of mature junipers ranges from 7” to 14”. Because of the scattered nature of the vegetation, not all acres within the established boundaries of the unit will require the same amount of labor to achieve the specifications outlined below.

Item 0002 – Boundary Lodgepole Mastication

1. Approximate Acreage: 137 acres

2. Location of Work Site as shown on Work Location Maps: Project area is located in Fremont County, Idaho approximately 14 miles west/southwest of Island Park, Idaho (T13N R41E Sec. 31-34). Access is made by way of the Yale-Kilgore (A2) Road, Old Kilgore Road, Green Canyon Road (FS 167) and unimproved two-track roads. The treatment will be implemented on federal land administered by the BLM’s IFD, USFO (see Unit Maps). Elevations at the treatment site range from 6,300 feet to 6,400 feet above sea level.

3. Scope of Work: The primary objective of the treatment is to remove lodgepole pine (Pinus contorta) that have encroached into the adjacent aspen (Populus tremuloides) stands and are outcompeting the aspens for resources and nutrients. Additionally, the treatment will reduce fuel loadings and extreme fire danger that exist around the community of Island Park, as well as improve forest health and wildlife habitat.

4. Detailed Unit Information: The Boundary unit consists of even-aged, densely stocked patches of lodgepole pine with intermixed aspen and occasional Douglas fir trees and brush. Aspen is also intermixed within the lodgepole pine stands but WILL NOT be impacted unless otherwise directed by the Contracting Officer's Representative (COR) or Project Inspector (PI). Lodgepole pine density within the unit ranges from 50 stems/acre to 90 stems/acre, while the diameter at breast height (DBH) of mature lodgepoles range from 3” to 10”.

TITLE: USFO Conifer Mastication Page 7

1.0 GENERAL

1.1 Introduction: The BLM USFO is soliciting fuels management services to treat woody vegetation to reduce the risk of wildland fires while promoting the expansion of aspen and sagebrush steppe communities.

1.2 Background: The Cedar Hollow treatment unit consists of juniper woodlands and sagebrush steppe habitat, with ≤20 percent juniper canopy cover and ≥15 percent sagebrush canopy cover. Juniper encroachment reduces the quality and quantity of sagebrush obligate habitat through the competition of limited resources and direct removal of sagebrush steppe vegetation. In contrast, the Boundary treatment unit is comprised of even-aged, densely stocked patches of lodgepole pine with intermixed aspen. Aspen stands within the project area are categorized as even aged and decadent, are being encroached upon by adjacent conifer species, and lack the level of reproduction necessary to maintain healthy clones. Not only will the mechanical treatment remove conifers that compete with aspens for available nutrients and resources, but it will also provide the disturbance necessary to promote aspen suckering and increase age class diversity. Fuel loadings within the two units range from less than ½ ton per acre to as high as 20 tons or more per acre.

1.3 Purpose: The purpose of these treatments is to reduce fuel loadings and future wildland fire severity, expand sagebrush steppe habitat, reduce soil erosion, and promote aspen health and expansion. Treatments that focus on reducing fuel loads and increasing crown spacing within encroached shrubland and dense forest/woodland vegetation types have been shown to reduce the severity of wildland fire as well as improve shrubland and woodland health and wildlife habitat. In addition, grinding may enhance moisture retention for vegetative development, create microsites for natural seed recruitment, and aid in the control of noxious weeds.

1.4 Scope of Work: The grinding units total 463 acres (Cedar Hollow 326 acres, and Boundary 137 acres). The objective of the treatments is to remove juniper and lodgepole pine within the designated treatment areas that have encroached into the sagebrush steppe and aspen woodlands. All designated trees will be completely severed, ground up, with the remaining stump no taller than six inches above ground level on the uphill side and no live limbs remaining. The Contractor will furnish all tools, labor, supervision, equipment, materials, supplies, transportation, training, and incidentals necessary to accomplish the removal of trees and treatment of slash in accordance with the specifications provided.

2.0 LOCATION

2.1 Location of Project Areas: Treatment units are located approximately 14 miles west/southwest of Island Park, Idaho (Boundary) and four miles northwest of Ashton, Idaho (Cedar Hollow). All work will be performed on land administered by the Bureau of Land Management. General-purpose maps will be included. Once the project is accepted by the contractor, maps will be provided by and agreed upon by BLM and the contractor. Refer to the treatment unit imagery and land status maps for general location and site conditions of the individual treatment areas.

2.2 Project Boundary Marking: The location and access to the areas are shown on the project location and treatment unit maps. The treatment units may be identifiable by flagging, paint on trees, or a combination of both. Treatment units may also be marked by changes in vegetation, roads, topography changes, or streams.

If these types of project area boundaries are used, the contractor will be notified. All areas may be flagged in colored flagging and an Avenza map file provided prior to starting implementation of the project.

2.3 Access: Legal public access to the project area will be identified on the map prior to the contractor starting the implementation phase. Seasonal road closures may exist (contractor will be notified of closures upon award). Contractor will assume responsibility for any additional access if desired. If roads or any type of access become subject to damage, because of adverse weather conditions or other natural and or political

TITLE: USFO Conifer Mastication Page 8 reasons, the COR will relay information to the contractor, and a Stop Work Order may be implemented by the Contracting Officer (CO) until other access can be decided.

2.4 Work Camps: Camping on agency-administered lands may be allowed through agency official approval.

Should such a work camp be authorized, the Contractor shall maintain the camp in an orderly and sanitary manner. All fire regulations and permits shall be followed. All garbage and refuse shall be removed from the camp site(s) by the Contractor and disposed of offsite before final payment is made.

3.0 EQUIPMENT

3.1 General: The Contractor shall treat designated areas in conformance with these specifications and the Detailed Specifications. Unless otherwise specified, the Contractor shall furnish all equipment, labor, supplies, and materials required to complete the job. The Contractor shall furnish properly equipped personnel experienced in operating the equipment to be used. The Contractor shall service and repair his/her equipment as necessary to maintain satisfactory progress on work. Contractor is responsible for all costs incidental to equipment move-in and move-out associated with the project.

3.2 Equipment: The Contractor shall furnish sufficient equipment to satisfactorily treat the designated area(s) in the time specified as required in the Detailed Specifications.

a. Be a wheeled or tracked mounted vehicle equipped with either hydraulic or PTO driven mastication head with a minimum head lift height of 12.5’ to alter the vegetation type in accordance with the specified level of work, prescription, or as otherwise as described under specifications.

i. Preference will be given to machines with boom-mounted grinding heads that enable the operator to reach over leave trees/vegetation and vertically grind the trees to be removed.

b. Be of durable design and construction to withstand the stresses of natural obstructions within the treatment units such as rocks, stumps, dust, and the general unevenness of the land.

c. Be free of fluid leaks and have hoses in good operating condition.

d. Be equipped with a mastication head capable of performing the work described in this document.

e. Be of a quality that guarantees the contractor’s safety.

f. Meet or exceed the requirements listed under SAFETY.

g. Contractor shall insure that all equipment is power washed and free of soil, seeds, vegetative matter, or other debris that could contain noxious weed seeds prior to being transported to BLM-administered land. For purposes of this provision, equipment shall be considered debris free when a visual inspection does not disclose such material.

4.0 EXECUTION OF WORK

4.1 It shall be the responsibility of the Contractor (i.e., knowledge and experience of the crew leader) to determine the quantity of work needed to meet specifications identified in this SOW. Acreage of the units were determined by calculations based on a horizontal plane using GIS technology. The treatment units are located in areas that, during the winter months, may receive two feet or more of snow annually.

4.2 Pre-Work Conference: Prior to commencement of work, a meeting may be requested by the CO to be attended by the Contractor, the COR, and PI. The meeting will be held at the Upper Snake Field Office at a time mutually agreeable to the Contractor and the CO to discuss the work schedule and to familiarize both parties with the responsibilities of each under this contract. At this time a work schedule showing dates, locations, equipment, and employees working on this project shall be provided by the Contractor to the CO.

TITLE: USFO Conifer Mastication Page 9

4.3 Progress Reports: Contractor will provide weekly progress summaries, during treatment, to the BLM Representative (COR and/or PI). Regular communication between BLM Representatives and the Contractor is required to help alleviate any problems or potential delays.

4.4 Crew Foreman: A crew foreman must be on-site directing work at all times. This person will also serve as an on the ground contact person for the COR/PI. Failure to maintain a crew foreman will result in suspension of work until a crew foreman is provided. A maximum of five (5) days will be allowed to produce a qualified foreman. Failure to produce a qualified on-the-ground foreman within five days may result in the CO issuing a Suspend Work Order. CO and COR must be informed of any changes in Crew Foreman.

4.5 Personnel Requirements: The crew is responsible for maintaining a safe working environment following OSHA standards. The Contractor must attend the pre-work meeting and provide a written performance plan including crew size prior to beginning work.

4.6 Specifications for Treatment: Woodland Tree/Shrub Mastication

a. Cut and grind all living juniper and lodgepole pine trees, including saplings and seedlings, within the identified treatment units.

b. Any and all trees to be cut shall be completely severed, ground up, with the remaining stump no taller than six inches above ground level on the uphill side. Woody slash shall be less than 4-inches in diameter and less than 3-feet in length. No live limbs shall be left on the stump of cut trees.

c. Chip depth will be even with the normal plane of the ground surface and spread as evenly as possible. Average chip depth will not exceed 6-inches over the treatment area.

d. Avoidance areas (no mastication) may be identified within the treatment units and designated with flagging, i.e., cultural sites, survey monuments, leave trees, etc.

e. A tracked excavator or similar equipment with a grinding head attachment will be required to accomplish the project work effectively. This type of machine is needed due to snow depth, topography/slope, and to reduce impacts from ground disturbance.

f. Work will not begin unless the ground is dry or frozen/snow covered. Should implementation result in excessive rutting, a Stop Work Order will be issued. Work may resume only when the area has sufficiently dried out.

g. Any/all skid trails or two-track roads or any other disturbance created by equipment or vehicles maneuvering the project area will be reclaimed as a part of the site cleanup requirements.

h. Crossing perennial, intermittent, or ephemeral drainage features would be avoided unless deemed absolutely necessary. If it is deemed necessary to cross these features, crossing of drainage features with flowing water would be coordinated with the BLM. Crossing of dry drainage features would be conducted as close to 90 degrees to the long axis of the feature as possible and would minimize disturbance. Damage to drainage features may require repair at the contractor’s expense to restore natural water flow.

i. The treatment units are open to public access and will remain so during the treatment. As such, the contractor shall furnish warning signs to be placed on the roadside entrances into treatment units.

Signs shall be a minimum of 3 feet by 3 feet in dimension and shall warn of flying debris.

j. Period of performance will be 92 calendar days.

4.7 Protection of Improvements: The COR may order a cessation of work if vehicles are operated on roads within the work area when ground or weather conditions cause or lead to loss of traction. Such conditions usually develop where frozen ground is thawing, when snow is melting, and during or immediately following rainstorms. Any soil and ground disturbance caused by equipment during and after operations will be rehabilitated.

TITLE: USFO Conifer Mastication Page 10

4.8 Salvage Rights: No salvage will be allowed.

4.9 Work stoppages: The Contractor agrees to work diligently to complete the mastication treatment. The Government reserves the right to stop mastication operations at any time when conditions are considered sufficiently unfavorable to warrant stoppage. Stoppage shall continue until mastication operations are again authorized by the Government. Because of the nature of the work, any time for which work is suspended by the Government because of unsuitable conditions or phase II fire restrictions will not be counted against the contract completion time. However, no monetary compensation will be given to the Contractor by reason of such work suspension.

4.10 Notification of Cessation or Restart of work: The Contractor will notify the COR whenever he/she intends to cease operations for three or more days and will notify the COR before starting operations after a shutdown of three or more days.

4.11 Termination for convenience of the Government: Because of the nature of the work, the Contracting Officer may, by written notice to the Contractor, terminate this contract, in whole or in part, when it is in the best interest of the Government. To the extent that this contract is so terminated, the Government shall be liable only for payment in accordance with the payment provisions of this contract for work satisfactorily completed prior to the effective date of termination.

4.12 Completion of contract: The Contract will be considered completed and payment due when all areas furnished to the Contractor by the Government have been treated to the standards specified above.

4.13 Risk damages: The Contractor shall assume all risks in connection with performance of the contract and shall be liable for any or all damages to persons or property in connection with the execution of work by employees of the Contractor.

5.0 INSPECTION AND ACCEPTANCE

5.1 Inspection:

a. The Government COR/PI will make periodic inspections as a basis for acceptance and payment and recommendations for adjustments in work quality while work is in progress. The Contractor is encouraged to participate in inspections while they are being conducted.

b. As the basis for payment, inspections for compliance with specifications will be made for work units reported as completed by the contractor. All plots will be averaged together to determine payment.

c. A combination of Ocular or Physical Inspections will be made on a series of plots located at different intervals across each work unit. A sufficient number of plots will be taken to obtain at least one percent sample of the work unit.

d. The following information will be recorded for each plot inspected if more than 10 percent of the treated area has these items found in them. The treated areas will get a failing grade if:

i. Stumps taller than six inches above ground level

ii. Severed trees are not completely grinded

iii. Live limbs are left on the stump

iv. Chips not spread as evenly on the ground as possible

5.2 Determination of Work Quality Percentage:

a. Work quality percentages are derived from data developed from inspection plots. The final work quality percentage times the bid price determines the pay. A work quality percentage of 90 percent or higher will result in full payment. If any of the reasons stated above in the Inspection section part (d)

TITLE: USFO Conifer Mastication Page 11 are the primary reason for unsatisfactory work, the Contractor shall rework areas designated by the Government until satisfactory work quality is obtained.

5.3 Acceptance:

a. Satisfactory Work Quality: A minimum work quality standard of 90 percent is required.

b. Unsatisfactory Work Quality: Based on inspection results, if the work quality percentage falls below 90 percent, the CO will immediately notify the Contractor in writing and instruct the Contractor to improve the quality of the work. The contractor may ask for a meeting between themselves, CO and COR and PI to discuss a resolution. If the quality of the work is not raised to an acceptable level within two consecutive workdays after written notification or within time decided at the meeting, the CO may issue a Stop Work Order and/or Termination of Contract.

c. Final payment shall not be granted until the project is complete to the satisfactory quality standard.

Payment will be made at the unit price per treated acre specified in the Bid Schedule which is made a part hereof and shall include the cost of all work described in this paragraph and the Detailed Specifications, including any retreating, if such work is required.

6.0 GOVERNMENT FURNISHED PROPERTY

6.1 The Government will provide the following items to the Contractor:

a. Provide various USGS 7.5-minute quadrangles (1:24,000 scales) or GIS equivalent with unit boundaries clearly identified.

b. An Avenza map file will be provided that delineates the perimeter and non-treatment interior islands.

The contractor must have a smart device capable accepting and displaying Avenza map files.

c. The BLM will flag all cadastral survey monuments and other avoidance areas depicted on the Avenza treatment map.

d. A BLM Representative (COR/PI) will be available for technical guidance and when inspection is requested by the contractor. Regular communications between the BLM representatives and the contractor will alleviate any problems or delays.

e. A list of contacts, including emergency contacts, will be provided at the pre-work meeting

7.0 SAFETY

7.1 Mastication equipment must meet the following OSHA standards:

a. Protective cab glazing material.

b. Rollover protective structure (ROPS).

c. Falling object protective structure (FOPS).

7.2 It is the responsibility of the contractor to ensure for the safety of employees and general public during treatment. The treatment units will remain open to public access and, as such, the contractor shall furnish roadside warning signs to be placed at treatment unit access points. Signs shall be high visibility, with minimum dimensions of 3-feet by 3-feet, and shall warn of flying debris.

a. Should public safety become a concern, the contractor shall stop all operations and work with the COR/PI to resolve the issue.

7.3 Primarily for purposes of fire prevention and control, the Contractor shall comply with the following provisions:

TITLE: USFO Conifer Mastication Page 12

a. The Contractor shall comply with all the applicable Idaho State Fire Prevention Laws, Rules, Regulations, and Standards.

b. All equipment will have the following:

i. A serviceable chemical fire extinguisher of at least 12-pounds minimum capacity. Such fire extinguisher shall be filled and in operating condition.

ii. A shovel in good condition with not less than a three (3) foot handle and a blade not less than seven and three-quarters (7 3/4) inches wide.

c. The CO may require additional fire tools and fire equipment as the fire danger warrants.

7.4 All diesel and/or gasoline operated engines will be equipped with spark arresters.

7.5 Remove all concentrations of wood dust and debris from equipment daily.

7.6 If a fire is started or discovered, work crews will immediately notify Eastern Idaho Interagency Fire Center

(208) 524-7600. Idaho Fire Restrictions Plan will be followed.

7.7 Fuel Storage: Storage of flammables and combustibles may occur on site. Storage of flammable and combustibles shall follow State and Federal Regulations.

a. Only approved containers and portable tanks shall be used for storage and handling of flammable liquids. Approved safety cans or Department of Transportation approved containers shall be used for the handling and use of flammable liquids in quantities of 5-gallons or less, except that this shall not apply to those flammable liquid materials which are highly viscid (extremely hard to pour), which may be used and handled in original shipping containers. For quantities of one gallon or less, the original container may be used, for storage, use and handling of flammable liquids.

b. Safety can shall mean an approved container, of not more than 5-gallons capacity, having a spring-closing lid and spout cover and so designed that it will safely relieve internal pressure when subjected to fire exposure.

c. Storage areas shall be kept free of weeds, debris, and other combustible material not necessary to the storage.

d. At least one portable 12-pound (minimum) “ABC” fire extinguisher shall be located not less than 25-feet, nor more than 75-feet, from any flammable liquid storage area located outside.

e. Areas in which flammable liquids are transferred at one time, in quantities greater than 5-gallons from one tank or container to another tank or container, shall be separated from other operations by 25-feet distance or by construction having a fire resistance of at least 1-hour. Drainage or other means shall be provided to control spills. Adequate natural or mechanical ventilation shall be provided to maintain the concentration of flammable vapor at or below ten percent of the lower flammable limit.

TITLE: USFO Conifer Mastication Page 13

EVALUATION

The Government will award a contract resulting from this solicitation to the responsible offeror whose offer conforms to the terms of the solicitation and will be most advantageous to the Government, price and other factors considered. The following factors shall be used to evaluate offers:

i Technical Capability;

ii Applicant Qualifications (Prior Relevant Experience);

iii Past Performance;

iv Price.

Technical Capability, Applicant Qualifications, and Past Performance, when combined, are significantly more important than Price.

The overall proposal shall consist of a completed Standard Form 1449, completed Bid Schedule, and a detailed work plan that demonstrates the capability to meet the technical aptitude of the Statement of Work.

Failure to provide required information may result in a non-responsive quote.

Evaluation Factor No. 1: Technical Capability

1. Proposals must clearly demonstrate the ability to complete the contract within the required period of performance. This is to include a work plan, schedule, and how the Contractor will coordinate and communicate with the Government. If subcontractors will be used describe how they will be selected, their business address, corporate officers, and points of contact.

2. Describe your firm’s quality control and safety process. This should include, but is not limited to:

Inspection Method, Crew/Equipment Management, Communication Plan, Emergency Procedures, etc.

3. Describe available equipment to include type and capabilities. Attach a list of mechanical equipment that is owned by the Contractor, including make and model, to be used on the job.

Attach a list of mechanical equipment to be used on the job that shall be either rented or purchased by the Contractor.

Evaluation Factor No. 2: Applicant Qualifications

Provide prior relevant experience for each of the key personnel and crew members proposed, i.e., Contractor Representative, Equipment Operator, Mechanic, etc. Prior experience should be in performing forestry related treatments or relevant work of a similar nature and within similar budgetary and time constraints.

1. Personnel – Offeror shall provide information of key personnel and crew members. Provide relevant information as it pertains to the individuals experience, capabilities, certifications, licenses, expertise and involvement in the project and proposal.

3. Experience working in remote locations (dealing with adverse weather conditions, poor access, limited or no services, environmental hazards, etc.)

The Government will evaluate qualifications based on the extent to which the personnel meet or exceeds skills, experience, and/or education required in performing the specifications in the Statement of Work.

TITLE: USFO Conifer Mastication Page 14

Evaluation Factor No. 3: Prior Experience and Past Performance

1. Referencing the firms Past Performance information, submit a reference list with a minimum of two (2) and no more than five (5) recent and relevant projects.

**The list shall include the following valid information:

(a) Offeror’s (Company/Division) Name;

(b) Project Title and Description and State;

(c) Contracting Agency or Customer;

(d) Contract Number/Contract Value;

(e) Point of Contact’s (POC) Name/Phone/Email;

(f) Start and end date of Period of Performance (month and year).

The Government will determine whether the Offeror consistently delivered quality services in a timely manner.

Past performance will be assessed on the extent of client satisfaction, effectiveness in managing and directing resources, effectiveness in managing project time and performance schedules, reasonable and cooperative behavior, and quality of previous performance with clients.

Adequacy of Offeror's demonstrated past performance in similar contracts or projects for federal agencies and/or private organizations in terms of price control, quality of work and compliance with performance schedules. In addition to responses received the Government reserves the right to consider information obtained from any other sources when evaluating the offeror’s past performance.

Evaluation Factor No. 4: Price

1. Submit completed Bid Schedule for the list of Line Items provided in the solicitation. Price will be evaluated after evaluations of the technical proposals. Each price proposal shall be evaluated for reasonableness. An offered price that is too high or too low may indicate the offeror does not understand the requirements of the contract and may be grounds for eliminating its proposal.

2. Material unbalancing between line items may be cause for rejection of the offeror’s proposal.

Award Determination

The Government will award a contract to the Contractor(s) whose proposal: (a) conforms to the terms of the solicitation and (b) provides the best value to the Government.

Award may not necessarily be made to the Offeror(s) submitting the lowest price. Award may not be made on all items depending on availability of funds.

TITLE: USFO Conifer Mastication Page 15

ATTACHMENTS

(attached separately)

1. USFO Conifer Mastication Location Map

2. Cedar Hollow Juniper Mastication Unit Imagery Map

3. Cedar Hollow Juniper Mastication Unit Land Status Map

4. Boundary Lodgepole Mastication Unit Imagery Map

5. Boundary Lodgepole Mastication Unit Land Status Map

6. Wage Determination

TITLE: USFO Conifer Mastication Page 16

SECTION 2 - CONTRACT CLAUSES

1. 52.252-2 Clauses Incorporated by Reference (Feb 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): https://www.acquisition.gov/browse/index/far#

52.204-13 System for Award Management Maintenance (Oct 2018) 52.204-18 Commercial and Government Entity Code Maintenance (Aug 2020) 52.204-19 Incorporation by Reference of Representations and Certifications (Dec 2014) 52.212-4 Contract Terms and Conditions - Commercial Products and Commercial Services (Dec 2022) 52.215-8 Order of Precedence-Uniform Contract Format (Oct 1997) 52.223-2 Affirmative Procurement of Biobased Products under Service and Construction Contracts

(Sept 2013) 52.223-3 Hazardous Material Identification and Material Safety Data (Alt I) (Jul 1995) 52.223-6 Drug-Free Workplace (May 2001) 52.232-23 Assignment of Claims (May 2014) 52.232-39 Unenforceability of Unauthorized Obligations (Jun 2013) 52.232-40 Providing Accelerated Payments to Small Business Subcontractors (Nov 2021) 52.233-4 Applicable Law for Breach of Contract Claim (Oct 2004) 52.236-2 Differing Site Conditions (Apr 1984) 52.242-15 Stop-Work Order (Aug 1989)

2. 52.212-5 Contract Terms and Conditions Required to Implement Statutes Or Executive Orders--Commercial Products and Commercial Services (Dec 2022)

(a) The Contractor shall comply with the following Federal Acquisition Regulation (FAR) clauses, which are incorporated in this contract by reference, to implement provisions of law or Executive orders applicable to acquisitions of commercial products and commercial services:

(1) 52.203-19, Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements (JAN 2017) (section 743 of Division E, Title VII, of the Consolidated and Further Continuing Appropriations Act, 2015 (Pub.

L. 113-235) and its successor provisions in subsequent appropriations acts (and as extended in continuing resolutions)).

(2) 52.204-23, Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by Kaspersky Lab and Other Covered Entities (NOV 2021) (Section 1634 of Pub. L. 115-91).

(3) 52.204-25, Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment. (NOV 2021) (Section 889(a)(1)(A) of Pub. L. 115-232).

(4) 52.209-10, Prohibition on Contracting with Inverted Domestic Corporations (NOV 2015).

(5) 52.233-3, Protest After Award (AUG 1996) (31 U.S.C. 3553).

(6) 52.233-4, Applicable Law for Breach of Contract Claim (OCT 2004) (Public Laws 108-77 and 108-78 (19 U.S.C. 3805 note)).

(b) The Contractor shall comply with the FAR clauses in this paragraph (b) that the Contracting Officer has indicated as being incorporated in this contract by reference to implement provisions of law or Executive orders applicable to acquisitions of commercial products and commercial services:

[Contracting Officer check as appropriate.] __ (1) 52.203-6, Restrictions on Subcontractor Sales to the Government (JUN 2020), with Alternate I (NOV 2021) (41 U.S.C. 4704 and 10 U.S.C. 4655). (Over 250K) __ (2) 52.203-13, Contractor Code of Business Ethics and Conduct (NOV 2021) (41 U.S.C. 3509)).

__ (3) 52.203-15, Whistleblower Protections under the American Recovery and Reinvestment Act of 2009 https://www.acquisition.gov/browse/index/far#

TITLE: USFO Conifer Mastication Page 17

(JUN 2010) (Section 1553 of Pub. L. 111-5). (Applies to contracts funded by the American Recovery and Reinvestment Act of 2009.)

XX (4) 52.204-10, Reporting Executive Compensation and First-Tier Subcontract Awards (JUN 2020) (Pub. L. 109-282) ( 31 U.S.C. 6101 note).

__ (5) [Reserved].

__ (6) 52.204-14, Service Contract Reporting Requirements (OCT 2016) (Pub. L. 111-117, section 743 of Div. C).

__ (7) 52.204-15, Service Contract Reporting Requirements for Indefinite-Delivery Contracts (OCT 2016) (Pub. L. 111-117, section 743 of Div. C).

__ (8) 52.209-6, Protecting the Government’s Interest When Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment. (NOV 2021) (31 U.S.C. 6101 note).

__ (9) 52.209-9, Updates of Publicly Available Information Regarding Responsibility Matters (OCT 2018) (41 U.S.C. 2313).

__ (10) [Reserved].

__ (11) 52.219-3, Notice of HUBZone Set-Aside or Sole-Source Award (OCT 2021) (15 U.S.C. 657a).

__ (12) 52.219-4, Notice of Price Evaluation Preference for HUBZone Small Business Concerns (OCT 2021) (if the offeror elects to waive the preference, it shall so indicate in its offer) (15 U.S.C. 657a).

__ (13) [Reserved] XX (14) (i) 52.219-6, Notice of Total Small Business Set-Aside (NOV 2020) (15 U.S.C. 644).

__ (ii) Alternate I (MAR 2020) of 52.219-6.

__ (15) (i) 52.219-7, Notice of Partial Small Business Set-Aside (NOV 2020) (15 U.S.C. 644).

__ (ii) Alternate I (MAR 2020) of 52.219-7.

__ (16) 52.219-8, Utilization of Small Business Concerns (OCT 2022) (15 U.S.C. 637(d)(2) and (3)).

__ (17) (i) 52.219-9, Small Business Subcontracting Plan (OCT 2022) (15 U.S.C. 637(d)(4)).

__ (ii) Alternate I (NOV 2016) of 52.219-9.

__ (iii) Alternate II (NOV 2016) of 52.219-9.

__ (iv) Alternate III (JUN 2020) of 52.219-9.

__ (v) Alternate IV (SEP 2021) of 52.219-9.

__ (18) (i) 52.219-13, Notice of Set-Aside of Orders (MAR 2020) (15 U.S.C. 644(r)).

__ (ii) Alternate I (MAR 2020) of 52.219-13.

__ (19) 52.219-14, Limitations on Subcontracting (OCT 2022) (15 U.S.C. 637s).

__ (20) 52.219-16, Liquidated Damages—Subcontracting Plan (SEP 2021) (15 U.S.C. 637(d)(4)(F)(i)).

__ (21) 52.219-27, Notice of Service-Disabled Veteran-Owned Small Business Set-Aside (OCT 2022) (15 U.S.C. 657f).

XX (22) (i) 52.219-28, Post Award Small Business Program Rerepresentation (OCT 2022) (15 U.S.C. 632(a)(2)).

__ (ii) Alternate I (MAR 2020) of 52.219-28.

__ (23) 52.219-29, Notice of Set-Aside for, or Sole-Source Award to, Economically Disadvantaged Women- Owned Small Business Concerns (OCT 2022) (15 U.S.C. 637(m)).

__ (24) 52.219-30, Notice of Set-Aside for, or Sole-Source Award to, Women-Owned Small Business Concerns Eligible Under the Women-Owned Small Business Program (OCT 2022) (15 U.S.C. 637(m)).

__ (25) 52.219-32, Orders Issued Directly Under Small Business Reserves (MAR 2020) (15 U.S.C. 644(r)).

__ (26) 52.219-33, Nonmanufacturer Rule (SEP 2021) (15U.S.C. 637(a)(17)).

XX (27) 52.222-3, Convict Labor (JUN 2003) (E.O.11755).

__ (28) 52.222-19, Child Labor-Cooperation with Authorities and Remedies (DEC 2022) (E.O.13126). (Supplies) XX (29) 52.222-21, Prohibition of Segregated Facilities (APR 2015).

XX (30) (i) 52.222-26, Equal Opportunity (SEP 2016) (E.O.11246).

__ (ii) Alternate I (FEB 1999) of 52.222-26.

__ (31) (i) 52.222-35, Equal Opportunity for Veterans (JUN 2020) (38 U.S.C. 4212). (Over 250K) __ (ii) Alternate I (JUL 2014) of 52.222-35.

XX (32) (i) 52.222-36, Equal Opportunity for Workers with Disabilities (JUN 2020) (29 U.S.C. 793).

__ (ii) Alternate I (JUL 2014) of 52.222-36.

TITLE: USFO Conifer Mastication Page 18

__ (33) 52.222-37, Employment Reports on Veterans (JUN 2020) (38 U.S.C. 4212). (Over 250K) __ (34) 52.222-40, Notification of Employee Rights Under the National Labor Relations Act (DEC 2010) (E.O. 13496).

XX (35) (i) 52.222-50, Combating Trafficking in Persons (NOV 2021) (22 U.S.C. chapter 78 and E.O. 13627).

__ (ii) Alternate I (MAR 2015) of 52.222-50 (22 U.S.C. chapter 78 and E.O. 13627).

__ (36) 52.222-54, Employment Eligibility Verification (MAY 2022) . (Executive Order 12989). (Not applicable to the acquisition of commercially available off-the-shelf items or certain other types of commercial products or commercial services as prescribed in FAR 22.1803.) (Over 250K) __ (37) (i) 52.223-9, Estimate of Percentage of Recovered Material Content for EPA–Designated Items (May 2008) (42 U.S.C. 6962(c)(3)(A)(ii)). (Not applicable to the acquisition of commercially available off-the-shelf items.)

__ (ii) Alternate I (MAY 2008) of 52.223-9 (42 U.S.C. 6962(i)(2)(C)). (Not applicable to the acquisition of commercially available off-the-shelf items.)

__ (38) 52.223-11, Ozone-Depleting Substances and High Global Warming Potential Hydrofluorocarbons (Jun 2016) (E.O. 13693).

__ (39) 52.223-12, Maintenance, Service, Repair, or Disposal of Refrigeration Equipment and Air Conditioners

(JUN 2016) (E.O. 13693).

__ (40) (i) 52.223-13, Acquisition of EPEAT®-Registered Imaging Equipment (JUN 2014) (E.O.s 13423 and 13514).

__ (ii) Alternate I (OCT 2015) of 52.223-13.

__ (41) (i) 52.223-14, Acquisition of EPEAT®-Registered Televisions (JUN 2014) (E.O.s 13423 and 13514).

__ (ii) Alternate I (Jun2014) of 52.223-14.

__ (42) 52.223-15, Energy Efficiency in Energy-Consuming Products (MAY 2020) (42 U.S.C. 8259b).

__ (43) (i) 52.223-16, Acquisition of EPEAT®-Registered Personal Computer Products (OCT 2015) (E.O.s 13423 and 13514).

__ (ii) Alternate I (JUN 2014) of 52.223-16.

XX (44) 52.223-18, Encouraging Contractor Policies to Ban Text Messaging While Driving (JUN 2020) (E.O. 13513).

__ (45) 52.223-20, Aerosols (JUN 2016) (E.O. 13693).

__ (46) 52.223-21, Foams (Jun2016) (E.O. 13693).

__ (47) (i) 52.224-3 Privacy Training (JAN 2017) (5 U.S.C. 552 a).

__ (ii) Alternate I (JAN 2017) of 52.224-3.

__ (48) 52.225-1, Buy American-Supplies (NOV 2021) (41 U.S.C. chapter 83).

__ (49) (i) 52.225-3, Buy American-Free Trade Agreements-Israeli Trade Act (DEC 2022) (41 U.S.C.chapter83, 19 U.S.C. 3301 note, 19 U.S.C. 2112 note, 19 U.S.C. 3805 note, 19 U.S.C. 4001 note, Pub. L. 103-182, 108-77, 108-78, 108-286, 108-302, 109-53, 109-169, 109-283, 110-138, 112-41, 112-42, and 112-43.

__ (ii) Alternate I [Reserved].

__ (iii) Alternate II (DEC 2022) of 52.225-3.

__ (iv) Alternate III (JAN 2021) of 52.225-3.

__ (50) 52.225-5, Trade Agreements (DEC 2022) (19 U.S.C. 2501, et seq., 19 U.S.C. 3301 note).

XX (51) 52.225-13, Restrictions on Certain Foreign Purchases (FEB 2021) (E.O.’s, proclamations, and statutes administered by the Office of Foreign Assets Control of the Department of the Treasury).

__ (52) 52.225-26, Contractors Performing Private Security Functions Outside the United States (Oct 2016) (Section 862, as amended, of the National Defense Authorization Act for Fiscal Year 2008; 10 U.S.C. Subtitle A, Part V, Subpart G Note).

__ (53) 52.226-4, Notice of Disaster or Emergency Area Set-Aside (Nov2007) (42 U.S.C. 5150).

__ (54) 52.226-5, Restrictions on Subcontracting Outside Disaster or Emergency Area (Nov2007) (42 U.S.C. 5150).

__ (55) 52.229-12, Tax on Certain Foreign Procurements (FEB 2021).

__ (56) 52.232-29, Terms for Financing of Purchases of Commercial Products and Commercial Services

(NOV 2021) (41 U.S.C. 4505, 10 U.S.C. 3805).

TITLE: USFO Conifer Mastication Page 19

__ (57) 52.232-30, Installment Payments for Commercial Products and Commercial Services (NOV 2021) (41 U.S.C. 4505, 10 U.S.C. 3805).

XX (58) 52.232-33, Payment by Electronic Funds Transfer-System for Award Management (OCT2018) (31 U.S.C. 3332).

__ (59) 52.232-34, Payment by Electronic Funds Transfer-Other than System for Award Management (Jul 2013) (31 U.S.C. 3332).

__ (60) 52.232-36, Payment by Third Party (MAY 2014) (31 U.S.C. 3332).

__ (61) 52.239-1, Privacy or Security Safeguards (AUG 1996) (5 U.S.C. 552a).

__ (62) 52.242-5, Payments to Small Business Subcontractors (JAN 2017) (15 U.S.C. 637(d)(13)).

__ (63) (i) 52.247-64, Preference for Privately Owned U.S.-Flag Commercial Vessels (NOV 2021) (46 U.S.C. 55305 and 10 U.S.C. 2631).

__ (ii) Alternate I (APR 2003) of 52.247-64.

__ (iii) Alternate II (NOV 2021) of 52.247-64.

(c) The Contractor shall comply with the FAR clauses in this paragraph (c), applicable to commercial services, that the Contracting Officer has indicated as being incorporated in this contract by reference to implement provisions of law or Executive orders applicable to acquisitions of commercial products and commercial services:

[Contracting Officer check as appropriate.] XX (1) 52.222-41, Service Contract Labor Standards (AUG 2018) (41 U.S.C. chapter67). (Services Only) XX (2) 52.222-42, Statement of Equivalent Rates for Federal Hires (MAY 2014) (29 U.S.C. 206 and 41 U.S.C. chapter 67). (Services Only) __ (3) 52.222-43, Fair Labor Standards Act and Service Contract Labor Standards-Price Adjustment (Multiple Year and Option Contracts) (AUG 2018) (29 U.S.C. 206 and 41 U.S.C. chapter 67).

__ (4) 52.222-44, Fair Labor Standards Act and Service Contract Labor Standards-Price Adjustment (May 2014) (29U.S.C.206 and 41 U.S.C. chapter 67).

__ (5) 52.222-51, Exemption from Application of the Service Contract Labor Standards to Contracts for Maintenance, Calibration, or Repair of Certain Equipment-Requirements (May 2014) (41 U.S.C. chapter 67).

__ (6) 52.222-53, Exemption from Application of the Service Contract Labor Standards to Contracts for Certain Services-Requirements (MAY 2014) (41 U.S.C. chapter 67).

XX (7) 52.222-55, Minimum Wages Under Executive Order 14026 (JAN 2022).

XX (8) 52.222-62, Paid Sick Leave Under Executive Order 13706 (JAN 2022) (E.O. 13706).

__ (9) 52.226-6, Promoting Excess Food Donation to Nonprofit Organizations (Jun 2020) (42 U.S.C. 1792).

(d) Comptroller General Examination of Record. The Contractor shall comply with the provisions of this paragraph (d) if this contract was awarded using other than sealed bid, is…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .