SATPC0037447 Tab 07 SOW_Redacted.pdf

PDF 275 KB Posted

Attached to
Support for advancing readout and optical coupling Federal contract opportunity
Solicitation number
80NSSC25892826Q
Issued by
National Aeronautics and Space Administration Shared Services Center

About this file

This Statement of Work outlines requirements for support services at NASA's Goddard Space Flight Center for the ROSES/SAT project focused on advancing readout of large-format Mid-IR Transition-Edge Sensor Arrays. The contractor will perform packaging and wirebonding of test articles in the Observational Cosmology Laboratory (665) cleanroom, assemble 2dMUX arrays, integrate packages in cryogenic systems, and provide mechanical engineering support including CAD design and component drafting.

The work will be performed at multiple Goddard facilities including Building 34 (rooms C258A and C205), Building 24 (room C136), and Building 11's packaging laboratories from January 1, 2025 through December 31, 2025. The effort requires 0.25 FTEs and does not authorize any travel or procurement. The contract will support quality control according to project specifications for the assembly and testing of sensor arrays and related components.

View the file

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

1. Objective/Requirements will support the packaging and wirebonding of test articles in the

Observational Cosmology Laboratory (665) cleanroom, work with packaging and integration of engineers in B11 to assemble 2dMUX arrays and integrate packages in cryogenic systems for testing. He will also provide mechanical engineering support with computer aided design software and drafting of components as needed. He will perform quality checks according to the specifications of the project.

2. Characteristics, Scope, and Specs -Format Mid-IR Transition-

25 FTEs (reference only over period of performance noted below). No travel or procurement is authorized for this task.

3. Place of Performance Goddard Space Flight Center Building 34 Rm C258A (packaging cleanroom) and Rm C205 (laboratory) Building 24 Rm C136 Building 11 various packaging laboratories

4. Period of Performance 1/1/2025 12/31/2025