RFI-1212134548 Q&A Sheet (As of 4/30/13)
Question(s)
Answer
1.
How are these services currently being performed? Under contract? In-house?
The services for this RFI are currently under contract. Refer to the “Place of Performance” section for location information.
2.
If these requirements are currently being performed under a contract, Who is the Contractor? What is the contract number?
The Government does not intend to award a contract on the basis of this RFI. Your response will be treated as information only.
3.
Is there an estimated value range for this requirement?
The Government is conducting market research for technical support services to develop, deploy and transition financial data in all phases of its Unified Financial Management System (UFMS) project.
4.
Is there a projected date for the release of a pre-solicitation notice or an RFP?
If a solicitation is released, it will be synopsized on the General Services Administration Advantage E-Buy (e-buy) website. Responders are responsible for monitoring www.ebuy.gsa.gov for additional updates and solicitation, if released.
5.
May we, at your convenience, have an opportunity to briefly discuss our capability statement with you?
The Government will not respond to any questions via telephone calls or faxes.
6.
What is the actual due date?
May 9, 2013
7.
The RFI states that the contractor’s personnel will be required to “Analyze, design, develop, implement and maintain client server applications over distributed networks and related protocols”. Are these client server applications referring to the IMS and the MetaStorm BPM product suite or other applications? If it is other applications, please provide additional information regarding the programming languages, databases, and technical infrastructure the contractor will need to support.
The client/server applications refer to components of the Invoice Management System (IMS) process hosted on the Enterprise Process Automation System (EPAS) platform. The applications utilized by IMS are Metastorm BPM, Metastorm Integration Manager (MIM), Business Objects Enterprise and Crystal Reports. The EPAS databases are hosted on Oracle.
8.
What is the anticipated period of performance and the expected contract start date?
See Answers #2, #3 and #4.
9.
Please clarify if the FBI requires a company to provide a narrative to describe its core competencies or does the FBI just require a company to confirm it registered in the System for Award Management (SAM) under the NAICS codes specified by the FBI along with a listing of the company’s PCS relevant to the RFI.
The FBI requires a company to provide a narrative that describes its core competencies along with a listing of the company’s PCS relevant to the RFI.
10.
In providing a capability statement can companies provide expertise as a team (i.e. prime and subcontractors) for this response?
Yes
11.
Will the FBI also accept PDF format?
Yes, a PDF format is acceptable for this effort.
12.
Please clarify the reference to “number 2, 3, and 4 above.” Should this reference be just to number 2 above?
Please submit answers for Item #2.
13.
Is a ROM required as part of this response? If a ROM is not required, can the two pages be allocated to responding to items 1 and 2?
After further review, a ROM is not required for this market research. Respondents may use the two pages for Items #1 and #2.
14.
Is the FBI considering issuing the final solicitation as a small business set aside?
See Answers #2, #3 and #4.