SATPC0031686 Tab 04 4 SOW.pdf

PDF 183 KB Posted

Attached to
NPOL Radar UPS Capacitors replacement Federal contract opportunity
Solicitation number
80NSSC23837792Q
Issued by
National Aeronautics and Space Administration Shared Services Center

About this file

This statement of work outlines a requirement to replace capacitors on an APC MGE Galaxy 5000 120 KVA UPS at the NPOL radar site. The contractor shall remove and replace 20 capacitors rated at 6000uf and 500VDC, 3 capacitors rated at 200uF and 330VAC, and 3 capacitors rated at 400uF and 330VAC/600VDC. The work is to ensure proper operation of the UPS once completed. Performance will take place at 7632 5 Mile Branch Road in Newark, Maryland. While the capacitors are manufactured to order and will take 18-20 weeks to ship after notice to proceed, the contractor is expected to schedule replacement services with the NASA WFF POC upon award of the solicitation for this work under number 80NSSC23837792Q.

View the file

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

1. Objec�ve/Requirements

• During the replacement of the NPOL APC MGE Galaxy 5000 120 KVA Science Container UPS a preven�ve maintenance inspec�on was performed by Allcom Global Services. Due to the age of the AC/AC capacitors they recommend that they be replaced.

2. Characteris�cs, Scope, and Specs

• The contractor shall remove and replace capacitors associated with APC MGE Galaxy 5000 120

KVA UPS.

o Quan�ty 20: Cap, 6000uf, 500VDC, Stud Mount o Quan�ty 3: Capacitor, 200uF, 330VAC o Quan�ty 3: Cap, Duca�, 400uF, 330VAC, 600VDC

• The contractor shall ensure proper opera�on of the APC MGE Galaxy 5000 120 KVA UPS a�er the work is performed.

3.Place of Performance

• NPOL radar site, 7632 5 Mile Branch Road, Newark MD, 21841

4. Period of Performance

• These capacitors are not inventoried items and are manufactured to order, so are expected to ship to our installa�on team approx. 18-20 weeks a�er no�ce to proceed (NTP provided upon outage approvals). Please allow addi�onal �me for transport (~1 week). Upon award, an AllCom Project Manager will contact the NASA WFF POC to schedule these replacement services.

File details come from the government source that posted it. Updated .