Robertson_Draw_Fence_Replacement_-_Specifications_-_04-01-2022.pdf

PDF 326 KB Posted

Attached to
ROBERTSON DRAW FENCE REPLACEMENT Federal contract opportunity
Solicitation number
140L3622Q0014
Issued by
Department of the Interior Bureau of Land Management

View the file

Other files for this federal contract opportunity

Other files attached to ROBERTSON DRAW FENCE REPLACEMENT, newest first.
File Type Posted
Sol_140L3622Q0014_Amd_0002.pdf PDF
Robertson_Draw_Fence_Replacement_-_SOI_-_04-01-2022_0001.pdf PDF
Sol_140L3622Q0014_Amd_0001.pdf PDF
Robertson_Draw_Fence_Replacement_-_Drawings_-_04-01-2022.pdf PDF
DI_137_Release_of_Claims.pdf PDF
Payment_Bond_(SF_25A_Exp_08-31-22).pdf PDF
General_Decision__MT20220065_(2-25-2022)_Carbon_County.pdf PDF
Sol_140L3622Q0014.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Technical Specifications for

ROBERTSON DRAW FENCE REPLACEMENT

BUREAU OF LAND MANAGEMENT

5001 Southgate Drive

Billings, Montana 59101

APRIL 2022

PROJECT SPECIFICATIONS

TABLE OF CONTENTS

Specification Page No

TABLE OF CONTENTS

GENERAL REQUIREMENTS

Statement of Work ................................................................................................ SOW(1-9) 01009 General Information and Requirements ....................................................01009(1-4) 01505 Mobilization ..............................................................................................01505(1-2)

SITE WORK

02834 Wire Fences and Gates ..............................................................................02834(1-7) Work Data Sheet ....................................................................................................... WDS-1

STATEMENT OF WORK

ROBERTSON DRAW FENCE REPLACEMENT SOW-1

STATEMENT OF WORK (SOW)

PROJECT: The Bureau of Land Management (BLM) Billings Field Office (BiFO) located in Billings, MT has a need for new fence installation, fence removal and replacement, removal of existing brace structures, and installation of new steel braces in Carbon County nearest the Town of Belfry, Montana and the City of Red Lodge, Montana. More specifically, the project takes place near BLM roads located near Grove Creek Road and Meeteetse Trail Road. All work takes place in Section

(S) 25 & S26 of Township (T) 8S and Range (R) 20E; S18 of T8S and R21E; and S4, S5, S6, S8, S9, S15, and S17 of T9S and R21E. All fence work is on land owned by the BLM.

The project is divided into a base bid and three (3) Additive Alternates that will be awarded based on the availability of funds. The Government may elect to award the Base Bid and/or any combination of the option bids. The Base Bid and Additive Alternates are described as follows:

The Base Bid involves furnishing labor, tools, equipment, supplies, and materials to construct approximately 489 rods of new barbed 4-wire fence (3 barbed with bottom barbless wire) with all steel fence posts and braces, and including gates; to remove and dispose of approximately 268 rods of existing woven wire and barbed wire fence; and to replace approximately 268 rods of woven and barbed wire fence with new barbed 4-wire fence (3 barbed with bottom barbless wire) with all steel fence posts and braces, and including gates, per this SOW, the supplemental specifications, and as designated on the Construction Drawing Sheet 4 of 19: Base Bid – 1 – New Fence; and Sheet 5 of 19: Base Bid – 2 – Replace Fence. Contractor shall connect existing barbed wire fences to new structures as designated by the Contracting Officer Representative and per this SOW and the supplemental specifications.

Additive Alternate 1 involves furnishing labor, tools, equipment, supplies, and materials to remove and to replace existing wood braces with steel braces, and install new steel braces, on existing barbed wire fence lines as designated by the COR, as staked in the field, and as shown on the Construction Drawing Sheet 6 of 19: Add Alt 1 – 1 – Replace Fence.

Contractor shall connect existing barbed wire fence to new structures as designated by the Contracting Officer Representative and per this SOW and the supplemental specifications.

Additive Alternate 2 involves furnishing labor, tools, equipment, supplies, and materials to remove and to replace existing wood braces with steel braces, and install new steel braces, on existing barbed wire fence lines as designated by the COR, as staked in the field, and as shown on the Construction Drawing Sheet 7 of 19: Add Alt 2 – 1 – New Braces; Sheet 8 of 19: Add Alt 2 – 2 – New Braces; Sheet 9 of 19: Add Alt 2 – 3 – New Braces;

and Sheet 10 of 19: Add Alt 2 – 4 – New Braces. Contractor shall connect existing barbed wire fences to new structures as designated by the Contracting Officer Representative and per this SOW and the supplemental specifications.

ROBERTSON DRAW FENCE REPLACEMENT SOW-2

Additive Alternate 3 involves furnishing labor, tools, equipment, supplies, and materials to remove and to replace existing wood braces with steel braces, and install new steel braces, on existing barbed wire fence lines as designated by the COR, as staked in the field, and as shown on the Construction Drawing Sheet 11 of 19: Add Alt 3 – 1 – New Braces; and Drawing Sheet 12 of 19: Add Alt 3 – 2 – New Braces. Contractor shall connect existing barbed wire fence to new structures as designated by the Contracting Officer Representative and per this SOW and the supplemental

Note: The fence routes and proposed new brace structures shown on the Construction Drawings are the fence lines and brace structures to be constructed. However, not all of the existing corners and panels to be removed along the construction routes are shown, and there may be additional new steel brace panel structures needed along the existing fence alignments designated by the COR and staked in the field. Additional brace structures removed and/or installed will be paid for per the contract unit bid price for that Additive Alternate.

1.0 GENERAL INFORMATION

1.1 If the SOW and the supplemental specifications conflict in requirements, the SOW shall govern. Except where the Contract Documents include more stringent requirements, applicable industry standards shall have the same force and effect as if bound or copied directly into the Contract Documents to the extent referenced. Such standards are made a part of the Contract Documents by reference.

1.2 The successful bidder will be responsible for all work including all material, labor, transportation, equipment, supervision, and the performance of all operations to complete the work as required by this SOW.

1.3 For all BLM requirements, see the information contained on each of the drawing sheets enclosed titled, “Robertson Draw Fence Replacement.” The required information is on the drawings as notes and tables. The instructions contained in the notes and tables, as well as the information in the attached specifications, supplement this SOW.

1.4 It is recommended for the Contractor and any sub-contractors to attend the pre-bid site tour prior to bidding to understand the existing site conditions. No monies will be added to the contract due to issues that arise from the Contractor’s lack of understanding of the existing site conditions.

1.5 Stipulations for Period of Performance: No on-site work shall occur until after

July 15, 2022 due to stipulations related to Sage Grouse, Migratory Birds, and Grizzly Bears. The Notice to Proceed may be issued prior to this date at the Contracting Officer’s (CO) discretion to allow for the ordering of products, submittal approvals, and other work not associated with the work involved at the actual site.

ROBERTSON DRAW FENCE REPLACEMENT SOW-3

1.6 Grizzly Bear Stipulations:

1.6.1 Food and Waste Storage/Disposal: Human, pet and livestock food (except baled or cubed hay without additives), and garbage shall be attended or stored in an approved bear resistant manner. During daytime hours, at least one adult person (attendee), 18 years of age or older, must be physically present within 100 feet of attractants.

During nighttime hours, all attractants shall be stored in a bear-resistant manner. Food, garbage, and other attractants, including all livestock grain and pellets, shall be stored using an approved storage technique when camp is unattended.

1.6.2 Attractants: Attractants (such as food leftovers or cooking grease) shall not be buried, discarded, or burned in an open campfire.

Leftover food or food waste products may be placed in an appropriate, sealed container and packed out with garbage.

Leftover food or other attractants may be burned in a contained stove fire. Attractants may be placed into a suitable container (i.e.

tin can) to prevent leaching into the ground and burned over an open campfire. Any remaining attractants unconsumed by burning shall be placed with other garbage and packed out.

1.6.3 Approved Bear-Resistant Storage Techniques: Any attractants, including food and garbage, (shall be) stored in one of the following ways if unattended: Secured in a hard-sided camper, vehicle trunk, cab, or trailer cab; secured in a hard-sided dwelling or storage building; suspended at least 10 feet up (from the bottom of the suspended item) and 4 feet out from any upright support, i.e.

tree, pole; stored in an approved bear-resistant container; stored within an approved and operating electric fence; stored in any combination of these methods; or stored by methods that are approved in writing by the BLM Field Manager.

1.6.4 Carcasses: Wildlife carcasses, birds, fish, or other animal parts that are within 1/2-mile of any camp or sleeping area shall be stored in a bear-resistant manner during nighttime hours. If a wildlife carcass is within an attended camp during daytime hours, it may be on the ground.

1.6.5 Leave No Trace: Leave No Trace principles shall be followed.

Human waste shall be disposed of using an engineered bag waste containment system (e.g., wag bag) or other appropriate sealed container. With this method, all solid waste, including bags, must be contained in a leakproof, bear-proof, hard-sided container with a screw-on or ratchet-locking lid. All captured solid human waste shall be disposed of off public lands in accordance with applicable regulations. All gray water shall be strained. Gray water shall be disposed of in the river to avoid attracting bears to camping areas with food-scented water. Remaining food waste shall be disposed of in a trash containment system. A ground cloth shall be used in kitchen areas to catch micro trash. All trash, leftover food, and litter shall be packed out and disposed of off Public Lands.

ROBERTSON DRAW FENCE REPLACEMENT SOW-4

1.6.6 Safety and Reporting: The permittee and associated employees are each required to have full, unexpired bear spray in their physical possession to reduce the potential for bear conflicts, and shall recommend that clients also carry full, unexpired bear spray. Any wildlife incidents/conflicts shall be reported to the BLM Billings Field Office within 24 hours. First aid and communication capabilities shall be available for immediate use at all times. The Contractor shall report to the BLM any activities or behaviors that may cause resource damage or otherwise be considered detrimental to resources at the site. The participants assume all risks for natural phenomena that may be encountered.

2.0 DESCRIPTION OF WORK

2.1 Base Bid – New Fence Installation and Remove & Replace Fence

2.1.1 Drawing Sheets: Sheet 4 of 19: Base Bid – 1 – New Fence; Sheet

5 of 19: Base Bid – 2 – Replace Fence

2.1.2 General: Furnish all labor, tools, equipment, supplies, and materials to properly install new four (4)-wire (three (3)-barbed with bottom smooth), all steel fence per the above referenced drawing Sheet 4 of 19, the standard details located in the Construction Drawings, and the attached supplemental specifications. Also furnish all labor, tools, equipment, supplies, and materials to remove and replace fence per drawing Sheet 5 of 19, the standard details locate in the Construction Drawings, and the attached supplemental specifications.

2.1.3 Execution:

2.1.3.1 Sheet 4 of 19: Base Bid Plan Sheet 1 – New Fence

Installation: Connect existing fence wire to new fence panel structure on both ends of the new fence line. Splice new wire to existing wires to lengthen as needed to properly tack wire to the new steel panel structure. Hand stretch/tighten the existing fence wires between the new fence structure and the first steel post of the existing fence.

Broken wires from tightening/stretching existing wires between the new steel panel structure and the first steel post of the existing fence line shall be the responsibility of the Contractor to fix. Any wires broken in the existing fence line due to tightening/stretching of existing wires that are not in the vicinity of the new steel brace structure and the first steel t-post after the new steel brace structure, shall be the responsibility of the Government. See Specification 02834 – Wire Fences and Gates for specifications related to installation of the new fence line.

2.1.3.2 Sheet 5 of 19: Base Bid Plan Sheet 2 – Remove and

Replace Fence: Remove and dispose of existing fence, and install new fence in its place, per Specification 02834 – Wire Fences and Gates, per the Construction Drawings, and as staked in the field, if different from the drawings.

ROBERTSON DRAW FENCE REPLACEMENT SOW-5

Connect existing fence wire to new fence panel structure on both ends of the new fence line. Splice new wire to existing wires to lengthen as needed to properly tack wire to the new steel panel structure. Hand stretch/tighten the existing fence wires between the new fence structure and the first steel post of the existing fence. Broken wires from tightening/stretching existing wires between the new steel panel structure and the first steel post of the existing fence line shall be the responsibility of the Contractor to fix. Any wires broken in the existing fence line due to tightening/stretching of existing wires that are not in the vicinity of the new steel brace structure and the first steel t-post after the new steel brace structure, shall be the responsibility of the Government.

2.2 Additive Alternate 1 – Remove and Replace Fence

2.2.1 Drawing Sheet: Sheet 6 of 19: Add Alt 1 – 1 – Replace Fence

2.2.2 General: Furnish all labor, tools, equipment, supplies, and materials to remove and replace existing fence with new four (4)-wire (three (3)-barbed with bottom smooth), all steel fence per the above referenced drawing sheet, the standard details located in the Construction Drawings, and the attached supplemental specifications.

2.2.3 Execution:

2.2.3.1 Sheet 6 of 19: Additive Alternate 1 – Remove and

Replace Fence: If the Base Bid is awarded, connect new fence to the new steel stress panel at the southern end of the Base Bid Plan Sheet 2 fence alignment per the Construction Drawings. Remove and dispose of existing fence, and install new fence in its place, per Specification 02834 – Wire Fences and Gates, per the Construction Drawings, and as staked in the field, if different from the drawings. The final steel stress panel structure of this alignment shall be placed at the boundary of the State Land, as shown on the Construction Drawings and as staked in the field. Connect existing fence wire to new fence panel structure on both ends of the new fence line. Splice new wire to existing wires to lengthen as needed to properly tack wire to the new steel panel structure. Hand stretch/tighten the existing fence wires between the new fence structure and the first steel post of the existing fence. Broken wires from tightening/stretching existing wires between the new steel panel structure and the first steel post of the existing fence line shall be the responsibility of the Contractor to fix. Any wires broken in the existing fence line due to tightening/stretching of existing wires that are not in the vicinity of the new steel brace structure and the first steel t-post after the new steel brace structure, shall be the responsibility of the Government.

ROBERTSON DRAW FENCE REPLACEMENT SOW-6

2.3 Additive Alternate 2 – New Steel Braces and Gates

2.3.1 Drawing Sheets: Sheet 7 of 19: Add Alt 2 – 1 – New Braces;

Sheet 8 of 19: Add Alt 2 – 2 – New Braces; Sheet 9 of 19: Add Alt 2 – 3 – New Braces; Sheet 10 of 19: Add Alt 2 – 4 – New Braces

2.3.2 General: Furnish all labor, tools, equipment, supplies, and materials to remove existing wood brace assemblies, to replace existing wood brace assemblies with new steel brace assemblies, and to install new steel brace assemblies in various locations per the above referenced drawing sheets, the standard details located in the Construction Drawings, the attached supplemental specifications, as designated on the ground with construction stakes, and as designated by the COR. There may be additional corners and panel structures to be removed, replaced, or installed new along the construction routes that may not be shown in the Construction Drawings. Additional items removed and/or installed will be paid for by the actual quantity removed or installed per the unit bid price of the item.

2.3.3 Execution:

2.3.3.1 Remove and dispose of existing wood panel structures as designated in the field, as designated by the COR, and as described in Specification 02834 – Wire Fences and Gates.

Install new steel brace structures in locations as designated on the contract drawings, as staked in the field, as directed by the COR, as described in Specificaiton 02834 – Wire Fences and Gates, and as shown in the standard details.

Connect existing barbed wire fence to the new steel panel structure at each location designated by the Construction Drawings, as staked in the field, or as designated by the COR. Splice new wire to existing wires to lengthen as needed to properly tack wire to the new steel panel structure. Hand stretch/tighten the existing fence wires between the new fence structure and the first steel post of the existing fence. Broken wires from tightening/stretching existing wires between the new steel panel structure and the first steel post of the existing fence line shall be the responsibility of the Contractor to fix. Any wires broken in the existing fence line due to tightening/stretching of existing wires that are not in the vicinity of the new steel brace structure and the first steel t-post after the new steel brace structure, shall be the responsibility of the Government.

2.4 Additive Alternate 3 – New Steel Braces

2.4.1 Drawing Sheets: Sheet 11 of 19: Add Alt 3 – 1 – New Braces;

Sheet 12 of 19: Add Alt 3 – 2 – New Braces

2.4.2 General: Furnish all labor, tools, equipment, supplies, and materials to remove existing wood brace assemblies, to replace existing wood brace assemblies with new steel brace assemblies, ROBERTSON DRAW FENCE REPLACEMENT SOW-7 and to install new steel brace assemblies in various locations per the above referenced drawing sheets, the standard details located in the Construction Drawings, the attached supplemental specifications, as designated on the ground with construction stakes, and as designated by the COR. There may be additional corners and panel structures to be removed, replaced, or installed new along the construction routes that may not be shown in the Construction Drawings. Additional items removed and/or installed will be paid for by the actual quantity removed or installed per the unit bid price of the item.

2.4.3 Execution:

2.4.3.1 Remove and dispose of existing wood panel structures as designated in the field, as designated by the COR, and as described in Specification 02834 – Wire Fences and Gates.

Install new steel brace structures in locations as designated on the contract drawings, as staked in the field, as directed by the COR, as described in Specificaiton 02834 – Wire Fences and Gates, and as shown in the standard details.

Connect existing barbed wire fence to the new steel panel structure at each location designated by the Construction Drawings, as staked in the field, or as designated by the COR. Splice new wire to existing wires to lengthen as needed to properly tack wire to the new steel panel structure. Hand stretch/tighten the existing fence wires between the new fence structure and the first steel post of the existing fence. Broken wires from tightening/stretching existing wires between the new steel panel structure and the first steel post of the existing fence line shall be the responsibility of the Contractor to fix. Any wires broken in the existing fence line due to tightening/stretching of existing wires that are not in the vicinity of the new steel brace structure and the first steel t-post after the new steel brace structure, shall be the responsibility of the Government.

3.0 GENERAL REQUIREMENTS

3.1 Contractor shall remove all rubbish/debris off location upon final completion of the project and shall provide daily clean-up of work area.

3.2 All work shall be inspected by the government to ensure all work complies with the product manufacturer’s installation instructions, recommendations, industry standards, and any applicable codes.

3.3 The aesthetic values of the site and surrounding area are of prime importance.

The Contractor shall take all care necessary to preserve all plant life and other natural features. Any surface damage outside the extents of the project cause by the Contractor shall be corrected by the Contractor at their expense.

ROBERTSON DRAW FENCE REPLACEMENT SOW-8

3.4 A pre-work conference shall be held prior to the start of work. The Contractor will be notified in advance of meeting time, date, and place. The purpose will be to review required work, project drawings, specifications, construction schedules, payroll and payments, and administrative provisions of the Contract. The Contractor, Subcontractors, and the persons responsible for coordination of the work shall be present at the meeting. Be prepared to summarize and explain procedures planned for the project.

3.5 Contractor shall work between the hours of time one-half-hour before sunrise to one-half-hour after sunset each day, Monday through Friday, unless otherwise approved by the Contracting Officer. Contractor cannot work on Federal holidays or weekends unless otherwise authorized by the Contracting Officer.

3.6 Attached project drawings include fence alignments and approximate locations of new fence structures. All plan dimensions and project quantities are for informational purposes only and may vary during the project. There may be additional corners and panel structures to be removed, replaced, or installed new, along the construction routes that may not be shown in the Construction Drawings. The Contractor is encouraged to visit the site and determine actual quantities and site conditions prior to bidding. No monies will be added to the contract due to issues that arise from the Contractor’s lack of understanding of the existing site conditions.

3.7 The Contractor shall be responsible for any damage to new or existing infrastructure, construction, equipment, etc., resulting from their own construction procedures. Any damage shall be repaired or replaced by the Contractor, at Contractor's expense, to the satisfaction of the Contracting Officer.

4.0 SUBMITTALS

4.1 See Specification 01009 – General Information and Requirements for requirements regarding submitting submittals and format for submittals.

4.2 The successful bidder will submit the following for approval to the Contracting Officer Representative at the preconstruction meeting:

4.2.1 Proposed product specifications (3 copies per each) for the following:

4.2.1.1 Heavy Duty Barbed Wire

4.2.1.2 Heavy Duty Barbless Wire

4.2.1.3 Steel Brace Rail

4.2.1.4 Steel Brace Posts

4.2.1.5 Brace Wires

4.2.1.6 Miscellaneous Wire

4.2.1.7 Heavy Duty Steel Line Posts (T-posts)

4.2.1.8 Wood Gate Stays & Wood Treatment

4.2.1.9 Drill Stem Mechanical Gate Closers (Gate Closer and Gate

Loop)

4.2.2 Proposed equipment to be used to complete the job.

ROBERTSON DRAW FENCE REPLACEMENT SOW-9

4.2.3 Provide the Government with an estimated construction schedule prior to beginning work. When requested during the project, Contractor shall submit an updated schedule within three (3) working days of request.

4.2.4 Provide the Government with proof of product manufacturer’s product warranty and certification that the installation was performed according to the terms and conditions of the warranty.

GENERAL INFORMATION AND REQUIREMENTS

ROBERTSON DRAW FENCE REPLACEMENT 01009-1

SPECIFICATION 01009

PART 1: GENERAL

1.1 SUMMARY:

A. Description of Work: Furnishing labor, tools, equipment, supplies, and materials to perform the requirements of the Statement of Work (SOW) in accordance with these supplemental

B. Location: Work under this contract is located in Carbon County, Montana. The Work locations are shown on the Construction Drawings.

C. Work Data Sheet: Designates the type and quantity of work required at each project location, and dimensions required for structures as shown on typical drawings.

1.2 DEFINITIONS:

A. Approvals: Approval of the submittals is an indication that the Contractor's submittals have been reviewed and that there are no objections, except as noted. Approval of deviations shall apply only to those deviations or omissions from the requirements of the drawings and specifications brought to the CO’s attention in writing. After approval of an item, the Contractor may submit a substitute for approval when the approved item cannot be purchased or delivered in time to avoid delay in completion of the project.

1.3 REFERENCES:

Referenced Specifications/Standards with Abbreviations and/or Acronyms: Wherever the following acronyms are used in these specifications or on the drawings, they are to be construed the same as the respective expressions represented. Copies of the referenced specifications/standards referred to herein may be procured by the Contractor, from the following:

ASTM American Society for Testing and Materials PO Box C700 West Conshohocken, PA 19248-2959

AWPA American Wood Preserver’s Association PO Box 361784

Birmingham, AL 35236-1784

1.4 SUBMITTAL:

A. Scope: Submittals shall be based on the requirements listed in these contract specifications.

B. Requirements: For required submittals, allow seven (7) working days for review. Submittals

ROBERTSON DRAW FENCE REPLACEMENT 01009-2

shall be delivered to the Contracting Officer’s Representative (COR) for review.

C. Identification of Submittal: Submit two copies of each submittal for approval. Completely identify each submittal by showing at least the following information:

1. Contact information to include name and phone number of Contractor’s representative(s) who provided the submittal for review.

2. Name of project as it appears in these specifications.

3. Contract number, drawing number, and specification section number to which the submittal applies.

4. Whether this is an original submittal or re-submittal.

5. Each item shall note the manufacturer's name, address, and telephone number.

1.5 QUALITY ASSURANCE:

A. Codes and Standards: The work shall comply with codes and standards applicable to each type of work and as listed in the individual sections of these specifications. This contract incorporates materials, applications, and tests by reference, with the same force and effect as when they were given in full text.

B. Conflict: Where a conflict occurs between reference documents and project specifications, the project specifications shall govern.

1.6 DELIVERY, STORAGE, AND HANDLING:

A. Delivery: The Contractor shall protect products incorporated into the work from damage while in transit to the site. Products must be delivered in original unopened containers with manufacturer's name, brand designation, and contents legibly indicated.

B. Storage: The Contractor shall provide temporary storage facilities for products. The storage area shall permit access for inspection and handling. No material shall be stored with direct contact to the ground or exposed to direct sunlight, per manufactures recommendations.

C. Handling: The Contractor shall load and unload products in such a manner that protects them from damage.

1.7 PROJECT/SITE CONDITIONS:

A. Access to the Work: Any off-road travel not within the disturbance of the fence (six (6) feet either side of the fence line) needs to have prior approval public roads damaged by the Contractor shall be restored at Contractor's expense to the same condition they were in at the commencement of work. Construction activity may be restricted during wet or frozen conditions. Mechanized equipment use will be avoided if the equipment causes rutting to a

ROBERTSON DRAW FENCE REPLACEMENT 01009-3

depth of 4 inches or greater. The project area is known to exhibit “hard” soils. Small to large, hard stones can be common in both the topsoil and subsoils. Further detail can be found online at the Natural Resources Conservation Service Web Soil Survey. Survey monuments or markers disturbed or removed during construction shall be reset at the Contractors expense.

B. Environmental Considerations: Operations of the Contractor upon government premises including storage of materials, camping areas, and equipment parking shall be confined to approved areas.

1.8 SEQUENCING AND SCHEDULING:

A. Work Schedule: The schedule shall be submitted at the pre-work conference. When requested, the Contractor shall submit an updated schedule within three (3) working days.

PART 2: PRODUCTS

(There are no applicable requirements.)

PART 3: EXECUTION

3.1 PROJECT MEETINGS:

A. Pre-Work Conference:

1. Notification: A pre-work conference will be held prior to the start of work. The

Contractor will be notified in advance of meeting time, date, and place. The purpose will be to review required work, project drawings and specifications, construction schedules, payroll and payments, and administrative provisions of the contract.

2. Attendance: The Contractor, subcontractors, and the persons responsible for coordination of the work shall be present at the meeting.

3. Presentation: The Contractor shall be prepared to summarize and explain procedures planned for the project.

B. Progress Meetings:

1. Location: Meetings shall be held at the project site or as determined by the CO.

2. Notification: Meetings may be called by either the CO or the Contractor. Request shall state who should attend and include an agenda.

C. Final Inspection:

1. Location: Meeting shall be held at the project site, or as determined by the CO.

ROBERTSON DRAW FENCE REPLACEMENT 01009-4

2. Notification: The Contractor shall notify the Project Inspector (PI) or COR at least three (3) working days prior to the completion date to ensure the final inspection is scheduled.

3. Superintendent shall be present during this inspection.

3.2 PREPARATION:

A. Work Layout: The Government will set stakes or posts to give the Contractor measurements, lines, and grades necessary for the work executed under the contract.

B. Installation Changes: As-built record drawings shall be maintained by the Contractor and the Government of actual installations deviated from the contract drawings, or where not otherwise located by dimension, elevation, or other reference on the contract drawings.

3.3 PROTECTION OF EXISTING PROPERTIES

A. General

1. Take precautions to protect all adjoining private and public property and facilities, including underground and overhead utilities, structures, and fences. Restore or replace all disturbed or damaged facilities to its original condition at the Contractor’s expense.

2. Contact utility owners using the Montana One Call System for utility locates before starting work. The Contractor is also responsible for ensuring that all private and public utilities are located within the work area, including any fees associated with locates.

Protect the utilities exposed during the work and prevent damaging underground utilities adjacent to excavations. Immediately notify the utility owner of any construction damage. Repairs of damage to utilities are at the expense of the Contractor.

PART 4: MEASUREMENT AND PAYMENT

4.1 METHOD OF MEASUREMENT:

A. Units: The work described in this section will not be measured for payment.

4.2 BASIS OF PAYMENT:

A. Payment: No direct payment for the work described under this section will be made. The

Contractor shall include consideration for this item in the Schedule of Items (SOI) for other items of the contract.

END OF SPECIFICATION

MOBILIZATION

ROBERTSON DRAW FENCE REPLACEMENT 01505-1

SPECIFICATION 01505

A. Section Includes: Preparatory work and operations, including those necessary to the movement of personnel, equipment, supplies and incidentals to the project site; and for other work and operations to be performed, or costs incurred prior to beginning work, on the various items on the project site. This specification does not include moves between project sites.

PART 2: PRODUCTS

A. Units: Progress payments will be made as follows:

1. When 5 percent of the original contract amount is earned from other bid items, 50 percent of the amount bid for mobilization or 5 percent of the original contract amount, whichever is lesser, will be paid.

2. When 10 percent of the original contract amount is earned from other bid items, 100 percent of the amount bid for mobilization or 10 percent of the original contract amount, whichever is lesser, will be paid.

3. Upon completion of work for the project, payment of the amount bid for mobilization in excess of 10 percent of the original contract amount, will be paid.

4. The total sum of all payments shall not exceed the original contract amount bid for mobilization, regardless of the fact that the contractor may have shut down the work on the project or moved equipment away from the project and then back again.

4.2 BASIS OF PAYMENT:

A. Payment: No direct payment for moves between project sites will be made. The Contractor shall include consideration for moves between project sites in the Schedule of Items (SOI)

ROBERTSON DRAW FENCE REPLACEMENT 01505-2

for other items of the Contract. Prices and payment will be full compensation for the work described in this section. No modification and adjustments shall be allowed for costs and changes to mobilization despite changes in fuel or transportation costs. Payment will be made under:

Pay Item Pay Unit 01505(1) Mobilization .................................................................................................... Lump Sum

WIRE FENCES AND GATES

ROBERTSON DRAW FENCE REPLACEMENT 02834-1

SPECIFICATION 02834

A. Section Includes: Installing, with Contractor furnished property, barbed wire fences, gates, and various steel panels.

1.2 REFERENCES:

A. American Society for Testing and Materials

ASTM A 121-86 Zinc-Coated (Galvanized) Steel Barbed Wire ASTM A 641-82 Zinc-Coated (Galvanized) Carbon Steel Wire ASTM A 702-87 Steel Fence, Posts, and Assemblies, Hot-Wrought ASTM A 116-00 Zinc-Coated (Galvanized) Steel Woven Wire ASTM A53/A 53M Pipe, Steel, Black and Hot-Dipped, Zinc-Coated, Welded and Seamless ASTM A121-19 Zinc-Coated (Galvanized) Steel Barbed Wire ASTM A641-19 Zinc-Coated (Galvanized) Carbon Steel Wire ASTM A702-13(18) Steel Fence, Posts, and Assemblies, Hot-Wrought ASTM A53-20 Pipe, Steel, Black and Hot-Dipped, Zinc-Coated, Welded and

Seamless

B. American Wood Preserver's Association

AWPA U1-20 User Specifications for Treated Wood AWPA T1-20 Processing and Treatment Standards AWPA P1/P13-19 Standard for Creosote Preservative (CR) AWPA P2-19 Standard for Creosote Solutions (CR-S) AWPA P23-14 Standard for Chromated Copper Arsenate Type C (CCA-C) AWPA P36-16 Standard for Copper Naphthenate (CuN) AWPA P35-16 Standard for Pentachlorophenol (PCP) AWPA P48-15 Standard for Copper Azole Type C (CA-C)

1.3 SUBMITTALS:

A. Certification: The Contractor shall furnish written certification from the treating plant stating that chemicals and methods used, for wood preservation and net amount of preservative retained, are in conformance with applicable standards. Contractor-furnished gates and accessories will be approved by the Contracting Officer (CO) prior to installation.

Furnish written certification from the manufacturer that the Contractor-furnished fence posts and wire conform to the requirements of this section. Submittals shall be according to Specification 01009 - General Information and Requirements and/or the Statement of Work

ROBERTSON DRAW FENCE REPLACEMENT 02834-2

(SOW).

PART 2: PRODUCTS

2.1 CONTRACTOR - FURNISHED MATERIALS:

A. Heavy Duty Barbed Wire: (Redbrand or Approved Equal) Two (2), 12-1/2-gauge galvanized wires twisted together with 2-point barbs of 14-gauge wire spaced 4 to 6 inches apart. Wire and barbs shall be zinc-coated steel, with a zinc coating of at least 0.28 oz/ft2 of coated surface area and a minimum breaking strength of 950 lb.-force. The barbed wire shall be a heavy duty wire conforming to ASTM A121 requirements. Failure to meet any of these requirements shall result in the rejection of the material at the time of inspection.

B. Heavy Duty Barbless Wire: (Redbrand or Approved Equal) Two (2), 12-1/2-gauge galvanized wires twisted together. Wire shall be zinc-coated steel wire of at least 0.28 oz/ft2 of coated surface area and a minimum breaking strength of 950 lb.-force. The wire shall be heavy duty with a high tensile strength, low stretch, tight braiding per rod, conform to all ASTM A641 requirements and must be tagged accordingly. Failure to meet any of these requirements shall result in the rejection of the material at the time of inspection.

C. Steel Brace Rail: Shall be a minimum of 6-feet and no greater than 8-feet long, singular piece of round tubular steel constructed with a minimum 1-7/8-inch outside diameter by minimum 11-gauge wall thickness. Brace rail ends shall be pressed flat on both ends and be equipped with both a 90- and 45-degree angle capable of being mounted both horizontally as well as diagonally on all bracing structures. Brace banding shall be 2-7/8-inch heavy duty galvanized brace band, measuring 1 inch wide by minimum 1/8-inch wall thickness and attached with 3/8-inch galvanized grade five (5) carriage bolts, 1-1/2-inch to 2-inch in length, with grade five (5) galvanized flange nuts.

D. Steel Brace Posts: Shall be 2-7/8-inch outside diameter (OD) by 0.217-inch minimum wall thickness, Oil Company Tubular Goods (OCTG) steel pipe. Pipe shall be used/recycled structural OCTG casing or drill pipe in sound structural condition, clean and radiation free (<12 µR/hr.), or new reject pipe, or unused surplus pipe. Surface rust is acceptable;

however, any material that is excessively pitted, rusty, flaking, peeling, or corroded will be rejected. Pipe with splits, bends, or thin spots (hot spots) will not be accepted. Pipe shall be free from oil debris. All pipe that is concrete lined, lined with any synthetic material, or has holes or perforations shall not be accepted. All drill stem threads and/or collars shall be removed.

E. Brace Wires: Shall be four (4), 9-gauge barbless galvanized wires or two (2), 12-1/2-gauge double twisted galvanized barbless-wires twisted tight (total of four (4) strands). The minimum weight of zinc coating for 9-gauge wire shall be at least 0.35 oz/ft2 of coated surface area and 0.28 oz/ft2 for 12-1/2-gauge wire.

F. Miscellaneous Wire: Wire for gate loops, fastening wood stays, and each deadman shall be

9-gauge or 12-1/2-gauge double twisted galvanized wire.

ROBERTSON DRAW FENCE REPLACEMENT 02834-3

G. Staples: Shall be at least 9-gauge, barbed, bright finished or galvanized, have slash-cut points, and be 1-3/4-inches long.

H. Nails: Shall be 60 D ring shank at least 6-inches long.

I. Heavy Duty Steel Line Posts (T-posts): (Chicago Steel or Approved Equal) Shall be heavy-duty grade steel posts painted green with white, silver, or lime green tops or painted gray with red, white, or silver tops, “T” bar type, with a swaged or riveted anchor plate which does not easily bend or twist when an obstruction is hit during the driving process. Other steel post painted colors can be allowed on a case-by-case basis with the approval of the CO. Posts shall be furnished with clip-type fasteners. Punched tabs for fastening wires are not acceptable. Steel posts shall be manufactured from wrought, rail, or new billet steel, and shall weigh a minimum of 1.33 lb./ft. exclusive of the anchor plate, which shall weigh a minimum of 0.67 lbs., with a minimum of 18 sq. inches in area. Posts shall meet all ASTM A702 requirements and must be tagged accordingly. Failure to meet any of these requirements shall result in the rejection of material at the time of inspection.

J. Wood Gate Stays: Wood gate stays shall be sound single stem members. A slight bend in one plane is acceptable. Posts are not acceptable if a straight line drawn from the geometric center of the top to the geometric center of the butt of the post falls outside of the body of the post. Posts that are twisted, rotted, excessively bent or have checks greater than half their thickness are considered unsound and are not acceptable. Wood gate stays may be full stem members, sawn members, square cross-section members, or split members. The Work Data Sheet shall indicate the required post diameters, dimensions, and the depths to be set.

1. Minimum diameter for gate stays shall be 3-inches at the small end and length shall be minimum 4-feet.

2. The following species will be acceptable if treated for the full length: Ponderosa pine, Lodgepole pine, and Douglas-fir. Split Western Redcedar posts will be acceptable if the butt is treated for a minimum depth in the ground plus 6-inches. The following species will be acceptable without treatment: Honey Locust, Juniper, Osage Orange, and White Oak.

K. Wire Gates: Shall have the same type of wire and wire spacing as the fence as shown in the drawings unless otherwise stated on the Work Data Sheet. Wire gates shall have wire stays between the wood end stays unless wood stays must be utilized to allow the gate to stay upright to properly function. Any panels installed on each side of the gates shall be paid as separate installation items.

L. Drill Stem Mechanical Gate Closers: Assembly shall include:

1. Gate Closer: A36 rolled round steel bar 3/16-inch to 5/16-inch diameter or adjustable minimum 3/16-inch diameter galvanized steel cable wire loop with a minimum Working Load Limit (WLL) 840 lb.-force and Minimum Breaking Load (MBL) 4200

ROBERTSON DRAW FENCE REPLACEMENT 02834-4

lb.-force, fastened to a cam lever device. The pipe cover shall be constructed of a minimum 11-gauge steel plating made to rest upon and exceed the diameter of the 2- 7/8 inch steel brace post. The mechanical break over latch shall be attached to a minimum of 2-3/8-inch OD by 11-gauge minimum wall thickness tubular steel stem that slides securely into the 2-7/8-inch OD steel brace post a minimum of 6-inches. The closer must be capable of fitting over a minimum three (3) inch diameter wood gate stay and securely holding the gate stay in place. Alternatives require prior approval by the Contracting Officer Representative (COR) with submission of samples.

2. Gate Loop: A minimum 3/16-inch diameter galvanized steel cable wire loop with a minimum Working Load Limit (WLL) 840 lb.-force and Minimum Breaking Load (MBL) 4200 lb.-force, securely connected to the steel brace post with a 3-inch U-bolt muffler clamp assembly 6-inches from the ground and shaped so that the minimum 3-inch diameter gate stay will be securely held in place. The muffler clamp shall be secured to the steel brace post with 9/16-inch grade five (5) galvanized round U-bolt and galvanized flange nuts. A sleeve shall be welded to the muffler clamp, parallel to a leg of the U-bolt. Another sleeve shall be welded parallel to the other leg of the U-bolt, on the same face of the muffler clamp. The sleeve shall be large enough to allow free movement of the steel galvanized cable but small enough to keep terminated ends from passing through when the loop is under pressure. The galvanized steel cable shall be threaded through the sleeves to form a loop without a bind and the ends shall be crimped with a flattened 9/16-inch grade five (5) galvanized nut further secured by a weld. Alternatives require prior approval by the COR with submission of samples.

2.3 WOOD TREATMENT PRACTICES:

A. General: The following treatments may be used. Minimum net retentions and penetrations shall be according to AWPA U1. Treatment method shall be according to AWPA T1, except as otherwise noted. When a treated member must be bored or cut during construction, thoroughly swab untreated surfaces with an approved preservative.

B. Pentachlorophenol Method: Five percent pentachlorophenol solution conforming to AWPA

P35, Type A.

C. Chromated Copper Arsenic: Waterborne preservative conforming to AWPA P23, Type C.

D. Creosote: Shall be according to AWPA P2.

E. Butt-End Treatment for Split Western Redcedar Only: When split western redcedar posts are used with treatment on butt only, treatment may be by either the cold soaking or hot bath process. Either pentachlorophenol or Creosote (Coal tar) solution may be used.

Minimum net retention of preservative shall be 20 lb./ft3 for creosote solutions and 1 lb./ft3 for pentachlorophenol.

ROBERTSON DRAW FENCE REPLACEMENT 02834-5

3.1 PREPARATION:

A. Clearing: Maximum mowed/clearing width is 6-feet on each side of the fence line. Provide minimum disturbance to existing grass and sod. Any blade work or other surface disturbance shall require prior approval from the CO.

3.2 INSTALLATION:

A. General: Drive steel posts. All line posts shall be steel as designated on the Work Data

Sheet.

B. Driving Posts:

1. Steel Line Posts (t-post): Drive posts plumb, into the ground to the depth shown on the

Drawings, Work Data Sheet, or until the top of the anchor plate of the steel line post (t-post) is 1-inch below existing ground surface. When rock formations prevent driving, remove anchor plate of the line post and excavate or drill holes a minimum of 18-inches deep and slightly larger than the diameter of the post. Place posts in the holes and grout the post solidly in position with cement grout or mortar.

2. Steel Brace Posts: Posts shall be driven plumb, into the ground to the depth shown on the Drawings and Work Data Sheet.

C. Corner Panel, End Panel, and Stress Panel Assemblies: Set posts as specified. Fabricate panels as shown on the Drawings and indicated on the Work Data Sheet.

D. Figure Fours and Rock Jacks: May be used in rock. Figure fours shall be used in lieu of steel posts, and rock jacks in lieu of wood line posts, except where a series of figure fours are required, a rock jack shall be substituted for every fifth figure four. Figure fours and rock jacks shall be constructed as shown on the drawings or only with prior approval from the COR.

E. Wire: Stretch tightly and securely attach to steel line posts with standard wire clips. Wire is properly stretched when it is springy to the touch. Terminate wire at each steel end post, wood gate stay, steel corner post, or steel stress panel. Wrap wire around the post two (2) times and tie off by wrapping around the incoming wire a minimum of four (4) times.

F. Brace Wire: Shall be double-looped and twisted tight with a stick or post. The Contractor shall ensure that one end of the post or stick is long enough to physically rest behind as well as being physically secured to the horizontal brace member to prevent wire from unwinding.

All brace wires that lie on the groundward side of all support structures shall not exceed an overall height of 6-inches above the existing ground surface. All brace wires shall have their own twist stick or post, unless otherwise approved by the CO.

G. Wire Spacing: The wire spacing will be from the ground up. Bottom wire shall be smooth unless designated otherwise. Spacing for all projects is indicated on the Work Data Sheet.

ROBERTSON DRAW FENCE REPLACEMENT 02834-6

H. Gates: Shall be installed according to the drawings, unless directed otherwise by the Work

Data Sheet or COR.

I. Mechanical Gate Closures: Line up the latch with the gate. Adjust latch assembly after installation so that the latch does not bind, and the gate hangs properly.

J. Deadman: Shall be installed at all minor depressions when the spacing between the bottom wire and the ground exceed 20-inches. Deadman can be rock weighing a minimum of 50-lbs. resting on the ground or a 5-1/2-feet steel post driven angled into the ground a minimum of 4-feet parallel and in line with the fence attached with additional double twisted wire of the same material as the bottom wire. See drawing Sheet 18 of 19: Deadman At Minor Depression. Salvageable steel posts as approved and designated by the COR shall be allowed as deadman.

3.3 FENCE REMOVAL:

A. Shall include removal and disposal of staples, clips, stays, wire, wood & steel posts, various panels, fence marking lathe, plus salvage of steel posts, wood posts, and gates as designated and determined by the Contractor and as approved by the COR. All removed material shall become the responsibility of the Contractor. Designated salvageable material shall be stockpiled, utilized as directed, and approved by the COR. Material not salvaged shall become the property of the Contractor. The Contractor shall be responsible to remove, haul away, and dispose of all material as directed and approved by the COR. Roll and secure wire, posts, gates, and dispose of materials off Government lands. Materials may be stockpiled in COR approved locations for minimum periods of time. Submit fence removal and stockpile plans to the COR for approval prior to performing work. No woven wire shall be returned to any of the fence permittees or other operators unless approval is given by the COR. Wood and steel posts shall not be cut off at the ground level. Wood or steel posts that break off at the ground level shall be pulled or the stub shall be pushed a minimum 6-inches below the ground surface. Any large holes or voids in the ground from pulled posts shall be covered or filled with appropriate sod or backfill to eliminate any safety hazards. Wood posts shall not be stockpiled and burned on Federal Land.

3.3 EXISTING BRACE STRUCTURE REMOVAL & DISPOSAL:

A. Shall include removal and disposal of staples, clips, wire, wood posts, various panels, fence marking lathe, plus salvage of steel posts, and wood posts as designated and determined by the Contractor and as approved by the COR. All removed material shall become the responsibility of the Contractor. Designated salvageable material shall be stockpiled, utilized as directed, and approved by the COR. Material not salvaged shall become the property of the Contractor. The Contractor shall be responsible to remove, haul away, and dispose of all material as directed and approved by the COR. Dispose of materials off Government lands.