The document provided appears to be the "Salient Characteristics" for the Aqua-Dyne Blastmax 50 (or equal) high pressure water jetting system, which is the subject of a federal contract opportunity solicited by the Defense Logistics Agency (DLA) Maritime Puget Sound Naval Shipyard/TRF Bangor.
The key details are:
- The Aqua-Dyne Blastmax 50 system (or equal) must have a high pressure water jetting capability of 10,000 PSI at 7 GPM, with a manual pressure control valve, rupture disc/relief valve, and be approximately 48" tall x 45" wide x 34" deep to allow for portability and fit into naval vessel engineering spaces.
- The system must be Nationally Recognized Testing Laboratory (NRTL) certified to comply with applicable OSHA regulations.
- The system must have integral lifting points and forklift slots/tubes for proper handling and lifting.
- The federal contract opportunity is for a firm-fixed price contract for a "Blast Machine" under NAICS code 334419, with a 750 employee size standard. Quotes must be submitted via email or fax by the deadline.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| EXHIBIT B CDRL.pdf | ||
| SPMYM2-24-Q-1620.pdf | ||
| EXHIBIT A CDRL.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Aqua-Dyne Blastmax 50 (or equal) Salient Characteris�cs
1. High Pressure Water Je�ng System (for cleaning Heat Exchanger Tubes)
* Rated for 10K PSI
* Rated for 7 GPM
* Manual Pressure Control Valve
* Rupture Disc for 11K PSI (Relief Valve will suffice if Rupture Disc not feasible)
* Dimensions of the system to be approximately: 48” Tall x 45” Wide x 34” Deep to allow for being portable and allowing system to fit down into the engineering.
spaces of a Naval Vessel.
* Equipped for ½” NPT outlet for Aeroquip quick connects for Hoses along with
Aeroquip quick connects for pressure gauge and relief valve.
* Standard Motor Control Cabinet (MCC) to be installed in lieu of the Variable
Frequency Drive (VFD) and a Fused Knife Disconnect installed on the unit.
* 10 Micron Filter installed on the water side.
* 50 HP Motor, 480V, 3 Phase, 60Hz, 59.2 Am
2. NRTL Cer�fica�on
* The equipment and its component parts shall be in compliance with applicable Code of Federal Regula�ons (CFR) Title 29, Part 1910. By defini�on, any equipment will be deemed acceptable and approved by TRF, Bangor, if it meets specific Occupa�onal Safety and Health Administra�on (OSHA) condi�ons outlined in CFR Title 29, Part 1910; Subparts "O" and "S". Specifically, equipment will be "Accepted" by TRF, Bangor, if it has been inspected and found by a Na�onally Recognized Tes�ng Laboratory (NRTL) to conform to specified plans or procedures of applicable codes. The equipment (as a whole system) shall be Na�onally Recognized Tes�ng Laboratory (NRTL) inspected and cer�fied (by an OSHA authorized third party). Two (2) “hard” copies of the NRTL cer�fica�on report shall be provided. If the equipment type/model has already been NRTL inspected and cer�fied, a cer�fica�on report (two (2) ”hard” copies) or documenta�on mounted on the equipment, (which acknowledges it is NRTL cer�fied), shall be provided.
3. Li�ing and Handling Cer�fica�on
* Li�ing and Handling - The specified equipment shall be equipped with four “maximum load” (including the total weight of the unit, including water, etc.) crane li�ing capable integral (not bolted on) li�ing point items such as lugs, thru-holes, pad-eyes, trunnions and ISO container corner fi�ngs (designed, located, installed and cer�fied per Process Instruc�on (PI) for “Padeyes: Temporary and Permanent;
Installa�on, Use and Removal of” (PI No. 611-400-026B), for Trident Refit Facility, Bangor (TRF, Bangor) ( A copy of this document can be provided upon request), mounted on the top of the unit, correctly spaced for even and level li�ing by a single crane hook (without use of spreader bar). The base of the equipment shall also have con�nuous full-length forkli� slots/tubes (in one direc�on) for handling the unit with a forkli� truck. The forkli� slots/tubes shall be sufficient size (to allow a small to medium forkli� to transport the equipment), and have sufficient separa�on (between the forkli� slots/tubes).
Each unit shall be tested. The Li�ing and Handling Cer�fica�on documenta�on shall be provided (for each unit) prior to delivery of the equipment.