Spec.pdf
PDF 2 MB Posted
- Attached to
- Multi-year, Multi-Award IDIQ General Construction Federal contract opportunity
- Solicitation number
- SB1341-14-RP-0046
About this file
Task Order - Specs
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| SITE.pdf | ||
| Prebid_Questions_-_Answers.pdf | ||
| site_visit_sign-in.pdf | ||
| workzones.pdf | ||
| Amendment_001_-_SF30.pdf | ||
| 099123_FL_-_INTERIOR_PAINTING.pdf | ||
| Solicitation_-_updated_6-30.pdf | ||
| Drawing_222.pdf | ||
| Drawing_223.pdf | ||
| Davis_Bacon.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NIST CONCOURSES
Bldg’s 222 & 223
100% CONSTRUCTION DOCUMENTS
CONSTRUCTION SPECIFICATIONS
May 16, 2014
100% CD SUBMISSION CONSTRUCTION SPECIFICATIONS
NIST CONCOURSES Bldg’s 222 & 223
Plant Division Page 1 May 16, 2014 National Institute of Standards and Technology Table of contents ToC - 1
PROJECT MANUAL
SPECIFICATION INDEX
DIVISION 1 – GENERAL REQUIREMENTS
011000 Summary 013100 Project Management and Coordination 013200 Construction Progress Documentation 013300 Submittal Procedures 014000 Quality Requirements 014200 References 015000 Temporary Facilities and Controls 015100 Project Construction Signage 015639 Temporary Tree and Plant Protection 016000 Product Requirements 016400 Substitutions Prior to Offering 016401 Product Options and Substitutions After Execution of Contract 017300 Execution 017700 Closeout Procedures 017823 Operation and Maintenance Data 017839 Project Record Documents
DIVISION 02 – SITE CONSTRUCTION
024119 Selective Structure Demolition
DIVISION 03 – CONCRETE
033000 Cast-In-Place Concrete
DIVISION 05
054000 Cold Formed Metal Framing
DIVISION09
092900 Gypsum Board
DIVISION 04, 06, 07, 08, 10, & Following 054000 Cold Formed Metal Framing
END
Plant Division
Summary
Page 1 June 24, 2014
011000 - 1
NIST
NIST CONCOURSES BLDG’S 222 & 223
SECTION 011000 - SUMMARY
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes:
1. Project information.
2. Work covered by Contract Documents.
3. Work by Contracting Officer.
4. Work under separate contracts.
5. Purchase contracts.
6. Contractor-furnished, Contracting Officer-installed products.
7. Work restrictions.
8. Specification and drawing conventions.
B. Related Section:
1. Division 01 Section "Temporary Facilities and Controls" for limitations and procedures governing temporary use of Contracting Officer’s facilities.
1.3 PROJECT INFORMATION
A. Project Identification: Concourse Floor and Door Repairs, Buildings 222 and 223
1. Project Location: Buildings 222 and 223; National Institute of Standards and Technology (NIST), Gaithersburg, MD Campus
B. Project Duration: All work shall be completed within 120 calendar days from the issuance of . the Notice-to-Proceed (NTP).
1.4 WORK COVERED BY CONTRACT DOCUMENTS
A. The Work of the Project is defined by the Contract Documents and consists of the following:
Summary
Page 2 June 24, 2014
011000 - 2
1. The project consists of select interior concrete slab on grade removal and installation of new structural concrete slab with supporting concrete beam construction in order to remedy slab and entry door deflection distress. Construction includes installation of new structural framing per the contract drawings with the potential for utility relocation upon discovery.
1.5 WORK RESTRICTIONS
A. Work Restrictions, General: Comply with restrictions on construction operations.
1. Comply with limitations on use of public streets and other requirements of authorities having jurisdiction.
B. On-Site Work Hours: Limit work in the existing building to weekend hours of 6:00p.m.Friday through 11:00pm Sunday on indicated in Sheet Note 4 noted on Drawings 222-294 and 223-388, unless otherwise approved by the COR. Approval to work during times other than specified above must be approved in writing by the COR at least 72 hours in advance of the planned work date.
C. Nonsmoking Building: Smoking is not permitted within the building or within 25 feet of entrances, operable windows, or outdoor air intakes.
1.6 ACCESS TO SITE
A. General: Contractor shall have limited use of Project site for construction operations as indicated on Drawings by the Contract limits and as indicated by requirements of this Section.
B. Use of Site: Limit use of Project site to areas within the contract limits indicated. Do not disturb portions of Project site beyond areas in which the Work is indicated.
1. Limits: Confine construction operations to limits of disturbance as indicated on drawings.
2. Driveways, Walkways, and Entrances: Keep driveways and entrances serving the premises clear and available to the Contracting Officer, Contracting Officer’s representatives, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.
3. Parking: Parking will be restricted to the area shown adjacent to the laydown area.
Requests for additional or alternate parking should be made in writing to the COR.
Fifteen (15) feet of clearance shall be maintained around all fire hydrants at all times.
4. The Contractor and his employees and subcontractors shall become familiar with and obey all NIST Site Regulations, including fire, traffic, and security regulations. All personnel employed on the site shall keep within the limits of the work (and avenues of ingress and egress), and shall not enter any restricted areas unless required to do so and are cleared for such entry. The Contractor’s equipment shall be conspicuously marked for identification.
5. Material Storage: All materials shall be stored in the lay down area. The Contractor shall adequately protect all materials from the weather.
1.7 SPECIFICATION AND DRAWING CONVENTIONS
Summary
Page 3 June 24, 2014
011000 - 3
A. Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations.
These conventions are as follows:
1. Imperative mood and streamlined language are generally used in the Specifications. The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.
2. Specification requirements are to be performed by Contractor unless specifically stated otherwise.
B. Division 01 General Requirements: Requirements of Sections in Division 01 apply to the Work of all Sections in the Specifications.
C. Drawing Coordination: Requirements for materials and products identified on the Drawings are described in detail in the Specifications. One or more of the following are used on the Drawings to identify materials and products:
1. Terminology: Materials and products are identified by the typical generic terms used in the individual Specifications Sections.
2. Abbreviations: Materials and products are identified by abbreviations published as part of the U.S. National CAD Standard and scheduled on Drawings.
3. Keynoting: Materials and products are identified by reference keynotes referencing
Specification Section numbers found in this Project Manual.
1.8 MISCELLANEOUS PROVISIONS
A. Public Release of Information:
1. The Contractor shall not publicly release information, photographs, or other documents concerning any aspect of the materials or services relating to this bid, contract, or purchase order without the prior written approval of the Contracting Officer.
2. Insert the substance of clause “#1” above in each sub-contract and purchase order related to this project.
B. Permits: In addition to the requirements of the clause entitled “Permits and Responsibilities”, permits are required for but not necessarily limited to welding, and burning,. Prior to commencing these activities, the Contractor shall submit an application for a permit to the COR.
C. Asbestos Material: No asbestos containing material is expected to be encountered by the
Contractor on this project. If material is encountered that looks suspicious but must be disturbed, do not touch the material and immediately notify the COR in writing. Within fourteen (14) calendar days, the Government will perform laboratory tests to determine if there is asbestos. If asbestos is not a danger, the Contracting Officer will direct the Contractor to proceed without change. If the material encountered is asbestos and must handled, the Contracting Officer will direct a change.
Summary
Page 4 June 24, 2014
011000 - 4
1.9 OCCUPATIONAL SAFETY AND HEALTH
A. NIST, as a Federal government facility in the State of Maryland, is under the jurisdiction of the OSHA Region III regional office, which may assign an OSHA Compliance Safety and Health Officer (CSHO) to conduct safety and health inspections of the Contractor’s operations at the NIST Gaithersburg site. Accordingly, the Contractor is subject to OSHA Citations and Notices of Penalty for noncompliance with OSHA standards. To protect its own interests, NIST may also conduct periodic safety and health inspections to assure that NIST employees/property are not at risk of injury/damage from Contractor operations, and to avoid the risk of OSHA Citations under the OSHA multi-employer worksite provisions.
1. Pre-work Safety Meeting: Representatives of the Contractor shall meet with the
Contracting Officer and his/her safety representative(s) prior to the start of work under this contract for the purpose of reviewing the Contractor’s safety and health programs and discussing implementation of all safety and health provisions pertinent to the work to be performed under the contract. The Contractor shall be prepared to discuss, in detail, the measures he/she intends to take in order to control any unsafe or unhealthy conditions associated with the work to be performed under the contract. If directed by the Contracting Officer, this meeting may be held in conjunction with other meetings which are scheduled to take place prior to start of work under this contract. The level of detail for the safety meeting is dependent upon the nature of the work and the potential inherent hazards. The Contractor’s principal on-site representative(s), the general superintendent, and his/her safety representative(s) shall attend this meeting.
2. Safety and Health Standards Compliance: The Contractor shall comply (and shall ensure that firms acting as agents or subcontractors to the prime Contractor also comply) with all applicable OSHA Safety and Health Standards for Construction (29CFR1926) and OSHA General Industry Occupational Safety and Health Standards (29CFR1910). Additionally, the Contractor shall comply with all applicable site safety and health requirements. The NIST Safety Office will provide guidance/consultation regarding specific site requirements.
3. Special Emphasis Standards: While the Contractor is responsible for compliance with all applicable OSHA Safety and Health Standards, special emphasis will be placed upon the following:
a. Fall Protection: Fall protection measures shall be implemented as required via use of suitable guardrails/ barricades; safety belts/harnesses/lanyards/ lifelines; safety nets; or other approved means. Particular emphasis is to be focused on the requirements stipulated in Subpart L (Scaffolding), Subpart M (Floor and Wall Openings), Subpart R (Steel Erection) and Subpart X (Stairways and Ladders) of 29CFR1926 (Safety and Health Standards for Construction).
b. Excavations and Trenching: With regard to excavations (including trenches), the soil at the NIST Gaithersburg site shall be considered previously excavated and therefore unstable. Accordingly, persons entering excavations five (5) or more feet deep shall be protected from cave-ins by an adequate protective system designed in accordance with the requirements of 29CFR1926.652(b) or (c). All other applicable requirements for excavations as contained in Subpart P (Excavations) of 29CFR1926 shall be implemented.
Summary
Page 5 June 24, 2014
011000 - 5
c. Confined Spaces: Entry into permit-required confined spaces must be in accordance with the requirements stipulated in the OSHA Permit-Required Confined Space standard (29CFR1910.146). The Contractor shall be responsible for all confined space entry requirements including personnel training, documented entry permit system, atmospheric contractor funded testing/ monitoring, forced ventilation, personal protective equipment, and emergency procedures/equipment.
d. Hazard Communication: As applicable (i.e., when chemicals are used on-site by the Contractor), the Contractor shall develop, implement and maintain at the workplace a written hazard communication program meeting the requirements of 29CFR1926.59 (for construction contracts) or 29CFR1910.1200 (for other than construction contracts). The contractor shall ensure that each container of hazardous chemicals at the worksite is labeled, tagged or otherwise marked with the identity of the hazardous chemical(s) contained therein and that such markings show hazard warnings appropriate for employee protection. The Contractor shall provide employees with information and training on hazardous chemicals in their work area at the time of initial assignment and whenever a new hazardous chemical is introduced into their work area. The Contractor shall also provide employees with information on any operations in their work area where hazardous chemicals are present; and the location and availability of the written hazard communication program, including the required list(s) of hazardous chemicals, and material safety data sheets (MSDS) required by the standard.
e. Control of Hazardous Energy (Lockout/Tag out): In accordance with the provisions of OSHA standards 29CFR1910.147 and 29CFR1926.417, the Contractor shall establish and implement a program consisting of energy control procedures, employee training and periodic inspections to ensure that before any employee performs any servicing or maintenance on electrical circuits/equipment, machines or other equipment/systems where the unexpected energizing, start up or release of stored energy could occur and cause injury, the circuit/machine/equipment/system shall be isolated from the energy source and rendered inoperative.
f. Electrical Installations and Work Practices: The Contractor shall comply with all applicable installation safety requirements, safety-related maintenance and environmental considerations, and safety requirements for special equipment as contained in Subpart K (Electrical) of 29CFR1926.
g. Personal Protective and Life Saving Equipment: In accordance with the provisions of Subpart E (Personal Protective and Life Saving Equipment) of 29CFR1926, the Contractor shall ensure that protective equipment (including personal protective equipment for eyes, head, face, head and extremities; protective clothing;
respiratory devices; and protective shields and barriers) shall be provided, used and maintained in a sanitary and reliable condition whenever it is necessary by reason of hazards of process or environment, chemical hazards, radiological hazards, or mechanical irritants encountered in a manner capable of causing injury or impairment in the function of the body through absorption, inhalation or physical contact.
Summary
Page 6 June 24, 2014
011000 - 6
h. Tools-Hand and Power: The Contractor shall ensure compliance with all applicable safety requirements for tools (hand and power) as outlined in Subpart I (Tools-Hand and Power) of 29CFR1926.
i. Welding and Cutting: The Contractor shall ensure compliance with all applicable safety requirements pertaining to welding and cutting operations as outlined in Subpart J (Welding and Cutting) of 29CFR1926.
j. Motor Vehicles and Mechanized Equipment: The Contractor shall ensure compliance with the safety requirements pertaining to motor vehicles and mechanized equipment (materials handling equipment and pile driving equipment) as contained in Subpart O (Motor Vehicles, Mechanized Equipment, and Marine Operations) of 29CFR1926.
4. General Site Safety Requirements: For the protection of NIST employees, other agency employees and the general public, the following general worksite safety requirements shall be observed by the Contractor.
a. Precautions: The Contractor shall take all necessary precautions to prevent injury to the public, building occupants, and damage to property of others. For the purposes of this contract, the public or building occupants shall include all persons not employed by the Contractor or a subcontractor working under his/her direction.
b. Housekeeping: Form and scrap lumber with protruding nails/fasteners and all other debris shall be kept clear from all work areas. Combustible scrap and debris shall be removed at regular intervals. Containers shall be provided for collection and separation of all refuse. Covers shall be provided on containers used for flammable or harmful substances. Wastes should be disposed of at frequent intervals.
c. Storage: Storing, positioning, and use of equipment, tools, materials, scraps, and trash in a manner likely to present a hazard to the public or building occupants by its accidental shifting, ignition, or other hazardous qualities is prohibited.
d. Obstructions: No corridor, aisle, stairway, door, or exit shall be obstructed or used in such a manner as to encroach upon routes or ingress or egress utilized by the public or building occupant, or to present un-safe or unhealthy condition to the public or building occupant.
e. Radiation Safety: the Contractor shall not bring to or use at NIST any radioactive materials or radio-graphic devices without explicit prior approval from Health Physics for each use of such devices. Any such use shall be in compliance with restrictions and procedures prescribed by NIST Health Physics (Bldg. 245, Room C125, x5800). Any work conducted in a NIST Restricted Area (as defined by the Nuclear Regulatory Commission and applied by NIST) shall comply with NIST procedural requirements and, in particular, specific training requirements for all persons entering that area. No area posted with Radioactive Material, Radiation Area, High Radiation Area, or Very High Radiation Area sign shall be entered without prior approval from Health Physics (i.e., all work in such areas requires prior clearance from NIST Health Physics).
Summary
Page 7 June 24, 2014
011000 - 7
f. Work Area Restrictions: Work shall not be performed in any area occupied by the public or Federal employees unless specifically permitted by the contract or the Contracting Officer and unless adequate steps are taken for the protection of the public or Federal employees.
g. Fences and Barricades: Wherever practicable, the work area shall be fenced, barricaded, or otherwise blocked off from the public or building occupants to prevent unauthorized entry into the work area.
h. Alternate Precautions: When the nature of the work prevents isolation of the work area and the public or building occupants may be in or pass through, under, or over the work area, alternate precautions such as the posting of signs, the use of signal persons, the erection of barricades, or similar protection around particularly hazardous operations shall be used as appropriate.
i. Public Thoroughfare: When work is to be performed over a public thoroughfare, such as a sidewalk, road, lobby, or corridor, the thoroughfare shall be closed, if possible, or other precautions taken such as the installation of screens or barricades.
j. Removal of Fences and Barricades: Fences and barricades shall be removed upon completion of the project, in accordance with local ordinance and to the satisfaction of the Contracting Officer or his/her representative(s).
1.10 SALVAGE
A. The Government does not assume responsibility for any loss or damage to materials or structures on the site salvage value of which the Contractor may have reflected in his bid.
1.11 CEREMONIES
A. Subject to mutually satisfactory agreements between the parties of the contract, the Government may enter the premises during the term of the contract to conduct ceremonies, such as laying the cornerstone or dedication ceremonies, and to occupy temporarily such portions of the premises as may be necessary.
1.12 PUBLIC RELEASE OF INFORMATION
A. The contractor shall not publicly release information, photographs, or other documents concerning any aspect of the materials or services relating to this bid, contract, or purchase order without the prior written approval of the Contracting Officer.
Summary
Page 8 June 24, 2014
011000 - 8
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 011000
Project Management and Coordination 013100 - 1
SECTION 013100 - PROJECT MANAGEMENT AND COORDINATION
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:
1. General project coordination procedures.
2. Administrative and supervisory personnel.
3. Coordination drawings.
4. Requests for Information (RFIs).
5. Project meetings.
6. Inspections
B. Each contractor shall participate in coordination requirements. Certain areas of responsibility are assigned to a specific contractor.
C. Related Sections:
1. Division 01 Section "Construction Progress Documentation" for preparing and submitting Contractor's construction schedule.
2. Division 01 Section "Execution" for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.
3. Division 01 Section "Closeout Procedures" for coordinating closeout of the Contract.
4. Division 01 Section "General Commissioning Requirements" for coordinating the Work with Contracting Officer's commissioning authority.
1.3 DEFINITIONS
A. RFI: Request from Contracting Officer, COR, or Contractor seeking information from each other during construction.
Plant Division Page 2 May 16, 2014
Project Management and Coordination 013100 - 2
1.4 DOCUMENTATION FOR CONTRACTOR
A. In addition to one set of reproducible large-scale contract drawings, a set of electronic files of the contract drawings will be furnished to the Contractor without charge. Additional sets will be furnished on request at the cost of reproduction.
B. Omissions from the drawings or specifications or the mis-description of details of work which are manifestly necessary to carry out the intent of the drawings and specifications, or which are customarily performed, shall not relieve the Contractor from performing such omitted or mis-described details of the work but they shall be performed as if fully and correctly set forth and described in the drawings and specifications.
C. The Contractor shall check all drawings and specifications furnished him immediately upon their receipt and shall in writing within fourteen (14) calendar days from receipt of award, notify the Contracting Officer of any discrepancies. Figures marked on drawings shall in general be followed in preference to scale measurements. Large-scale drawings shall in general govern small-scale drawings; the Contractor shall compare all drawings and verify the figures before laying out the work and will be responsible for any errors which might have been avoided thereby.
1.5 INFORMATIONAL SUBMITTALS
A. Subcontract List: Prepare a written summary identifying individuals or firms proposed for each portion of the Work, including those who are to furnish products or equipment fabricated to a special design. Use CSI Form 1.5A. Include the following information in tabular form:
1. Name, address, and telephone number of entity performing subcontract or supplying products.
2. Number and title of related Specification Section(s) covered by subcontract.
3. Drawing number and detail references, as appropriate, covered by subcontract.
B. Key Personnel Names: Prior to 15 days of starting construction operations, submit a list of key personnel assignments, including superintendent and other personnel in attendance at Project site. Any changes to the key personnel shall be submitted for Approval in advance. Identify individuals and their duties and responsibilities; list addresses and telephone numbers, including home, office, and cellular telephone numbers and e-mail addresses. Provide names, addresses, and telephone numbers of individuals assigned as alternates in the absence of individuals assigned to Project.
1. Post copies of list in project meeting room, in temporary field office and by each temporary telephone. Keep list current at all times.
Plant Division Page 3 May 16, 2014
Project Management and Coordination 013100 - 3
1.6 COORDINATION
A. Coordination: Coordinate construction operations included in different Sections of the Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections that depend on each other for proper installation, connection, and operation.
1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.
2. Coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair.
3. Make adequate provisions to accommodate items scheduled for later installation.
B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.
1. Prepare similar memoranda for Contracting Officer and separate contractors if coordination of their Work is required.
C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:
1. Preparation of Contractor's construction schedule.
2. Preparation of the schedule of values.
3. Installation and removal of temporary facilities and controls.
4. Delivery and processing of submittals.
5. Progress meetings.
6. Preinstallation conferences.
7. Project closeout activities.
8. Startup and adjustment of systems.
9. Project closeout activities.
D. Conservation: Coordinate construction activities to ensure that operations are carried out with consideration given to conservation of energy, water, and materials. Coordinate use of temporary utilities to minimize waste. The Contractor must also provide manufacturer’s Material Data Safety Sheets (MSDS), VOC limits and other material content or manufacturing specification information as required and noted in subsequent Specification sections.
1.7 AS BUILT DRAWINGS
A. The Contractor shall maintain at the job site one set of full-size contract drawings marked to show any changes and/or revisions which have been made from the contract drawings, Plant Division Page 4 May 16, 2014
Project Management and Coordination 013100 - 4 including buried or concealed construction and utility features revealed during the course of construction. The Contractor shall record the horizontal and vertical location of all buried utilities that differ from the contract drawings. These drawings shall be available for review by the COR at all times. Upon completion of the work, the Contractor shall deliver the marked sets of prints to the COR in the original units of measure. Requests for partial payments will not be approved if the marked prints are not current, and request for final payment will not be approved until the marked prints are delivered to the Contracting Officer.
1.8 REQUESTS FOR INFORMATION (RFIs)
A. General: Immediately on discovery of the need for additional information or interpretation of the Contract Documents, Contractor shall prepare and submit an RFI in the form specified.
1. COR will return RFIs submitted to COR by other entities controlled by Contractor with no response.
2. Coordinate and submit RFIs in a prompt manner so as to avoid delays in Contractor's work or work of subcontractors.
B. Content of the RFI: Include a detailed, legible description of item needing information or interpretation and the following:
1. Project name.
2. Project number.
3. Date.
4. Name of Contractor.
5. Name of COR.
6. RFI number, numbered sequentially.
7. RFI subject.
8. Specification Section number and title and related paragraphs, as appropriate.
9. Drawing number and detail references, as appropriate.
10. Field dimensions and conditions, as appropriate.
11. Contractor's suggested resolution. If Contractor's solution(s) impacts the Contract Time or the Contract Sum, Contractor shall state impact in the RFI.
12. Contractor's signature.
13. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop
Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.
a. Include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments on attached sketches.
C. RFI Forms: Provide template form that is agreeable to the COR.
Plant Division Page 5 May 16, 2014
Project Management and Coordination 013100 - 5
D. COR's Action: COR will review each RFI, determine action required, and respond. Allow 10 calendar days for COR's response for each RFI. RFIs received by COR after 1:00 p.m. will be considered as received the following working day.
1. The following RFIs will be returned without action:
a. Requests for approval of submittals.
b. Requests for approval of substitutions.
c. Requests for coordination information already indicated in the Contract
Documents.
d. Requests for adjustments in the Contract Time or the Contract Sum.
e. Requests for interpretation of COTR's actions on submittals.
f. Incomplete RFIs or inaccurately prepared RFIs.
2. COR's action may include a request for additional information, in which case COR's time for response will date from time of receipt of additional information.
3. COR's action on RFIs that may result in a change to the Contract Time or the Contract Sum may be eligible for Contractor to submit Change Proposal according to Division 01 Section "Contract Modification Procedures."
a. If Contractor believes the RFI response warrants change in the Contract Time or the Contract Sum, notify the Contracting Officer in accordance with the Changes clause.
E. On receipt of COR's action, update the RFI log and immediately distribute the RFI response to affected parties. Review response and notify COR within seven days if Contractor disagrees with response.
F. RFI Log: Prepare, maintain, and submit a tabular log of RFIs organized by the RFI number.
Submit log weekly. Include the following:
1. Project name.
2. Name and address of Contractor.
3. Name and address of COR.
4. RFI number including RFIs that were dropped and not submitted.
5. RFI description.
6. Date the RFI was submitted.
7. Date COR's response was received.
1.9 PROJECT MEETINGS
A. General: Schedule and conduct meetings and conferences at Project site, unless otherwise indicated.
Plant Division Page 6 May 16, 2014
Project Management and Coordination 013100 - 6
1. Attendees: Inform participants and others involved, and individuals whose presence is required, of date and time of each meeting. Notify COR of scheduled meeting dates and times.
2. Agenda: Prepare the meeting agenda. Distribute the agenda to all invited attendees.
3. Minutes: Entity responsible for conducting meeting will record significant discussions and agreements achieved. Distribute the meeting minutes to everyone concerned, including Contracting Officer, and COR, within three days of the meeting.
4. Performance of the contract includes the Contractor attending all meetings deemed necessary by the Contracting Officer.
B. Preconstruction Conference: CO will schedule and conduct a preconstruction conference before starting construction, at a time convenient to Contracting Officer and COR, but no later than 15 days after execution of the Agreement.
1. Conduct the conference to review responsibilities and personnel assignments.
2. Attendees: Authorized representatives of Contracting Officer, COR, and their consultants; Contractor and its superintendent; major subcontractors; suppliers; and other concerned parties shall attend the conference. Participants at the conference shall be familiar with Project and authorized to conclude matters relating to the Work.
3. Agenda: Discuss items of significance that could affect progress, including the following:
a. Tentative construction schedule.
b. Critical work sequencing and long-lead items.
c. Designation of key personnel and their duties.
d. Lines of communications.
e. Procedures for processing field decisions and Change Orders.
f. Procedures for RFIs.
g. Procedures for testing and inspecting.
h. Procedures for processing Applications for Payment.
i. Distribution of the Contract Documents.
j. Submittal procedures.
k. Sustainable design requirements.
l. Preparation of record documents.
m. Use of the premises.
n. Work restrictions.
o. Working hours.
p. Contracting Officer's occupancy requirements.
q. Responsibility for temporary facilities and controls.
r. Procedures for moisture and mold control.
s. Procedures for disruptions and shutdowns.
t. Construction waste management and recycling.
u. Parking availability.
v. Office, work, and storage areas.
w. Equipment deliveries and priorities.
x. First aid.
Plant Division Page 7 May 16, 2014
Project Management and Coordination 013100 - 7
y. Security.
z. Progress cleaning.
4. Minutes: Entity responsible for conducting meeting will record and distribute meeting minutes.
C. Preinstallation Conferences: Conduct a preinstallation conference at Project site before each construction activity that requires coordination with other construction.
1. Attendees: Installer and representatives of manufacturers and fabricators involved in or affected by the installation and its coordination or integration with other materials and installations that have preceded or will follow, shall attend the meeting. Advice COR of scheduled meeting dates.
2. Agenda: Review progress of other construction activities and preparations for the particular activity under consideration, including requirements for the following:
a. Contract Documents.
b. Options.
c. Related RFIs.
d. Related Change Orders.
e. Purchases.
f. Deliveries.
g. Submittals.
h. Review of mockups.
i. Possible conflicts.
j. Compatibility requirements.
k. Time schedules.
l. Weather limitations.
m. Manufacturer's written instructions.
n. Warranty requirements.
o. Compatibility of materials.
p. Acceptability of substrates.
q. Temporary facilities and controls.
r. Space and access limitations.
s. Regulations of authorities having jurisdiction.
t. Testing and inspecting requirements.
u. Installation procedures.
v. Coordination with other work.
w. Required performance results.
x. Protection of adjacent work.
y. Protection of construction and personnel.
3. Record significant conference discussions, agreements, and disagreements, including required corrective measures and actions.
4. Reporting: Distribute minutes of the meeting to each party present and to other parties requiring information.
Plant Division Page 8 May 16, 2014
Project Management and Coordination 013100 - 8
5. Do not proceed with installation if the conference cannot be successfully concluded.
Initiate whatever actions are necessary to resolve impediments to performance of the Work and reconvene the conference at earliest feasible date.
D. Project Closeout Conference: Schedule and conduct a Project closeout conference, at a time convenient to Contracting Officer and COR, but no later than 90 days prior to the scheduled date of Substantial Completion.
1. Conduct the conference to review requirements and responsibilities related to Project closeout.
2. Attendees: Authorized representatives of Contracting Officer, COR, and their consultants; Contractor and its superintendent; major subcontractors; suppliers; and other concerned parties shall attend the meeting. Participants at the meeting shall be familiar with Project and authorized to conclude matters relating to the Work.
3. Agenda: Discuss items of significance that could affect or delay Project closeout, including the following:
a. Preparation of record documents.
b. Procedures required prior to inspection for Substantial Completion and for final inspection for acceptance.
c. Submittal of written warranties.
d. Requirements for preparing operations and maintenance data.
e. Requirements for delivery of material samples, attic stock, and spare parts.
f. Requirements for demonstration and training.
g. Preparation of Contractor's punch list.
h. Procedures for processing Applications for Payment at Substantial Completion and for final payment.
i. Submittal procedures.
j. Coordination of separate contracts.
k. Contracting Officer's partial occupancy requirements.
l. Installation of Contracting Officer's furniture, fixtures, and equipment.
m. Responsibility for removing temporary facilities and controls.
4. Minutes: Entity conducting meeting will record and distribute meeting minutes.
E. Progress Meetings: Conduct progress meetings at biweekly intervals.
1. Coordinate dates of meetings with preparation of payment requests.
2. Attendees: In addition to representatives of Contracting Officer and COR, each contractor, subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented at these meetings. All participants at the meeting shall be familiar with Project and authorized to conclude matters relating to the Work.
3. Agenda: Review and correct or approve minutes of previous progress meeting; distribute corrected meeting minutes within 48 hours. Review other items of significance that could affect progress. Include topics for discussion as appropriate to status of Project.
Plant Division Page 9 May 16, 2014
Project Management and Coordination 013100 - 9
a. Contractor's Construction Schedule: Review progress since the last meeting.
Determine whether each activity is on time, ahead of schedule, or behind schedule, in relation to Contractor's construction schedule. Determine how construction behind schedule will be expedited; secure commitments from parties involved to do so. Discuss whether schedule revisions are required to ensure that current and subsequent activities will be completed within the Contract Time.
1) Review schedule for next period.
b. Review present and future needs of each entity present, including the following:
1) Interface requirements.
2) Sequence of operations.
3) Status of submittals.
4) Deliveries.
5) Off-site fabrication.
6) Access.
7) Site utilization.
8) Temporary facilities and controls.
9) Progress cleaning.
10) Quality and work standards.
11) Status of correction of deficient items.
12) Field observations.
13) Status of RFIs.
14) Status of proposal requests.
15) Pending changes.
16) Status of Change Orders.
17) Pending claims and disputes.
18) Documentation of information for payment requests.
4. Minutes: Contractor shall be responsible for conducting the meeting, will record, and distribute the meeting minutes to each party present and to parties requiring information.
a. Schedule Updating: Revise Contractor's construction schedule after each progress meeting where revisions to the schedule have been made or recognized. Issue revised schedule concurrently with the report of each meeting.
F. Coordination Meetings: Conduct Project coordination meetings at regular intervals. Project coordination meetings are in addition to specific meetings held for other purposes, such as progress meetings and pre-installation conferences.
1. Attendees: In addition to representatives of Contracting Officer and COR, each contractor, subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented at these meetings. All participants at the meetings shall be familiar with Project and authorized to conclude matters relating to the Work.
Plant Division Page 10 May 16, 2014
Project Management and Coordination 013100 - 10
2. Agenda: Review and correct or approve minutes of the previous coordination meeting.
Review other items of significance that could affect progress. Include topics for discussion as appropriate to status of Project.
a. Combined Contractor's Construction Schedule: Review progress since the last coordination meeting. Determine whether each contract is on time, ahead of schedule, or behind schedule, in relation to combined Contractor's construction schedule. Determine how construction behind schedule will be expedited; secure commitments from parties involved to do so. Discuss whether schedule revisions are required to ensure that current and subsequent activities will be completed within the Contract Time.
b. Schedule Updating: Revise combined Contractor's construction schedule after each coordination meeting where revisions to the schedule have been made or recognized. Issue revised schedule concurrently with report of each meeting.
c. Review present and future needs of each contractor present, including the following:
1) Interface requirements.
2) Sequence of operations.
3) Status of submittals.
4) Deliveries.
5) Off-site fabrication.
6) Access.
7) Site utilization.
8) Temporary facilities and controls.
9) Work hours.
10) Hazards and risks.
11) Progress cleaning.
12) Quality and work standards.
13) Change Orders.
3. Reporting: Record meeting results and distribute copies to everyone in attendance and to others affected by decisions or actions resulting from each meeting.
1.10 SCHEDULING OF INSPECTIONS
A. When specified inspections or tests are required by the Contract Documents, the work involved shall not proceed beyond the point until such inspections or tests have been approved by the COR. The Contractor shall inform the COR of progress of the work and shall give the COR a minimum of three (3) working days written notice of appropriate times for specified inspections and tests. The Contractor shall insure that the portion of work to be inspected is safe and accessible.
B. The Contractor and COR shall jointly develop agendas subject to the COR’s approval for all inspections/tests. All required labor, materials, equipment, instruments, lubricants and
Plant Division Page 11 May 16, 2014
Project Management and Coordination 013100 - 11 incidentals necessary to perform these inspections/tests shall be furnished by the Contractor.
All discrepancies and deficiencies observed during each inspection/test shall be noted and corrected and, if directed by the COR, the inspection/test of equipment and systems previously found deficient shall be rescheduled and performed at no additional cost to the Government.
1.11 FIELD INVESTIGATIONS
A. Contractors shall adhere to the requirements of the “Guidelines for Contractors and A/E Firms Performing Site Investigations and Field Work at NIST” when they are performing site investigations and fieldwork.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 013100
Construction Progress Documentation 013200 - 1
SECTION 013200 - CONSTRUCTION PROGRESS DOCUMENTATION
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes administrative and procedural requirements for documenting the progress of construction during performance of the Work, including the following:
1. Start-up construction schedule.
2. Contractor's construction schedule.
3. Daily construction reports.
4. Field condition reports.
5. Special reports.
B. Related Sections:
1. Division 01 Section "Submittal Procedures" for submitting schedules and reports.
2. Division 01 Section "Quality Requirements" for submitting a schedule of tests and inspections.
1.3 DEFINITIONS
A. Activity: A discrete part of a project that can be identified for planning, scheduling, monitoring, and controlling the construction project. Activities included in a construction schedule consume time and resources.
1. Critical Activity: An activity on the critical path that must start and finish on the planned early start and finish times.
2. Predecessor Activity: An activity that precedes another activity in the network.
3. Successor Activity: An activity that follows another activity in the network.
B. Cost Loading: The allocation of the schedule of values for the completion of an activity as scheduled. The sum of costs for all activities must equal the total Contract Sum, unless otherwise approved by COR.
Construction Progress Documentation 013200 - 2
C. Critical Path: The longest connected chain of interdependent activities through the network schedule that establishes the minimum overall Project duration and contains no float.
D. Event: The starting or ending point of an activity.
E. Float: The measure of leeway in starting and completing an activity.
1. Float time belongs to Contracting Officer.
2. Free float is the amount of time an activity can be delayed without adversely affecting the early start of the successor activity.
3. Total float is the measure of leeway in starting or completing an activity without adversely affecting the planned Project completion date.
F. Resource Loading: The allocation of manpower and equipment necessary for the completion of an activity as scheduled.
1.4 INFORMATIONAL SUBMITTALS
A. Format for Submittals: Submit required submittals in the following format:
1. PDF electronic file.
2. Two paper copies.
B. Start-up construction schedule.
1. Approval of cost-loaded start-up construction schedule will not constitute approval of schedule of values for cost-loaded activities.
C. Start-up Network Diagram: Of size required to display entire network for entire construction period. Show logic ties for activities.
D. Contractor's Construction Schedule: Initial schedule, of size required to display entire schedule for entire construction period.
1. Submit a working electronic copy of schedule, using software indicated, and labeled to comply with requirements for submittals. Include type of schedule (initial or updated) and date on label.
E. Reports: Submit each of the following reports. Format for each activity in reports shall contain activity number, activity description, cost and resource loading, original duration, remaining duration, early start date, early finish date, late start date, late finish date, and total float in calendar days.
F. Daily Construction Reports: Submit at weekly intervals.
Construction Progress Documentation 013200 - 3
G. Field Condition Reports: Submit at weekly intervals.
1.5 QUALITY ASSURANCE
A. Prescheduling Conference: Conduct conference at Project site to comply with requirements in Division 01 Section "Project Management and Coordination." Review methods and procedures related to the preliminary construction schedule and Contractor's construction schedule, including, but not limited to, the following:
1. Review software limitations and content and format for reports.
2. Verify availability of qualified personnel needed to develop and update schedule.
3. Discuss constraints, including work stages and interim milestones.
4. Review delivery dates for Contracting Officer-furnished products.
5. Review schedule for work of Contracting Officer's separate contracts.
6. Review time required for review of submittals and resubmittals.
7. Review requirements for tests and inspections by independent testing and inspecting agencies.
8. Review time required for completion and startup procedures.
9. Review and finalize list of construction activities to be included in schedule.
10. Review submittal requirements and procedures.
11. Review procedures for updating schedule.
1.6 COORDINATION
A. Coordinate preparation and processing of schedules and reports with performance of construction activities and with scheduling and reporting of separate contractors.
B. Coordinate Contractor's construction schedule with the schedule of values, list of subcontracts, submittal schedule, progress reports, payment requests, and other required schedules and reports.
1. Secure time commitments for performing critical elements of the Work from entities involved.
2. Coordinate each construction activity in the network with other activities and schedule them in proper sequence.
PART 2 - PRODUCTS
2.1 CONTRACTOR'S CONSTRUCTION SCHEDULE, GENERAL
A. Time Frame: Extend schedule from date established for commencement of the Work to date of Substantial Completion.
Construction Progress Documentation 013200 - 4
1. Contract completion date shall not be changed by submission of a schedule that shows an early completion date, unless specifically authorized by Change Order.
B. Activities: Treat each separate area as a separate numbered activity for each principal element of the Work. Comply with the following:
1. Activity Duration: Define activities so no activity is longer than 20 days, unless specifically allowed by COR.
2. Procurement Activities: Include procurement process activities for the following long lead items and major items, requiring a cycle of more than 60 days, as separate activities in schedule. Procurement cycle activities include, but are not limited to, submittals, approvals, purchasing, fabrication, and delivery.
3. Submittal Review Time: Include review and resubmittal times indicated in Division 01 Section "Submittal Procedures" in schedule. Coordinate submittal review times in Contractor's construction schedule with submittal schedule.
4. Startup and Testing Time: Include not less than 15 days for startup and testing.
5. Substantial Completion: Indicate completion in advance of date established for
Substantial Completion, and allow time for COR's administrative procedures necessary for certification of Substantial Completion.
6. Punch List and Final Completion: Include not more than 30 days for punch list and final completion.
C. Constraints: Include constraints and work restrictions indicated in the Contract Documents and as follows in schedule, and show how the sequence of the Work is affected.
1. Work by Contracting Officer: Include a separate activity for each portion of the Work performed by Contracting Officer.
2. Products Ordered in Advance: Include a separate activity…