This statement of work outlines requirements for upgrading a firearms range at the Bureau of Reclamation's Grand Coulee Dam facility. The contractor shall uninstall existing equipment, salvaging all reusable items, and install new infrastructure and equipment at both the 50-yard and 100-yard ranges. This includes twelve fixed turning target stands, dual running man targets, bobber targets, and ballistic knee walls at the 50-yard range, along with six additional fixed target stands and an expanded concrete pad and knee wall at the 100-yard range. All new equipment must meet the salient characteristics specified and include a three-year comprehensive warranty, demonstration of existing equipment removal, independent and computerized target control, wireless remote tablet operation, and on-site training. Delivery and installation of all items is required within 180 days of contract award at the specified Bureau of Reclamation warehouse location in Grand Coulee, Washington, and must be coordinated in advance with the designated point of contact.

The related federal contract opportunity is solicitation number 140R8123Q0222 for a Grand Coulee Training Center target system awarded by the Department of the Interior Bureau of Reclamation.

View the file

Other files for this federal contract opportunity

Other files attached to GRAND COULEE TRAINING CENTER TARGET SYS, newest first.
File Type Posted
ACQ_Sole_Source_Justification_Redacted.pdf PDF
Sol_140R8123Q0222.pdf PDF
140R8123Q0222.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work

Grand Coulee Range Upgrade

1.0 Project Background

The Bureau of Reclamation, Denver Security Division located in Denver, Colorado, has a requirement to upgrade the firearms range at Grand Coulee Dam.

2.0 Description of Hardware

Contractor shall uninstall existing equipment salvaging all reusable equipment, install all required infrastructure and new equipment that meets or exceeds all salient characteristics listed in Section 3.0 below. All items will be new/unused condition and have full manufacturer warranty. All equipment must be fully operational to manufacturer specifications.

3.0 Salient Characteristics

50-yard Range:

1. (12) Fixed Turning Target Stands Requires: 120v, 60 HZ, 16 FLA

2. Dual Running Man Pro- DRM PRO, Requires: Single Phase 200-240v (50/60HZ) 20A

3. 12 Bobber Xtreme Targets, Requires: 12V / < 100mA

4. 1 Ballistic Knee Wall, Rifle rated knee wall to protect all targets

100-yard Range:

5. 6 Fixed Turning Target Stands, Requires: 120v, 60 HZ, 16 FLA

6. 1 Ballistic Knee Wall, Rifle rated knee wall to protect all targets

7. 100-yard concrete pad to be expanded by 2-4 feet depth for the base of knee wall

All items:

8. Trusted Partner 3 Year Warranty: Comprehensive Trusted Partner Warranty covers both parts and labor due to manufacturing or product defects.

9. DEMO of all existing targets and knee wall materials

10. Independent target control

11. Computerized scenarios and exposure times

12. All electrical power requirements to be installed

13. Wireless remote tablet control with Touch Screen Master Control

14. Test and function check all target systems, correct all errors prior to turnover

15. On-site training of BOR personnel on operation and basic maintenance

4.0 Delivery

All equipment will be delivered and installed within 180 days of contract award at:

Bureau of Reclamation HWY 155, Warehouse B, Door 6 Grand Coulee, WA 99155 C/O Nate Stull

These are secure facilities. Delivery must be coordinated by phone at least 24 hours in advance with the designated point of contact (provided after contract award). All vehicles, equipment and personnel are subject to inspection prior to entry to the compound.