RFQ_10206379_FINAL_3.27.25.pdf

PDF 1 MB Posted

Attached to
Concrete Engineering Services State and local contract opportunity
Solicitation number
10206379
Issued by
California

About this file

This is a Request for Qualifications (RFQ) No. 10206379 issued by the California Department of Water Resources (DWR), Division of Engineering, Geotechnical Services Branch, seeking qualified firms to provide concrete engineering services for the State Water Project (SWP), California Aqueduct, and state flood control systems. The contract will run from September 25, 2025, through September 25, 2028, with the option of two one-year amendments, and may result in the award of up to two contracts. Firms will be responsible for reviewing contract documents, providing technical consultation, and supporting concrete-related engineering tasks across 13 areas of specialization including concrete aggregates, cementitious materials, chemical admixtures, concrete production, and underwater concrete. A mandatory virtual pre-SOQ conference is scheduled for April 7, 2025, and statements of qualifications (SOQs) are due by 2:00 PM PT on May 2, 2025.

The contract will be based on the contractor's actual costs with a fixed profit rate of 10%, and hourly billing rates will be escalated annually using the Employment Cost Index. Contractors will be selected through a two-step process involving SOQ evaluation and interviews, with SOQ and interview scores weighted equally at 50%. The Department of Water Resources encourages small business and disabled veteran business enterprise (DVBE) participation, though certification is not required. Contractors must comply with various state and federal requirements, including provisions related to confidential information, political reform, and generative artificial intelligence disclosure. The contract will assign work to the most qualified contractor per area of specialization based on availability, with response times ranging from 24 hours for emergency tasks to 2 days for routine tasks.

View the file

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFQ No. 10206379

Division of Engineering Architectural and Engineering Contract Program 715 P Street 4th Floor Sacramento, CA 95814

REQUEST FOR QUALIFICATIONS NO. 10206379

Concrete Engineering Services

TO ALL PROSPECTIVE APPLICANTS

March 27, 2025

The Department of Water Resources (DWR), Division of Engineering, Geotechnical Services Branch, invites qualified firms to submit a Statement of Qualification (SOQ). The services to be provided will be to assist with the engineering analysis, review, and evaluation of concrete used in the design, construction, and repair of the State Water Project (SWP) facilities, the California Aqueduct, and State flood control systems. For these facilities, the Contractor will review contract documents related to concrete construction or repair, assist with design and construction, and provide expert technical consultation in the area of concrete engineering and related specific problems or issues. Services will be provided by firms (or individuals) for a variety of facilities throughout the state.

The specific work and deliverables are identified in Exhibit A, Description of Services, and will support the Division of Engineering’s Geotechnical Services Branch.

This package contains Request for Qualifications (RFQ) No. 101206379. In submitting your SOQ, you will comply with the instructions found herein. The SOQ must be received by 2:00 PM Pacific Time (PT) on Friday, May 2, 2025, at the address indicated in Section X, Submission of SOQs of the enclosed RFQ.

The services to be provided may require that work be done independently or partnered with other DWR employees but always at the direction of the DWR.

The estimated length term for this agreement is September 25, 2025, through September 25, 2028 (three years) with the option of up to two one-year amendments (see Exhibit E, No. 17 - Multiple Years Option(s)). This solicitation may result in the award of up to two contracts. See Section VII, Evaluation Process, and Exhibit E, Work Assignment paragraph 19.

DWR reserves the right to cancel or modify this RFQ up to the date and time the SOQ is due and to waive immaterial deviations with any of the SOQs. Additionally, DWR is not responsible for any preparation costs incurred by firms submitting an SOQ.

A copy of the State of California’s (State) General Terms and Conditions, Special Terms and Conditions for the Department of Water Resources (Architectural and Engineering), and Additional Provisions (Exhibits C, D and E) are provided in this RFQ. These terms and conditions are NON-NEGOTIABLE. Any questions regarding these, or any other, terms and conditions MUST be addressed in writing during the question-and-answer period.

The Contractor Certification Clauses (available at:

https://www.dgs.ca.gov/OLS/Resources/Page-Content/Office-of-Legal-Services-Resources-List- Folder/Standard-Contract-Language#@ViewBag.JumpTo), contain terms and conditions that may apply to person(s) doing business with the State, and that may apply to your agreement. If

STATE OF CALIFORNIA – CALIFORNIA NATURAL RESOURCES AGENCY GAVIN NEWSOM, Governor

DEPARTMENT OF WATER RESOURCES

https://www.dgs.ca.gov/OLS/Resources/Page-Content/Office-of-Legal-Services-Resources-List-Folder/Standard-Contract-Language#@ViewBag.JumpTo https://www.dgs.ca.gov/OLS/Resources/Page-Content/Office-of-Legal-Services-Resources-List-Folder/Standard-Contract-Language#@ViewBag.JumpTo awarded the contract, you must sign and return Page One of the CCC 04/2017 prior to award.

The Certification must be renewed every three years and will be updated when the State makes revisions to the clauses.

Please see instructions in Section IV of the enclosed RFQ on how to submit questions regarding services to be performed or submission requirements.

ATTENTION: SIGNIFICANT UPDATES TO THE REQUEST FOR QUALIFICATIONS (RFQ)

PROCESS ARE IDENTIFIED ON THIS COVER LETTER AND DESCRIBED FURTHER IN

THE ATTACHED RFQ. THIS RFQ CONTAINS REVISED LANGUAGE AND A NEW FORMAT.

PLEASE READ IN ITS ENTIRETY.

DUE TO NEW NEGOTIATION REQUIREMENTS, PARTICIPATION IN THIS SOLICITATION

REQUIRES MANDATORY ATTENDANCE OF THE PRE-SOQ CONFERENCE.

PLEASE NOTE THE FOLLOWING CHANGES:

1. A mandatory virtual pre-SOQ Conference specific to the new negotiations process will conducted as stated in Section IV - Mandatory Pre-SOQ Conference. Also, in RFQ Section IV, directions are given for the Question and Answer period for non-negotiation related RFQ questions.

2. Section VIII - Negotiation is a new section which describes the updated negotiations process for DWR for Architectural & Engineering (A&E) contracts.

a. Negotiations will be based on a Firm’s (including subcontractor(s)) true and actual cost.

b. Negotiations will now require submission of company policies on how they compensate their employees.

3. Section XV – Generative Artificial Intelligence (GenAI) Disclosure, which describes the new GenAI disclosure requirements when submitting a Statement of Qualifications.

4. GenAI Disclosure & Factsheet (STD 1000) is the Standard form required as a part of a Statement of Qualifications

5. Exhibit E, No. 8 - Substitutions of Personnel, contains revisions.

6. The following Exhibit E clauses are now published as part of the RFQ and are no longer negotiable items:

a. Exhibit E, No. 2 - Reimbursement Clause. The process of requesting short term excess lodging is now incorporated into this clause. *NOTE: Effective October 1, 2024, the State has adopted the federal standard and non-standard reimbursement lodging rates, as well as rates for Meals and Incidental Expenses.

Please click on the link within the Reimbursement Clause to view the new Federal reimbursement rates.

b. Exhibit, E, No. 14 - Profit (identifies published profit that will be calculated into fully loaded hourly rates).

c. Exhibit E, No. 15 - Escalation (identifies how escalation will be addressed).

d. Exhibit E, No. 16 - Mark-up (for subcontractor and other direct costs).

e. Exhibit E, No. 17 - Multiple year option(s) (identifies options to amend for additional years).

7. Exhibit E, No. 18 - Other Contracts with Similar Services.

8. Exhibit E, No. 19 – Contractor Availability.

TABLE OF CONTENTS

1. Request for Qualifications Section I - Authority Section II - Definitions for Purposes of this Solicitation Section III - Background Section IV - Mandatory Pre-SOQ Conference Section V - Statement of Qualification (SOQ) Requirements Section VI - Selection Criteria Section VII - Evaluation Process Section VIII - Negotiations Section IX - SOQ Conditions Section X - Submission of SOQs Section XI - Time Schedule Section XII - Contract Obligations Section XIII - Disabled Veterans Business Enterprise Requirement Section XIV - Small Business (SB) Program Section XV - Generative Artificial Intelligence (GenAI) Disclosure……………………………………… 15

2. Payee Data Record (Std. 204)

3. SOQ Checklist

4. Potential Qualified Firms Certification Sheet

5. Explanation of Items on Potential Qualified Firms Certification Sheet

6. References

7. GenAI Disclosure & Factsheet (STD 1000)………………………………………………………………22

8. Sample Standard Agreement (Std. 213)

9. Exhibit A Scope of Work Attachment 1 – Contractor Areas of Specialization Scores Attachment 2 – Sample Task Order Attachment 3 – Sample Task Order Budget Cost Detail

10. Exhibit B Budget Detail and Payment Provisions Attachment 1 – Rate Sheet Attachment 2 – Additional Payment Provisions

11. Exhibit C General Terms and Conditions

12. Exhibit D Special Terms and Conditions – Department of Water Resources Attachment 1 – Recycled Content Certification

13. Exhibit E Additional Provisions Attachment 1 – Standard Contract Provisions Regarding Political Reform Act Compliance Attachment 2 – Protection of Confidential and Sensitive Information Attachment 3 – Non-Disclosure Certificate

14. Exhibit FEMA Certificate Regarding Lobbying

I. Authority

The Department of Water Resources (DWR) is authorized to contract with qualified firms, as described in Government Code Section 4525(a), for the services listed in Government Code Section 4525(d), 4525(e), and 4525(f).

A. California Public Contract Code § 6106 B. Regulations adopted pursuant to Government Code Section 4526:

C. California Code of Regulations Title 23, Division 2, Chapter 1.7, Sections 380 through 391

II. Definitions for Purposes of this Solicitation

A. “DWR” means the Department of Water Resources.

B. The term “architectural and engineering (hereafter “A&E”) services” shall include all architectural, landscape architectural, environmental, engineering, land surveying, and construction project management services, as well as incidental services that members of these professions and those in their employ may logically or justifiably perform, including permitting and environmental studies, rights-of-way services, design phase services, construction phase services, public outreach and meeting facilitation related to the foregoing. “A&E services” shall not include legal services rendered to the Department, provided that nothing in these regulations shall prevent an A&E Contractor from consulting legal counsel and including the fees as part of its reasonable overhead. (23 CCR § 381)

C. “Firm” means any individual, firm, partnership, corporation, association, or other legal entity permitted by law to practice the professions of architecture, landscape architecture, engineering, environmental services, land surveying, or construction project management. (23 CCR § 381)

D. For information regarding “subcontractors” or “subcontracting”, please reference Exhibit D, No. 5 – Potential Subcontractors and Exhibit D, No. 6 – Subcontractors.

E. Key Personnel are individual(s) who are expected to perform key roles to meet contract requirements, including subcontractors. The Key Personnel composition shall be representative of the categories identified in Section VII, Selection Criteria. Key Personnel are expected to be utilized throughout the life of the contract(s) that result(s) from the RFQ. The Firm is required to identify the key personnel in their organization chart (see Section VI, Statement of Qualifications (SOQ) Requirements) with a symbol (i.e., such as a star or picture of a key).

F. Agreement also means Contract.

https://leginfo.legislature.ca.gov/faces/codes_displaySection.xhtml?lawCode=GOV&sectionNum=4525.

https://leginfo.legislature.ca.gov/faces/codes_displaySection.xhtml?lawCode=PCC&sectionNum=6106.

https://leginfo.legislature.ca.gov/faces/codes_displaySection.xhtml?lawCode=GOV&sectionNum=4526.

https://govt.westlaw.com/calregs/Browse/Home/California/CaliforniaCodeofRegulations?guid=IB819C6F05B6E11EC9451000D3A7C4BC3&originationContext=documenttoc&transitionType=Default&contextData=(sc.Default) https://govt.westlaw.com/calregs/Browse/Home/California/CaliforniaCodeofRegulations?guid=IB819C6F05B6E11EC9451000D3A7C4BC3&originationContext=documenttoc&transitionType=Default&contextData=(sc.Default)

G. “RFQ” is an acronym for Request for Qualifications, the solicitation document used to request a Statement of Qualifications of firms that perform A&E services (23 CCR § 381).

H. “SOQ” is an acronym for Statement of Qualifications, the response to an RFQ or annual announcement submitted by firms that perform A&E services (23

CCR § 381).

III. Background

The Department of Water Resources (DWR) is responsible for the design, construction, operation, and maintenance of the California State Water Project (SWP). The SWP is a water storage and delivery system of dams, reservoirs, aqueducts, power plants, and pumping plants extending more than 700 miles—two-thirds the length of California. In addition, DWR is responsible for the maintenance and operation of the State’s flood control systems, which include canals, channels, weirs, and other hydraulic structures.

Concrete is one of the most prominent engineering materials used throughout the SWP.

In order to ensure a safe and reliable water system for the State, DWR must stay abreast with concrete technology and concrete construction methods.

Please see Exhibit A, Scope of Work, for a description of services.

IV. Mandatory Pre-SOQ Conference:

Virtual Meeting Information

Monday, April 7, 2025 at 10:00 AM PT

Microsoft Teams Meeting Join the meeting now

Meeting ID: 270 439 538 044 Passcode: cF3Hi7yo

Dial in by phone

+1 916-573-2034,,309932550# United States, Sacramento Find a local number

Phone conference ID: 309 932 550#

Prospective firms attending this mandatory pre-SOQ conference will receive information specific to the new negotiation process. At the time of selection, the most qualified firm will be instructed to submit their financial documents and rate sheet per Section VIII.

Negotiations. The negotiation process will be discussed in further detail during the pre- SOQ Submittal Conference.

In the event a prospective firm is unable to attend the mandatory negotiation question and answer meeting, an authorized representative may attend on the prospective firm’s behalf. The representative may sign in for only one (1) firm.

https://teams.microsoft.com/l/meetup-join/19%3ameeting_ZmIwMDJlNzktNTBkNC00N2JiLThjZmUtN2QwOTZjMTU2MWUw%40thread.v2/0?context=%7b%22Tid%22%3a%22b71d5652-4b83-4257-afcd-7fd177884564%22%2c%22Oid%22%3a%22505d8b6d-e78f-44ad-8d59-326e71696b49%22%7d tel:+19165732034,,309932550 https://dialin.teams.microsoft.com/464bff6b-35d5-4089-a809-0d998fd161ce?id=309932550

Two Phase Question and Answer Period

General RFQ Questions and Answers

Questions must be submitted in writing via email by 2:00 PM PT on Friday, April 4, 2025 to Mai Moua at Mai.Moua@water.ca.gov.

Answers regarding general RFQ questions will be provided via information letter/addendum on Thursday, April 10, 2025.

Mandatory Pre-SOQ Conference

There will be a mandatory, virtual, negotiation question and answer meeting held on Monday, April 7, 2025 at 10:00 AM PT. Negotiation follow-up questions must be submitted in writing via email by 5:00 PM PT on Friday, April 4, 2025 to Mai Moua at Mai.Moua@water.ca.gov.

No SOQ will be accepted unless Firm attends the mandatory Pre-SOQ Conference meeting.

At the Mandatory Pre-SOQ Conference all attendees will be required to identify their name, name of firm they represent, telephone number and email address.

Answers regarding Negotiations, Scope of Work and general RFQ questions will be provided via information letter/addendum on Thursday, April 10, 2025.

Please note this mandatory pre-SOQ conference negotiation may not be recorded.

V. Statement of Qualification (SOQ) Requirements

A. The SOQ should contain, at minimum, information for an objective evaluation of the Firm’s qualifications as it relates to Part VI, Selection Criteria. Please limit your SOQ to a maximum of thirty (30) pages including, cover letters, resumes, lists of projects, and licenses. Materials such as SOQ Checklist, Potential Qualified Firms – Certification Sheet, References, Conflict of Interest Statement, Certification Regarding Lobbying (See Exhibit FEMA), Table of Contents, Cover Sheets, tabs, and dividers do not count towards the thirty pages. Provide four hard copies along with an electronic copy. SOQs must be tabbed and labeled consistent with the below sections and contain the following information:

1. Introduction of Firm’s Team

a. Legal name and corresponding address of Firm, as written in the Potential

Qualified Firms - Certification Sheet (see page 19).

b. Firm’s Point of Contact.

i. Name, Title, Name of Firm, Telephone Number and E-mail Address.

Provide contact information for a representative of the firm that DWR can contact for additional information.

c. Complete this section for the Firm and all subcontractors.

i. Firm Name and address, including subcontractor(s) names and addresses. If a firm has branch offices, indicate each individual branch mailto:Mai.Moua@water.ca.gov that will have a key role on the team.

ii. Describe the organization of the Firm’s team, including identifying the Key Personnel and each of their roles and responsibilities as it relates to the services found in Exhibit A, Scope of Work.

iii. Organizational Chart. The Firm is required to identify key personnel, including subcontractor(s), in their organizational chart with a symbol (e.g. such as a star or a key). Limited to 1 page, folded to 8-1/2” x 11”, not to exceed 11” x 17”.

iv. Staff Availability. The Firm will provide a statement, a table or a graph (bar chart, pie chart, etc.) showing the percentage of staff availability of the team proposed to work on the contract. Firm with one employee only need to provide a statement.

v. Firm, including subcontractor(s) registration numbers with the California Department of Industrial Relations (If applicable).

2. Qualifications of Firm’s Key Personnel (Includes Subcontractors)

a. Describe the education and experience of the Key Personnel corresponding with Section VI, Selection Criteria, Paragraph A.

i. Education and experience related to each item as described in Selection Criteria Sections A.1 – A.13. Describe the team’s key personnel and their competencies that clearly delineate how their experience fulfills the requirements of each item in Selection Criteria Sections A.1-A.13.

ii. Information on projects for which the individual prepared, reviewed, and/or evaluated structural concrete materials, calculations, plans and specifications, construction inspection, and knowledge transfer. These projects should be related to planning, design, repair, and renovation of water storage, conveyance, flood protection or power generation facilities, and other associated hydraulic structures. Indicate personnel who were part of the project and duration.

b. Provide resumes of all Key Personnel on organizational chart and expected to be utilized. For each example project listed in the resumes, include the length of time spent on each project (month/year to month/year).

Include education (degree obtained, field of study, school name (location), date completed), professional licenses (state and license #), certificates, training, and project experience including publications and research within the last 5 years as it relates to the Exhibit A, Scope of Work. Include years of professional experience and the length of time spent on each project (month/year to month/year).

All proposed personnel to be utilized will be grouped by Firm. Personnel resumes shall be arranged by classification and numbered for each individual firm.

c. Provide copies of current, valid Professional Civil Engineer license, California preferred but not required. An image of the current licensee status as provided by the California license lookup feature at www.bpelsg.ca.gov or from another state board’s license lookup service will suffice to meet this requirement.

3. Firm’s Team Project Experience

a. Provide example projects that best illustrate the Firm’s competencies and qualifications as they relate to the services found in Exhibit A, Scope of Work.

Provide brief project descriptions and current client contact information for verification (this is in addition to references required in Section V, Statement of Qualification (SOQ) Requirements, References). The example projects, which best illustrate the proposed team’s competencies and qualifications for the contract, will represent services performed by individuals from the Firm, including subcontractors, available to do the work and listed on the Organizational Chart.

4. Certification Sheets

a. Provide the Potential Qualifying Firms Certification Sheet (see page 19) signed by an individual who is authorized to bind the firm contractually. The signature must indicate the title or position that the individual holds in the firm.

The Certification Sheet must be returned in the SOQ package. A SOQ will be rejected if the certification sheet is unsigned or omitted.

b. The Certificate Regarding Lobbying (see Exhibit FEMA, page 5 of 7) must be signed by the Contractor’s authorized official. The name and title of the Contractor’s authorized official signing the Certification must be identified. The Certification must be returned in the SOQ package. An SOQ will be rejected if the Certification is unsigned or omitted.

5. References

a. Provide three references for similar types of services within the last five years.

At least one of the provided references must be non-DWR. At a minimum, complete the references form on page 21.

6. Conflict of Interest Statement

a. The Firm will identify any of the conditions listed in and state their ability to meet the terms and conditions addressed in Exhibit D – Conflict of Interest, and Exhibit E, Political Reform Act.

VI. Selection Criteria

A. Each Firm’s SOQ for this proposed contract service will be evaluated and scored in accordance with the below selection criteria. These criteria will also be used during the interview process to assess each applicant. This solicitation may result in the award of up to two contracts.

Professional experience of the firm’s key personnel in relation to the following areas of specialization are key criteria. Each SOQ should clearly delineate and address the firm’s relevant experience and how that experience fulfills the requirements of the work.

1. Concrete Aggregates

2. Cementitious Materials

3. Chemical Admixtures

4. Concrete Production

5. Concrete Plant Operations

6. Roller-compacted Concrete

7. Mass Concrete

8. Self-consolidating Concrete

9. Quality Control Testing

10. Concrete Inspection

11. Concrete Repairs

12. Concrete Placement

13. Underwater Concrete

VII. Evaluation Process

A. After the SOQ submittal date and time, each SOQ will be checked for the presence or absence of required information in conformance with Section V, Statement of Qualification (SOQ) Requirements. If any required information is absent, the SOQ may be rejected. DWR reserves the right to cancel or modify this RFQ up to the date and time the SOQ is due and to waive immaterial deviations with any of the SOQs.

B. Up to two contracts may be awarded from this solicitation based on concrete engineering expertise for the areas of specialization. A panel of DWR personnel will evaluate the SOQs in accordance with the published Selection Criteria items A.1- A.13. All submitted SOQs will be scored by the panel. Separate interviews will then be held with at least three of the firms deemed to be the most highly qualified to provide the needed services or with all firms if less than three apply. Interviews will be held virtually, and interview questions will not be shared with Firms in advance of the interview. The Firm’s attendees will only be key personnel identified in the Firm’s SOQ. A panel of DWR personnel will evaluate interviews in accordance with the published Selection Criteria items A.1 - A.13. The SOQ and interview scores will then be weighted 50% and 50% respectively of the overall points in the evaluation. Once the contract(s) is/are awarded, work will be assigned to the contractor(s) consistent with Exhibit E, No. 19 – Contractor Availability.

C. If any presentations are required, the cost of the presentation will be the responsibility of the Firm. DWR will make no reimbursement.

Once the DWR panel has selected the most qualified Firm(s), DWR will notify that/those respective Firm(s).

VIII. Negotiations

A. The DWR negotiation process will be based on the Firm’s actual cost with a fixed profit rate that DWR has established. See Exhibit E, Additional Provisions for the published profit rate, the annual escalation for the hourly billing rates, and subcontractor markup for this contract.

B. At the time of selection, the most qualified firm(s) will be instructed to submit their financial documents and rate sheets. The Firm’s submission must be electronic and must be submitted no later than five (5) business days after notification of selection or otherwise determined by DWR. Financial documents will include resumes for all personnel, true and actual payroll records, financial records that support fringe benefits, overhead costs, and general administration, documentation or records that support costs incurred by utilizing subcontractors, historical and true records of other direct cost charges, and compensation policies. Compensation policies will include shift differential policies, holiday policies, and how the Firm’s personnel and subcontractor personnel receive compensation for overtime (hours worked over an established work week). The specific financial documents will be identified during the Mandatory Pre-SOQ Conference (see Section IV) and when the most qualified firm gets notified of selection. The prime Firm will be responsible for submitting the complete financial documents for their personnel, including any subcontractors.

Submissions of the Firm’s rate sheet must be provided electronically to DWR on a Microsoft Excel spreadsheet titled RFQ No. 10206379 followed by the name of the Firm as it appears on SOQ. Failure to submit a complete financial documents package or rate sheet may result in termination of negotiations.

C. After the financial documents and rate sheet have been received, DWR will begin to review the documentation to ensure the documents are complete and requested reimbursement is appropriate. Discussions with the most qualified applicant regarding the submitted financial documents, rate sheet, and resumes will occur after DWR’s review in order to determine a cost that is fair and reasonable to the State. Any missing documentation or comments from DWR will need to be resolved timely; see Section XI, Time Schedule. If DWR is unable to successfully negotiate a cost agreement with the most qualified Firm, negotiations will begin with the next most qualified Firm, and so on. If DWR is unable to negotiate a fair and reasonable cost with any Firm, DWR may elect not to award the contract and may elect to proceed with a new solicitation.

D. Unsuccessful Firm’s will be notified by DWR following award of the contract.

E. Nothing in this RFQ shall require DWR to award a contract.

IX. SOQ Conditions

In addition to Section VI, Selection Criteria and Section VII, Evaluation Process, the following SOQ conditions apply:

A. Firms must keep the interview selection, interview content, most qualified selection, and contract negotiations confidential until the contract is awarded.

B. Evaluations will be available for public inspection at the conclusion of the selection and award process under the California Public Records Act (Government Code Section 6250 et seq.) and subject to review by the public.

C. DWR considers confidential financial information provided by firms as a part of negotiations to not be subject to the Public Records Act.

D. On March 4, 2022, Governor Gavin Newsom issued Executive Order N-6-22 (the

EO) regarding Economic Sanctions against Russia and Russian entities and individuals. “Economic Sanctions” refers to sanctions imposed by the U.S.

government in response to Russia’s actions in Ukraine, as well as any sanctions imposed under state law. By submitting a bid or proposal a Statement of Qualifications (SOQ), Contractor represents that it is not a target of Economic Sanctions. Should the State determine Contractor is a target of Economic Sanctions or is conducting prohibited transactions with sanctioned individuals or entities, that shall be grounds for rejection of the Contractor’s SOQ any time prior to contract execution, or, if determined after contract execution, shall be grounds for termination by the State.

X. Submission of SOQs

A. Four (4) hard copies and one (1) text readable pdf copy of the SOQ must be emailed to Mai Moua at Mai.Moua@water.ca.gov.

Alternative options of SOQ submission is to mail, overnight, or hand deliver (hand deliver by appointment only) the text readable pdf copy of the SOQ on a USB Flash Drive to the following addresses:

Mail: Overnight or Hand Delivery:

Department of Water Resources Department of Water Resources Division of Engineering Division of Engineering Attention: Mai Moua Attention: Mai Moua P. O. Box 942836 715 P Street, 4th Floor, Mailbox 6 Sacramento, CA 94236-0001 Sacramento, CA 95814 Phone: (916) 882-0864 Phone: (916) 882-0864

B. The SOQs must be received by 2:00 PM PT on Friday, May 2, 2025. Envelopes should be clearly labeled: “Statement of Qualifications, No. 10206379. SOQs WILL NOT BE OPENED UNTIL Friday, May 2, 2025.” SOQs received after the due date and time will be returned unopened to the submitting party.

C. DWR is not responsible for any costs incurred by the Firms’ for preparation of

SOQs.

D. All materials (except brochures) submitted in response to this RFQ shall become

State property and will not be returned. Brochures of non-selected Firm’s may be picked up where they were submitted after award has been made.

E. An SOQ may be rejected if it is conditional or incomplete, or if it contains any proposed alternate terms, alterations of form, or other irregularities of any kind.

https://gcc02.safelinks.protection.outlook.com/?url=https%3A%2F%2Fwww.gov.ca.gov%2Fwp-content%2Fuploads%2F2022%2F03%2F3.4.22-Russia-Ukraine-Executive-Order.pdf&data=05%7C01%7C%7C28a4c28038ae446efda008da6679d6cf%7Cb71d56524b834257afcd7fd177884564%7C0%7C0%7C637934970719385209%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C3000%7C%7C%7C&sdata=UrRQWpdi0r26m4VTb2rnqz66qeF%2BBB%2B4Yk3HtTmfPpY%3D&reserved=0

The State may reject all SOQs and may cancel or modify this RFQ up to the date the SOQ is due. DWR reserves the right to reject all SOQs.

F. Before the SOQ submission deadline, a Firm may withdraw its SOQ by submitting a written withdrawal request to the State, signed by the Firm or an agent authorized in accordance with the preceding paragraph. A Firm may thereafter submit a new SOQ prior to the SOQ submission deadline. SOQs may not be revised without good cause and DWR’s consent subsequent to SOQ submission deadline.

G. DWR may modify the RFQ prior to the date fixed for submission of SOQs by the issuance of an addendum posted to California State Contracts Register via Cal eProcure (FI$Cal).

H. Firms are cautioned not to rely on DWR, during the evaluation, to discover and report any defects and errors in the submitted documents. Firms, before submitting their documents, should carefully proof them for errors and adherence to the RFQ requirements. DWR may, but is not required to, waive minor deviations from submission requirements.

XI. Time Schedule*

A. RFQ published CSCR 3-27-25

Integrated Marketing Systems 3-27-25

B. SOW and General RFQ Questions Deadline 4-4-25 at 2:00 PM

C. Mandatory Pre-SOQ Conference 4-7-25 at 10:00 AM

D. Answers Deadline 4-10-25

E. SOQ Submission Deadline 5-2-25 at 2:00 PM

DWR will make every effort to commit to the dates listed below. DWR expects the same commitment from firms. If a firm is not able to meet the timelines listed below F – M, DWR may opt to begin negotiations with the next most qualified firm. DWR reserves the right to change the dates:

F. Interview Dates (estimated dates) 5-19-25 – 5-27-25

G. Most qualified Firm is selected and request of Financial Documents and Rate Sheet (estimated date) 5-29-25 **Start of Negotiations

H. Submission of Financial Documents and Rate Sheet Due (estimated date, 5 days after selection) 6-5-25

I. DWR Completes Review of Financial Documents and Rate Sheet; DWR Provides Comments and Requests Missing Information (estimated date) 6-16-25

J. Submission of resumes for all staff, if needed (estimated date, 3 days after DWR completes review) 6-19-25

K. Submission of requested documentation necessary to complete negotiations (estimated date, 3 days after DWR completes review) 6-19-25

L. Completion date for final Rate Sheet (estimated date) 6-26-25

M. Completion date for contract negotiations (estimated date) 6-26-25

N. Contract approval (estimated date) 7-25-25

**Negotiation Workshop: After the most qualified is determined and financial documentation has been received, DWR will start rate negotiations. A negotiation workshop may be held if necessary to complete the negotiation process.

XII. Contract Obligations

A. The following documents, when completed and approved, along with the resume(s) will comprise the contract (sample contract starting on page 24):

1. A Standard Agreement (STD. 213).

2. Scope of Work in Exhibit A and any corresponding attachments.

3. Budget Detail and Payment Provisions in Exhibit B and any corresponding attachments.

4. General Terms and Conditions in Exhibit C.

5. Special Terms and Conditions for the Department of Water Resources in

Exhibit D and any corresponding attachments.

6. Additional Provisions listed in Exhibit E and any corresponding attachments.

7. Required Provisions Under Code of Federal Regulations in Exhibit FEMA.

B. The following documents are not exhibits, but are required prior to award of contract:

1. Contractor Certification Clause (CCC 04/2017)

2. Payee Data Record (Std. 204)

3. Insurance certificates and endorsements as stated in Exhibit E.

XIII. Disabled Veteran Business Enterprise (DVBE) Requirement

A. Firms are strongly encouraged to provide certification of Disabled Veterans

Business Enterprise (DVBE) status. DVBE certification may be obtained from the

Department of General Services, Office of Small Business and DVBE Services (OSDS), and should be attached to the SOQ if DVBE status is claimed. DVBE participation is not required and in no way affects the selection process criteria for this contract.

B. For additional DVBE information DWR encourages you to work with and contact Joanne Arcilla, Small Business and DVBE Program Manager at (916) 707-4593 or via email at SB.DVBE@water.ca.gov.

XIV. Small Business (SB) Program

A. In recognition of the significant economic contribution made by California’s small business sector, Government Code 14838 (a) mandates each California agency and department to meet an annual California Small Business participation goal of 25 percent of non-governmental procurements. This goal is achieved through contract awards made directly to the Small Business community or through subcontracted partnerships between Prime firms and California certified small businesses. DWR strongly encourages Prime Firms to partner with California certified Small Businesses in response to this solicitation. Firms that include California certified small businesses as an initial team member, or those which are added subsequent to contract execution through the amendment or task order process, are required to identify the Small Business firm status of each firm as appropriate and will be required to report expenditures made to these business concerns. This will allow DWR to track, tabulate and report overall expenditures made in the Small Business sector as required by the Department of General Services.

C. For additional DVBE information DWR encourages you to work with and contact

Joanne Arcilla, Small Business and DVBE Program Manager at (916) 707-4593 or via email at SB.DVBE@water.ca.gov.

XV. Generative Artificial Intelligence (GenAI) Disclosure

A. The State of California seeks to realize the potential benefits of GenAI, through the development and deployment of GenAI tools, while balancing the risks of these new technologies.

B. Submitters must notify the State in writing if their solution or service includes, or makes available, any GenAI technology, including GenAI from third parties or subcontractors.

C. The State has developed a GenAI Disclosure & Factsheet to be completed by the Submitters.

D. Failure to disclose GenAI to the State and submit the GenAI Disclosure & Factsheet will result in disqualification of the Submitter and may void any resulting contract. The State reserves its right to seek any and all relief it may be entitled to as a result of such non-disclosure. Upon receipt of a Submitter GenAI Disclosure & Factsheet, the state reserves the right to incorporate GenAI Special Provisions into the final contract or reject Submitters that present an unacceptable level of risk to the State.

mailto:SB.DVBE@water.ca.gov https://gcc02.safelinks.protection.outlook.com/?url=https%3A%2F%2Fleginfo.legislature.ca.gov%2Ffaces%2Fcodes_displaySection.xhtml%3FsectionNum%3D14838.%26lawCode%3DGOV&data=05%7C01%7C%7Ce37584d997f047245a2608db99e16991%7Cb71d56524b834257afcd7fd177884564%7C0%7C0%7C638272965640869848%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C3000%7C%7C%7C&sdata=A2acIySFo1oRvViSicW18%2B1jzyM9DBtB9qi4tMsTOIc%3D&reserved=0 mailto:SB.DVBE@water.ca.gov

SOQ CHECKLIST

Please submit the following items in your SOQ in the order listed below. Additionally, the SOQ will not be considered responsive unless the following documents are included in your SOQ Submission.

DWR reserves the right to waive immaterial deviations:

Section 1 - Introduction of Firm’s Team

Legal name and corresponding address of Firm

Name, title, address, telephone number, and email address of person DWR can concerning the Firm’s SOQ.

Proposed Team, including legal names, list of office address(es), description of organization of Firm’s team, Organization Chart of Firm’s team, percentage of availability, and (if applicable) DIR registration numbers.

Section 2 - Qualification of Firm’s Key Personnel

Education and experience of Key Personnel

Resumes of all Key Personnel

Copies of valid professional license/registration/certification

Section 3 - Firm Project Experience

Projects to illustrate Firm’s competencies and qualifications.

Section 4 - Certification Sheets

Potential Qualified Firms Certification Sheet (signed by Firm’s authorized individual)

Generative Artificial Intelligence (GenAI) Disclosure (STD 1000) (signed by Firm’s authorized individual)

Certification Regarding Lobbying (Page 5 of Exhibit FEMA) (Signed by Firm’s authorized individual)

Section 5 - References

Three (3) references and of those, one (1) should be Non-DWR References

Section 6 - Conflict of Interest Statement that identifies any of the conditions listed in and states the Firm’s ability to meet the terms and conditions addressed in Exhibit D – Conflict of Interest, and Exhibit E, Political Reform Act.

One text readable digital (pdf) copy of the SOQ emailed, or one text readable digital (pdf) copy on a USB Flash Drive of the SOQ mailed, overnighted, or hand delivered.

Please return a completed copy of this checklist with your SOQ.

POTENTIAL QUALIFIED FIRMS - CERTIFICATION SHEET

Concrete Engineering Services – RFQ No. 10206379

This Potential Qualification Firms – Certification Sheet must be signed and returned along with all the required documents, as indicated in Section VI, Statement of Qualification (SOQ) Requirements. The SOQ must be transmitted in a sealed envelope in accordance with all SOQ instructions.

A. Your all-inclusive SOQ is submitted as follows:

B. All Attachments follow behind this cover letter. (See SOQ Checklist)

C. Your signature affixed hereon and dated certifies that you have complied with all the requirements of this RFQ document. Your signature authorizes the verification of this certification.

>>> AN INCOMPLETE OR UNSIGNED SOQ WILL BE CAUSE FOR REJECTION <<<

1. Company Legal Name 2. Telephone Number

2a. Fax Number

3. Address

Indicate your organization type:

4. Sole Proprietorship 5. Partnership 6. Corporation

Indicate the applicable employee and/or corporation number:

7. Federal ID No. (FEIN) 8. California Corporation No.

Indicate applicable license and/or certification information:

9. Contractors’ State License Board Number

10. PUC License Number

CAL-T-

11. Required Licenses/Certifications

12. Authorized Individual’s Name (Print) 13. Title

14. Signature 15. Date

16. Are you certified with the Department of General Services, Office of Small Business and DVBE Services (OSDS) as:

a. Small Business Enterprise Yes No If yes, enter certification number:

b. Disabled Veteran Business Enterprise Yes No If yes, enter your service code below:

NOTE: A copy of your Certification is required to be included if either of the above items is checked “YES.”

Date application was submitted to OSDS, if an application is pending:

(SEE NEXT PAGE FOR EXPLANATIONS ON POTENTIAL QUALIFIED FIRMS

CERTIFICATION SHEET)

EXPLANATION OF ITEMS ON POTENTIAL QUALIFIED FIRMS

CERTIFICATION SHEET

The Potential Qualified Firms – Certification Sheet on page 19 will be completed and submitted in accordance with the SOQ requirements. An authorized individual’s signature on this document certifies that the Firm complied with all the RFQ requirements.

(1), (2), (2a), and (3) are self-explanatory.

(4) A sole proprietorship is a form of business in which one person owns all the assets of the business in contrast to a partnership and corporation. The sole proprietor is solely liable for all the debts of the business.

(5) A partnership is a voluntary agreement between two or more competent persons, as co-owners, to place their money, effects, labor, and skill, or some or all of them in lawful commerce or business, with the understanding that there shall be a proportional sharing of the profits and losses between them.

(6) A corporation is an artificial person or legal entity created by or under the authority of the laws of a state or nation, composed, in some rare instances, of a single person and his successors, being the incumbents of a particular office, but ordinarily consisting of an association of numerous individuals.

(7) (If applicable) The Federal Employer Identification Number will need to be provided and will used for company identification and verification of tax compliance.

(8) (If applicable) The California Corporation Number will need to be provided and will be used to check if the corporation is in good standing with the State of California.

(9) (If applicable) A Contractors’ State License Board Number will be provided and used for verification of Contractor’s license for Public Works Agreements.

(10) (If applicable) A Public Utilities Commission (PUC) license for Public Works Agreements will be provided and used for verification.

(11) Complete by indicating the type of license and/or certification for services described.

(12), (13), (14), and (15) are self-explanatory.

(16) Identify if Firm is a certified Small Business Enterprise (a) or Disabled Veteran Business

Enterprise (b). If Firm is either a Small Business Enterprise or Disable Veteran Business Enterprise, the Firm’s certification number will need to be provided or when the application to the Department of General Services, Office of Small Business and DVBE Services (OSDS) was submitted.

REFERENCES

Provide three references of similar types of services performed within the last five (5) years. At least one (1) should be non-DWR.

Name of Firm: Telephone Number:

Name of Contact:

Street Address: City: State: Zip Code:

Year Service Performed:

Service:

STATE OF CALIFORNIA RFQ No. 10206379

STANDARD AGREEMENT

STD 213 (Rev 06/03) AGREEMENT NUMBER

REGISTRATION NUMBER

1. This Agreement is entered into between the State Agency and the Contractor named below:

STATE AGENCY'S NAME

CONTRACTOR'S NAME

2. The term of this through

Agreement is:

3. The maximum amount $ of this Agreement is:

4. The parties agree to comply with the terms and conditions of the following exhibits which are by this reference made a part of the Agreement.

Exhibit A – Scope of Work pages

Exhibit B – Budget Detail and Payment Provisions pages

Exhibit C – General Terms and Conditions pages

Exhibit D – Special Terms and Conditions for DWR (Over $5,000 Standard Payable), DWR 9544 (Rev 9/06) pages

Exhibit E – Additional Provisions pages

Items shown with an Asterisk (*) are hereby incorporated by reference and made part of this agreement as if attached hereto.

These documents can be viewed at www.ols.dgs.ca.gov/Standard+Language IN WITNESS WHEREOF, this Agreement has been executed by the parties hereto.

CONTRACTOR California Department of General Services Use Only

CONTRACTOR’S NAME (if other than an individual, state whether a corporation, partnership, etc.)

BY (Authorized Signature)

DATE SIGNED(Do not type)

PRINTED NAME AND TITLE OF PERSON SIGNING

ADDRESS

STATE OF CALIFORNIA

AGENCY NAME

BY (Authorized Signature)

DATE SIGNED(Do not type)

PRINTED NAME AND TITLE OF PERSON SIGNING

DGS Approval not required per Public

Contract Code 10335 (a)

ADDRESS

Exhibit A

ARCHITECTURAL & ENGINEERING CONTRACTS

Department of Water Resources, Division of Engineering

SCOPE OF WORK

Concrete Engineering Services

I. DESCRIPTION OF SERVICES

1. The Contractor will provide the Department of Water Resources (DWR), Division of Engineering (DOE), Geotechnical Services Branch (GSB) with engineering analysis, review, and evaluation of concrete used in the design, construction, and repair of the State Water Project (SWP) facilities, the California Aqueduct, and State flood control systems. For these facilities, the Contractor will review contract documents related to concrete construction or repair, provide assistance during design and construction, and provide expert technical consultation in the area of concrete engineering and related specific problems or issues. Specific tasks to support such work are listed in scope of work items 2 and 3 below. The Contractor will provide DOE, GSB, on an as needed and as directed basis, concrete engineering expertise for the areas of specialization as follows:

a. Concrete Aggregates

b. Cementitious Materials

c. Chemical Admixtures

d. Concrete Production

e. Concrete Plant Operations

f. Roller-Compacted Concrete

g. Mass Concrete

h. Self-Consolidating Concrete

i. Quality Control Testing

j. Concrete Inspection

k. Concrete Repairs

l. Concrete Placement

m. Underwater Concrete

2. The Contractor will be required to perform some or all of the following specific tasks, but always at the direction of the DWR Contract Manager and on an as-needed basis:

a. Answer questions and solve problems regarding the use of cement, concrete additives, sealants, aggregates, cementitious materials, chemical admixtures, concrete test equipment, and procedures.

b. Review concrete specifications, mix designs, and project submittals related to the design, production, handling, and placement of concrete.

c. Provide guidance on concrete qualification tests, quality control testing, and inspection.

d. Provide guidance on reducing green-house gas emissions related to concrete production and calculate global warming potential of concrete.

e. Prepare reports containing findings, conclusions, and recommendations.

3. The Contractor will provide the following services to support scope of work items 1 and 2 above.

a. Attend project meetings and site visits. Provide informal and/or formal verbal and written comments at the conclusion of each meeting and/or site visit.

b. Provide concrete engineering knowledge transfer to DWR staff.

DELIVERABLES

If DWR determines additional detail, clarification, and direction is needed to be performed and deliverables to be provided, pursuant to this scope of work, DWR may issue Task Orders (See Exhibit A, Attachment 2 – Sample Task Order, and Exhibit A, Attachment 3 – Sample Task Order Budget Detail). Deliverables will be provided in accordance with the Deliverables and Other Work Product clause in Exhibit E.

Deliverables are listed in the table below.

The deliverables supporting scope of work items 1 – 3 above include:

Deliverable Due Date Comments of preliminary construction contract drawings and specifications

Within two (2) weeks of receiving a written request from the DWR Contract Manager

Responses to Request for Information (RFI) and submittals

As directed by DWR Contract Manager normally within 2 - 5 calendar days after receiving RFI or submittal.

Written memos or reports containing findings, recommendations, and conclusions.

As identified by the DWR Contract Manager

Email correspondence response to DWR concrete related inquiries

Within 2 - 5 calendar days of receiving a written request from the DWR Contract Manager

Meeting notes As identified by the DWR Contract Manager Verbal comments As identified by the DWR Contract Manager Note: DWR may define different due dates as necessary via the issuance of Task Orders.

JOB SITE VISITS

The Contractor may be required to attend meetings and job site visits throughout State Water Project facilities.

CONTRACTOR AVAILABILITY

Work will be assigned according to Exhibit E, Paragraph 19 – Contractor Availability.

CONTACT INFORMATION

The Contract Managers during the term of this agreement will be:

Department of Water Resources (Name of Selected Contractor)

Feraidon Ataie Name 715 P Street, 4th Floor Street Address Sacramento, California 95814 City, State, Zip Code Phone: (916) 547-4690 Phone:

Email: feraidon.ataie@water.ca.gov Email:

Contract Managers may be changed by written notice to the other party.

RFQ 10206379

Exhibit A, Attachment 1

Contractor Areas of Specialization Scores

THIS IS A PLACEHOLDER PAGE.

This will be the Contractor Scores and will reflect how the work will be assigned based on how the contractors were scored relative to the specific concrete engineering expertise areas of specialization.

Exhibit A, Attachment 2

ARCHITECTURAL & ENGINEERING CONTRACTS

SAMPLE TASK ORDER

(To be developed by DWR Contract/Task Order Manager)

TASK ORDER NO. XX

Contractor:

Request for Services under Standard Agreement No. 46000XXXXX

Dated:

(Instructions: The purpose of a task order is to provide specific detail regarding deliverables, schedule, and cost detail of each task. Applicable terms and conditions of the original contract, as amended, apply. Do not address terms and conditions in this document.)

DESCRIPTION OF TASK:

Provide a one or two sentence summary of work to be performed under this task order.

Only tasks that fit within the original scope of work may be assigned by a task order.

SCOPE OF WORK:

A. Description

Detailed description and location of service being requested – may include several separate subtasks which are related to completing the main project or task. Include reference from Contract Scope of Work for which the subtask is related. For example:

1. Contractor will conduct a site visit to the five repair sites to document the existing conditions, surrounding land uses, and view the construction areas. This task is covered under original scope of work, contract number 46000XXXXX, Exhibit A, Item X.x.xxx.

2. Contractor will prepare a brief description of the project (including defining the…

This is the start of the file's text. The full file is on GovTribe.