Q A - Pasadena Roof R4.doc
DOC document 24 KB Posted
- Attached to
- RECOVERY- Pasadena Roof Replacement Federal contract opportunity
- Solicitation number
- Not on record
About this file
Questions and Answers
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Additional Contractual documents.zip | ZIP file | |
| Amended Scope of Work.doc | DOC document | |
| SIGN_IN_SHEET_PASADENA_ROOF.pdf | ||
| Pasadena Roof Assessment - Clock Tower Ledge.pdf | ||
| Summary of Work Specification review.pdf | ||
| FBO docs.zip | ZIP file | |
| Specs drawings.zip | ZIP file |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Pasadena Roof Replacement
Rev. 2-26-2010
General Questions During Meeting:
Questions Asked at the Pasadena Pre-bid Roof Meeting
1. Can they self-certified that they are a small business?
Answer. Contact the local SBA office
2. What are the Fire and Safety guidelines that should be followed? We have the guidelines, what else should be posted on the FBO website to be referenced?
Answer: Please refer to PBS P-100 and the GSA “PV Fire Safety Guide” as posted on the FBO website.
3. Why an SRI 112?
Answer: SRI of 112 was an error in the Summary of Work, please see published amendment for corrected section and SRI. Also, note Cool Roof performance justification amendment.
4. What will we be using as staging Area?
Answer: Each staging will be done by roof sections.
5. Will we be raising the height of any flashing?
Answer: Please see summary of work and added amendment.
6. Was Asbestos testing done?
Answer: "GSA has performed asbestos surveys, and may perform additional testing prior to construction. Nonetheless if the Contractor suspects previously unidentified ACMs the Contractor should notify GSA and with GSA's concurrence may test for asbestos. If ACMs are detected GSA will reimburse the Contractor for the direct cost of reasonable testing as agreed when GSA approved the testing, and also GSA will be responsible for any necessary abatement (to be performed by a third party hired by GSA). If no ACMs are detected the Contractor is responsible for testing costs."
Further – the tests performed by the designing company are attached this solicitation.