About this file

Attachment 1 - Supply Scope of Work

View the file

Other files for this federal contract opportunity

Other files attached to Puchasing Mitigation Credits for Mosiac Floodplain, newest first.
File Type Posted
Clauses_and_Provisions.pdf PDF
Sol_R15PS00851.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation: R15PS00851 Attachment 1

Supply Scope of Work

Riparian Mosaic Floodplain Mitigation Credits

Date: April 13, 2015

1.0 Background

The Joint Federal Project (JFP) is being implemented by the Bureau of Reclamation (Reclamation) and the Army Corps of Engineers (Corps), Sacramento District. The JFP addresses improved hydrologic control of reservoir releases and the Corps’ flood damage reduction objectives for the lower American River. The main feature of the JP is the construction of a new auxiliary spillway adjacent to the Left Wing Dam of the Folsom Facility. Construction of the JP would impact wetlands and waters of the U.S. The project is located at the Folsom Dam and Reservoir, at the confluence of the North and South Forks of the American River. This reservoir straddles Placer, Sacramento, and El Dorado Counties, in the State of California.

2.0 Scope

Reclamation proposes to enter into a contract for purchase of up to 26.5 acres of riparian mosaic floodplain mitigation credits from a Corps certified mitigation bank that serves the Project area.

The number of credits purchased is commensurate with the amount of time that it would take to purchase. For every month that the mitigation is not purchased, you use a multiplier of 0.05, and add that to the amount plus 1, and then multiply that by the amount originally required (e.g., 10 acres, which is 10 credits).

3.0 Type of Contract

The government will award a fixed price contract.

4.0 Period of Performance

The period of performance is for 2016.

5.0 Place of Performance

The work to be performed under this contract will be performed at a Corps certified mitigation bank that serves the Project area.

6.0 Applicable Publications (Current Editions)

Corps of Engineers Permit #SPK-2007-01068 Final Folsom Dam Safety and Flood Damage Reduction Environmental Impact Statement/Environmental Impact Report/Record of Decision, dated March 2007

Solicitation: R15PS00851 Attachment 1

7.0 Objectives

Meet the jurisdictional features that were identified within the Project area:

Impacted (Acres) Swale/Drainage 0.282 Other Waters 50.3 Forest Wetlands 8.8