Sol_140A2322R0029.pdf
PDF 1 MB Posted
- Attached to
- Remove and Replace Irrigation System Federal contract opportunity
- Solicitation number
- 140A2322R0029
About this file
This solicitation document requests proposals to remove and replace an irrigation system supporting a football field at the Tuba City Boarding School. Key details include:
-
The solicitation is issued by the Bureau of Indian Affairs Bureau of Indian Education for a project located at the Tuba City Boarding School in Arizona. The work includes removing the existing irrigation system and installing a new system along with leveling the field and installing new sod.
-
Proposals are due by April 22nd, 2022. The period of performance is 127 calendar days from notice to proceed. The contractor must provide all labor, materials, equipment and supervision to complete the project. Wage rates and other requirements like insurance and background checks apply. The project is set aside 100% for small business.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Attachment_1_140A2322R0029_Terms_and_Conditions_05252022_0002.pdf | ||
| Sol_140A2322R0029_Amd_0002.pdf | ||
| Sol_140A2322R0029_Amd_0001.pdf | ||
| Attachment_8_BIA_School_Facilities_Design_Handbook_3-30-07.pdf | ||
| Attachment_4_SF25A_Payment_Bond.pdf | ||
| Attachment_3_SF25_Performance_Bond.pdf | ||
| Attachment_1_Wage_Determination_AZ20220030_02252022.pdf | ||
| Attachment_7_PAST_PERFORMANCE_QUESTIONNAIRE.pdf | ||
| Attachment_5_Specialized_Experience_Information_Sheet.docx | DOCX document | |
| Attachment_2_BIA_Adopted_Federal_Health_and_Safety_Codes_and_Standards.pdf | ||
| Attachment_6_Project_Price_Breakdown.xlsx | XLSX spreadsheet |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOLICITATION, OFFER,
AND AWARD
2. TYPE OF SOLICITATION
6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.
PAGE OF PAGES
7. ISSUED BY CODE 8. ADDRESS OFFER TO
SOLICITATION
(Construction, Alteration, or Repair)
1. SOLICITATION NO. 3. DATE ISSUED
IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.
9.
INFORMATION
a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."
CALL:
FOR
SEALED BID (IFB)
NEGOTIATED (RFP)
0040566139
Indian Education Acquisition Office
1011 Indian School Rd.
Suite 352A Albuquerque NM 87104
A23
Matthew Lucas at Matthew.Lucas@bie.edu
Matthew Lucas 941-304-2333
1x 04/22/2022
140A2322R0029
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)
Project Title: Remove and Replace Irrigation/Sprinkler System
Project Location: Tuba City Boarding School, 306 Main St, Tuba City, AZ 86045
Magnitude of Construction: $500,000 to $1,000,000
NAICS - 221310 - Water Supply and Irrigation Systems; Size Standard $30M
PSC Code - Z1CA - Maintenance of Schools
Project Description: All labor, supervision, parts and equipment to remove and replace the irrigation system supporting the Tuba City Boarding School football field.
This requirement is set-aside 100% for small business.
- SECTION A - CONTRACT FORM
- SECTION B - SUPPLIES OR SERVICES AND PRICES
- SECTION C - DESCRIPTION AND SPECIFICATIONS
- SECTION D - PACKAGING AND MARKING
- SECTION E - INSPECTION AND ACCEPTANCE
- SECTION F - DELIVERIES OR PERFORMANCE
- SECTION G - CONTRACT ADMINISTRATION DATA
- SECTION H - SPECIAL CONTRACT REQUIREMENTS
Continued ...
11. The Contractor shall begin performance
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and is not required.is, b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
d. Offers providing less than
12b. CALENDAR DAYSYES NO
(If "YES", indicate within how many calendar days after award in Item 12b.)
5 127 calendar days and complete it within ________________ ________________ calendar days after receiving
52.211-10
05/24/2022
NSN 7540-01-155-3212
x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________
STANDARD FORM 1442 (Rev. 4-85)
Prescribed by GSA
FAR(48 CFR) 53.236-1(d)
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)
16. REMITTANCE ADDRESS (Include only if different than item 14.)
CODE FACILITY CODE
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGEMENT OF AMENDMENTS
OFFER (Must be fully completed by offeror)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this document and return (Contractor is not required to sign this document.)
Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award.
No further contractual document is necessary.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE
BY
2PAGE OF
Matthew Lucas
28. NEGOTIATED AGREEMENT 29. AWARD
Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, copies to issuing office.)
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
STANDARD FORM 1442 (REV. 4-85) BACK
Continued...
ITEM NO.
(A)
SUPPLIES/SERVICES
(B)
QUANTITY
(C)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
NAME OF OFFEROR OR CONTRACTOR
3 44
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
140A2322R0029
- SECTION I - CONTRACT CLAUSES
- SECTION J - LIST OF ATTACHMENTS
- SECTION K - Representations, certifications, and other statements of offerors or respondents
- SECTION L - INSTRUCTIONS, CONDITIONS, and
NOTICES TO OFFERORS
- SECTION M - EVALUATION FACTORS FOR AWARD
AT THE TIME OF PROPOSAL SUBMISSION, interested contractors MUST be actively registered in the
System for Award Management at https://www.sam.gov.
Delivery Location Code: 0009062084
BIE TUBA CITY BOARDING SCHOOL
PO 187
306 Main Street
TUBA CITY AZ 86045 US
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
Contents
SECTION B – PRICE SCHEDULE
B1. PRICE SCHEDULE
SECTION C – DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK
C1. STATEMENT OF WORK (SOW)
SECTION D – PACKAGING AND MARKING
D1. PACKAGING AND MARKING
SECTION E – INSPECTION AND ACCEPTANCE
E1. 52.252-02 CLAUSES INCORPORATED BY REFERENCE FEB 1998
E2. DAILY REPORTING REQUIREMENT
E3. FINAL INSPECTION
SECTION F -- DELIVERIES OR PERFORMANCE
F1. 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK APRIL 1984
F2. 52.211-12 LIQUIDATED DAMAGES--CONSTRUCTION SEP 2000
F3. 52.211-13 TIME EXTENSIONS SEP 2000
F4. 52.211-18 VARIATION IN ESTIMATED QUANTITY APR 1984
F5. 52.236-15 SCHEDULES FOR CONSTRUCTION CONTRACTS APR 1984
F6. 52.242-14 SUSPENSION OF WORK APR 1984
F7. ASSESSMENT AND APPORTIONMENT OF LIQUIDATED DAMAGES
F8. NOTICE OF DELAY
F9. RECYCLING AND DISPOSAL OF REFUSE
SECTION G – CONTRACT ADMINISTATION DATA
G1. 1452.201-70 AUTHORITIES AND DELEGATIONS (SEP 2011)
G2. CONTRACT ADMINISTRATION GOVERNMENT
G3. CONTRACT ADMINISTRATION – CONTRACTOR
G4. CONTRACTING OFFICER'S REPRESENTATIVE
G5. INVOICE AND PAYMENT
G6. INSTRUCTIONS FOR SUBMITTING MATERIAL APPROVALS
SECTION H – SPECIAL CONTRACT REQUIREMENTS
H1. TRIBAL TAXES, REQUIREMENTS AND/OR RESTRICTIONS:
H2. DRAWINGS AND OTHER DATA TO BECOME PROPERTY OF GOVERNMENT
H3. WORK OUTSIDE REGULAR WORK HOURS
H4. 1452.228-70 Liability Insurance (JUL 1996)
H5. TIME FOR SUBMISSION OF EVIDENCE OF INSURANCE
H6. VOLATILE ORGANIC COMPOUNDS (VOC) COMPLIANCE PLAN
H7. WAGE RATES
H8. CERTIFICATION OF PAYMENTS-RELEASE OF CLAIM
H9. SUBCONTRACT DATA
H10. CONTRACTOR SECURITY REQUIREMENTS
H11. REAL ID ACT OF 2005
H12. TEMPORARY FACILITIES
H13. EXISTING UTILITIES
H14. DIFFERING SITE CONDITION NOTICE
H15. DOCUMENTATION OF PROPOSALS FOR EQUITABLE ADJUSTMENTS
H16. NON-COMPLIANCE WITH CONTRACT REQUIREMENTS
H17. COVID-19 GUIDELINES
H18. BACKGROUND INVESTIGATION
H19. REMOVAL OF PERSONNEL
Part II - Contract Clauses
SECTION I – CONTRACT CLAUSES
I1. 52.252-02 CLAUSES INCORPORATED BY REFERENCE FEB 1998
CLAUSES INCORPORATED BY FULL TEXT
I2. 52.225-9 BUY AMERICAN–CONSTRUCTION MATERIALS (Nov 2021) I3. 52.236-21 Specifications and Drawings for Construction. (ALT 1 APR 1984)
Part III - List of Documents, Exhibits, and Other Attachments
SECTION J LIST OF ATTACHMENTS
Part IV - Representations and Instructions
SECTION K REPRESENTATIONS, CERTIFICATIONS, AND OTHER STATEMENTS OF OFFERORS
K1. 52.252-01 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE FEB 1998
K2. 52.204-8 Annual Representations and Certifications (Jan 2022) K3. 52.204-24 Representation Regarding Certain Telecommunications and Video Surveillance Services or Equipment (Nov 2021) K4. 52.222-23 Notice of Requirement for Affirmative Action to Ensure Equal Employment Opportunity for Construction (Feb 1999) K5. 52.225-10 Notice of Buy American Requirement-Construction Materials MAY 2014
SECTION L – INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS OR RESPONDENTS
L1. 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE FEB 1998
L2. SOLICITATION PROVISIONS IN FULL TEXT
L3. 52.216-1 Type of Contract APR 1984 L4. 52.222-5 Construction Wage Rate Requirements-Secondary Site of the Work. May 2014 L5. 52.233-2 Service Of Protest SEP 2006 L6. DIAR 1452.233-2 Service of Protest Department of the Interior (JUL 1996) (Deviation)
L7. INSTRUCTION TO OFFERORS:
GENERAL INFORMATION
SECTION M – EVALUATION FACTORS FOR AWARD
M1. Basis for Contract Award:
SECTION B – PRICE SCHEDULE
B1. PRICE SCHEDULE
ITEM
NUMBER
DESCRIPTION OF
SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 Contractor is required to furnish all labor, supervision, transportation, tools, and materials remove and replace the irrigation system of the Tuba City Boarding School Football Field in accordance with the statement of work.
1.00 JB _____________ ______________
Project Location:
Tuba City Boarding School 306 Main St.
Tuba City, AZ 86045
Period of Performance:
127 Days from Notice To Proceed
Subtotal: $_________ Bonding: $_________
Tribal Taxes As Required: $_________ All State Taxes (as applicable): $_________
Grand Total $_________
END OF SECTION B – PRICE SCHEDULE
SECTION C – DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK
C1. STATEMENT OF WORK (SOW)
Tuba City Boarding School Tuba City, Arizona - Coconino County Arizona
Grounds/Football Field Installation of Irrigation/Sprinkler System
Overview
The requirement is for the removal and replacement of Irrigation/Sprinkler system of the Tuba City Boarding School Football Field.
The work is to remove the current irrigation/sprinkler system and install a new replacement system to include leveling of the resulting field and the installation of new sod. The playing field shall be leveled to meet required codes. Project shall comply with current Bureau of Indian Affairs Design Handbook and Energy Savings Requirement.
General Information:
The Irrigation/Sprinkler and leveling of field Project is located on the Navajo Reservation. Tuba City Boarding School is a K-8 School, located at 306 Main Street in Tuba City, Arizona, Coconino County.
Project includes ALL schematic design and construction services necessary to provide a complete, water efficient, fully functional, and operational irrigation system for the area described in the attached photos below. The project includes the demolition, removal and disposal of the old irrigation system, installation of the new irrigation system, leveling of the ground in accordance with the required codes and regulations and replacement of the sod for the entire area identified.
The football field is located north of TCBS campus and is approximately 88,502 SF. The measurement includes the additional areas on the sideline and past the endzones. (See attached photo) This area shall be field verified by contractor personnel and is considered approximate.
No Alcohol, drugs, or tobacco products is allowed on TCBS Campus
The Contractor will be responsible for the safety of the site location which may include installation fencing and barricades as well as signage to warn employees and the public of the on-going repair/installation work.
Statement of Work:
• Contractor shall replace the existing Irrigation/ Sprinkler system with a new system, this is a like for like replacement. Upon completion of the installation of new irrigation system the field shall be leveled, and sod installed.
• Contractor shall provide equipment specifications, equipment/shop drawings and schematics, submittals, and all other necessary work to properly size and install Irrigation/Sprinkler System and leveling of field. This includes all related calculations relating to the water pressures within the system to ensure proper zone/coverage.
• Contractor shall produce schematic drawings indicating locations of drainage, piping, motors, sprinkler heads, thermostats, valves, and all other pertinent parts of an Irrigation/Sprinkler System.
• All Materials are to be supplied and installed by the Contractor. They shall be new and in perfect operating condition.
• Manufacturer to provide 1 year equipment warranty.
• Contractor shall be responsible to identify (Blue Stake) all utilities, overhead and undergroundlines, before any construction can commence.
• Contractor in coordination with the school shall prepare site designated area with groundwork, of which includes excavation, and grading site in providing a clean substrate.
• Contractor is responsible for cleanup after each day. Remove all debris onsite during the duration of this project. The contractor bears all responsibility and all associated or related costs with the removal and disposal of all debris from properties of the United States Government.
• Contractor shall provide a copy of the manifest for the disposal of all debris to the Tuba City Boarding School Facility office for environmental records.
Mobilization:
• Awarded contractor shall provide all labor, materials, equipment, supervision, transportation, and all other services to complete project in full.
Contractor shall be responsible for mobilization cost of materials, equipment, office trailer, storage bins and other construction items that need transporting to project site before startingup.
Security Background Clearance:
A background check approval is required from B.I.A. Security before any work is started for this project to commence. All workers are required to wear badges during regular work hours.
All workers must wear masks while on campus and during work hours. The Jobsite Superintendentshall report to the school's front office each day to indicate number of workers on site and provide daily work schedule.
Code Requirements:
The following codes, handbooks, regulatory agency requirements and all other applicable codes shall apply to this project.
International Plumbing Code National Electric Code American Disability Act Code EPA Code of Regulations
Navajo Nation EPA OSHA Requirements Government, State & Local Code
DELIVERY REQUIREMENTS:
i. Produce and deliver construction shop drawings of the equipment and its locations.
ii. Produce and equipment schedule for all equipment installed, identifying part numbers and the number of pieces each.
iii. Provide a schedule which will identify outage requirements, and project specifications) suitable for BIE design approval and for permitting and construction purposes.
iv. Project permitting, when required.
v. Administrative services during construction including coordination of product submittals, reviews, and approvals, and coordinating and documenting weekly project status meetings.
vi. Construct the project in an efficient, code-compliant manner that fully meets the project’s performance, cost, and time-line objectives.
vii. Conduct construction activities during regular 8-to-5 business hours except when work requires water or electric outages to BIE facilities. Work requiring water or electric outages will be completed outside of regular business hours and must be coordinated and approved by the COR at least 2 weeks in advance of the work being performed.
viii. Coordinate all trades, subcontractors, and equipment vendor personnel on the project.
ix. Purchase and manage the delivery and staging of construction material.
x. Provide on-going construction status and completion updates in coordination with the
COR.
xi. Coordinate with the COR for project inspectors for scheduling outages that impact the campus personnel.
xii. Demonstrate fully functional systems to the COR.
xiii. Provide Operations and Maintenance materials for all systems installed.
xiv. Provide 2-hour user training on all systems installed.
DELIVERY SCHEDULE:
The Contractor will be required to complete the work specified herein and deliver the items called for under this Statement of Work to the Contracting Officer as follows:
Draft Shop Drawings & Onsite Review 15 Workdays Final Shop Drawing and Equipment Submittals 10 Workdays Approval of Shop Drawings and Equipment Submittals 20 Workdays Construction & Installation 60 Workdays Substantial Completion Inspection 1 Workday Punch List Items 21 Workdays
Period of Performance:
Period of Performance will be 127 calendar days from Notice to Proceed.
Drawing Distribution: Two (2) Sets of schematic shop drawings and equipment schedule(s) shall be distributed to the following individuals:
1. LeRoy Begay, COR Arizona Navajo North - Facility Management Office PO Box 36 Highway 160 & Warrior Drive Tuba City, AZ 86045
2. Ed Folgheraiter, TCBS Facility Manager Tuba City Boarding School PO Box 187 Tuba City, AZ 86045
3. Don Coffland, Principal, Tuba City Boarding School 306 Main Street Tuba City, AZ 86045
Construction Progress Meetings The Construction Contractor must conduct regular progress meetings no less than biweekly during construction. The Contractor’s project manager and construction superintendent must attend each meeting. The Contractor must provide a meeting agenda no less than one day before each meeting and provide meeting minutes no more than three days after each meeting.
Debris Disposal/Demolition:
The Contractor shall remove all debris generated by of caused by the demolition work in this contract. The Contractor bears all responsibility and all associated or related costs with the removal and disposal of all debris from properties of the United States Government. The Contractor is required to comply with applicable Environmental Protection Agency (EPA), Federal, State, and local Government laws, policies and regulations while engaged in the removal and disposal debris. The Contractor shall transport the debris off the boundaries of the Navajo Reservation to an approved EPA landfill. The Government is not responsible in any way, financially or otherwise, for the success or failure of arrangements for disposal of debris between the Contractor and other parties.
Navajo Nation and State Taxes:
The Contractor is responsible and required to pay Navajo Nation Tribal Tax, which is equal to 6 percent of their total bid amount. In addition, the Contractor is responsible for all local and state gross taxes.
Certified Weekly Payrolls:
The Contractor is required to submit weekly-certified payroll to the Government for the term of the project.
1/21/22, 2:35 PM Tuba City Boarding School - Google Maps
Measure Estimated Distance Total area: 88,501.72 ft2 (8,222.08 m2)
Total distance: 1,253.62 ft (382.10 m)
END OF SECTION C – DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK
SECTION D – PACKAGING AND MARKING
D1. PACKAGING AND MARKING
A. All shipments of materials, equipment and/or supplies to the project site shall be addressed to the Contractor and not the Government. Preservation, packaging, and packing shall be in accordance with standard practices for commercial packaging.
B. Government personnel are not authorized to accept deliveries for the contractor, nor are they responsible for off-loading shipments. A contractor representative must be present to accept deliveries.
END OF SECTION D – PACKAGING AND MARKING
SECTION E – INSPECTION AND ACCEPTANCE
E1. 52.252-02 CLAUSES INCORPORATED BY REFERENCE FEB 1998
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this address: https://www.acquisition.gov/far and https://www.acquisition.gov/diar
CLAUSES TITLE DATE
52.246-12 Inspection of Construction AUG 1996
E2. DAILY REPORTING REQUIREMENT
The Contractor shall prepare and file a "Contractor's Daily Report", for each day of contract performance.
Description must include contract number and work being performed. These reports shall be delivered to, or if directed, mailed to the Contracting Officer’s Representative on Fridays. The daily report shall include the name of Contractors and Subcontractors on-site, the number of workers and their labor categories employed on-site, the work being performed, the type of equipment on-site, any change order work being performed, and whether the work being performed is on schedule. Reports shall be numbered, dated and signed by the Contractor or his Project Manager. Failure to submit the daily reports could result in payments being withheld until such time as all daily reports are current.
E3. FINAL INSPECTION
A. Contractor Self-Inspection. Prior to the completion date, the Contractor’s Quality Control Manager shall conduct a self-inspection of the site and document all items needing correction by means of a punch list. The corrected punch list shall be provided to the Contracting Officer’s Representative at the same time the pre-final inspection is requested. All punch list items must be corrected prior to requesting the pre-final inspection.
B. The Contractor and the Contracting Officer’s Representative will jointly conduct a pre-final inspection prior to requesting a final inspection. Any item needing correction shall be noted on the Pre-Final Inspection Punch List. Any discrepancies noted will be corrected prior to any final inspection. The Contracting Officer Representative may schedule more than one pre-final inspection if he determines it necessary.
C. When the Contractor is ready for final inspection, he will request final inspection in writing to the Contracting Officer and Contracting Officer’s Representative (COR). A copy of the Pre-Final Punch List shall be attached to this request with the corrective action taken noted. The final inspection will be requested at least 48 hours before the desired date.
D. The final inspection shall be performed with the Contractor by the COR, Contracting Officer, Safety Officer, and representatives of the using activity. Any discrepancies noted will be corrected within the time specified in the contract for the completion of work.
1. Prior to close-out and final payment of the contract, the following are required:
2. All submittals; to be submitted as required by the contract and may include product submittals, as-built drawings, manuals, etc.
3. All warranties; to be submitted with the request for Final Inspection.
4. Contractor’s Release; to be submitted with the Contractor’s final invoice.
END OF SECTION E – INSPECTION AND ACCEPTANCE
https://www.acquisition.gov/far https://www.acquisition.gov/diar
SECTION F -- DELIVERIES OR PERFORMANCE
F1. 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK APRIL 1984
The Contractor shall be required to (a) commence work under this contract receipt within (5) days of the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than one hundred twelve (127) calendar days. The time stated for completion shall include final cleanup of the premises.
(End of Clause)
F2. 52.211-12 LIQUIDATED DAMAGES--CONSTRUCTION SEP 2000
(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of $131.93 for each calendar day of delay until the work is completed or accepted.
(b) If the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.
F3. 52.211-13 TIME EXTENSIONS SEP 2000
Time extensions for contract changes will depend upon the extent, if any, by which the changes cause delay in the completion of the various elements of construction. The change order granting the time extension may provide that the contract completion date will be extended only for those specific elements related to the changed work and that the remaining contract completion dates for all other portions of the work will not be altered. The change order also may provide an equitable readjustment of liquidated damages under the new completion schedule.
(End of Clause)
F4. 52.211-18 VARIATION IN ESTIMATED QUANTITY APR 1984
If the quantity of a unit-priced item in this contract is an estimated quantity and the actual quantity of the unit-priced item varies more than 15 percent above or below the estimated quantity, an equitable adjustment in the contract price shall be made upon demand of either party. The equitable adjustment shall be based upon any increase or decrease in costs due solely to the variation above 115 percent or below 85 percent of the estimated quantity. If the quantity variation is such as to cause an increase in the time necessary for completion, the Contractor may request, in writing, an extension of time, to be received by the Contracting Officer within 10 days from the beginning of the delay, or within such further period as may be granted by the Contracting Officer before the date of final settlement of the contract.
Upon the receipt of a written request for an extension, the Contracting Officer shall ascertain the facts and make an adjustment for extending the completion date as, in the judgment of the Contracting Officer, is justified.
(End of Clause)
F5. 52.236-15 SCHEDULES FOR CONSTRUCTION CONTRACTS APR 1984
(a) The Contractor shall, within five days after the work commences on the contract or another period of time determined by the Contracting Officer, prepare and submit to the Contracting Officer for approval three copies of a practicable schedule showing the order in which the Contractor proposes to perform the work, and the dates on which the Contractor contemplates starting and completing the several salient features of the work (including acquiring materials, plant, and equipment). The schedule shall be in the form of a progress chart of suitable scale to indicate appropriately the percentage of work scheduled for completion by any given date during the period. If the Contractor fails to submit a schedule within the time prescribed, the Contracting Officer may withhold approval of progress payments until the Contractor submits the required schedule.
(b) The Contractor shall enter the actual progress on the chart as directed by the Contracting Officer, and upon doing so shall immediately deliver three copies of the annotated schedule to the Contracting Officer.
If, in the opinion of the Contracting Officer, the Contractor falls behind the approved schedule, the Contractor shall take steps necessary to improve its progress, including those that may be required by the
Contracting Officer, without additional cost to the Government. In this circumstance, the Contracting Officer may require the Contractor to increase the number of shifts, overtime operations, days of work, and/or the amount of construction plant, and to submit for approval any supplementary schedule or schedules in chart form as the Contracting Officer deems necessary to demonstrate how the approved rate of progress will be regained.
(c) Failure of the Contractor to comply with the requirements of the Contracting Officer under this clause shall be grounds for a determination by the Contracting Officer that the Contractor is not prosecuting the work with sufficient diligence to ensure completion within the time specified in the contract. Upon making this determination, the Contracting Officer may terminate the Contractor's right to proceed with the work, or any separable part of it, in accordance with the default terms of this contract.
(End of Clause)
F6. 52.242-14 SUSPENSION OF WORK APR 1984
(a) The Contracting Officer may order the Contractor, in writing, to suspend, delay, or interrupt all or any part of the work of this contract for the period of time that the Contracting Officer determines appropriate for the convenience of the Government.
(b) If the performance of all or any part of the work is, for an unreasonable period of time, suspended, delayed, or interrupted (1) by an act of the Contracting Officer in the administration of this contract, or (2) by the Contracting Officer's failure to act within the time specified in this contract (or within a reasonable time if not specified), an adjustment shall be made for any increase in the cost of performance of this contract (excluding profit) necessarily caused by the unreasonable suspension, delay, or interruption, and the contract modified in writing accordingly. However, no adjustment shall be made under this clause for any suspension, delay, or interruption to the extent that performance would have been so suspended, delayed, or interrupted by any other cause, including the fault or negligence of the Contractor, or for which an equitable adjustment is provided for or excluded under any other term or condition of this contract.
(c) A claim under this clause shall not be allowed--
(1) For any costs incurred more than 20 days before the Contractor shall have notified the Contracting Officer in writing of the act or failure to act involved (but this requirement shall not apply as to a claim resulting from a suspension order); and
(2) Unless the claim, in an amount stated, is asserted in writing as soon as practicable after the termination of the suspension, delay, or interruption, but not later than the date of final payment under the contract.
(End of Clause)
F7. ASSESSMENT AND APPORTIONMENT OF LIQUIDATED DAMAGES
Liquidated damages will be assessed from the completion date indicated in the contract or extensions thereof to the date of substantial completion as actually achieved by the Contractor, as determined by the Contracting Officer.
F8. NOTICE OF DELAY
If the Contractor receives a notice of any change in the work, or if any other conditions arise which are likely to cause or are causing delays which the Contractor believes may result in late completion of the project, the Contractor shall notify the Contracting Officer. The Contractor’s notice shall state the effect, if any, of such change or other conditions upon the approved schedule, and shall state in what respects, if any, the relevant schedule, or the completion date should be revised. The Contractor shall give this notice not more than three (3) days after the first event-giving rise to the delay or prospective delay. Only the Contracting Officer may revise the approved time schedule.
F9. RECYCLING AND DISPOSAL OF REFUSE
With the exception of materials specifically indicated or specified to be salvaged for reuse in construction, or turned over to the Government, all refuse, excess or waste materials resulting from construction operations shall become the property of the Contractor and shall be recycled and/or disposed of off Government property. All disposals shall be done in accordance with federal, state, and local laws and regulations.
(End of Local Clause)
END OF SECTION F – DELIVERIES OR PERFORMANCE
SECTION G – CONTRACT ADMINISTATION DATA
G1.1452.201-70 AUTHORITIES AND DELEGATIONS (SEP 2011)
(a) The Contracting Officer is the only individual authorized to enter into or terminate this contract, modify any term or condition of this contract, waive any requirement of this contract, or accept nonconforming work.
(b)The Contracting Officer will designate a Contracting Officer's Representative (COR) at time of award. The COR will be responsible for technical monitoring of the contractor's performance and deliveries. The COR will be appointed in writing, and a copy of the appointment will be furnished to the Contractor. Changes to this delegation will be made by written changes to the existing appointment or by issuance of a new appointment.
(c) The COR is not authorized to perform, formally or informally, any of the following actions:
(1) Promise, award, agree to award, or execute any contract, contract modification, or notice of intent that changes or may change this contract;
(2) Waive or agree to modification of the delivery schedule;
(3) Make any final decision on any contract matter subject to the Disputes Clause;
(4) Terminate, for any reason, the Contractor's right to proceed;
(5) Obligate in any way, the payment of money by the Government.
(d)The Contractor shall comply with the written or oral direction of the Contracting Officer or authorized representative(s) acting within the scope and authority of the appointment memorandum. The Contractor need not proceed with direction that it considers to have been issued without proper authority. The Contractor shall notify the Contracting Officer in writing, with as much detail as possible, when the COR has taken an action or has issued direction (written or oral) that the Contractor considers to exceed the COR's appointment, within 3 days of the occurrence. Unless otherwise provided in this contract, the Contractor assumes all costs, risks, liabilities, and consequences of performing any work it is directed to perform that falls within any of the categories defined in paragraph (c) prior to receipt of the Contracting Officer's response issued under paragraph (e) of this clause.
(e) The Contracting Officer shall respond in writing within 30 days to any notice made under paragraph (d) of this clause. A failure of the parties to agree upon the nature of a direction, or upon the contract action to be taken with respect thereto, shall be subject to the provisions of the Disputes clause of this contract.
(f) The Contractor shall provide copies of all correspondence to the Contracting Officer and the COR.
(g)Any action(s) taken by the Contractor, in response to any direction given by any person acting on behalf of the Government or any Government official other than the Contracting Officer or the COR acting within his or her appointment, shall be at the Contractor's risk.
(End of clause)
G2. CONTRACT ADMINISTRATION GOVERNMENT
All administrative questions shall be directed to the below:
Matthew Lucas, Contract Specialist, 1011 Indian School Rd NW Albuquerque, NM 87104 Phone: 941-304-2333 Email: matthew.lucas@bie.edu
(End of Local Clause)
G3. CONTRACT ADMINISTRATION – CONTRACTOR
Designate a person whom the Government may contact during the period of the contract for prompt action on matters pertaining to the administration of the contract. Authorized Administrator is:
Company Name: ______________ Point of Contact: ______________ Email: ______________ Address: ______________ Telephone Number: ______________
(End of Local Clause)
G4. CONTRACTING OFFICER'S REPRESENTATIVE
A. The Contracting Officer shall designate a Contracting Officer's Representative (COR) who will represent the Contracting Officer in the technical phase of the work. The COR's duties, responsibilities, and limitations of authority will be set forth in a written COR designation letter. A copy of the COR designation letter will be made available to the Contractor.
B. The COR is not authorized to make any changes to the terms and conditions of this contract. Only the Contracting Officer is authorized to make any changes to the contract by a properly written signed modification to the contract.
C. The Contracting Officer is the only official who can legally commit or obligate the Government for expenditure of public funds.
(End of Local Clause)
G5. INVOICE AND PAYMENT
Electronic Invoicing and Payment Requirements – Invoice Processing Platform (IPP) (April 2013)
Payment requests must be submitted electronically through the U.S. Department of the Treasury's Invoice Processing Platform system (IPP). "Payment request" means any request for contract financing payment or invoice payment by the Contractor. To constitute a proper invoice, the payment request must comply with the requirements identified in the applicable Prompt Payment clause included in the contract, or the clause 52.212-4 Contract Terms and Conditions - Commercial Items included in commercial item contracts. The IPP website address is: https://www.ipp.gov.
Under this contract, the following documents are required to be submitted as an attachment to the IPP invoice: A copy of the contractor’s invoice shall be included with the IPP invoice. If no invoice is attached, the Invoice will be rejected.
The Contractor must use the IPP website to register, access and use IPP for submitting requests for payment. The Contractor Government Business Point of Contact (as listed in SAM) will receive enrollment instructions via email from the Federal Reserve Bank of Boston (FRBB) within 3 - 5 business days of the contract award date.
Contractor assistance with enrollment can be obtained by contacting the IPP Production Helpdesk via email ippgroup@bos.frb.org or phone (866) 973-3131. If the Contractor is unable to comply with the requirement to use IPP for submitting invoices for payment, the Contractor must submit a waiver request in writing to the Contracting Officer with its proposal or quotation.
(End of Local Clause) mailto:matthew.lucas@bie.edu https://www.ipp.gov/ mailto:ippgroup@bos.frb.org
G6. INSTRUCTIONS FOR SUBMITTING MATERIAL APPROVALS
Submittals must be provided in sufficient time and in such sequence to avoid delays in the work. Test reports and certifications shall be submitted and approved prior to payment for the applicable item. Corrected O&M Manuals must be received by the Government prior to the Final Inspection. Materials, samples, drawings, etc., shall be submitted on the Government provided form.
(End of Local Clause)
END OF SECTION G – CONTRACT ADMINISTATION DATA
SECTION H – SPECIAL CONTRACT REQUIREMENTS
H1. TRIBAL TAXES, REQUIREMENTS AND/OR RESTRICTIONS:
a. Special attention is called to FAR Clause 52.236-7, Permits and Responsibilities and FAR Clause 52.229-3, Federal, State, and Local Taxes. Offerors are responsible for contacting the tribe or tribal organization involved with regard to any requirements regarding tribal taxes, royalties and/or other applicable tribal laws or ordinances. Any costs associated with this section shall be included in the contractor's quote.
H2. DRAWINGS AND OTHER DATA TO BECOME PROPERTY OF GOVERNMENT
All designs, drawings, specifications, notes and other works developed in the performance of this contract shall become the sole property of the Government and may be used on any other design or construction without additional compensation to the Contractor. The Government shall be considered the "person for whom the work was prepared" for the purpose of authorship in any copyrightable work under 17 U.S.C. 201(b). With respect thereto, the Contractor agrees not to assert or authorize others to assert any rights nor establish any claim under the design patent or copyright laws.
H3. WORK OUTSIDE REGULAR WORK HOURS
If the contractor desires to perform work under this contract outside regular work hours or on Saturdays, Sundays or holidays, he shall apply, in writing, to the Contracting Officer no less than 10 calendar days prior to the planned start of such work. Regular work hours are, for the purpose of this clause, those hours the activity or Command where the work is to be performed normally works on a day-by-day basis. Application by the Contractor does not imply consent by the Government. Each application will be considered, and a decision made, on the potential benefit of permitting such work. Approval of a Contractor's application under this clause will be, unless otherwise agreed in writing, at no additional cost to the Government.
H4. 1452.228-70 Liability Insurance (JUL 1996)
The Contractor shall procure and maintain during the term of this contract and any extension thereof liability insurance in form satisfactory to the Contracting Officer by an insurance company which is acceptable to the Contracting Officer. The named insured parties under the policy shall be the Contractor and the United States of America. The amounts of the insurance shall be not less than as follows:
Employer's liability coverage of at least $100,000 is required, except in States with exclusive or monopolistic funds that do not permit workers' compensation to be written by private carriers.
General Liability: $500,000.00 per occurrences.
Automobile liability: $200,000.00 per person; $500,000.00 per occurrence and $20,000.00 property damage.
Each policy shall have a certificate evidencing the insurance coverage. The insurance company shall provide an endorsement to notify the Contracting Officer 30 days prior to the effective date of cancellation or termination of the policy or certificate; or modification of the policy or certificate which may adversely affect the interest of the Government in such insurance. The certificate shall identify the contract number, the name and address of the Contracting Officer, as well as the insured, the policy number and a brief description of contract services to be performed. The contractor shall furnish the Contracting Officer with a copy of an acceptable insurance certificate prior to beginning the work.
(End of clause)
H5. TIME FOR SUBMISSION OF EVIDENCE OF INSURANCE
The Contractor shall provide evidence of the insurance required under this contract within ten (10) days after contract award. Failure to timely submit this evidence, in a form acceptable to the Contracting Officer, may result in rescinding or termination of the contract by the Government.
H6. VOLATILE ORGANIC COMPOUNDS (VOC) COMPLIANCE PLAN
a) Contractor's are required to comply with local VOC laws and regulations and shall have an acceptable
VOC compliance plan. The plan shall demonstrate that the use of paints, solvents, adhesives and cleaners comply with local VOC laws and regulations governing VOC materials, and that all required permits have been obtained or will be obtained prior to starting work involving VOC's, in the air quality district in which the work will be performed.
b) The compliance plan shall be submitted by the Contractor to the Contracting Officer within five (5) calendar days after receipt of contract, and prior to the use of any "VOC" materials on the project site. The Government will approve or disapprove the Contractor's compliance plan within five calendar days after receipt. Should the Government reject the compliance plan, the Contractor shall resubmit a revised compliance plan within three calendar days after receipt of the rejection notification. Failure on the part of the Contractor to submit an acceptable "VOC" plan, shall not be grounds for a time extension to the performance period.
c) An acceptable compliance plan shall contain, as a minimum:
d) A listing of each material subject to restrictions in the air quality management district in question;
e) The rule governing its use;
f) A description of the actions which the Contractor will use to comply with the laws and regulations, and plans to report to the Contracting Officer any changes in the status of compliance during the life of the contract.
g) Alternatively, if no materials are subject to the restrictions in the air quality management district where the work will be performed, or if there are no restrictions, the compliance plan shall so state.
H7.WAGE RATES
Applicable Construction Wage Rate Requirements are in effect at the time of contract and will apply. If crafts or trades are required in the performance of this project for which no wage is listed in the Department of Labor Wage Decision, the Contracting Officer shall be notified in writing.
H8.CERTIFICATION OF PAYMENTS-RELEASE OF CLAIM
The Contractor, prior to receiving a progress or final payment under this contract, shall submit to the Contracting Officer a certification that the Contractor has made payment from proceeds of prior payments, or that he will make timely payment from the proceeds of the progress or final payment then due him, to his subcontractors and suppliers in accordance with his contractual arrangements. The Contractor shall submit to the Contracting Officer, together with his request for final payment, a properly executed Contractor's Release form. Failure to submit this completed release shall result in delay of final payment.
H9.SUBCONTRACT DATA
The Contractor shall submit an executed Statement and Acknowledgment Standard Form 1413, to the Contracting Officer for every subcontractor (including every subcontractor of the second or lower tier) that will be performing work at the construction site. This shall be done before the subcontractor begins work. This form provides an acknowledgment by the subcontractor that mandatory "flow-down" contract clauses have been included in his contract in accordance with FAR Clause 52.222-11. The Prime Contractors will be given copies of Form SF 1413 after award of a contract. Completing this form creates no contractual relationship between subcontractors and the Government.
H10. CONTRACTOR SECURITY REQUIREMENTS
At the Pre-construction Conference [or prior to beginning work on the contract], the Contractor shall provide a list of all on-site personnel, including sub-contractors (including second and third-tier subcontractors) and suppliers, to the Contracting Officer. The contractor shall update this list when changes occur. Contractor personnel not listed may be denied access to the facility. Contractor personnel will be restricted to designated working areas. Any personnel violating this policy may lose access to the facility. Contractor personnel shall have photo identification at all times while working on BIE facilities. Contractors shall provide the COR with 24 hours of advance notice of every delivery to the site (e.g., concrete, lumber, etc...) and provide the company name, delivery person, and phone number of the firm(s) making deliveries. Otherwise access to the BIA facility may be denied. Special security provisions may apply to some requirements. Employees may be required to submit to a background check and be United States citizens.
H11. REAL ID ACT OF 2005
The Real ID Act of 2005 established minimum security standards for license issuance and production and prohibits Federal agencies from accepting for certain purposes driver's licenses and identification cards from states not meeting the Act's minimum standards. To this purpose there are five states that are not in compliance with the Act nor have they received an extension to come into compliance with the act. Those states are Illinois, Minnesota, Missouri, New Mexico and Washington State. Anyone under this contract, to include subcontractors, who holds a driver's license from any of states without approved licenses and require access to a BIE facility will be required to provide identification other than a driver's license to gain access. It is the responsibility of the Contractor to ensure that they are in accordance with the Real ID Act and any other requirements for base access. For the states of Washington and Minnesota an enhanced driver's license is acceptable to gain access. Other forms of identification that are acceptable for BIE facility access are included as an attachment to this modification.
Further information on the Real ID Act can be found here: http://www.dhs.gov/real-id-enforcement-brief#
H12. TEMPORARY FACILITIES
(a) STORAGE: The location for exterior stock piling of materials shall be arranged by the COR and
Project Manager. The Contractor shall be responsible for protecting materials stockpiled against weather, damage, theft, and other risks of loss. The BIA assumes no responsibility for material or equipment left in the storage area.
(b) SANITARY FACILITIES: Toilet facilities may be available for Contractor use. The Contractor shall ensure the facilities remain clean. Contractors may be required to provide toilet facilities at some sites.
(c) WATER AND ELECTRICITY: Water and 120V electricity may be available at no cost to the Contractor. Should water and electricity be available contractor, the Contractor will bear connection costs. Cost of these utility connections and disconnections is the responsibility of the Contractor.
H13. EXISTING UTILITIES
Utility locations when shown are approximate. The contractor shall field verify all utility locations before digging or trenching. This shall include but not be limited to the use of sonic, electronic or magnetic detection devices, by noting pull box and utility box locations at the surface, and by potholing. Contractor shall be responsible for repairing any utilities damaged during construction at no additional cost to the Government.
H14. DIFFERING SITE CONDITION NOTICE
The Contractor shall provide written notice to the Contracting Officer of a differing site condition within 1 day of occurrence following FAR 52.236-2, Differing Site Conditions.
http://www.dhs.gov/real-id-enforcement-brief
H15. DOCUMENTATION OF PROPOSALS FOR EQUITABLE ADJUSTMENTS
a. ITEMIZATION OF PROPOSALS AND REQUESTS. The Contractor shall submit any request for equitable adjustment in the contract price, including any change proposal submitted in accordance with the Changes and Changed Conditions (52.243-5) clause, in the form of a lump sum proposal supported with an itemized breakdown of all increases and decreases in the contract price in the detail required by the Contracting Officer, The request shall include all costs and delays related to or arising out of the change or event giving rise to the proposed adjustment, including any delay…