This is a Request for Quote (RFQ) for electrical construction work issued by the USDA Agricultural Research Service (ARS).

The solicitation seeks a contractor to wire an extruder power system and make it operational at the PWA Healthy Processed Foods Research facility in Albany, California. The work must be completed within 30 days of award, with a mandatory performance bond requirement. This is a Total Small Business set-aside under NAICS code 238210 (Electrical Contractors and Other Wiring Installation Contractors). Prospective offerors must be registered in the System for Awards Management (SAM) with active registration at solicitation closing. Offers are due by May 11, 2026, at 0630 AM CST, with a Request for Information (RFI) deadline of May 4, 2026, at 0630 AM CST. The government intends to make a single award based on Lowest Priced Technically Acceptable (LPTA) methodology. Award will be made as a firm fixed-price commercial construction contract. Offerors must submit a completed Standard Form 1442, proof of California electrical licensing, and all required documentation via email to david.reynolds2@usda.gov. Technical acceptability requires meeting all solicitation requirements; past performance must be rated acceptable, and pricing must be fair and reasonable. The offer validity period is 90 calendar days from the offer due date.

View the file

Other files for this federal contract opportunity

Other files attached to Extruder Power Wiring, newest first.
File Type Posted
Attachment 1 - SOW.pdf PDF
Attachment 2 - Wage Determination CA20260018.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOLICITATION, OFFER,

AND AWARD

2. TYPE OF SOLICITATION

6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.

PAGE OF PAGES

7. ISSUED BY CODE 8. ADDRESS OFFER TO

SOLICITATION

(Construction, Alteration, or Repair)

1. SOLICITATION NO. 3. DATE ISSUED

IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.

9.

INFORMATION CALL

a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."

FOR

SEALED BID (IFB)

NEGOTIATED (RFP)

1167903

USDA ARS ACQUISITION AND PROPERTY D

5601 SUNNYSIDE AVENUE

RM 3-2102

BELTSVILLE MD 20705

ARS-1232SA

DAVID REYNOLDS 970-851-3646

104/22/2026

1232SA26Q0520

INVITATION FOR BID

REQUEST FOR PROPOSAL

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)

A. Project Title: Extruder Power Wiring

B. Competition is set aside for Total Small Business. Applicable NAICS code is

238210, Electrical Contractors and Other Wiring Installation Contractors.

C. Prospective offerors shall be registered with Systems for Awards Management

(SAM) with an active registration at the time of solicitation closing.

D. All Requests for Information (RFIs) are due no later 5/4/26 @0630 AM CST.

11. The Contractor shall begin performance within

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)

13. ADDITIONAL SOLICITATION REQUIREMENTS:

a. Sealed offers in original and is not required.is, b. An offer guarantee

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

d. Offers providing less than

12b. CALENDAR DAYSYES NO

(If "YES", indicate within how many calendar days after award in Item 12b.)

10 30 calendar days and complete it within ________________ ________________ calendar days after receiving

05/11/2026

NSN 7540-01-155-3212

x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________

STANDARD FORM 1442 (Rev. 12/2022)

Prescribed by GSA

FAR(48 CFR) 53.236-1(d)

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)

16. REMITTANCE ADDRESS (Include only if different than item 14.)

CODE FACILITY CODE

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGEMENT OF AMENDMENTS

OFFER (Must be fully completed by offeror)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO THE UNITED STATES CODE AT

26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this document solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE

BY

2PAGE OF

USDA ARS ACQUISITION AND PROPERTY D

5601 SUNNYSIDE AVENUE

RM 3-2102

BELTSVILLE MD 20705

ARS-1232SA

DAVID W. REYNOLDS

28. NEGOTIATED AGREEMENT 29. AWARD

and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations,certifications, and specifications incorporated by reference in or attached to this contract.

copies to issuing office.) Contractor agrees to furnish

10 U.S.C. 3204(a) 41 U.S.C. 3304(a)

STANDARD FORM 1442 (REV. 12/2022) BACK

Continued...

and return

(Contractor is not required to sign this document.) Your offer on this

ITEM NO.

(A)

SUPPLIES/SERVICES

(B)

QUANTITY

(C)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

NAME OF OFFEROR OR CONTRACTOR

3 29

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

1232SA26Q0520

Delivery: 30 Days After Award

Delivery Location Code: ARS-1291H4

PWA HEALTHY PROCESSED FOODS RESEARC

800 BUCHANAN STREET

ALBANY CA 94710 US

0001 Wire Extruder Power and make operational.

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

Extruder Power

1232SA26Q0520

Technical Data - Technical data and supporting documentation associated with this solicitation are available through the following sources:

1. Solicitation Attachments The following documents are included as attachments to this solicitation and can be accessed via the “Attachments/Links” section of the posting.

Attachment 1 – Statement of Work Attachment 2 – Wage Determination

Project Location

Project locations are listed in:

Attachment 1 – Statement of Work

Federal Acquisition Regulation (FAR) and United States Department of Agriculture Acquisition Regulation (AGAR) Clauses and Provisions The clauses and provisions contained herein are applicable to any order awarded as a result of this solicitation. The terms and conditions set forth herein supersede all other terms and conditions.

Acceptance of the order in accordance with (IAW) FAR 12.201-1(b)(2) constitutes acceptance of all terms and conditions contained herein.

As part of the Revolutionary FAR Overhaul (RFO), system updates may lag policy updates. The System for Award Management (SAM) may continue to require entities to complete representations based on provisions that are not included in this solicitation. Contracting officers will rely on representations from offers based on provisions in the solicitation. Entities are not required to, nor are they able to, update their entity registration to remove these representations in SAM.

52.252-2 Clauses Incorporated by Reference Feb 1998 This solicitation incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also the full text of the clause may be accessed electronically at Internet address https://www.acquisition.gov/far-overhaul/far-part-deviation-guide/far-overhaul-part-52

52.212-4 Terms and Conditions—Commercial Products and Commercial Services (Nov 2025) ☐ Alternate I (Nov 2025) of 52.212-4

This is a commercial construction acquisition. FAR 52.212-4 is amended as follows:

(b) Inspection/Acceptance. Inspection and Acceptance will be conducted in accordance with FAR 52.246-12, Inspection of Construction (Aug 1996).

(d) Changes. Changes will be handled in accordance with the following FAR clause(s):

☐ FAR 52.243-4, Changes (Nov 2025)

☒ FAR 52.243-5, Changes and Changed Conditions (Nov 2025) 52.203-17 Contractor Employee Whistleblower Rights (Nov 2023) 52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements (Jan 2017) 52.222-50 Combating Trafficking in Persons (Nov 2025)

☐ Alternate I (Nov 2025) of 52.222-50 52.226-8 Encouraging Contractor Policies to Ban Text Messaging While Driving (May 2024) 52.232-39 Unenforceability of Unauthorized Obligations (Jun 2013) 52.232-40 Providing Accelerated Payments to Small Business Subcontractors (Mar 2023) 52.233-3 Protest After Award (Sep 2025) 52.233-4 Applicable Law for Breach of Contract Claim (Sep 2025) 52.240-91 Security Prohibitions and Exclusions (Nov 2025)

☐ Alternate I (Nov 2025) of 52.240-91 52.244-6 Subcontracts for Commercial Products and Commercial Services (Nov 2025)

The following clauses are applicable if checked:

☐ 52.203-6 Restrictions on Subcontractor Sales to the Government (Jun 2020) with Alternate I (Nov 2021) of 52.203-6 ☐ 52.203-13 Contractor Code of Business Ethics and Conduct (Nov 2021) ☒ 52.204-9 Personal Identity Verification of Contractor Personnel Jan 2011 ☒ 52.204-13 System for Award Management—Maintenance (Nov 2025) ☐ 52.204-91 Contractor identification (Nov 2025) ☐ 52.209-6 Protecting the Government’s Interest When Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment (Sep 2025) ☐ 52.209-9 Updates of Publicly Available Information Regarding Responsibility Matters (Sep 2025) ☒ 52.209-10 Prohibition on Contracting with Inverted Domestic Corporations (Sep 2025) ☐ 52.219-4 Notice of Price Evaluation Preference for HUBZone Small Business Concerns (Nov 2025) ☒ 52.219-6 Notice of Total Small Business Aside (Nov 2025)

☐ Alternate I (Mar 2020).

☐ 52.219-8 Utilization of Small Business Concerns (Nov 2025) ☐ 52.219-9 Small Business Subcontracting Plan (Nov 2025)

☐ Alternate III (Nov 2025) of 52.219-9.

☐ Alternate IV (Nov 2025) of 52.219-9

☐ 52.219-14 Limitations on Subcontracting (Nov 2025) ☐ 52.219-16 Liquidated Damages—Subcontracting Plan (Nov 2025) ☐ 52.219-33 Nonmanufacturer Rule (Nov 2025) ☒ 52.222-3 Convict Labor (June 2003) ☒ 52.222-19 Child Labor—Cooperation with Authorities and Remedies (Nov 2025) ☐ 52.222-35 Equal Opportunity for Veterans (Nov 2025)

☐ Alternate I (Jul 2014) of 52.222-35

☐ 52.222-36 Equal Opportunity for Workers with Disabilities (Nov 2025) ☐ Alternate I (Jul 2014) of 52.222-36

☐ 52.222-37 Employment Reports on Veterans (Nov 2025) ☐ 52.222-40 Notification of Employee Rights Under the National Labor Relations Act (Dec 2010) ☐ 52.222-41 Service Contract Labor Standards (Aug 2018) ☐ 52.222-42 Statement of Equivalent Rates for Federal Hires (May 2014)

This Statement is for Information Only:

It is not a Wage Determination

Employee Class Monetary Wage -- Fringe Benefits

☐ 52.222-43 Fair Labor Standards Act and Service Contract Labor Standards -- Price Adjustment (Multiple Year and Option Contracts) (Aug 2018) ☐ 52.222-44 Fair Labor Standards Act and Service Contract Labor Standards -- Price Adjustment (May 2014) ☐ 52.222-51 Exemption from Application of the Service Contract Labor Standards to Contracts for Maintenance, Calibration, or Repair of Certain Equipment-Requirements (May 2014) ☐ 52.222-53 Exemption from Application of the Service Contract Labor Standards to Contracts for Certain Services-Requirements (Nov 2025) ☐ 52.222-54 Employment Eligibility Verification (Nov 2025) ☒ 52.222-62 Paid Sick Leave Under Executive Order 13706 (Jan 2022) ☒ 52.222-90 Addressing DEI Discrimination by Federal Contractors (Apr 2026) ☒ 52.223-2 Reporting of Biobased Products Under Service and Construction Contracts (Nov 2025) ☐ 52.223-9 Estimate of Percentage of Recovered Material Content for EPA-Designated Items (May 2008)

☐ Alternate I (May 2008) of 52.223-9 ☐ 52.223-11 Ozone-Depleting Substances and High Global Warming Potential Hydrofluorocarbons (Nov 2025) ☐ 52.223-12 Maintenance, Service, Repair, or Disposal of Refrigeration Equipment and Air Conditioners (Nov 2025) ☒ 52.223-23 Sustainable Products and Services (Nov 2025) ☐ 52.224-3 Privacy Training (Jan 2017)

☐ Alternate I (Jan 2017) of 52.224-3 ☐ 52.225-1 Buy American-Supplies (Nov 2025)

☐ Alternate I (Oct 2022) of 52.225-1 ☐ 52.225-3 Buy American--Free Trade Agreements--Israeli Trade Act (Nov 2025)

☐ Alternate II (Nov 2025) of 52.225-3.

☐ Alternate III (Nov 2025) of 52.225-3.

☐ Alternate IV (Oct 2022) of 52.225-3 ☐ 52.225-5 Trade Agreements (Nov 2023) ☐ 52.225-19 Contractor Personnel in a Designated Operational Area or Supporting a Diplomatic or Consular Mission outside the United States (May 2020) ☐ 52.225-26 Contractors Performing Private Security Functions Outside the United States (Oct 2016) ☐ 52.226-4 Notice of Disaster or Emergency Area Set-Aside (Nov 2007) ☐ 52.226-5 Restrictions on Subcontracting Outside Disaster or Emergency Area (Aug 2025) ☐ 52.229-12 Tax on Certain Foreign Procurements ☐ 52.232-29 Terms for Financing of Purchases of Commercial Products and Commercial Services (Nov 2021) ☐ 52.232-30 Installment Payments for Commercial Products and Commercial Services (Nov 2021) ☒ 52.232-33 Payment by Electronic Funds Transfer— System for Award Management (Oct 2018) ☐ 52.232-34 Payment by Electronic Funds Transfer—Other Than System for Award Management (Jul 2013) ☐ 52.232-36 Payment by Third Party (Nov 2025) ☐ 52.240-92 Security Requirements (Nov 2025)

☐ Alternate II (Nov 2025) of 52.240-92 ☐ 52.240-93 Basic Safeguarding of Covered Contractor Information Systems (No 2025) ☐ 52.247-64 Preference for Privately Owned U.S.-Flag Commercial Vessels (Nov 2025)

☐ Alternate I (Apr 2023) of 52.247-64.

☐ Alternate II (Nov 2021) of 52.247-64

The Contractor shall comply with the following FAR Clauses for Commercial Construction.

52.222-6 Construction Wage Rate Requirements 52.222-7 Withholding of Funds 52.222-8 Payrolls and Basic Records 52.222-9 Apprentices and Trainees 52.222-10 Compliance with Copeland Act Requirements 52.222-11 Subcontracts (Labor Standards) 52.222-12 Contract Termination-Debarment 52.222-14 Disputes Concerning Labor Standards 52.222-15 Certificate of Eligibility 52.236-5 Material and Workmanship

The following clauses are applicable when checked:

☐ 52.222-30 Construction Wage Rate Requirements-Price Adjustment (None or Separately Specified Pricing Method (Aug 2018) ☐ 52.222-31 Construction Wage Rate Requirements-Price Adjustment (Percentage Method) (Aug 2018)

☒ 52.222-32 Construction Wage Rate Requirements-Price Adjustment (Actual Method) (Nov 2025) ☒ 52.225-9 Buy American-Construction Materials (Nov 2025) ☐ Alternate I (Oct 2022) of 52.25-9 ☐ 52.225-11 Notice of Buy American Requirement-Construction Materials under Trade Agreements (Nov 2025) ☐ Alternate I (Nov 2025) (of 52.225-11 ☐ Alternate II (Oct 2022) of 52.225-11 ☒ 52.228-2 Additional Bond Security (Oct 1997) ☐ 52.228-5 Insurance-Work on Government Installation (Jan 1997) ☐ 52.228-11 Individual Surety-Pledge of Assets (Feb 2021) ☒ 52.228-13 Alternative Payment Protections (Jul 2020) ☒ 52.228-14 Irrevocable Letter of Credit (Nov 2014) ☐ 52.228-15 Performance and Payment Bonds-Construction (Jun 2020) ☒ 52.228-17 Individual Surety-Pledge of Assets (Bid Guarantee) (Feb 2021) ☒ 52.236-2 Differing Site Conditions (Jul 2025) ☒ 52.236-3 Site Investigation and Conditions Affecting the Work (Jul 2025) ☒ 52.236-6 Superintendent by the Contractor (Jul 2025) ☒ 52.236-7 Permits and Responsibilities (Jul 2025) ☒ 52.236-8 Other Contracts (Jul 2025) ☒ 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements (Jul 2025) ☒ 52.336-10 Operations and Storage Areas (Jul 2025) ☐ 52.236-11 Use and Possession Prior to Completion (Jul 2025) ☒ 52.236-12 Cleaning Up (Jul 2025) ☐ 52.236-13 Accident Prevention (Jul 2025) ☐ Alternate I (Nov 1991) of 52.236-13 ☒ 52.236-14 Availability and Use of Utility Services (Jul 2025) ☐ 52.236-15 Schedules for Construction Contracts (Jul 2025) ☐ 52.236-16 Quantity Surveys (Jul 2025) ☐ Alternate I (Apr 1984) of 52.236-16 ☐ 52.236-17 Layout of Work (Jul 2025) ☐ 52.236-21 Specifications and Drawings for Construction (Jul 2025) ☐ Alternate I (Apr 1984) of 52.236-21 ☐ Alternate II (Apr 1984) of 52.236-21 ☒ 52.242-14 Suspension of Work (Apr 1984) ☐ 52.248-3 Value Engineering (Oct 2025) ☐ Alternate I (Apr 1984) of 52.248-3

Other Applicable Clauses

AGAR Clauses

452.203-71 Anti-Discrimination and Diversity, Equity, and Inclusion (DEI) Compliance (Dec 2025)

(a) By entering into this contract, the Contractor certifies that:

(1) It is compliant with all applicable Federal anti-discrimination laws and the Equal Protection principles of the U.S. Constitution, and it will remain compliant for the duration of the contract.

(2) Neither it nor any subcontractor or teaming partner operates or funds any program, policy, or initiative that promotes DEI in a manner that violates any applicable Federal anti-discrimination laws, including but not limited to Title VI and VII of the Civil Rights Act of 1964, or the Equal Protection principles of the U.S. Constitution, and the Contractor and any subcontractor or teaming partner will not do so for the duration of the contract.

(b) If the Contractor participates in, facilitates, or funds programs that implicate Title VI of the Civil Rights Act of 1964 or Title IX of the Education Amendments of 1972, as amended, including but not limited to grants to or for schools, colleges, universities, 4-H programs, non-governmental organization (NGO) programs, sports programs, and education-related grants to prisons or other detention facilities, the Contractor certifies that it will remain compliant with those laws, including the requirements set forth in Executive Order 14168, Defending Women from Gender Ideology Extremism and Restoring Biological Truth to the Federal Government, and Executive Order 14173, Ending Illegal Discrimination and Restoring Merit-Based Opportunity.

(c) The Contractor affirms that the above requirements are conditions of payment that go to the essence of the contract and are therefore material terms of the contract. Payments under the contract are predicated on compliance with the above requirements, and therefore the Contractor is not eligible for funding under the contract or to retain any funding under the contract absent compliance with the above requirements.

(d) This certification reflects a change in the Government’s position regarding the materiality of the foregoing requirements and therefore any prior payment of similar claims does not reflect the materiality of the foregoing requirements to this contract.

(e) Submission of a knowing false statement relating to Contractor’s compliance with the above requirements and/or eligibility for the contract may subject the Contractor to liability under the False Claims Act, 31 U.S.C. § 3729, and/or criminal liability, including under 18 U.S.C. §§ 287 and 1001.

(f) The Contractor must include the provisions of this clause in all subcontract solicitations.

(g) Failure on the part of the Contractor or its subcontractors to comply with the terms of this clause may be grounds for the Contracting Officer to terminate this contract for default.

(End of Clause)

452.204–70 Modification for Contract Closeout (Apr 2026)

(a) If unliquidated funds in the amount of $1000 or less remain on the contract, the Contracting Officer (Contracting Officer) may issue a unilateral modification for deobligation. The contractor will receive a copy of the modification but is not required to provide a signature. The Contracting Officer will immediately proceed with contract closeout upon completion of the period of performance, receipt and acceptance of supplies or services, and final payment.

(b) For commercial contracts not exceeding the simplified acquisition procedure threshold under FAR 12.001(c), if more than $1,000 in unliquidated funds remain at closeout, the Contracting Officer will issue a bilateral deobligation modification. Only the modification requires the contractor’s signature, though a Release of Claims may be requested. If the required documents are not returned within 60 days, the Contracting Officer will issue a unilateral modification and proceed with closeout once performance is complete, acceptance is confirmed, and final payment is made.

(c) For all other non-commercial or non–cost‑reimbursement contracts, if more than $1,000 in unliquidated funds remain at closeout, the Contracting Officer will issue a bilateral deobligation modification and a Release of Claims, both requiring contractor signature. If these documents are not returned within 120 days, the Contracting Officer will issue a unilateral modification u and proceed with closeout upon completion of performance, acceptance, and final payment.

(End of Clause)

452.204‑71 Personal Identity Verification and Workforce Integrity of Contractor Employees (Apr 2026)

(a) Compliance with PIV Requirements. The contractor must comply with the personal identity verification (PIV) policies and procedures established by the United States Department of Agriculture (USDA) Directives 4620‑002 series, Homeland Security Presidential Directive 12, and any implementing guidance issued by the Contracting Officer. The contractor must appoint a representative responsible for PIV compliance and must maintain a current list of employees eligible for a USDA LincPass or otherwise authorized to perform work under this contract.

(b) PIV Sponsor Availability. The PIV Sponsor for this contract is the designated Government point of contact identified in the contract, typically the COR unless otherwise specified. The Government will notify the contractor of any changes. The contractor remains responsible for meeting all PIV obligations regardless of changes in sponsor availability.

(c) Contractor Workforce Integrity and Accountability. The contractor is fully responsible for ensuring that all individuals performing under this contract are properly vetted, eligible for access, authorized to perform the work, and accurately represented. At a minimum, the contractor must implement lawful and effective internal controls to:

(1) Verify the identity, work authorization, and qualifications of all personnel assigned;

(2) Ensure only the individuals presented to USDA for PIV enrollment or identity verification perform work;

(3) Detect and address indicators of identity fraud, unauthorized substitution, or other workforce integrity risks; and

(4) Ensure continuous oversight of personnel, including remote workers, in accordance with any reporting requirements specified in the Contract.

(d) Mandatory Removal and Replacement. If the Government determines that a contractor employee fails to meet eligibility, security, integrity, or performance requirements, the Contracting Officer may direct the contractor to remove the individual from performance. The contractor must:

(1) Remove the employee immediately upon notice;

(2) Provide a qualified replacement at no additional cost to the Government; and

(3) Ensure continuity of operations so as not to impact mission requirements.

(4) Failure to promptly remove or replace employees when directed may result in remedies including withholding payment, termination, or other actions authorized under this contract.

(e) Impact on Contractor Performance. Contractor compliance with this clause, including timely removal and replacement of personnel, adherence to PIV requirements, and maintenance of workforce integrity, is a material requirement of this contract. Incidents of identity discrepancies, failure to maintain an eligible workforce, submission of personnel who do not match verified identities, unauthorized substitutions, or failure to comply with Government direction may result in termination and will be documented in the contractor’s performance assessment and reflected in the Contractor Performance Assessment Reporting System (CPARS).

(f) Subcontractor Applicability. The contractor must include this clause in all subcontracts requiring routine unaccompanied physical access to a Federally controlled facility and/or routine unaccompanied access to a Federally controlled information system. The contractor is accountable for ensuring subcontractor compliance.

(g) No Government Direction of Hiring Practices. Nothing in this clause authorizes the Government to direct the contractor’s internal hiring processes or require the disclosure of personal information beyond what is authorized by law, regulation, or contract terms. The contractor remains solely responsible for determining lawful methods to meet the requirements of this clause.

(End of Clause)

452.232-71 Progress Payments for Commercial Construction Contracts (Dec 2025)

(a) Contractor entitlement to progress payments. The Contractor may request progress payments monthly as the work proceeds, or at more frequent intervals as determined by the Contracting

Officer, on estimates of work accomplished that meets the standards of quality established under the contract, as approved by the Contracting Officer.

(b) Computation of amounts. Progress payments will be authorized when the payment requested is properly due in accordance with this contract; the work will be performed in accordance with the contract; and there has been no impairment or diminution of the Government’s security under this contract. The Contracting Officer may authorize consideration of:

(5) Materials delivered on site and preparatory work;

(6) Materials delivered to the Contractor at locations other than the site, if:

i. Specifically authorized by the contract; and

ii. The Contractor provides satisfactory evidence of title and intended use in the contract.

(c) Contractor request for progress payments. The Contractor’s request for progress payments shall include the following:

(1) An itemization of the amounts requested, related to the various elements of work required by the contract;

(2) A listing of the amount included for work performed by each subcontractor;

(3) A listing of the total amount of each subcontract;

(4) A listing of the amounts previously paid to each subcontractor; and

(5) Additional supporting data in a form and detail required by the Contracting Officer.

(d) Contractor Certification. Each request for progress payment shall be accompanied by the following certification:

I hereby certify, to the best of my knowledge and belief, that—

(1) The amounts requested are only for performance in accordance with the specifications, terms, and conditions of the contract;

(2) All payments due to subcontractors and suppliers from previous payments received under the contract have been made, and timely payments will be made from the proceeds of the payment covered by this certification, in accordance with subcontract agreements and the requirements of Chapter 39 of Title 31, United States Code;

(3) This request for progress payments does not include any amounts which the prime contractor intends to withhold or retain from a subcontractor or supplier in accordance with the terms and conditions of the subcontract; and

(4) This certification is not to be construed as final acceptance of a subcontractor’s performance.

________________________________________________(name) ________________________________________________(title) ________________________________________________(date)

(e) Access for verification of payment entitlement. To verify the Contractor’s entitlement to progress payments under this contract, the Contractor shall provide the Government, upon request and during normal business hours, access to the following:

(1) Records and Documentation:

(i) Certified progress payment requests and supporting documentation;

(ii) Subcontractor and supplier invoices, payment records, and lien waivers;

(iii)Updated schedule of values and progress schedules;

(iv) Quality assurance and inspection reports;

(v) Payroll records, if applicable under labor provisions.

(2) Facilities and Worksite Access:

(i) Physical access to the construction site for inspection of work progress;

(ii) Access to off-site storage locations for materials billed but not yet incorporated into the work; or (iii)Access to any fabrication facilities where contract-related work is being performed.

(3) Access to electronic invoicing or project management systems used to track progress and payments, if such systems are used in contract performance.

(f) Dates for payment. A progress payment under this clause is a contract progress payment under the Prompt Payment clause of this contract, and except as provided in paragraph (g) of this clause, approved requests shall be paid within 30 days of submittal of a proper request for payment.

(g) Liquidation of progress payments. Progress payments shall be liquidated by deducting from the payment of each item the total unliquidated amount of progress payments made for that separately priced unit of that line item. The liquidation amounts for each line item shall be clearly delineated in each request for progress payment submitted by the Contractor.

(h) Security for progress payments. In the event the Contractor fails to provide adequate security as required in this contract, no progress payment shall be made under this contract. Upon receipt of adequate security, progress payments shall be made, including all previous payments to which the Contractor is entitled, in accordance with the terms of the contract. If at any time the Contracting Officer determines that the security provided by the Contractor is insufficient, the Contractor shall promptly provide such additional security as the Contracting Officer determines necessary. In the event the Contractor fails to provide such additional security, the Contracting Officer may collect or liquidate such security that has been provided, and suspend further payments to the Contractor; the Contractor shall repay to the Government the amount of unliquidated progress payments as the Contracting Officer at his sole discretion deems repayable.

(i) Special terms regarding termination for cause. If this contract is terminated for cause, the Contractor shall, on demand, repay to the Government the amount of unliquidated progress payments. The Government shall be liable for no payment except as provided by the Termination for Cause paragraph of the clause at Federal Acquisition Regulation 52.212-4, Contract Terms and Conditions—Commercial Products and Commercial Services.

(j) Reservation of rights.

(1) No payment, vesting of title under this clause, or other action taken by the Government under this clause shall-

(i) Excuse the Contractor from performance of obligations under this contract; or

(ii) Constitute a waiver of any of the rights or remedies of the parties under the contract.

(2) The Government’s rights and remedies under this clause-

(i) Shall not be exclusive, but rather shall be in addition to any other rights and remedies provided by law or this contract; and

(ii) Shall not be affected by delayed, partial, or omitted exercise of any right, remedy, power, or privilege, nor shall such exercise or any single exercise preclude or impair any further exercise under this clause or the exercise of any other right, power, or privilege of the Government.

(k) Refund of unearned amounts. If the Contractor, after making a certified request for progress payments, discovers that a portion or all of such request constitutes a payment for performance by the Contractor that fails to conform to the specifications, terms, and conditions of this contract (hereinafter referred to as the "unearned amount"), the Contractor shall-

(1) Notify the Contracting Officer of such performance deficiency; and

(2) Be obligated to pay the Government an amount (computed by the Contracting Officer in the manner provided in paragraph (j) of this clause) equal to interest on the unearned amount from the 8th day after the date of receipt of the unearned amount until-

(i) The date the Contractor notifies the Contracting Officer that the performance deficiency has been corrected; or

(ii) The date the Contractor reduces the amount of any subsequent certified request for progress payments by an amount equal to the unearned amount.

(l) Retainage. If the Contracting Officer finds that satisfactory progress was achieved during any period for which a progress payment is to be made, the Contracting Officer shall authorize payment to be made in full. However, if satisfactory progress has not been made, the Contracting Officer may retain a maximum of 10 percent of the amount of the payment until satisfactory progress is achieved. When the work is substantially complete, the Contracting Officer may retain from previously withheld funds and future progress payments that amount the Contracting Officer considers adequate for protection of the Government and shall release to the Contractor all the remaining withheld funds. Also, on completion and acceptance of each separate building, public work, or other division of the contract, for which the price is stated separately in the contract, payment shall be made for the completed work without retention of a percentage.

(m) Title, liability, and reservation of rights. All material and work covered by progress payments made shall, at the time of payment, become the sole property of the Government, but this shall not be construed as-

(1) Relieving the Contractor from the sole responsibility for all material and work upon which payments have been made or the restoration of any damaged work; or

(2) Waiving the right of the Government to require the fulfillment of all the terms of the contract.

(3) The Government’s rights and remedies under this clause-

(i) Shall not be exclusive, but rather shall be in addition to any other rights and remedies provided by law or this contract; and

(ii) Shall not be affected by delayed, partial, or omitted exercise of any right, remedy, power, or privilege, nor shall such exercise or any single exercise preclude or impair any further exercise under this clause or the exercise of any other right, power, or privilege of the Government.

(n) Reimbursement for bond premiums. In making these progress payments, the Government shall, upon request, reimburse the Contractor for the amount of premiums paid for performance and payment bonds (including coinsurance and reinsurance agreements, when applicable) after the Contractor has furnished evidence of full payment to the surety. The retainage provisions in paragraph (l) of this clause shall not apply to that portion of progress payments attributable to bond premiums.

(o) Final payment. The Government shall pay the amount due the Contractor under this contract after-

(1) Completion and acceptance of all work;

(2) Presentation of a properly executed voucher; and

(3) Presentation of release of all claims against the Government arising by virtue of this contract, other than claims, in stated amounts, that the Contractor has specifically excepted from the operation of the release. A release may also be required of the assignee if the Contractor’s claim to amounts payable under this contract has been assigned under the Assignment of Claims Act of1940 ( 31 U.S.C.3727 and 41 U.S.C. 6305).

(p) Limitation because of undefinitized work. Notwithstanding any provision of this contract, progress payments shall not exceed 80 percent on work accomplished on undefinitized contract actions. A "contract action" is any action resulting in a contract, as defined in FAR subpart 2.1, including contract modifications for additional supplies or services, but not including contract modifications that are within the scope and under the terms of the contract, such as contract modifications issued pursuant to the Changes clause, or funding and other administrative changes.

(End of clause)

Special Contract Requirements

1. Directives, Instructions and References: Only the Contracting Officer shall issue directives/instructions defining the roles and responsibilities and appointment of a Contracting Officer Representative (COR); Location Monitor (LM); Project Manager (PM); Occupational Health & Safety Manager and/or any other functional appointment as deemed necessary for the scope of work.

2. Work Management: The Contractor shall manage the total work effort associated with the services required to meet the performance objectives and standards. Such management includes but is not limited to planning, scheduling, cost accounting, report preparation, establishing and maintaining records, and quality control. The Contractor shall provide a staff with the necessary management expertise to assure performance objectives and standards are met.

3. Materials and Equipment: Materials and equipment may not be stored at the job-lay-down area after work hours unless approved in advance by the Contracting Officer. There will not be office space available at any location. All job site lay down areas are dependent upon the size and location of the work. Job site availability will be identified in the Scope of Work.

4. Service Interruptions/ Utility Outages: If any utilities or other services must be discontinued (even temporarily) due to scheduled contract work, the Contractor shall notify the Contracting Officer Representative ten calendar days in advance to allow notification of affected tenants and customers. If the discontinued service is due to an emergency breakdown the Contractor shall notify the Contracting Officer Representative as soon as practicable.

At a minimum, include the location of the outage, utilities being affected, duration of outage and any necessary sketches. Once approved, and prior to beginning work on the utility system requiring shut down, attend a pre- outage coordination meeting with the Contracting Officer to review the scope of work and the lock-out/tag-out procedures for worker protection. No work will be performed on energized electrical circuits unless proof is provided that no other means exist.

5. OSHA: Contractor must maintain a workplace and ensure that workplace conditions conform to applicable OSHA standards.

6. Prime Contract Site Superintendence: The Contractor shall provide an on-site superintendent on this contract. The site superintendent shall be employed and work directly for the Prime Contractor. On-site representation from the prime contractor during construction activities is mandatory, regardless of the type/magnitude of the work being performed by subcontractors. The prime contractor site superintendent may have other duties and may hold “dual hat” responsibilities, but superintendent duties are the first priority of the superintendent.

7. Employee Requirements: The Contractor shall provide experienced, qualified, and capable personnel to perform the work in this contract. Personnel shall be fully knowledgeable of all safety and environmental requirements associated with the work they perform. Competent personnel shall be provided as required by the contract. Contractor staff may be required to obtain a USDA Linc Pass badge. Contractors shall adhere to the most current USDA access or badging requirements.

Documents need to obtain the Linc Pass shall be provided by the Government after award, if required.

8. Employee Conduct/ Removal of Employees: Contractor employees and Subcontractor employees shall conduct themselves in a proper, efficient, courteous and businesslike manner. The Contractor shall remove from the site any individual whose continued employment is deemed by the Contracting Officer to be contrary to the public interest or inconsistent with the best interests of Agricultural Research Service. The Contracting Officers decision is final and not negotiable.

Additionally, reference FAR 52.236-5 Material and Workmanship “The Contracting Officer may require, in writing, that the Contractor remove from the work any employee the Contracting Officer deems incompetent, careless, or otherwise objectionable.”

9. Final Inspection:

a. A final inspection shall be made only when all the materials have been furnished, all the work has been performed, and all the construction provided for by the contract has been completed in accordance with the terms, conditions, specifications, and drawings set forth in this contract. If, upon examination by the Contracting Officer, his/her designated representative, and Government inspection personnel, the project is determined not sufficiently completed to have warranted a final inspection, the Contractor may be held financially liable for any additional cost of re-inspection when material and workmanship are not ready at the time specified by the Government for project inspection.

b. Contractor shall give the Contracting Officer ten (10) calendar days advance notice, in writing, of the date the work will be fully completed and ready for final inspection.

c. The Contracting Officer will notify the Contractor of any discrepancies and/or omissions noted at the final inspection by providing a "punchlist" as to the discrepancies/omissions, replacement of materials and performance or re-performance of any unsatisfactory work necessary for final acceptance. This notification shall not in any way be deemed an extension of the contract completion date. If all construction required by the contract is found completed and all contractual documents (i.e. payrolls, shop/as-builts/red-line drawings, release from claims, etc.) have been submitted, the Contracting Officer shall notify the Contractor of such in writing by processing the final payment for the project.

d. Acceptance shall be final and conclusive, except for latent defects, fraud, or such gross mistakes as may amount to fraud, or regarding the Government’s right under any warranty or guarantee.

10. Final Acceptance: Upon written notification that all deficiencies identified during the final inspection have been corrected, the Contracting Officer will schedule a final acceptance inspection of the work. If all construction required by the contract is determined to be complete and all requisite contract deliverables (e.g., certified payroll records, as- built drawings, warranty documents, etc.)

have been submitted and approved by the Government, the Contracting Officer shall notify the Contractor in writing of such acceptance. Acceptance shall be final and conclusive except for latent defects, fraud, gross mistakes amounting to fraud, or the Government’s rights under any warranty or guarantee.

11. As-Built Drawings: On completion of the contract (if required), one set of paper specifications, and one hard copy and one set of digital PDF or AutoCAD format of each of the contract drawings accompanying those specifications shall be neatly and clearly marked in red to show all variations between the construction actually provided and that indicated or specified and delivered to the CO. Where a choice of materials and/or methods is permitted, the as-built drawings shall define the construction actually provided. Representation of such variation shall conform to standard drafting practice and include such supplementary notes, legends and details as may be necessary. The contractor shall stamp the term RECORD DOCUMENTS, date and sign all plastic reproducible, drawings and volumes of marked specifications. Legibility and clear portrayal of the as-built construction and marked prints shall be subject to approval by the Contracting Officer with the recommended approval of the Engineer.

12. Invoice Preparation and Submission: Based upon acceptance of required contract deliverables, the contractor shall submit an original invoice and one copy to the Contracting Officer and the COR:

The contractor shall include the following information on each invoice in order to be considered a proper invoice:

Name and address of contractor. Invoice number and Invoice date. Contract number.

Description of work and period of performance.

Name, title, phone number, and complete mailing address of official to whom payment is to be sent.

Name, title, phone number, and complete mailing address of person to notify in the event of a defective invoice.

Taxpayer Identification Number (TIN) and SAM UEI Number.

Invoices must be submitted with ARS-371 and ARS-372, along with certified payroll records, Contractor certification, and updated CPM Schedule.

Once the paper invoice has been approved by the Contracting Officer, the Contractor shall submit the invoice electronically through the U.S. Department of Treasury Invoice Processing Platform (IPP) at www.ipp.gov. This is a mandatory requirement.

13. State Taxes and State Tax Exemptions: The Contractor is responsible to include any state taxes into the contract pricing as necessary. The Contractor shall be responsible for knowing the state tax exemption process for the state in which they are proposing. The USDA will not navigate the process or seek out guidance/clarification for the state tax exemption process. The USDA will limit their involvement in the state tax exemption process to simple signature approval of documents and/or submission of Contractor completed documents to an email address, etc. Contractor shall include the state taxes into their proposed offer pricing as necessary. The USDA will not entertain any request for equitable adjustment based upon state tax requirements.

14. Payments for Stored Materials Under Construction Contracts: Payment to a contractor for stored materials is approved on a case-by-case basis, but certain conditions must first be met. Stored material considered acceptable for payment would include equipment and/or material of large dollar value and that will be incorporated into the specific project, such as boilers, transformers, windows, concrete block, brick, steel, etc. Smaller items, such as screws, nails, wiring, conduit, fittings, fasteners, and other items that are readily available from suppliers or other materials that are delivered on an ongoing basis, are not eligible for payment as stored material off-site.

a. Stored Materials on the Job Site: In order to be eligible for payment for materials stored on the job site, the contractor must provide the following to the CO:

1. Identify the specific materials, including a full description, manufacturer, model numbers, quantity, etc.;

2. Demonstrate clear title to the material (e.g., submission of paid invoice(s)); and,

3. Provide a written acknowledgement that they, the construction contractor, are fully responsible and liable for the security of the materials.

The CO does not have to modify the contract to authorize payment for stored materials on the job site; however, the materials and their value must be itemized on the ARS Form 372, Contractor’s Request for Payment Transmittal. The Contracting Officer’s Representative (COR) or other personnel designated by the CO (e.g., Resident Inspector) must verify the presence and quantity of the materials on site to the CO.

b. Stored Materials Off-Site: Payment for material delivered to the Contractor at off-site location(s) is authorized in accordance with FAR Clause 52.232-5 (b)(2) (however this is under the sole discretion of the Contracting Officer who will either approve or disapprove payments for stored materials off-site, the Contractor is not entitled to payments for stored material off-site); provided, the Contractor fully complies with the following conditions:

1. Contractor furnishes evidence to the Contracting Officer that it has acquired title to such material (e.g., paid invoice(s), bill(s) of sale, etc.);

2. Contractor fully identifies the material (description, manufacturer, model number, quantities, etc.) in storage and certifies that said material will be used to perform this contract;

3. Contractor furnishes the exact location of the storage facility and material within it;

4. Contractor furnishes evidence that the storage facility is bonded and insured;

5. Contractor furnishes a written certified acknowledgment from the storage facility that they recognize the USDA Agricultural Research Service, as the owner of the materials;

6. Contractor provides written acknowledgment that it is fully responsible and liable for the security of the materials; and,

7. Contractor furnishes photographs of the material and the storage facility. The contractor must include on each invoice the address of the storage facility and an itemized breakdown of the stored materials. Only the cost for the materials will be paid. The cost for installation must be excluded from the invoiced amount since it will occur at a later time. The costs associated with storing the materials in a storage facility (e.g., rent, lease, etc.) shall not be charged to or paid for by the Government.

Payment for stored materials off-site shall be made only when in the best interest of the Government (USDA). The Contracting Officer has the sole authority to make this decision in which payment(s) will or will not be made for stored materials off-site. At no time will the Contractor have any “right” to demand payment for stored materials off-site.

15. Daily Construction Reports: The Contractor shall maintain a daily record of quality control measures performed for each shift of Contractor or Subcontractor operations on an appropriate format. These records shall provide factual evidence that continuous quality control inspections have been performed, including but not limited to the following: job progress, problems encountered;

problems resolved; type and number of inspections; results of inspections or tests including all computations; nature of defects; causes for rejection; safety violations; proposed remedial action;

and corrective action taken. These records shall cover both conforming and defective items and shall include a statement that all supplies and materials incorporated in the work are in full compliance with the terms of the contract. The Contractor shall maintain a current record of all inspections and shall furnish to the Contracting Officer on a daily basis (or as often as agreed upon with the Contracting Officer), legible copies of all inspection records for his permanent retention.