Dwarf Pecan Plot Land Clearing Scope of Work.pdf

PDF 3 MB Posted

Attached to
Land Clearing, Tree Transplanting & Tree Removal Federal contract opportunity
Solicitation number
RFQ-20-4329-FS01
Issued by
Department of Agriculture Agricultural Research Service

View the file

Other files for this federal contract opportunity

Other files attached to Land Clearing, Tree Transplanting & Tree Removal, newest first.
File Type Posted
Aerial view after Dwarf Tree's being cut down.pdf PDF
Aerial View prior to Dwarf Tree's being cut down.pdf PDF
Contractor Questions with Government Responses.pdf PDF
SF18 RFQ for Land Clearing.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Brush/ Clearing Tree Transplanting

Tree Removal U

Contractor to furnish all labor, transportation, materials, engineering and equipment to fifteen 15 and the t of 47 Dwarf P T (2"- 10" dia.). (See appendix 1) Additionally, the USDA has approximately 17 fully grown Pecan trees located on another plot that needs to be cut down and stumps removed. (See appendix 2) designated plot of to be cleared Dwarf Pecan Trees and recently the majority of trees have been cut down leaving approximately 3,100 stumps (2"- 10" dia.) that will have to be removed

a. Transplanting 47 Dwarf Pecan Tree's to an area near the clearing site that will be designated by USDA personnel.

b. Removal of all grubbing to remove .

All other vegetation that can be cleared shall be

c. Prior coordination with Contracting Officer (CO) or Location Representative must be accomplished for the proper accumulation areas for all chips/grindings and any other debris, roots, stumps, On-site burning of the accumulation piles may be authorized only with strict coordination with CO or Location Rep. Contractor may remove or transport waste/debris to off-site location. Contractor may chose to chip/grind on-site.

d. Upon clearing of site, all existing drainage ditches shall be identified and then cleared of all brush,

e. The

f. Any debris tossed onto the roads from contractor machinery must be cleared off the roads by the end of the work day. Any debris falling into the previously cleared areas will be cleaned up by the contractor.

g. Cut down and remove 17 fully grown Pecan Tree's in another deisgnated area.

The contractor shall use industry standard means to include the use of, but not limited to, heavy equipment (excavator, dozer, skid steer, trucks, etc. and hand held equipment (chain saws, grinders, hand held tools, etc. to perform brush and clearing services.

Contractor will furnish all equipment and personnel needed to remove any debris from paved areas during hauling or clearing activities.

BRUSH AND CLEARING

The Government will not furnish any facilities or equipment for any work that needs to be accomplished in this

. The contractor shall furnish all supplies needed to perform this contract according to all its terms.

The government will provide emergency service and emergency medical treatment for Contractor personnel who are injured or become critically ill while . The contractor will be required to transport injured or ill personnel to the appropriate medical treatment facility. Treated personnel will be responsible for reimbursing the government for the cost of medical treatment and patient transportation. For all emergencies, please dial (9 Fire emergencies/routine calls can also be reported at the before mentioned phone numbers.

The government shall not provide telephone services. If available, the contractor may use government phones in a case of emergencies during field and site work. No long distance telephone calls will be authorized.

Working hours for the contractor shall normally be between the hours of 0700-1 00 excluding Federal holidays. If the Contractor desires to work during periods other than above, a government representative need to be present. The Contractor shall make his/her request to the CO five (5) calendar days in advance of his/her intention to work during other periods to allow assignment of a government representative. If such force is reasonably available from assigned contract administrators or quality assurance personnel, the CO may authorize the contractor to perform work during periods other than normal duty hours/days.

The title to all waste, excess, and scrap generated as a direct result of this contract is vested in the Contractor Further location work other materials not accumulated from clearing is P

, ing

C

CO O

quote O e

O O i

PEFORMANCE WORK STATEMENT FOR

BRUSH AND TREE CLEARING

O s p s O

Area marked in blue boarder to have 47 tree's removed/transplanted and then the area cleared

Plot where 17 tree's need to be removed