This document outlines the salient characteristics for re-controlling a Drake thread grinder. The scope of work includes inspecting the existing machine for required data and programs to operate the new CNC control, removing the current Fanuc control and related components, and installing a new Fanuc CNC control with associated servos, motors, hardware and software. Additional requirements encompass machine leveling and alignment pre- and post-installation, compiling diagnostic reports, conducting training, and providing documentation. The related federal contract opportunity is solicitation number SPMYM223Q1703 from the Defense Logistics Agency Land and Maritime to re-control the Drake thread grinder in accordance with the salient characteristics specified.

View the file

Other files for this federal contract opportunity

Other files attached to DRAKE THREAD GRINDER RE-CONTROL, newest first.
File Type Posted
SPMYM2-23-Q-1703.pdf PDF
SPECIFICATION.pdf PDF
EXHIBITS A-C CDRLs.pdf PDF
STATEMENT OF WORK (SOW).pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SALIENT CHARACTERISTICS

DRAKE THREAD GRINDER RE-CONTROL

Re-control existing Drake Thread Grinder, Model # 702-2 Balancer, serial # 95528 to include the following minimum/equal features: Machine will be available for rebuild the third week of November 2023.

Inspect machine for all data, programs, macros etc. required to operate Drake thread grinder to ensure new CNC control will function as existing CNC control functions. Include all required data, programs, macros required to operate new controller. Include custom thread grinding macros and wheel dressing software.

Remove and replace existing Fanuc CNC Control, all servos, motors, hardware, software and any other items required to install new CNC Fanuc Control, servos, motors, hardware, software and any other associated items to re-control Drake thread grinder. Mount new control on flexible arm.

Metrology

Machine tool level and alignment pre and post re-control.

Perform mechanical adjustments to the machine tool as required to satisfy the OEM specifications for level and alignment.

Generate level and alignment report.

Perform operational test via customer defined test criteria TBD

SALIENT CHARACTERISTICS

DRAKE THREAD GRINDER RE-CONTROL

Project review

Compile all diagnostic reports and formulate overview of machine mechanical and electrical condition as found.

Document all operational functions as currently configured and generate software build sheet.

Define location and mounting configuration of all new equipment.

Catalog all system documentation.

Conduct operator training.

Conduct maintenance training.

Provide all manuals, warranties, instructions, documents and certificates pertaining to the machine tool re-control at a quantity of two each be provided in a format TBD and as specified by the job site data handling requirements.. All prints and parts lists to be drawn with CAD system.

Any and all modifications to any aspect of the machine will meet or exceed original specifications

Provide all wire, tags, conduit, flex and other miscellaneous equipment required to complete the installation per NFPA codes

All parts will be installed in accordance with all applicable customer specifications, and ISO, IEEE, ANSI, DIN, NFPA and any other standards listed within this contract, machine will have NRTL inspection when re-control is complete

Any shipping costs that would be incurred during rebuild to be included in price.

Inspect machine for all data, programs, macros etc. required to operate Drake thread grinder to ensure new CNC control will function as existing CNC control functions. Include all required data, programs, macros required to operate new controller. Inc...
Remove and replace existing Fanuc CNC Control, all servos, motors, hardware, software and any other items required to install new CNC Fanuc Control, servos, motors, hardware, software and any other associated items to re-control Drake thread grinder. ...
Metrology
Machine tool level and alignment pre and post re-control.
Perform mechanical adjustments to the machine tool as required to satisfy the OEM specifications for level and alignment.
Generate level and alignment report.
Project review
Compile all diagnostic reports and formulate overview of machine mechanical and electrical condition as found.
Document all operational functions as currently configured and generate software build sheet.
Define location and mounting configuration of all new equipment.
Catalog all system documentation.
Conduct operator training.
Conduct maintenance training.
Provide all manuals, warranties, instructions, documents and certificates pertaining to the machine tool re-control at a quantity of two each be provided in a format TBD and as specified by the job site data handling requirements.. All prints and part...
Any and all modifications to any aspect of the machine will meet or exceed original specifications
Provide all wire, tags, conduit, flex and other miscellaneous equipment required to complete the installation per NFPA codes
All parts will be installed in accordance with all applicable customer specifications, and ISO, IEEE, ANSI, DIN, NFPA and any other standards listed within this contract, machine will have NRTL inspection when re-control is complete
Any shipping costs that would be incurred during rebuild to be included in price.