Sol_140G0126Q0086.pdf

PDF 471 KB Posted

Attached to
CERC C3 Chiller Replacement Federal contract opportunity
Solicitation number
140G0126Q0086
Issued by
Department of the Interior US Geological Survey Office of Acquisitions and Grants

About this file

This is a Request for Quotations (RFQ) issued by the U.S. Geological Survey (USGS) for the CERC C3 Chiller Replacement project. The procurement is a 100% Service Disabled Veteran Owned Small Business (SDVOSB) set-aside for sealed bid/negotiated solicitation. The contract work includes all labor, materials, tools, equipment, and supervision necessary for C3 chiller replacement at the Columbia Environmental Research Center (CERC) in Columbia, Missouri, with delivery required 14 days after receipt of order. The NAICS code is 238220 (Plumbing, Heating, and Air-Conditioning Contractors) with a $19 million size standard. Quotations are due by 1700 hours on April 28, 2026, and must be submitted via email to Kimberly Schneider at kimberly_schneider@ios.doi.gov with a completed SF1442 form, signatures, and UEI (Unique Entity Identifier). An organized site visit is scheduled for Tuesday, April 21, 2026, at 9:00 AM local time at the Columbia Environmental Research Center with advance notice required.

The contract is a firm fixed-price award with payment protection required (either a performance/payment bond or irrevocable letter of credit at 100% of contract price) due within 10 days of award. The contractor must commence work within 10 calendar days and complete all work within 14 calendar days after receiving the notice to proceed. Eight line items are specified in the schedule including removal and disposal of existing equipment, chiller procurement and installation, chilled water storage tank, water coil replacement, isolation valve replacement, VFD replacement, optional electrical circuit installation, and comprehensive installation services including equipment disconnect and water treatment. Evaluation criteria include Technical Approach (acceptable/unacceptable basis) and Price, with award to the lowest priced, technically acceptable offer. The solicitation incorporates numerous FAR clauses including labor standards, construction wage requirements, inspection and acceptance standards, and various compliance and security provisions applicable to federal construction contracts.

View the file

Other files for this federal contract opportunity

Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(See ).

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid and "bidder".

SOLICITATION

1. SOLICITATION NO.

5. REQUISITION/PURCHASE REQUEST NO.

CODE

6. PROJECT NO.

8. ADDRESS OFFER TO

4. CONTRACT NO.

7. ISSUED BY

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)

11. The contractor shall begin performance within

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES", indicate within how many calendar days after award in Item 12b.)

13. ADDITIONAL SOLICITATION REQUIREMENTS:

a. Sealed offers in original and

b. An offer guarantee

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d. Offers providing less than

STANDARD FORM 1442 (REV. 12/2022)

Prescribed by GSA - FAR (48 CFR) 53.236-1(d) calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

is, is not required.

local time containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes copies to perform the work required are due at the place specified in Item 8 by (hour) award, YES NO notice to proceed. This performance period is mandatory negotiable.

calendar days and complete it within calendar days after receiving

a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

12b. CALENDAR DAYS

2. TYPE OF SOLICITATION

NEGOTIATED (RFP) REQUEST FOR PROPOSAL

3. DATE ISSUED PAGE OF

SEALED BID (IFB) INVITATION FOR BID

9. FOR

INFORMATION CALL

PAGES

140G0126Q0086

USGS OAG RESTON ACQUISITION BRANCH

205 NATIONAL CENTER

12201 SUNRISE VALLEY DRIVE

RESTON VA 20192

0044032433

GRB

Kimberly Schneider 0000

04/13/2026

04/28/2026

10 14 52.211-10

CERC C3 Chiller Replacement

100% Service Disabled Veteran Owned Small Business (SDVOSB) Set-aside

See Section L for Instructions and Section M for Evaluation Factors

***SITE VISIT SCHEDULED AND NOTED IN SECTION L, Reference FAR 52.236-27***

*Ref Section F for list of Deliverables*

*Payment Protection Required*

1 49

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement by the Government in writing within stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

OFFER (Must be fully completed by offeror)

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AWARD (To be completed by Government)

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)

CODE FACILITY CODE

15. TELEPHONE NO. (Include area code)

16. REMITTANCE ADDRESS (Include only if different than Item 14.)

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)

21. ITEMS ACCEPTED:

22. AMOUNT

26. ADMINISTERED BY

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)

31c. DATE

STANDARD FORM 1442 (REV. 12/2022) BACK

31b. UNITED STATES OF AMERICA

BY

31a. NAME OF CONTRACTING OFFICER (Type or print)

29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.

30b. SIGNATURE 30c. DATE

28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

copies to issuing office.) Contractor agrees to furnish

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

23. ACCOUNTING AND APPROPRIATION DATA

ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO THE UNITED STATES CODE AT

27. PAYMENT WILL BE MADE BY

10 U.S.C. 3204(a) ( ) 41 U.S.C. 3304(a) ( )

20b. SIGNATURE 20c. OFFER DATE

Continued...

AMENDMENT

NUMBER

DATE.

USGS OAG RESTON ACQUISITION BRANCH

205 NATIONAL CENTER

12201 SUNRISE VALLEY DRIVE

RESTON VA 20192

GRB

Kimberly Schneider

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGES

NAME OF OFFEROR OR CONTRACTOR

SUPPLIES/SERVICES

(B)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

OPTIONAL FORM 336 (4-86)

Sponsored by GSA FAR (48 CFR) 53.110

ITEM NO.

(A)

QUANTITY

(C)

NSN 7540-01-152-8067

140G0126Q0086

CERC C3 Chiller Replacement

Delivery: 14 Days After Receipt Of Order

Delivery Location Code: 0011277071

USGS Columbia Environmental Researc

4200 New Haven Road

Columbia MO 65201 US

00001 The contractor shall provide all labor, materials, tools, equipment and supervision necessary for the C3 chiller replacement at the

Columbia Environmental Research (CERC) in accordance with the Statement of Work (SOW).

*Reference Section B for Schedule of Items and provide breakdown*

Product/Service Code: 4130

Product/Service Description: REFRIGERATION AND

AIR CONDITIONING COMPONENTS

For questions on this solicitation contact

Kimberly Schneider, kimberly_schneider@ios.doi.gov.

Section B - Supplies or Services/Prices B-1 Schedule of Items

Section C - Description/Specifications C-1 Statement of Work

Section E - Inspection and Acceptance E-1 52.246-12 Inspection of Construction. (AUG 1996) E-2 52.246-13 Inspection - Dismantling, Demolition, or Removal of Improvements. (AUG 1996)

Section F - Deliveries or Performance F-1 Deliverables F-2 52.211-10 Commencement, Prosecution, and Completion of Work. (APR 1984) F-3 52.242-14 Suspension of Work. (APR 1984)

Section G - Contract Administration Data G-1 DOI ELECTRONIC INVOICING Electronic Invoicing and Payment Requirements - Invoice Processing Platform (IPP) (February 2021) G-2 GS0231 Technical Liaison-Technical Direction (NOV 2024) G-3 GS1131 Unilateral Deobligation of Unexpended Funds (MAY 2013) G-4 GS1354 List of subcontractors (Construction) (JUL 2001)

Section H - Special Contract Requirements H-1 GS1326 Indemnity (JUL 2001) H-2 GS1338 Notice to Government of Delays (JUL 2001) H-3 GS1346 Compliance with OSHA-Govt owned Facilities/Equipment (APR 2003) H-4 GS1348 Accident Reporting (APR 2003) H-5 GS1440 Wage Determination Applicable (JUL 2001)

Section I - Contract Clauses I-1 52.203-17 Contractor Employee Whistleblower Rights. (NOV 2023) I-2 52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements. (JAN 2017) I-3 52.204-13 System for Award Management Maintenance. (OCT 2018) I-4 52.204-18 Commercial and Government Entity Code Maintenance. (AUG 2020) I-5 52.209-6 Protecting the Government's Interest When Subcontracting With Contractors Debarred, Suspended, Proposed for Debarment, or Voluntarily Excluded. (JAN 2025) I-6 52.209-10 Prohibition on Contracting With Inverted Domestic Corporations. (NOV 2015) I-7 52.212-4 Contract Terms and Conditions - Commercial Products and Commercial Services. (NOV 2023) I-8 52.219-6 Notice of Total Small Business Set-Aside. (NOV 2020) I-9 52.222-3 Convict Labor. (JUN 2003) I-10 52.222-9 Apprentices and Trainees. (JUL 2005) I-11 52.222-19 Child Labor - Cooperation with Authorities and Remedies. (JAN 2025) I-12 52.222-36 Equal Opportunity for Workers with Disabilities. (JUN 2020) I-13 52.222-50 Combating Trafficking in Persons. (OCT 2025) I-14 52.228-2 Additional Bond Security. (OCT 1997) I-15 52.228-11 Individual Surety-Pledge of Assets. (FEB 2021) I-16 52.228-12 Prospective Subcontractor Requests for Bonds. (DEC 2022) I-17 52.228-13 Alternative Payment Protections. (JUL 2000) I-18 52.228-14 Irrevocable Letter of Credit. (NOV 2014) I-19 52.232-27 Prompt Payment for Construction Contracts. (JAN 2017) I-20 52.232-33 Payment by Electronic Funds Transfer - System for Award Management. (OCT 2018) I-21 52.232-40 Providing Accelerated Payments to Small Business Subcontractors. (MAR 2023) I-22 52.233-3 Protest After Award. (AUG 1996) I-23 52.233-4 Applicable Law for Breach of Contract Claim. (OCT 2004) I-24 52.236-3 Site Investigation and Conditions Affecting the Work. (APR 1984) I-25 52.236-5 Material and Workmanship. (APR 1984) I-26 52.236-7 Permits and Responsibilities. (NOV 1991) I-27 52.236-14 Availability and Use of Utility Services. (APR 1984) I-28 52.236-17 Layout of Work. (APR 1984) I-29 52.252-2 Clauses Incorporated by Reference. (FEB 1998) I-30 1452.225-70 Use of Foreign Construction Materials (JUL 1996) I-31 1452.228-70 Liability Insurance (JUL 1996) I-32 1452.236-70 Prohibition Against Use of Lead-based Paint (JUL 1996)

I-33 52.219-6 Notice of Total Small Business Set-Aside. (NOV 2020) (Deviation JAN 2026) I-34 52.222-6 Construction Wage Rate Requirements. (AUG 2018) (Deviation Effective Date) I-35 52.222-7 Withholding of Funds. (MAY 2014) I-36 52.222-8 Payrolls and Basic Records. (JUL 2021) I-37 52.222-10 Compliance With Copeland Act Requirements. (FEB 1988) I-38 52.222-11 Subcontracts (Labor Standards). (MAY 2014) (Deviation Effective Date) I-39 52.222-12 Contract Termination - Debarment. (MAY 2014) I-40 52.222-13 Compliance With Construction Wage Rate Requirements and Related Regulations. (MAY 2014) I-41 52.222-14 Disputes Concerning Labor Standards. (FEB 1988) I-42 52.222-15 Certification of Eligibility. (MAY 2014) I-43 52.223-23 Sustainable Products and Services. (MAY 2024) (Deviation Effective Date) I-44 52.226-8 Encouraging Contractor Policies To Ban Text Messaging While Driving. (MAY 2024) I-45 52.227-4 Patent Indemnity--Construction Contracts. (DEC 2007) I-46 52.232-5 Payments Under Fixed-Price Construction Contracts. (MAY 2014) I-47 52.236-2 Differing Site Conditions. (APR 1984) (Deviation JAN 2026) I-48 52.240-91 Security Prohibitions and Exclusions. (Deviation Effective Date) I-49 52.243-5 Changes and Changed Conditions. (APR 1984) (Deviation OCT 2025) I-50 52.249-10 Default (Fixed-Price Construction). (APR 1984) I-51 52.252-6 Authorized Deviations in Clauses. (NOV 2020) I-52 52.253-1 Computer Generated Forms. (JAN 1991) (Deviation Effective Date)

Section J - List of Documents, Exhibits and Other Attachments Section K - Representations, Certifications, and Other Statements of Bidders

K-1 52.203-18 Prohibition on Contracting with Entities that Require Certain Internal Confidentiality Agreements or Statements-Representation. (JAN 2017) K-2 52.225-25 Prohibition on Contracting with Entities Engaging in Certain Activities or Transactions Relating to Iran- Representation and Certifications. (JUN 2020) K-3 52.240-90 Security Prohibitions and Exclusions Representations and Certifications. (Deviation Effective Date)

Section L - Instructions,Conditions, and Notices to Bidders L-1 Instructions to Offerors addendum to 52.212-1 L-2 52.204-7 System for Award Management. (NOV 2024) L-3 52.204-16 Commercial and Government Entity Code Reporting. (AUG 2020) L-4 52.212-1 Instructions to Offerors - Commercial Products and Commercial Services. (SEP 2023) L-5 52.216-1 Type of Contract. (APR 1984) L-6 52.236-27 Site Visit (Construction). (FEB 1995) - Alternate I (FEB 1995) L-7 52.252-1 Solicitation Provisions Incorporated by Reference. (FEB 1998)

Section M - Evaluation Factors for Award M-1 52.212-2 Evaluation - Commercial Products and Commercial Services. (NOV 2021)

Section B - Supplies or Services/Prices B-1 Schedule of Items

CLIN CLIN Description QtyUOMUnit Price

Total Price

00001AA Removal and disposal of necessary equipment in accordance with the SOW 1 LS 00001AB Chiller in accordance with the SOW 1 EA 00001AC Chilled water storage tank in accordance with the SOW 1 EA 00001AD Replace faulty water coils in accordance with the SOW 1 LS 00001AE Replace isolation valves in accordance with the SOW 1 LS 00001AF Replace VFD in accordance with the SOW 1 LS 00001AG Optional: install new electrical circuit, if required, to support new chiller 1 LS

00001AH Installation of all equipment to include equipment disconnect, water treatment for chilled water loop, communications in accordance with the SOW 1 LS

Total

Section C - Description/Specifications C-1 Statement of Work

*Reference Attachment 1*

Section E - Inspection and Acceptance E-1 52.246-12 Inspection of Construction. (AUG 1996)

(a) Definition. Work includes, but is not limited to, materials, workmanship, and manufacture and fabrication of components.

(b) The Contractor shall maintain an adequate inspection system and perform such inspections as will ensure that the work performed under the contract conforms to contract requirements. The Contractor shall maintain complete inspection records and make them available to the Government. All work shall be conducted under the general direction of the Contracting Officer and is subject to Government inspection and test at all places and at all reasonable times before acceptance to ensure strict compliance with the terms of the contract.

(c) Government inspections and tests are for the sole benefit of the Government and do not-

(1) Relieve the Contractor of responsibility for providing adequate quality control measures;

(2) Relieve the Contractor of responsibility for damage to or loss of the material before acceptance;

(3) Constitute or imply acceptance; or

(4) Affect the continuing rights of the Government after acceptance of the completed work under paragraph (i) this-section.

(d) The presence or absence of a Government inspector does not relieve the Contractor from any contract requirement, nor is the inspector authorized to change any term or condition of the specification without the Contracting Officer's written authorization.

(e) The Contractor shall promptly furnish, at no increase in contract price, all facilities, labor, and material reasonably needed for performing such safe and convenient inspections and tests as may be required by the Contracting Officer. The Government may charge to the Contractor any additional cost of inspection or test when work is not ready at the time specified by the Contractor for inspection or test, or when prior rejection makes reinspection or retest necessary. The Government shall perform all inspections and tests in a manner that will not unnecessarily delay the work. Special, full size, and performance tests shall be performed as described in the contract.

(f) The Contractor shall, without charge, replace or correct work found by the Government not to conform to contract requirements, unless in the public interest the Government consents to accept the work with an appropriate adjustment in contract price. The Contractor shall promptly segregate and remove rejected material from the premises.

(g) If the Contractor does not promptly replace or correct rejected work, the Government may (1) by contract or otherwise, replace or correct the work and charge the cost to the Contractor or (2) terminate for default the Contractor's right to proceed.

(h) If, before acceptance of the entire work, the Government decides to examine already completed work by removing it or tearing it out, the Contractor, on request, shall promptly furnish all necessary facilities, labor, and material. If the work is found to be defective or nonconforming in any material respect due to the fault of the Contractor or its subcontractors, the Contractor shall defray the expenses of the examination and of satisfactory reconstruction. However, if the work is found to meet contract requirements, the Contracting Officer shall make an equitable adjustment for the additional services involved in the examination and reconstruction, including, if completion of the work was thereby delayed, an extension of time.

(i) Unless otherwise specified in the contract, the Government shall accept, as promptly as practicable after completion and inspection, all work required by the contract or that portion of the work the Contracting Officer determines can be accepted separately. Acceptance shall be final and conclusive except for latent defects, fraud, gross mistakes amounting to fraud, or the Government's rights under any warranty or guarantee.

(End of clause)

E-2 52.246-13 Inspection - Dismantling, Demolition, or Removal of Improvements. (AUG 1996)

(a) Unless otherwise designated by the specifications, all workmanship performed under the contract is subject to Government inspection at all times and places where dismantling or demolition work is being performed. The Contractor shall furnish promptly, and at no increase in contract price, all reasonable facilities, labor, and materials necessary for safe and convenient inspection by the Government. The Government shall perform inspections in a manner that will not unduly delay the work.

(b) The Contractor is responsible for damage to property caused by defective workmanship. The Contractor shall promptly segregate and remove from the premises any unsatisfactory facilities, materials, and equipment used in contract performance, and promptly replace them with satisfactory items. If the Contractor fails to proceed at once in a workmanlike manner with performance of the work or with the correction of defective workmanship, the Government may

(1) by contract or otherwise, replace the facilities, materials, and equipment or correct the workmanship and charge the cost to the Contractor and (2) terminate for default the Contractor's right to proceed. The Contractor and any surety shall be liable, to the extent specified in the contract for any damage or cost of repair or replacement.

Section F - Deliveries or Performance F-1 Deliverables

Deliverable Reference Due Deliver To Payment bond/Irrevocable Letter of Credit Section I: 52.228-13 Within 10 calendar days after receipt of contract award CO

Proof of Liability Insurance Section I: 1452.228-

Within 10 calendar days after receipt of contract award CO

Invoices Section G: DOI Electronic Invoicing, GS1126

Invoices for progress payments may be submitted no more frequently than monthly

IPP, Reference GS1126 for additional POC required submission

DI-137 Release of Claims Section I: 1452-204- 70 Submitted with final invoice IPP, Reference GS1126

Weekly payroll for contractor and each subcontractor Section I: 52.222-8

Within 10 days after regular payment date of the payroll week covered

CO, Ref: FAR 22.406-6(c)

SF1413 Statement and Acknowledgement of Subcontractor

Section G: GS1354 Within 10 calendar days after award CO

F-2 52.211-10 Commencement, Prosecution, and Completion of Work. (APR 1984)

The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 14 calendar days after the date the Contractor receives the notice to proceed . The time stated for completion shall include final cleanup of the premises.

(End of clause)

* The Contracting Officer shall specify either a number of days after the date the contractor receives the notice to proceed, or a calendar date.

F-3 52.242-14 Suspension of Work. (APR 1984)

(a) The Contracting Officer may order the Contractor, in writing, to suspend, delay, or interrupt all or any part of the work of this contract for the period of time that the Contracting Officer determines appropriate for the convenience of the Government.

(b) If the performance of all or any part of the work is, for an unreasonable period of time, suspended, delayed, or interrupted (1) by an act of the Contracting Officer in the administration of this contract, or (2) by the Contracting Officer's failure to act within the time specified in this contract (or within a reasonable time if not specified), an adjustment shall be made for any increase in the cost of performance of this contract (excluding profit) necessarily caused by the unreasonable suspension, delay, or interruption, and the contract modified in writing accordingly. However, no adjustment shall be made under this clause for any suspension, delay, or interruption to the extent that performance would have been so suspended, delayed, or interrupted by any other cause, including the fault or negligence of the Contractor, or for which an equitable adjustment is provided for or excluded under any other term or condition of this contract.

(c) A claim under this clause shall not be allowed (1) for any costs incurred more than 20 days before the Contractor shall have notified the Contracting Officer in writing of the act or failure to act involved (but this requirement shall not apply as to a claim resulting from a suspension order), and (2) unless the claim, in an amount stated, is asserted in writing as soon as practicable after the termination of the suspension, delay, or interruption, but not later than the date of final payment under the contract.

Section G - Contract Administration Data G-1 DOI ELECTRONIC INVOICING Electronic Invoicing and Payment Requirements - Invoice Processing Platform (IPP) (February 2021)

Payment requests must be submitted electronically through the U. S. Department of the Treasury's Invoice Processing Platform System (IPP).

"Payment request" means any request for contract financing payment or invoice payment by the Contractor. To constitute a proper invoice, the payment request must comply with the requirements identified in the applicable Prompt Payment clause included in the contract, or the clause 52.212-4 Contract Terms and Conditions - Commercial Items included in commercial item contracts. The IPP website address is: https://www.ipp.gov.

Under this contract, the following documents are required to be submitted as an attachment to the IPP invoice:

- Contractor generated invoice

- Payrolls

- Performance Statement for progress payment

- Release of Claims for final invoice

The Contractor must use the IPP website to register access and use IPP for submitting requests for payment. The Contractor Government Business Point of Contact (as listed in SAM) will receive enrollment instructions via email from the Federal Reserve Bank of St. Louis (FRBSTL) within 3 - 5 business days of the contract award date. Contractor assistance with enrollment can be obtained by contacting the IPP Production Helpdesk via email IPPCustomerSupport@fiscal.treasury.gov or phone (866) 973-3131.

If the Contractor is unable to comply with the requirement to use IPP for submitting invoices for payment, the Contractor must submit a waiver request in writing to the Contracting Officer with its proposal or quotation.

(End of Local Clause)

G-2 GS0231 Technical Liaison-Technical Direction (NOV 2024)

a) The performance required herein shall be subject to the technical clarification of the Technical Liaison (TL) as identified below. As used herein, "technical clarification" is defined as communication to help the contractor fully understand the requirements.

(b) The Technical Liaison is not delegated any Contracting Officer's Representative responsibilities.

(c) The Technical Liaison may not modify the requirements in any way. All modifications must be authorized by the Contracting Officer.

(d) The contractor shall immediately notify the Contracting Officer, in writing, if they believe the Technical Liaison is directing work outside the requirements of this contract. The contractor may not be reimbursed for any work outside the requirements of this contract.

(e) The Technical Liaison assigned for this contract is: *To be provided upon award*

Telephone: []

Email: []

G-3 GS1131 Unilateral Deobligation of Unexpended Funds (MAY 2013)

The contractor shall submit all invoices under the award no later than 90 calendar days after the period of performance has expired, unless a request for extension has been submitted to the Contracting Officer. After 120 days has passed since the expiration of the performance period, the government reserves the right to issue a unilateral modification deobligating any unexpended funds, and to initiate closeout procedures.

G-4 GS1354 List of subcontractors (Construction) (JUL 2001)

For purposes of monitoring compliance with the insurance and payroll reporting requirements of this contract, the contractor shall furnish a listing of all subcontractors to the Contracting Officer within 10 calendars days after contract award.

Section H - Special Contract Requirements H-1 GS1326 Indemnity (JUL 2001)

The contractor herein is "an independent contractor" and shall obtain all necessary insurance to protect himself from liability arising out of this contract. The contractor hereby agrees to indemnify and hold the Government harmless in connection with, any loss or liability from damage to or destruction of property or from injuries to or death of persons (including the agents and employees of both parties) if such damage, destruction, injury or death arises out of, or is caused by performance of work under this contract, unless such damage, destruction, injury or death is caused solely by the active negligence of the Government, its agents or employees. The contractor agrees to include this clause, appropriately modified, in all subcontracts to be performed under this contract.

H-2 GS1338 Notice to Government of Delays (JUL 2001)

In the event the contractor encounters difficulty in meeting performance requirements, or when it anticipates difficulty in complying with the contract delivery schedule or date, or whenever the contractor has knowledge that any actual or potential situation is delaying or threatens to delay the timely performance of this contract, the contractor shall immediately notify the contracting officer and the COR (if one has been designated), in writing, giving pertinent details.

This data shall be informational only in character. Notice under this provision shall not be construed as a waiver by the Government of any delivery schedule or date or of any rights or remedies provided by law or under this contract.

H-3 GS1346 Compliance with OSHA-Govt owned Facilities/Equipment (APR 2003)

Compliance with Occupational Safety and Health Act -- Government-Owned Performance of work hereunder shall comply with the provisions of the Occupational Health and Safety Act of 1970, as amended (OSHA). If, at any time during the performance of this contract, the Government-furnished facilities and/or equipment do not conform to OSHA standards, the contractor must so notify the Contracting Officer, in writing, including a recommendation of the corrective action needed.

H-4 GS1348 Accident Reporting (APR 2003)

If an accident occurs on Government-controlled facilities, a report must be provided to the Contracting Officer's Representative and the Contracting Officer within 48 hours. An accident is defined as an event which causes injury, illness, or loss or damage to Government-owned or private property. The contractor will cooperate with any ensuing Government accident investigation.

H-5 GS1440 Wage Determination Applicable (JUL 2001)

In the performance of this contract, the contractor shall comply with the requirements of U.S. Department of Labor Wage Determination Number MO20260084 dated 1/2/2026. The wage determination is incorporated into this contract as Attachment 3

Section I - Contract Clauses I-1 52.203-17 Contractor Employee Whistleblower Rights. (NOV 2023)

I-2 52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements. (JAN 2017)

I-3 52.204-13 System for Award Management Maintenance. (OCT 2018)

I-4 52.204-18 Commercial and Government Entity Code Maintenance. (AUG 2020)

I-5 52.209-6 Protecting the Government's Interest When Subcontracting With Contractors Debarred, Suspended, Proposed for Debarment, or Voluntarily Excluded. (JAN 2025)

I-6 52.209-10 Prohibition on Contracting With Inverted Domestic Corporations. (NOV 2015)

I-7 52.212-4 Contract Terms and Conditions - Commercial Products and Commercial Services.

(NOV 2023)

I-8 52.219-6 Notice of Total Small Business Set-Aside. (NOV 2020)

I-9 52.222-3 Convict Labor. (JUN 2003)

I-10 52.222-9 Apprentices and Trainees. (JUL 2005)

I-11 52.222-19 Child Labor - Cooperation with Authorities and Remedies. (JAN 2025)

I-12 52.222-36 Equal Opportunity for Workers with Disabilities. (JUN 2020)

I-13 52.222-50 Combating Trafficking in Persons. (OCT 2025)

I-14 52.228-2 Additional Bond Security. (OCT 1997)

The Contractor shall promptly furnish additional security required to protect the Government and persons supplying labor or materials under this contract if -

(a) Any surety upon any bond, or issuing financial institution for other security, furnished with this contract becomes unacceptable to the Government;

(b) Any surety fails to furnish reports on its financial condition as required by the Government;

(c) The contract price is increased so that the penal sum of any bond becomes inadequate in the opinion of the Contracting Officer; or

(d) An irrevocable letter of credit (ILC) used as security will expire before the end of the period of required security. If the Contractor does not furnish an acceptable extension or replacement ILC, or other acceptable substitute, at least 30 days before an ILC's scheduled expiration, the Contracting officer has the right to immediately draw on the ILC.

(End of clause)

I-15 52.228-11 Individual Surety-Pledge of Assets. (FEB 2021)

(a) The Contractor shall obtain from each person acting as an individual surety on a performance bond or a payment bond-

(1) A pledge of assets that meets the eligibility, valuation, and security requirements described in the Federal Acquisition Regulation (FAR) 28.203-1; and

(2) Standard Form 28, Affidavit of Individual Surety.

(b) The Contracting Officer may release a portion of the security interest on the individual surety's assets based upon substantial performance of the Contractor's obligations under its performance bond. The security interest in support of a performance bond shall be maintained-

(1) Contracts for the construction, alteration, or repair of any public building or public work of the Federal Government exceeding $150,000 (40 U.S.C. 3131). Until completion of any warranty period, or for 1 year following final payment, whichever is later.

(2) Contracts subject to alternative payment protection (see FAR 28.102-1(b)(1)). For the full contract performance period plus 1 year.

(3) Other contracts not subject to the requirements of paragraph (b)(1) of this clause. Until completion of any warranty period, or for 90 days following final payment, whichever is later.

(c) A surety's assets pledged in support of a payment bond may be released to a subcontractor or supplier upon Government receipt of a Federal district court judgment, or a sworn statement by the subcontractor or supplier that the claim is correct along with a notarized authorization of the release by the surety stating that it approves of such release.

The security interest on the individual surety's assets in support of a payment bond shall be maintained-

(1) Contracts for the construction, alteration, or repair of any public building or public work of the Federal Government exceeding $150,000 which require performance and payment bonds (40 U.S.C. 3131). For 1 year following final payment, or until resolution of all pending claims filed against the payment bond during the 1-year period following final payment, whichever is later.

(2) Contracts subject to alternative payment protection (see FAR 28.102-1(b)(1)). For the full contract performance period plus 1 year.

(3) Other contracts not subject to the requirements of paragraph (c)(1) of this clause. For 90 days following final payment.

(d) The Contracting Officer may allow the Contractor to substitute an individual surety, for a performance or payment bond, after contract award. The Contractor shall comply with the requirements of paragraph (a) of this clause within the timeframe established by the Contracting Officer.

(End of clause)

I-16 52.228-12 Prospective Subcontractor Requests for Bonds. (DEC 2022)

In accordance with section 806(a)(3) of Pub. L. 102-190, as amended by sections 2091 and 8105 of Pub. L. 103-355 (10 U.S.C. 4601 note prec.), upon the request of a prospective subcontractor or supplier offering to furnish labor or material for the performance of this contract for which a payment bond has been furnished to the Government pursuant to 40 U.S.C. chapter 31, subchapter III, Bonds, the Contractor shall promptly provide a copy of such payment bond to the requester.

(End of clause)

I-17 52.228-13 Alternative Payment Protections. (JUL 2000)

(a) The Contractor shall submit one of the following payment protections: 1) payment bond; or 2) Irrevocable Letter of Credit

(b) The amount of the payment protection shall be 100 percent of the contract price.

(c) The submission of the payment protection is required within 10 days of contract award.

(d) The payment protection shall provide protection for the full contract performance period plus a one-year period.

(e) Except for escrow agreements and payment bonds, which provide their own protection procedures, the Contracting Officer is authorized to access funds under the payment protection when it has been alleged in writing by a supplier of labor or material that a nonpayment has occurred, and to withhold such funds pending resolution by administrative or judicial proceedings or mutual agreement of the parties.

(f) When a tripartite escrow agreement is used, the Contractor shall utilize only suppliers of labor and material that signed the escrow agreement.

(End of clause)

I-18 52.228-14 Irrevocable Letter of Credit. (NOV 2014)

(a) "Irrevocable letter of credit" (ILC), as used in this clause, means a written commitment by a federally insured financial institution to pay all or part of a stated amount of money, until the expiration date of the letter, upon presentation by the Government (the beneficiary) of a written demand therefor. Neither the financial institution nor the offeror/Contractor can revoke or condition the letter of credit.

(b) If the offeror intends to use an ILC in lieu of a bid bond, or to secure other types of bonds such as performance and payment bonds, the letter of credit and letter of confirmation formats in paragraphs (e) and (f) of this clause shall be used.

(c) The letter of credit shall be irrevocable, shall require presentation of no document other than a written demand and the ILC (including confirming letter, if any), shall be issued/confirmed by an acceptable federally insured financial institution as provided in paragraph (d) of this clause, and-

(1) If used as a bid guarantee, the ILC shall expire no earlier than 60 days after the close of the bid acceptance period;

(2) If used as an alternative to corporate or individual sureties as security for a performance or payment bond, the offeror/Contractor may submit an ILC with an initial expiration date estimated to cover the entire period for which financial security is required or may submit an ILC with an initial expiration date that is a minimum period of one year from the date of issuance. The ILC shall provide that, unless the issuer provides the beneficiary written notice of non-renewal at least 60 days in advance of the current expiration date, the ILC is automatically extended without amendment for one year from the expiration date, or any future expiration date, until the period of required coverage is completed and the Contracting Officer provides the financial institution with a written statement waiving the right to payment. The period of required coverage shall be:

(i) For contracts subject to 40 U.S.C. chapter 31, subchapter III, Bonds, the later of-

(A) One year following the expected date of final payment;

(B) For performance bonds only, until completion of any warranty period; or

(C) For payment bonds only, until resolution of all claims filed against the payment bond during the one-year period following final payment.

(ii) For contracts not subject to 40 U.S.C. chapter 31, subchapter III, Bonds, the later of-

(A) 90 days following final payment; or

(B) For performance bonds only, until completion of any warranty period.

(d)(1) Only federally insured financial institutions rated investment grade by a commercial rating service shall issue or confirm the ILC.

(2) Unless the financial institution issuing the ILC had letter of credit business of at least $25 million in the past year, ILCs over $5 million must be confirmed by another acceptable financial institution that had letter of credit business of at least $25 million in the past year.

(3) The Offeror/Contractor shall provide the Contracting Officer a credit rating that indicates the financial institutions have the required credit rating as of the date of issuance of the ILC.

(4) The current rating for a financial institution is available through any of the following rating services registered with the U.S. Securities and Exchange Commission (SEC) as a Nationally Recognized Statistical Rating Organization (NRSRO).

NRSRO's can be located at the Web site http://www.sec.gov/answers/nrsro.htm maintained by the SEC.

(e) The following format shall be used by the issuing financial institution to create an ILC:

Issuing Financial Institution's Letterhead or Name and Address

Issue Date __________

Irrevocable Letter of Credit No. __________

Account party's name ___________

Account party's address __________

For Solicitation No. ___________ (for reference only)

To: (U.S. Government agency)

(U.S. Government agency's address)

1. We hereby establish this irrevocable and transferable Letter of Credit in your favor for one or more drawings up to United States $______. This Letter of Credit is payable at (issuing financial institution's and, if any, confirming financial institution's) office at (issuing financial institution's address and, if any, confirming financial institution's address) and expires with our close of business on ___________, or any automatically extended expiration date.

2. We hereby undertake to honor your or the transferee's sight draft(s) drawn on the issuing or, if any, the confirming financial institution, for all or any part of this credit if presented with this Letter of Credit and confirmation, if any, at the office specified in paragraph 1 of this Letter of Credit on or before the expiration date or any automatically extended expiration date.

3. (This paragraph is omitted if used as a bid guarantee, and subsequent paragraphs are renumbered.) It is a condition of this Letter of Credit that it is deemed to be automatically extended without amendment for one year from the expiration date hereof, or any future expiration date, unless at least 60 days prior to any expiration date, we notify you or the transferee by registered mail, or other receipted means of delivery, that we elect not to consider this Letter of Credit renewed for any such additional period. At the time we notify you, we also agree to notify the account party (and confirming financial institution, if any) by the same means of delivery.

4. This Letter of Credit is transferable. Transfers and assignments of proceeds are to be effected without charge to either the beneficiary or the transferee/assignee of proceeds. Such transfer or assignment shall be only at the written direction of the Government (the beneficiary) in a form satisfactory to the issuing financial institution and the confirming financial institution, if any.

5. This Letter of Credit is subject to the Uniform Customs and Practice (UCP) for Documentary Credits, International Chamber of Commerce Publication No.___ (Insert version in effect at the time of ILC issuance, e.g., "Publication 600, 2006 edition") and to the extent not inconsistent therewith, to the laws of ___________ (State of confirming financial institution, if any, otherwise State of issuing financial institution).

6. If this credit expires during an interruption of business of this financial institution as described in Article 17 of the UCP, the financial institution specifically agrees to effect payment if this credit is drawn against within 30 days after the resumption of our business.

Sincerely, (Issuing financial institution)

(f) The following format shall be used by the financial institution to confirm an ILC:

(Confirming Financial Institution's Letterhead or Name and Address)

(Date)

Our Letter of Credit Advice Number _____________

Beneficiary: ___________ (U.S. Government agency)

Issuing Financial Institution: __________________

Issuing Financial Institution's LC No.: ___________

Gentlemen:

1. We hereby confirm the above indicated Letter of Credit, the original of which is attached, issued by __________ (name of issuing financial institution) for drawings of up to United States dollars ___________/U.S. $_______ and expiring with our close of business on _____________ (the expiration date), or any automatically extended expiration date.

2. Draft(s) drawn under the Letter of Credit and this Confirmation are payable at our office located at

3. We hereby undertake to honor sight draft(s) drawn under and presented with the Letter of Credit and this Confirmation at our offices as specified herein.

4. (This paragraph is omitted if used as a bid guarantee, and subsequent paragraphs are renumbered.) It is a condition of this confirmation that it be deemed automatically extended without amendment for one year from the expiration date hereof, or any automatically extended expiration date, unless:

(a) At least 60 days prior to any such expiration date, we shall notify the Contracting Officer, or the transferee and the issuing financial institution, by registered mail or other receipted means of delivery, that we elect not to consider this confirmation extended for any such additional period; or

(b) The issuing financial institution shall have exercised its right to notify you or the transferee, the account party, and ourselves, of its election not to extend the expiration date of the Letter of Credit.

5. This confirmation is subject to the Uniform Customs and Practice (UCP) for Documentary Credits, International Chamber of Commerce Publication No.___ (Insert version in effect at the time of ILC issuance, e.g., "Publication 600, 2006 edition") and to the extent not inconsistent therewith, to the laws of ______________ (State of confirming financial institution).

6. If this confirmation expires during an interruption of business of this financial institution as described in Article 17 of the UCP, we specifically agree to effect payment if this credit is drawn against within 30 days after the resumption of our business.

Sincerely, (Confirming financial institution)

(g) The following format shall be used by the Contracting Officer for a sight draft to draw on the Letter of Credit:

Sight draft

(City, State)

(Date)___________________

(Name and address of financial institution)

Pay to the order of ______________ (Beneficiary Agency) ___________ the sum of United States $____________. This draft is drawn under Irrevocable Letter of Credit No. ______________.

(Beneficiary Agency)

(By)

(End of clause)

I-19 52.232-27 Prompt Payment for Construction Contracts. (JAN 2017)

I-20 52.232-33 Payment by Electronic Funds Transfer - System for Award Management. (OCT 2018)

I-21 52.232-40 Providing Accelerated Payments to Small Business Subcontractors. (MAR 2023)

I-22 52.233-3 Protest After Award. (AUG 1996)

I-23 52.233-4 Applicable Law for Breach of Contract Claim. (OCT 2004)

I-24 52.236-3 Site Investigation and Conditions Affecting the Work. (APR 1984)

(a) The Contractor acknowledges that it has taken steps reasonably necessary to ascertain the nature and location of the work, and that it has investigated and satisfied itself as to the general and local conditions which can affect the work or its cost, including but not limited to (1) conditions bearing upon transportation, disposal, handling, and storage of materials;

(2) the availability of labor, water, electric power, and roads; (3) uncertainties of weather, river stages, tides, or similar physical conditions at the site; (4) the conformation and conditions of the ground; and (5) the character of equipment and facilities needed preliminary to and during work performance. The Contractor also acknowledges that it has satisfied itself as to the character, quality, and quantity of surface and subsurface materials or obstacles to be encountered insofar as this information is reasonably ascertainable from an inspection of the site, including all exploratory work done by the Government, as well as from the drawings and specifications made a part of this contract. Any failure of the Contractor to take the actions described and acknowledged in this paragraph will not relieve the Contractor from responsibility for estimating properly the difficulty and cost of successfully performing the work, or for proceeding to successfully perform the work without additional expense to the Government.

(b) The Government assumes no responsibility for any conclusions or interpretations made by the Contractor based on the information made available by the Government. Nor does the Government assume responsibility for any understanding reached or representation made concerning conditions which can affect the work by any of its officers or agents before the execution of this contract, unless that understanding or representation is expressly stated in this contract.

(End of clause)

I-25 52.236-5 Material and Workmanship. (APR 1984)

I-26 52.236-7 Permits and Responsibilities. (NOV 1991)

I-27 52.236-14 Availability and Use of Utility Services. (APR 1984)

I-28 52.236-17 Layout of Work. (APR 1984)

I-29 52.252-2 Clauses Incorporated by Reference. (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): https://www.acquisition.gov/

(End of clause)

I-30 1452.225-70 Use of Foreign Construction Materials (JUL 1996)

(a) The Government has determined that the Buy American Act is not applicable to the following construction materials because they are not mined, produced, or manufactured in the U.S. in sufficient quantities of a satisfactory quality:

(1) []

(2) []

(3) []

(b) Offers based on the use of foreign construction materials other than those listed in (a) above may be acceptable if the Government determines that U.S. construction material is not available, would be impracticable or constitute an unreasonable price. Please contact the contracting officer with questions or comments concerning non-availability or impracticability of U.S. material.

(c)(1) Offers based upon use of foreign construction material for cost savings will be considered reasonable if the cost of each foreign construction material, plus 6 percent, is less than the cost of each comparable U.S. construction material.

The Contracting Officer shall compute the cost of each foreign construction material to include all delivery costs to the construction site, and any applicable duty (whether or not a duty-free entry certificate is issued.) This evaluation shall be made for each foreign construction material included in the offer, but not listed in subparagraph (a) above in this clause.

(2) Any contractor cost savings from post-award approval to substitute foreign construction material for U.S. construction material shall be passed on to the Government.

(d)(1) This offer is based on the use of foreign construction material not listed in (a) above. For each foreign item proposed the offeror shall furnish the following information for the foreign material offered: item description, supplier, unit of measure, quantity, unit price, duty (even if a duty free certificate is issued), delivery costs, and total price and shall also identify information on a U.S. item comparable to the foreign item including: supplier, unit of measure, quantity, unit price, delivery costs and total price.

(2) If the Government rejects the use of foreign construction material listed under paragraph (d)(1) above, the Government will evaluate the Contractor's offer using the offeror's stated price for the comparable U.S. construction material, and the offeror shall be required to furnish such domestic construction material at the Contractor's originally offered price. In preaward situations, an offer which does not state a price for a comparable U.S. construction material will be rejected by the Government. In postaward situations an offer proposing foreign material which does not state the price for the comparable U.S. construction material will be rejected by the Government. The Contractor shall use comparable U.S.

material for the project and any additional cost for the use of this U.S. material shall be absorbed by the Contractor.

(End of clause)

I-31 1452.228-70 Liability Insurance (JUL 1996)

(a) The Contractor shall procure and maintain during the term of this contract and any extension thereof liability insurance in form satisfactory to the Contracting Officer by an insurance company which is acceptable to the Contracting Officer.

The named insured parties under the policy shall be the Contractor and the United States of America. The amounts of the insurance shall be not less than as follows:

$200,000 each person*

$500,000 each occurrence*

$20,000 property damage*

(b) Each policy shall have a certificate evidencing the insurance coverage. The insurance company shall provide an endorsement to notify the Contracting Officer…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .