About this file
This is a Request for Qualifications (RFQ) issued by the Contra Costa Transportation Authority (CCTA) for on-call construction management services. CCTA seeks to select up to five qualified consulting firms to provide construction management support for transportation improvement projects throughout Contra Costa County, including smart signals, complete streets, shared mobility hubs, and bicycle facilities. The scope of services encompasses pre-construction activities, project administration and coordination, field oversight and inspection, schedule and reporting, public outreach, environmental coordination, materials testing, project closeout, and technology implementation. The ten anticipated projects listed range from $1.2 million to $30.0 million in construction value, with advertisement dates spanning from December 2025 through November 2026 and construction durations ranging from four to twenty months. A pre-proposal conference is scheduled for January 15, 2026, at 2:00 p.m. via Zoom. Written questions must be submitted by January 23, 2026, at 2:00 p.m., and proposals are due February 13, 2026, at 2:00 p.m. through the PlanetBids e-procurement system. Interviews are anticipated but not confirmed, and contract award dates are to be determined. Selected firms will enter into five-year Master Services Agreements with task orders issued for specific projects, with no guarantee of work volume.
The anticipated maximum aggregate contract value for all five awards is $15 million, though this amount is not guaranteed. Proposals must be submitted without cost information; only qualified firms selected based on technical qualifications will be asked to submit detailed cost proposals and rate schedules in a separate phase for pre-award audits and negotiations. Cost-plus-fixed-fee contracts will be established with overhead and fixed fees negotiated individually, with fixed fees capped at ten percent and subconsultant costs reimbursed at cost without markup. All work must comply with Caltrans Local Assistance Procedures Manual requirements and prevailing wage obligations under California Labor Code. Firms must be registered with the California Department of Industrial Relations, maintain financial management systems compliant with federal regulations, and provide certifications regarding debarment, lobbying activities, Iran contracting compliance, and indirect cost rates. Projects are funded through combinations of local, state, and federal sources. Proposers must demonstrate familiarity with federal procedures, Caltrans guidelines, and local agency coordination, with preference given to firms with local presence in Contra Costa County.
View the file
Other files for this state and local contract opportunity
| File | Type | Posted |
|---|---|---|
| Agreement_Professional Services_FEDERAL_Final.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFQ No. 25-3 Contra Costa Transportation Authority Page 1
NOTICE OF REQUEST FOR QUALIFICATIONS (RFQ) NO. 25-3
FOR ON-CALL CONSTRUCTION MANAGEMENT SERVICES
The Contra Costa Transportation Authority (CCTA) is searching for qualified firms to provide On- Call Construction Management (CM) services. Through this RFQ, CCTA will select up to five (5) qualified consultants for a Consultant Bench which CCTA may contract with to provide construction management services.
Projects may be funded by local, state and/or federal funding sources or a combination thereof.
The proposer will be required to comply with applicable National Environmental Policy Act and/or California Environmental Quality Act guidelines, various federal congressional acts and executive orders and guidelines from applicable federal, state and local laws and regulations.
See accompanying RFQ specifications for a detailed description of the scope of services and other important information for submitting proposals for this project. The on-call contracts on their own do not authorize or obligate a consultant to initiate any project task/work.
Anticipated Schedule
RFQ Issue Date December 19, 2025
Pre-Proposal Conference January 15, 2026 @ 2pm
Written Questions Due by Date January 23, 2026 @ 2pm
Submittal Due Date February 13, 2026 @ 2pm
Tentative Interview Date TBD
Notice of Intent to Award Date TBD
Anticipated Contract Award Date TBD
CCTA has implemented an e-Procurement system and utilizes "PlanetBids." This system streamlines procurement processes and offers expanded services to our vendors by allowing them to participate in CCTA procurements through the internet. Registration with PlanetBids is required to participate in this RFQ. Your registered account is also the only means of access to CCTA notifications, addenda, and other important elements of this procurement process. There are no fees to register or submit qualifications. Firms can access the system at www.ccta.net, click on “Get Involved” then select “Bid Opportunities.”
http://www.ccta.net/
RFQ No. 25-3 Contra Costa Transportation Authority Page 2
RFQ No. 25-3 Contra Costa Transportation Authority Page 3
CONTRA COSTA TRANSPORTATION AUTHORITY
REQUEST FOR QUALIFICATIONS (RFQ) NO. 25-3
FOR ON-CALL CONSTRUCTION MANAGEMENT SERVICES
I. INTRODUCTION AND BACKGROUND
CCTA is soliciting Statements of Qualifications (SOQs) from qualified firms to provide Construction Management (CM) services for upcoming projects throughout Contra Costa County. The Authority works in partnership with local jurisdictions to deliver transportation improvements that enhance mobility, safety, and accessibility for all users of the transportation system. These projects are funded through a combination of local, regional, state, and federal sources.
Projects covered by this RFQ and supported by the Authority include safe streets and roads for all, traffic signal modernization and smart signals, shared mobility hubs, and other improvements that enhance mobility throughout Contra Costa County. To ensure these projects are delivered efficiently, cost-effectively, and with minimal disruption to the traveling public, the Authority requires the support of experienced CM professionals with demonstrated expertise in contract administration, field inspection, quality assurance, schedule and cost control, and coordination with local agencies and stakeholders. Through this RFQ, the Authority seeks to identify qualified firms to assist in the successful delivery of these vital community serving projects.
II. SCOPE OF SERVICES
Consultants are expected to form fully functional construction management teams capable of delivering projects in conformance with local, state, and federal requirements. A list of anticipated projects which are expected to be delivered through the on-call is listed below. The projects shown below are not intended to be a complete list, nor does it guarantee the projects will be delivered by the Authority.
RFQ No. 25-3 Contra Costa Transportation Authority Page 4
Services include, but are not limited to, the duties of Resident Engineer, Assistant Resident Engineer, Civil Inspector, Electrical Inspector, Office Engineer, materials testing services, labor compliance services, and construction surveying quality assurance. Consultants should be prepared to implement construction management services following the Caltrans Local Assistance Procedures Manual (LAPM) and Construction Manual. Consultants should be familiar with CCTA’s Construction Contract Administration Guide. Examples of specific tasks to be provided include:
Pre-Construction Services
• Perform constructability and biddability reviews.
• Support advertising and awarding of construction contracts.
• Participate in pre-bid and pre-construction conferences.
Project Administration & Coordination
• Act as Resident Engineer and primary point of contact for all construction communications.
• Coordinate with contractors, local agencies, utilities, designers, and project stakeholders.
• Manage project correspondence, RFIs, submittals, and document control.
• Evaluate, negotiate, and prepare change orders.
• Identify potential claims and recommend solutions.
• Prepare staff reports and board resolutions.
• Prepare presentations and develop exhibits and supporting documentation.
• Ensure that the contractor has all required permits prior to construction.
• Monitor and track third party work.
• Prepare monthly staffing schedules.
• Assist or prepare project reimbursement invoices.
Project # Project Name Construction
Advertisement (Anticipated)
Construction Duration (Months)
Construction Estimate Program
31007 Concord Traffic Signal Modernization December 2025 4 $1.2M Smart Signals
31000 Countywide Smart Signals Project February 2026 16 $30.0M Smart Signals
31002 Antioch Bicycle Garden March 2026 5 $3.5M SS4A
31003 Antioch L Street Pathways to Transit June 2027 20 $15.0M SS4A
31004 Richmond Street Complete Streets March 2026 15 $11.0M SS4A
31005 Moraga Road/Canyon Rd Complete Streets May 2026 5 $2.6M SS4A
31009 Lamorinda Traffic Signal Modernization July 2026 8 $5.0M Smart Signals
31010 SF Bay Trail Gap Closure November 2026 19 $6.0M SS4A
8009.04 Shared Mobility Hub Martinez (Ph 1) February 2027 12 $1.5M Innovate 680
8009.04 Shared Mobility Hub Walnut Creek (Ph 1) June 2027 12 $1.5M Innovate 680
RFQ No. 25-3 Contra Costa Transportation Authority Page 5
Field Oversight & Inspection
• Perform daily field inspection of construction activities.
• Project specific needs may require inspectors from various disciplines.
• Monitor contractor performance for compliance with plans, specifications, and permits.
• Enforce traffic control, detour, and staging requirements.
• Track labor, equipment, and quantities in progress of work.
• Facilitate communication with other entities (railroad, various utilities, etc.).
• Monitor and track SWPPP and WPCP compliance.
Schedule & Reporting
• Review and monitor contractor schedules.
• Prepare daily reports, weekly progress summaries, and statements of working days.
• Maintain photographic and video documentation of construction progress.
• Track, log, and redline as-built changes; prepare record drawings.
• Maintain a log of punch list items.
• RE will perform daily or weekly diaries.
• Inspector will perform daily diaries.
Public Outreach
• Provide advance notification of construction impacts to community.
• Collaborate with local agencies on posting public notifications to project websites.
• Develop public outreach material.
Environmental Coordination & Monitoring
• Oversee compliance with environmental requirements and mitigation measures.
• Track and log the implementation of mitigation measures.
• Coordinate with various environmental groups.
• Ensure that contractor complies with permits from various environmental groups.
Surveying Quality Assurance
• Verify construction staking and layout.
• Support quantity calculations.
Materials Testing/Quality Assurance Testing
• Provide field and laboratory materials testing services.
• Maintain a log of tests in accordance with Caltrans LAPM.
• Conduct tests in accordance with specified intervals established in the Authority’s Quality
Assurance Program or per the Caltrans LAPM.
• Source inspection (as applicable).
RFQ No. 25-3 Contra Costa Transportation Authority Page 6
Project Closeout
• Facilitate final inspections and prepare final construction reports.
• Provide post-construction and warranty support services.
• Deliver all project documentation and certified as-built plans.
• Coordinate with Caltrans, Caltrans Local Assistance, and Contractor regarding required paperwork for project closeout and contract acceptance.
• Deliver all project documents to CCTA electronically.
• Prepare project award submissions.
Technology & Innovation
• Have the capability to implement drones for inspection and project records.
• Administer construction contracts electronically (E-Construction) with use of construction management software.
• Suggest other technologies to be implemented.
While the scope of services provided above serves as a general reference, proposers are expected to enhance and elaborate on it to highlight their experience, technical insight, and understanding of effective project delivery. Proposers are encouraged to expand upon this scope to demonstrate their understanding of CCTA needs.
III. PROPOSAL INSTRUCTIONS
A. GENERAL INSTRUCTIONS
Where two or more firms, persons or entities wish to submit one statement of qualifications in response to this RFQ, they should do so on a prime and subconsultant basis rather than as a joint venture. CCTA will contract with a single firm, person or entity only, and not with a joint venture. A firm that is the prime consultant on a contract awarded under this process may also be a subconsultant firm on another contract. Subconsultants can be on more than one team.
B. CONTACT INFORMATION
Proposers are cautioned not to discuss this RFQ with any official, Board Member or employee of CCTA. Neither proposers, nor anyone representing the proposer, are to discuss this RFQ with any consultant or contractor engaged by CCTA for assistance in preparing a response to the RFQ.
Violation of this prohibition may result in disqualification of the proposer.
C. PRE-PROPOSAL CONFERENCE
A virtual pre-proposal conference is scheduled for [January 15, 2026, at 2pm]. Pre-proposal attendance is not mandatory but is highly encouraged. The conference will be held via Zoom at:
https://ccta-net.zoom.us/j/84682453482?pwd=G9hVaWAvgzxhP0N9aFgYzJivKDJkUa.1 https://ccta-net.zoom.us/j/84682453482?pwd=G9hVaWAvgzxhP0N9aFgYzJivKDJkUa.1
RFQ No. 25-3 Contra Costa Transportation Authority Page 7
D. WRITTEN QUESTIONS/CLARIFICATIONS
All questions and/or clarifications to this RFQ must be submitted electronically through your registered account with PlanetBids, CCTA’s online procurement system, on or before the due date specified in the above Notice of RFQ. A late request or requests not submitted though PlanetBids will not be considered. CCTA will respond to all questions through PlanetBids by issuing a written addendum.
E. ADDENDA
CCTA reserves the right to revise the RFQ documents. Revisions and notifications thereof will be made by written addendum and made available to registered vendors with PlanetBids. CCTA will not be bound to any modifications to or deviations from the requirements set forth in this RFQ as a result of any oral discussions and/or instructions. Proposers must acknowledge receipt of any addenda in their statement of qualifications.
F. CONTRACT TYPE
The contract resulting from this RFQ, if awarded, will be for on-call services under a Master Services Agreement with individual task orders being issued through a mini-RFP process for specific projects. The on-call contract will be valid for five years from the date of approval. The anticipated maximum dollar amount for all contracts awarded under this solicitation will be $15M. It is understood and agreed that there is no guarantee, either expressed or implied, that this dollar amount will be authorized under the Master Services Agreement through task orders.
The Authority anticipates awarding up to five (5) contracts and ten task orders.
The contract type resulting from the mini-RFP process will be for cost-plus-fixed fee using the rate ranges, overhead, and fixed fee established in the Master Services Agreement or Master Contract. Consultants will be expected to propose project specific budgets delineated by work breakdown structure if selected to perform construction management services on any of the projects previously listed.
G. CONFLICT OF INTEREST
Any person or firm that has assisted CCTA in preparing any aspect of this RFQ or any support cost estimate associated with the Scope of Services related to this RFQ is prohibited from submitting a statement of qualifications in response to this RFQ. Firms that received assistance from any such person or entity, or who will use the services of such person or entity in performing the Work will be disqualified. A firm who is prohibited from submitting a statement of qualifications in response to this RFQ will not be prevented from participating in future projects to the extent that no direct conflict of interest exists at the time. Firms responsible for a project’s design may not participate in construction management or construction inspection contracts for the project. The determination of a conflict of interest, direct or incidental, shall be made by CCTA based upon substantial evidence.
RFQ No. 25-3 Contra Costa Transportation Authority Page 8
A conflict of interest could include, but is not limited to:
1. No contracting agency employee who participates in the procurement, management, or administration of federal or state funded contracts or subcontracts shall have, directly or indirectly, any financial or other personal interest in connection with such contract or subcontract;
2. No person or entity performing services for a contracting agency in connection with a federal or state funded project shall have, directly or indirectly, any financial or other personal interest, other than employment or retention by the contracting agency, in any contract or subcontract in connection with such project; and
3. No person or entity performing services for a contracting agency in connection with a federal-aid highway funded project shall have, directly or indirectly, any financial or other personal interest in any real property acquired for the project.
H. PRE-CONTRACTUAL EXPENSES/CANCELLATION OF RFQ
CCTA shall not be liable for any pre-contractual expenses incurred by the firm in preparation or submittal of their proposal. The proposer shall not include any such expenses as part of their price proposal. Prohibited pre-contractual expenses include any and all expenses incurred by the proposer prior to issuance of the Notice to Proceed by CCTA. CCTA additionally reserves the right to cancel this RFQ at any time prior to contract award without obligation in any manner for proposal preparation, interview, fee negotiation or other marketing costs accrued by proposers associated with this RFQ.
I. MATERIALS FURNISHED BY CCTA
All software, data, reports, surveys, drawings, and other documents furnished to the consultant by CCTA for the consultant’s use in the performance of work shall be made available only for use in performing the assignment and shall remain the sole property of CCTA. All such materials shall be returned to CCTA upon completion of work, termination of the contract, or other such time as CCTA may determine.
J. AMENDMENTS TO PROPOSALS
No amendment, addendum or modification to proposals will be accepted after the Submittal Due Date and Time as specified in the Notice of this RFQ.
K. PROTESTS
Any proposer may protest a contract award if the proposer believes that the award was inconsistent with CCTA’s policies or this RFQ is not in compliance with law. A protest must be filed in writing with CCTA (email is not acceptable) within five (5) business days after date of notification of contract award. Any protest submitted after 5:00 p.m. of the fifth business day after notification of contract award will be rejected by CCTA as invalid and the proposer’s failure
RFQ No. 25-3 Contra Costa Transportation Authority Page 9 to timely file a protest will waive the proposer’s right to protest the contract award. The proposer’s protest must include supporting documentation, legal authorities in support of the grounds for the protest and the name, address and telephone number of the person representing the proposer for purposes of the protest. Any matters not set forth in the protest shall be deemed waived. CCTA will review and evaluate the basis of the protest provided the protest is filed in strict conformity with the foregoing. CCTA shall provide the proposer submitting the protest with a written statement concurring with or denying the protest. Action by CCTA relative to the protest will be final and not subject to appeal or reconsideration. The procedure and time limits set forth in this Section are mandatory and are the proposer’s sole and exclusive remedy in the event of protest. Failure to comply with these procedures will constitute a waiver of any right to further pursue the protest, including filing a Government Code claim or legal proceedings.
L. CONFIDENTIALITY OF PROPOSAL
Pursuant to Michaelis, Montanari, & Johnson v. Superior Court (2006) 38 Cal.4th 1065, proposals submitted in response to this RFQ shall be held confidential by CCTA and shall not be subject to disclosure under the California Public Records Act (Cal. Government Code section 6250 et seq.)
until after either CCTA and the proposer have completed negotiations and entered into the Agreement or CCTA has rejected all proposals. All correspondence with CCTA including responses to this RFQ will become the exclusive property of CCTA and will become public records under the California Public Records Act. Furthermore, CCTA will have no liability to the proposer or any other party as a result of any public disclosure of any proposal or the Agreement.
If a proposer desires to exclude a portion of its proposal from disclosure under the California Public Records Act, the proposer must mark it as such and state the specific provision in the California Public Records Act which provides the exemption as well as the factual basis for claiming the exemption. For example, if a proposer submits trade secret information, the proposer must plainly mark the information as “Trade Secret” and refer to the appropriate section of the California Public Records Act which provides the exemption as well as the factual basis for claiming the exemption. Although the California Public Records Act recognizes that certain confidential trade secret information may be protected from disclosure, CCTA is not in a position to establish that the information that a proposer submits is a trade secret. If a request is made for information marked “Confidential”, “Trade Secret” or “Proprietary”, CCTA will provide proposers who submitted the information with reasonable notice for the proposer to seek protection from disclosure by a court of competent jurisdiction.
IV. PROPOSAL SUBMITTAL
Qualification, forms and all materials related to this RFQ are to be submitted electronically through your registered account with PlanetBids, CCTA’s online procurement system, on or before the due time and date specified in the above Notice of RFQ.
RFQ No. 25-3 Contra Costa Transportation Authority Page 10
A. PROPOSAL CONTENT
Interested parties responding to this RFQ are expected to submit one Statement of Qualifications (SOQ). All SOQs should be clear, concise, and provide enough information to minimize questions and assumptions. SOQs should be limited to no more than 20 (8 ½” x 11”) pages in no less than 11-point font excluding cover letter, table of contents, and the following items, which should be included as attachments: resumes, contract exceptions, and required exhibits/attachments. Page sizes greater than the letter size of 8.5” x 11” will be counted as two pages. CCTA accepts no financial responsibility for any costs incurred in the preparation of SOQs.
Upon receipt by CCTA, all accepted SOQ’s submitted in response to this RFQ will become property of CCTA.
Content that does not contain the required information will be deemed non-responsive and will not be considered.
If at any time during the RFQ process, a firm makes any changes to proposed key personnel or subconsultants, the firm must notify CCTA in writing of those proposed changes as soon as they are known. CCTA reserves the right to accept or reject such proposed changes or to revise the evaluation scoring to reflect the proposed staffing changes. All submittals must be formatted based on the sections below.
1. Cover Letter. Specific and required elements of this section includes the following:
• Provide a brief profile of the firm, including the types of services offered; the year founded; form of the organization (corporation, partnership, sole proprietorship);
number, size and location of offices; and number of employees.
• Identification of all proposed subconsultants including description of work to be performed by the firm.
• Indicate the location of the office from which the work will be performed.
• A list of all prime contracts (if any) awarded to the firm by CCTA for the last five (5) years. The list shall include a short description of the project, the award date, completion date, name of assigned Project Manager, and contract value.
• If proposer has ever been terminated from a contract, describe the facts and circumstances in detail.
• Acknowledgement of all addenda.
• A statement that the proposal is valid for 180 calendar days from the date of submission.
• A signed statement by an officer of the prime firm who can bind the firm to the
Agreement and attest that all information in response to this RFQ is true and correct.
2. Firm Background and Statement of Financial Health. Proposing firms shall provide a concise description of their background, including the firm’s history, size, organizational structure, areas of expertise, and years of experience providing construction management services for
RFQ No. 25-3 Contra Costa Transportation Authority Page 11 transportation and public works projects. Firms must also include a statement of financial health that demonstrates the company’s stability and capacity to perform the required services. This statement should address the firm’s overall financial condition, disclose any bankruptcy filings, or pending litigation within the past five years, and affirm the ability to provide necessary resources and insurance to support projects of varying size and complexity. State your firm’s ability to comply with a Caltrans pre-award audit as outlined in Caltrans LAPM Chapter 10.
3. Team Structure. Discuss the team’s organizational structure, special expertise, and experience of the firm’s key employees. Proposed staffing should include number of licensed and specialized staff for the list of projects under this RFQ and previous experience of those identified. Discuss current workload of the firm and individuals, and the ability to meet future staffing demands. List at least three references for each key employee (name, title, organization, email, and current phone number). Key employees must be available to work on awarded projects. Local resources are highly preferred. Identify if any staff have performed work on past CCTA projects and list the projects and role of the individual.
Provide an organizational chart that:
• Indicates the relationship of the prime consultant to the subconsultants’ areas of specialization, and names of the Project Manager and key team members.
• Clearly delineates communication and reporting relationships among the key personnel and staff, including subconsultants.
• Includes identification of all proposed subconsultants including description of the work to be performed by the firm and each subconsultant proposed.
4. Statement of Qualifications (SOQ). This section of the proposal should establish the ability of the proposing firm to satisfactorily perform the required work by reasons of experience in performing work of the same or similar nature.
• Approach and Management Plan. Describe the firm’s proposed approach and management plan for providing the services listed in the Scope of Services section.
Include strategies and processes used to perform work cost-effectively and to ensure projects are built on time and on budget.
• Qualifications and Experience. Proposers should state the qualifications and experience of the proposed team, emphasizing specific qualifications and experience related to the reference projects listed in the Scope of Services section. Please include representative projects for which the Proposer has provided services during the last five (5) years that includes client, project description and location, total value of services provided, project start and completion dates, total construction cost after project completion, construction cost at time of bid, key personnel involved, and sub-consultants employed (if any). Indicate if the proposer was a prime or subconsultant on the representative projects. Indicate if the projects utilized federal funds. This section should also include at
RFQ No. 25-3 Contra Costa Transportation Authority Page 12 least three references (name, title, organization, email, and current phone number) from other projects within the last five (5) years similar to the project(s) being proposed upon. Please describe how the teams met or exceeded expectations and how your firm helped resolve construction issues.
• Familiarity with Local, State, and Federal Procedures and Agencies. Demonstrate the firm’s knowledge of local, state, and federal procedures including the Caltrans LAPM.
Discuss familiarity with other local agencies. Consultants will be managing construction projects for CCTA in other local agencies and jurisdictions throughout Contra Costa County.
• Additional Information. Provide any additional and relevant information that would differentiate your firm. Discuss what construction management software your firm uses and how you plan to implement this software for any projects awarded though this on-call. Proposers should discuss their approach to submittal and RFI reviews and delegation of responsibilities.
5. Resumes. Provide resumes for both key and non-key consultant team members that include education, experience and applicable professional credentials of proposed project staff. Proposers are encouraged to limit the descriptions on the resume to relevant information. Provide enough resumes to demonstrate coverage of all work aspects, limited to relevant team members located close enough to perform work on these projects.
Indicate proximity to CCTA offices and identify which individuals are local to Contra Costa County.
6. Contract Exceptions. In submitting a statement of qualifications in response to this RFQ, the consultant is certifying that it takes no exceptions to this RFQ. Firms will be deemed to have accepted any and all terms and conditions not objected to or identified as an exception or deviation to this RFQ. Exceptions, if any, may be reason for rejection of a proposal. Failure to specify any particular exception in accordance with this Section shall preclude a proposer from taking exception or requesting revisions to any part of this RFQ following the proposal submission deadline.
B. COST PROPOSAL/RATE RANGE SCHEDULE (SEPARATE FILE).
Proposers are asked to submit only the technical information requested in this RFP. No cost proposals are to be included in this phase of the procurement process. The Authority will reopen the PlanetBids Portal for the top-ranked firms to submit their cost proposal/rate sheets.
The cost proposal/rate sheets will be opened only for the top-ranked firms that the Authority intends to contract with and will be utilized to perform pre-award audits concurrent with and as input to the negotiations. Notifications to submit the cost proposal will be via email through PlanetBids.
Task orders under this contract will be for cost-plus-fixed fee, which provides for payment of allowable incurred costs, to the extent prescribed in future task orders. Consultants will be
RFQ No. 25-3 Contra Costa Transportation Authority Page 13 expected to propose project specific budgets delineated by work breakdown structure if selected to perform construction management services on any of the projects previously listed.
Sub-consultant costs, travel, and all other direct costs will be reimbursed at cost with no mark-up allowed. Cost proposals shall comply with Caltrans’ Local Assistance Procedures Manual Chapter 10.
Cost proposals must include the following, and any other additional information requested by
CCTA:
• Names, mailing addresses, phone numbers and email addresses for prime consultant and all subconsultants;
• Prime and subconsultant generated Rate Schedule (Attachment A) in accordance with applicable Code of Federal Regulations;
• Other direct costs in conformance with the sample agreement.
Consultant Certification of Contract Costs and Financial Management System for the prime and all subconsultants. See Attachment B attached hereto and incorporated herein by this reference and one of the following, if available:
• A copy of the prior fiscal year, and most recently completed fiscal year cognizant approved ICR and approved state DOT Cognizant Letter of Approval;
• A copy of the prior fiscal year, and most recently completed fiscal year, ICR Schedules and audited report by an independent CPA. If a CPA audited ICR is available for the appropriate fiscal year (applicable one-year accounting period), then the consultant must use the audited ICR, or a lower ICR (see 23 CFR 172.7(b) for guidelines); or
• A copy of the prior, and most recently completed fiscal year, ICR(s) evaluation or audit report on a prior Caltrans or local agency contract, and any other governmental agency report/review/attestation.
Contracts shall not be awarded to a proposer without an adequate financial management and accounting system as required by 48 CFR Part 16.301-3, 2 CFR Part 200, and 48 CFR Part 31.
Selected firms shall comply with Caltrans LAPM, Chapter 10, regarding A&E Consultant Audit and Review Process. This includes requirements for establishing FAR compliant Indirect Cost Rates.
C. Required Forms
Prime and all subconsultants must review, complete, and sign the following items:
• Department of Industrial Relations (DIR) Registration Certification attached hereto as Attachment C and incorporated herein by this reference.
RFQ No. 25-3 Contra Costa Transportation Authority Page 14
• Iran Contracting Act Certification attached hereto as Attachment D and incorporated herein by this reference.
• Certificate of Proposer and Subconsultant(s) Regarding Debarment, Suspension and Other Responsibility Matters attached hereto as Attachment E and incorporated herein by this reference.
• Nonlobbying Certification attached hereto as Attachment F and incorporated herein by this reference.
• Disclosure of Lobbying Activities attached hereto as Attachment G and incorporated herein by this reference.
Required forms must be submitted as attachments in the statement of qualifications response file.
V. ACCEPTANCE OF PROPOSALS
CCTA reserves the right to accept or reject any and all submittals to this RFQ, or any item or part thereof, or to waive any informalities or irregularities in a submittal. CCTA reserves the right to cancel this RFQ at any time without prior notice and CCTA makes no representation that any contract will be awarded to any firm responding to this RFQ. CCTA reserves the right to reject all submittals and to re-issue (or not re-issue) a new RFQ for the same or similar scope of work. CCTA reserves the right to adjust or postpone key dates specified in the above Notice of RFQ for its own convenience.
VI. EVALUATION CRITERIA AND METHOD OF AWARD
The SOQ’s will be evaluated by a selection committee and scored (maximum of 100 points) using the following criteria:
1. Proposers Responsiveness to Proposal Requirements (10 points)
• Responsiveness to all items requested in the RFQ, such as completeness of submission, adherence to required page limits, overall organization, and clarity of SOQ.
2. Team Structure (20 points)
• Organizational structure of the team.
• Breadth and depth of resources provided given the reference projects listed.
• Identification of key staff and availability to meet staffing demands.
• Local presence.
3. Summary of Qualifications (50 points)
• Qualifications of staff experience on similar federally funded projects.
• Qualifications of firm experience on similar federally funded projects.
• Approach and management plan.
RFQ No. 25-3 Contra Costa Transportation Authority Page 15
• Additional information.
4. References (20 points)
a. Client references as to past project performance.
The selection committee retains the right to independently verify and evaluate relevant experience and client references, including any sources not mentioned in the SOQ.
Submittals receiving an initial score of less than 70 points will not be considered further in the selection process. Respondents that have received a score of 70 points or higher may, at CCTA’s sole discretion, be invited to an interview with the selection committee. CCTA reserves the right to not conduct oral interviews and determine the winning respondent based solely on the written SOQ. If oral interviews are held, individuals who are identified as key personnel in the SOQ are required to be in attendance at the interview. Based on the results of the interview, the selection committee may adjust initial scores on the evaluation criteria identified above to arrive at the final evaluation score.
VII. AWARD OF AGREEMENTS
CCTA intends to award agreements to qualified firms/teams. Consultants selected for a contract will remain eligible for consideration for task orders on an as-needed basis for the [five-year] term. While CCTA intends to engage the selected firm/team(s) based on capabilities, experience, availability and conflict of interest, no selected firm/team is guaranteed a task order. This RFQ does not in any way limit CCTA’s right to solicit contracts for similar or identical services if, in CCTA’s sole and absolute discretion, it determines the on-call teams are inadequate to satisfy its needs.
VIII. NOTIFICATION OF AWARD
Firms who submit a response to the RFQ shall be notified in writing when: the firm was not selected to receive further consideration in the RFQ process; the firm was selected for the interview process (if any) and after the RFQ Evaluation Committee’s recommendation to award has been determined.
IX. NEGOTIATION AND AWARD OF FUTURE TASK ORDERS
Following the establishment of contracts with the selected firm/team(s), CCTA, at its sole and absolute discretion, will solicit consultant firm/teams for project specific task orders and contracts. Depending on task order amount and funding source(s), consultant firm/teams may be invited to submit proposals and/or participate in oral interviews for specific scopes of work as part of the task order negotiation process. Teams are not required to include all subconsultants on every task order.
Interviews may consist of standard questions asked of each of the respondents, and specific questions regarding individual responses. CCTA reserves the right to interview any, all, or none of the on-call consultant teams to negotiate task orders. CCTA, in its sole discretion, has the right to approve or disapprove any staff person assigned to a task order before and throughout the contract term.
RFQ No. 25-3 Contra Costa Transportation Authority Page 16
CCTA has limited office space available for this contract and, with the exception of progress and coordination meetings, all work shall take place at the consultant offices or project sites. Respondents should be prepared to mobilize within 48 hours following contract negotiations and contract award by the CCTA Board.
X. PREVAILING WAGES
Certain labor categories under this Project may be subject to prevailing wages as identified in the State of California Labor Code commencing at sections 1720 et seq. and 1770 et seq. If applicable, employees working in these categories at the site must be paid not less than the basic hourly rates of pay and fringe benefits established by the California Department of Industrial Relations. Copies of the State of California wage schedules are available for review at www.dir.ca.gov/dlsr/. In addition, a copy of the prevailing rate of per diem wages will be made available at the CCTA’s office upon request. The successful proposer shall make copies of the prevailing rates of per diem wages for each craft, classification or type of worker needed to execute the work under the contract available to interested parties upon request and shall post copies at the successful proposer’s principal place of business and at the Project site.
It shall be mandatory upon the proposer to whom the Contract is awarded, and upon any subcontractors, to comply with all Labor Code provisions, which include but are not limited to the payment of not less than the said specified prevailing wage rates to all workers employed by them in the execution of the contract, employment of apprentices, hours of labor and debarment of contractors and subcontractors. Pursuant to Labor Code sections 1725.5 and 1771.1, the proposer and all subcontractors must be registered with the Department of Industrial Relations (“DIR”) at the time of submitting a proposal. No proposal will be accepted nor any contract entered into without proof of the proposer’s and subcontractors’ current registration with the DIR to perform public work. If awarded a contract, the successful proposer and its subcontractors, of any tier, shall maintain active registration with the DIR for the duration of the Project. The contract awarded pursuant to this proposal may also be subject to compliance monitoring and enforcement by the Department of Industrial Relations.
http://www.dir.ca.gov/dlsr/
RFQ No. 25-3 Contra Costa Transportation Authority Page 17
ATTACHMENT A
RATE SCHEDULES FOR CONSULTANT AND SUBCONSULTANTS
PRIMARY CONSULTANT**
CONSULTANT
SERVICES TO BE
PERFORMED
FAR
Multiplier
(Direct Labor and
Overhead) Fee* (in $)
Fee* (in %)
Example:
Consultant Name Design 2.603 $XXX 10%
SUBCONSULTANTS**
CONSULTANTS
SERVICES TO BE
PERFORMED
FAR
Multiplier
(Direct Labor and
Overhead) Fee* (in $)
Fee* (in %)
* Fee should not exceed 10%. (Total fixed fee cannot exceed $[insert dollar amount].)
** See next page for [Contractor or Consultant] Rate Schedules
RFQ No. 25-3 Contra Costa Transportation Authority Page 18
[Contractor or Consultant]/Subconsultant (Select one): [insert business/agency name]
Multiplier: [insert multiplier]
Fee: [insert fee]
Multiplier with Fee: [insert total multiplier plus fee]
CLASSIFICATION
BASE DIRECT
SALARY RATES
*FULLY LOADED SALARY
RATES
(Min – Max)
SAMPLE Project Manager $90.00- $100.00 $257.67 (min) – $286.30 (max)
Salary Ranges Effective through: [insert date]. Thereafter, the ranges may be adjusted annually in accordance with Section 2 of this Agreement.
* Fee should not exceed 10%. Total fixed fee cannot exceed $[insert dollar amount].
RFQ No. 25-3 Contra Costa Transportation Authority Page 19
ATTACHMENT B
CERTIFICATION OF INDIRECT COSTS AND FINANCIAL MANAGEMENT SYSTEM
FOR CONSULTANTS AND SUBCONSULTANTS
RFQ No. 25-3 Contra Costa Transportation Authority Page 20
RFQ No. 25-3 Contra Costa Transportation Authority Page 21
RFQ No. 25-3 Contra Costa Transportation Authority Page 22
ATTACHMENT C
DIR REGISTRATION CERTIFICATION
Pursuant to Labor Code sections 1725.5 and 1771.1, all contractors and subcontractors that wish to propose on, be listed in a proposal, or enter into a contract to perform public work must be registered with the Department of Industrial Relations. See http://www.dir.ca.gov/Public- Works/PublicWorks.html for additional information.
No proposal will be accepted nor any contract entered into without proof of the contractor’s and subcontractors’ current registration with the Department of Industrial Relations to perform public work. This requirement will apply to all work under this RFQ that is subject to the prevailing wage requirements set forth in Labor Code section 1720, et. seq., (“Prevailing Wage Work”) and to proposer and any subcontractor proposed to perform such work.
Proposer hereby certifies that it is aware of the registration requirements set forth in Labor Code sections 1725.5 and 1771.1 and is currently registered as a contractor with the Department of Industrial Relations.
Name of Proposer: ________________________________
DIR Registration Number: __________________________
*Name of Proposed Subcontractor: _______________________
DIR Registration Number: _______________________________
* Include additional sheets as necessary to list additional proposed subcontractors who will perform Prevailing Wage Work, and DIR registration numbers.
Proposer further acknowledges:
1. Proposer shall maintain a current DIR registration for the duration of the Project.
2. Proposer shall include the requirements of Labor Code sections 1725.5 and 1771.1 in its contract(s) with subcontractors engaged to perform any Prevailing Wage Work, and shall ensure that all such subcontractors are registered at the time of proposal opening and maintain registration status for the duration of the Project.
3. Failure to submit this form or comply with any of the above requirements may result in a finding that the proposal is non-responsive.
Signature: __________________________________________
Name and Title: ______________________________________
Dated:______________________________________________________ http://www.dir.ca.gov/Public-Works/PublicWorks.html http://www.dir.ca.gov/Public-Works/PublicWorks.html
RFQ No. 25-3 Contra Costa Transportation Authority Page 23
ATTACHMENT D
IRAN CONTRACTING ACT CERTIFICATION
(Public Contract Code section 2200 et seq.)
As required by California Public Contract Code section 2204, the proposer certifies subject to penalty for perjury that the option checked below relating to the proposer’s status in regard to the Iran Contracting Act of 2010 (Public Contract Code section 2200 et seq.) is true and correct:
The proposer is not:
(i) identified on the current list of persons and entities engaging in investment activities in Iran prepared by the California Department of General Services in accordance with subdivision (b) of Public Contract Code section 2203; or
(ii) a financial institution that extends, for 45 days or more, credit in the amount of $20,000,000 or more to any other person or entity identified on the current list of persons and entities engaging in investment activities in Iran prepared by the California Department of General Services in accordance with subdivision (b) of Public Contract Code section 2203, if that person or entity uses or will use the credit to provide goods or services in the energy sector in Iran.
CCTA has exempted the proposer from the requirements of the Iran Contracting Act of 2010 after making a public finding that, absent the exemption, CCTA will be unable to obtain the goods and/or services to be provided pursuant to the contract.
The amount of the contract payable to the proposer for the work does not exceed $1,000,000.
Signature:______________________________________
Title:__________________________________________
Firm:__________________________________________
Date:__________________________________________
Note: In accordance with Public Contract Code section 2205, false certification of this form shall be reported to the California Attorney General and may result in civil penalties equal to the greater of $250,000 or twice the Contract Price, termination of the Contract and/or ineligibility to bid on contracts for three years.
RFQ No. 25-3 Contra Costa Transportation Authority Page 24
ATTACHMENT E
CERTIFICATION OF OFFEROR/SUBCONSULTANT REGARDING DEBARMENT,
SUSPENSION, AND OTHER RESPONSIBILITY MATTERS
RFQ No. 25-3 Contra Costa Transportation Authority Page 25
CERTIFICATION OF PROPOSER REGARDING DEBARMENT,
SUSPENSION, AND OTHER RESPONSIBILITY MATTERS
The undersigned certifies to the best of his or her knowledge and belief, that
________________________________________ (name of proposer) and its principles:
1. Are not presently debarred, suspended, proposed for debarment, declared ineligible, or voluntarily excluded from covered transactions by any Federal department or agency;
2. Have not within a three-year period preceding this subcontract been convicted of or had a civil judgment rendered against them for commission of fraud or a criminal offense in connection with obtaining, attempting to obtain, or performing a public (Federal, State, or local) transaction or contract under a public transaction; violation of Federal or State antitrust statutes or commission of embezzlement, theft, forgery, bribery, falsification or destruction of records, making false statements, or receiving stolen property;
3. Are not presently indicted for or otherwise criminally or civilly charged by a governmental entity (Federal, State, or local) with commission of any of the offenses enumerated in Paragraph 2 of this certification; and
4. Have not within a three-year period preceding this subcontract had one or more public transactions (Federal, State, or local) terminated for cause or default. The Offeror certifies or affirms the truthfulness and accuracy of the contents of the statements submitted on or with this certification and understands that the provisions of 31 U.S.C. Sections 3801 et seq. are applicable thereto.
5. Are not on the Comptroller General’s list of ineligible consultants.
By:_________________________________ By:___________________________ (Signature) (Signature)
(Print Name) (Print Name)
(Title) (Title)
(Date) (Date)
RFQ No. 25-3 Contra Costa Transportation Authority Page 26
CERTIFICATION OF SUBCONSULTANT REGARDING DEBARMENT,
SUSPENSION, AND OTHER RESPONSIBILITY MATTERS
The undersigned certifies to the best of his or her knowledge and belief, that
___________________________________________ and its principles:
1. Are not presently debarred, suspended, proposed for debarment, declared ineligible, or voluntarily excluded from covered transactions by any Federal department or agency;
2. Have not within a three-year period preceding this subcontract been convicted of or had a civil judgment rendered against them for commission of fraud or a criminal offense in connection with obtaining, attempting to obtain, or performing a public (Federal, State, or local) transaction or contract under a public transaction; violation of Federal or State antitrust statutes or commission of embezzlement, theft, forgery, bribery, falsification or destruction of records, making false statements, or receiving stolen property;
3. Are not presently indicted for or otherwise criminally or civilly charged by a governmental entity (Federal, State, or local) with commission of any of the offenses enumerated in Paragraph 2 of this certification; and
4. Have not within a three-year period preceding this subcontract had one or more public transactions (Federal, State, or local) terminated for cause or default. The subconsultant certifies or affirms the truthfulness and accuracy of the contents of the statements submitted on or with this certification and understands that the provisions of 31 U.S.C. Sections 3801 et seq. are applicable thereto.
By:_________________________________ By:___________________________ (Signature) (Signature)
(Print Name) (Print Name)
(Title) (Title)
RFQ No. 25-3 Contra Costa Transportation Authority Page 27
ATTACHMENT F
NONLOBBYING CERTIFICATION FOR FEDERAL-AID CONTRACTS
The proposer certifies that to the best of his or her knowledge and belief that:
A. No state, federal or local agency appropriated funds have been paid, or will be paid by or on behalf of the Consultant to any person for influencing or attempting to influence an officer or employee of any state or federal agency; a Member of the State Legislature or United States Congress; an officer or employee of the Legislature or Congress; or any employee of a Member of the Legislature or Congress, in connection with the awarding of any state or federal contract; the making of any state or federal grant;
the making of any state or federal loan; the entering into of any cooperative agreement, and the extension, continuation, renewal, amendment, or modification of any state or federal contract, grant, loan, or cooperative agreement.
B. If any funds other than federal appropriated funds have been paid, or will be paid to any person for influencing or attempting to influence an officer or employee of any federal agency; a Member of Congress; an officer or employee of Congress, or an employee of a Member of Congress; in connection with this federal contract, grant, loan, or cooperative agreement; Consultant shall complete and submit Standard Form-LLL, “Disclosure Form to Report Lobbying”, attached hereto as “Exhibit 10-Q” and incorporated herein by this reference, in accordance with its instructions.
This certification is a material representation of fact upon which reliance was placed when this transaction was made or entered into. Submission of this certification is a prerequisite for making or entering into this transaction imposed by Section 1352, Title 31, U.S. Code. Any person who fails to file the required certification shall be subject to a civil penalty of not less than $10,000 and not more than $100,000 for each such failure.
Proposer also agrees by signing this document that he or she shall require that the language of this certification be included in all lower-tier subcontracts, which exceed $100,000 and that all such sub recipients shall certify and disclose accordingly.
By:_________________________________ By:___________________________ (Signature) (Signature)
(Print Name) (Print Name)
(T…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .