SATPC0031743 Tab 04 4 SOW.pdf
PDF 130 KB Posted
- Attached to
- Rotorcraft Test Bed Federal contract opportunity
- Solicitation number
- 80NSSC23839582Q
About this file
This statement of work outlines requirements for a rotorcraft test bed traverse system upgrade. The contractor shall replace one failed module on the existing system and update the programmable logic controller software to allow user selection of motion groups consisting of one to nine actuators. Deliverables include installing the replacement module, updating the panel view and PLC programs, revising the operators manual, and providing two spare modules. The period of performance is 30 days after receipt of order and work will take place at the NASA Langley Research Center. The related federal contract opportunity is a special notice from the National Aeronautics and Space Administration Shared Services Center to upgrade the rotorcraft test bed traverse system.
View the file
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
- 1 -
Rotorcraft Test Bed Traverse System Upgrade
Statement of Work
1. Task Order Title Rotorcraft Test Bed Traverse System Upgrade
2. Background Information The Rotorcraft Test Bed Traverse System was designed and fabricated in 2019 for wind-tunnel testing at the NASA Langley 14x22. One of the modules in the system had a hardware failure and a replacement is required. In addition, NASA has a new requirement to configure the system to allow user selection motion groups.
3. Description of the Work to be Performed:
The Contractor shall order 3 replacement MVI56E-GSC PLC modules, to replace the one bad module and provide NASA with two critical spares. The contractor shall update PLC to allow the user to select the number of actuators present and define a motion group of 1 to 9 actuators.
4. Deliverables/Milestones The contractor shall deliver the following:
1) Install the replacement PLC module
2) Updated PanelView Software with configuration changes
3) Update PLC program
4) Updated Operators Manual
5) Two Spare MVI56E-GSC PLC modules
5. Government Furnished Property The government shall provide access to the system in the Rotor Test Cell (RTC) of
B1212C.
- 2 -
6. Period of Performance 30 Days ARO
7. Place of Performance NASA Langley Research Center
| 1. Task Order Title |
| 2. Background Information |
| 3. Description of the Work to be Performed: |
| 4. Deliverables/Milestones |
| 5. Government Furnished Property |
| 6. Period of Performance |
| 7. Place of Performance |