Attachment 1 - Supply Scope of Work
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Clauses_and_Provisions.pdf | ||
| Sol_R15PS00851.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation: R15PS00851 Attachment 1
Supply Scope of Work
Riparian Mosaic Floodplain Mitigation Credits
Date: April 13, 2015
1.0 Background
The Joint Federal Project (JFP) is being implemented by the Bureau of Reclamation (Reclamation) and the Army Corps of Engineers (Corps), Sacramento District. The JFP addresses improved hydrologic control of reservoir releases and the Corps’ flood damage reduction objectives for the lower American River. The main feature of the JP is the construction of a new auxiliary spillway adjacent to the Left Wing Dam of the Folsom Facility. Construction of the JP would impact wetlands and waters of the U.S. The project is located at the Folsom Dam and Reservoir, at the confluence of the North and South Forks of the American River. This reservoir straddles Placer, Sacramento, and El Dorado Counties, in the State of California.
2.0 Scope
Reclamation proposes to enter into a contract for purchase of up to 26.5 acres of riparian mosaic floodplain mitigation credits from a Corps certified mitigation bank that serves the Project area.
The number of credits purchased is commensurate with the amount of time that it would take to purchase. For every month that the mitigation is not purchased, you use a multiplier of 0.05, and add that to the amount plus 1, and then multiply that by the amount originally required (e.g., 10 acres, which is 10 credits).
3.0 Type of Contract
The government will award a fixed price contract.
4.0 Period of Performance
The period of performance is for 2016.
5.0 Place of Performance
The work to be performed under this contract will be performed at a Corps certified mitigation bank that serves the Project area.
6.0 Applicable Publications (Current Editions)
Corps of Engineers Permit #SPK-2007-01068 Final Folsom Dam Safety and Flood Damage Reduction Environmental Impact Statement/Environmental Impact Report/Record of Decision, dated March 2007
Solicitation: R15PS00851 Attachment 1
7.0 Objectives
Meet the jurisdictional features that were identified within the Project area:
Impacted (Acres) Swale/Drainage 0.282 Other Waters 50.3 Forest Wetlands 8.8