This document outlines a Quality Assurance Surveillance Plan (QASP) for on-call ultrasound services provided to the Hershel "Woody" Williams VA Medical Center. The contractor will be evaluated on metrics including availability of technicians, privacy and security compliance, licensure and certification status, technical proficiency, and completion of required training. Performance will be monitored through methods such as direct observation, inspection, and review of user complaints and documentation. Contractors will receive a rating of exceptional, very good, satisfactory, marginal, or unsatisfactory based on these performance reviews. Any issues will be documented in a Contract Report and contractors must provide corrective action plans in response.
A related federal contract opportunity posted by the Huntington, WV VAMC seeks non-vascular ultrasound technicians. This requirement is set aside for small businesses to provide services to the VA facility.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| CONTRACTOR RULES OF BEHAVIOR Attachment 3.docx | DOCX document | |
| RFQ - 36C24522Q0508 06212022.pdf | ||
| CONTRACTOR CERTIFICATION Attachment 2.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Quality Assurance Surveillance Plan (QASP)
Page 1 of 10 Version 0007 Dated 02/18/2018
The contractor will be evaluated in accordance with the following:
For: Hershel “Woody” Williams VA Medical Center ON-Call Ultrasound service
Contract Description: Provision ON-Call Ultrasound Services to the Hershel “Woody” Williams VA Medical Centers Imaging Department.
The contractor will be evaluated in accordance of the following:
1. PURPOSE
This Quality Assurance Surveillance Plan (QASP) provides a systematic method to evaluate performance for the stated contract. This QASP explains the following:
• What will be monitored?
• How monitoring will take place.
• Who will conduct the monitoring?
• How monitoring efforts and results will be documented.
This QASP does not detail how the contractor accomplishes the work. Rather, the QASP is created with the premise that the contractor is responsible for management and quality control actions to meet the terms of the contract. It is the Government’s responsibility to be objective, fair, and consistent in evaluating performance.
This QASP is a “living document” and the Government may review and revise it on a regular basis. However, the Government shall coordinate changes with the contractor through contract modification. Copies of the original QASP and revisions shall be provided to the contractor and Government officials implementing surveillance activities.
2. GOVERNMENT ROLES AND RESPONSIBILITIES
The following personnel shall oversee and coordinate surveillance activities.
a. Contracting Officer (CO) – The CO shall ensure performance of all necessary actions for effective contracting, ensure compliance with the contract terms, and shall safeguard the interests of the United States in the contractual relationship. The CO shall also assure that the contractor receives impartial, fair, and equitable treatment under this contract. The CO is ultimately responsible for the final determination of the adequacy of the contractor’s performance.
Assigned CO: Crystal Hinton
b. Contracting Officer’s Representative (COR) – The COR is responsible for technical administration of the contract and shall assure proper Government surveillance of the contractor’s performance. The COR shall keep a quality assurance file. The COR is not empowered to make any contractual commitments or to authorize any contractual changes on the Government’s behalf.
Assigned COR: James D. Ward Organization or Agency: VA
Page 2 of 10 Version 0007 Dated 02/18/2018
3. CONTRACTOR REPRESENTATIVES
The following employee(s) of the contractor serve as the contractor’s program manager(s) for this contract.
Primary: James D. Ward:
X James D. Ward
Page 3 of 10 Version 0007 Dated 02/18/2018
4. PERFORMANCE STANDARDS
The contractor is responsible for performance of ALL terms and conditions of the contract. CORs will provide contract progress reports quarterly to the CO reflecting performance on this plan and all other aspects of the resultant contract. The performance standards outlined in this QASP shall be used to determine the level of contractor performance in the elements defined. Performance standards define desired services. The Government performs surveillance to determine the level of Contractor performance to these standards.
The Performance Requirements are listed below in Section 6. The Government shall use these standards to determine contractor performance and shall compare contractor performance to the standard and assign a rating. At the end of the performance period, these ratings will be used, in part, to establish the past performance of the contractor on the contract.
5. METHODS OF QA SURVEILLANCE
Various methods exist to monitor performance. The COR shall use the surveillance methods listed below in the administration of this QASP.
a. DIRECT OBSERVATION. Direct observation by VA personnel during visits to warehouse facilities as well as Veteran homes
b. PERIODIC INSPECTION. Inspections will be conducted both scheduled and unscheduled.
c. VALIDATED USER/CUSTOMER COMPLAINT: Complaints received from customers reported to contractor and VA will be logged and submitted to the contractor for immediate resolution/corrective action. Contract will monitor complaints monthly and report to the COR on a quarterly basis.
d. RANDOM SAMPLING: Option to be used in reviewing vendor employee and Veteran folders to ensure proper documentation is being maintained.
e. VERIFICATION AND/OR DOCUMENTATION PROVIDED BY CONTRACTOR: Receipt/evaluation of reports required in Performance Work Statement, Attachment D.
f. Other: Patient home inspection, patient satisfaction/complaints, monthly review of invoices for accuracy, timeliness of equipment delivery, accuracy of required documentation submitted, and adherence to Joint Commission Standards.
Page 4 of 10 Version 0007 Dated 02/18/2018
6.SAMPLE QASP PERFORMANCE REPORT DATE: August 22, 2018
Measures PWS Reference
Performance Requirement
Standard Acceptable Quality Level
Surveillance Method
Met AQL/DID
NOT MEET
AQL-
CPAR
RATING/ADD
COMMENTS
Availability of On Call Ultrasound Techs
Contract Technologist(s) shall be available as needed to properly perform tasks as specified.
All (100%) contract technologist (s) are on time and available to perform services.
Contract technicians(s) are on-time and available to perform services 100 % of the time required.
Periodic Inspection or Random Sampling
Privacy, Confidentiality and HIPAA
Special Contract Requirements
Contractor is aware of all laws, regulations, policies and procedures relating to Privacy, Confidentiality and HIPAA and complies with all standards Zero breaches of privacy or confidentiality
All (100%) contractor Technologist(s) comply with all laws, regulations, policies and procedures relating to Privacy, Confidentiality and HIPAA
100% compliance; no deviations.
Periodic Inspection or Random Sampling.
Contractor shall provide evidence of annual training required by VAMC, reports violations per VA Handbook 6500.6.
Maintains licensing, registration, and certification
2.1.2 and 2.1.3
Updated Licensing, registration and certification shall be provided as they are
All (100%) licensing, registration(s) and
All (100%) licensing, registration(s) and
Periodic Inspection or
Page 5 of 10 Version 0007 Dated 02/18/2018 renewed. Licensing and registration information kept current.
certification(s) for contract technologist(s) shall be provided as they are renewed.
Licensing and registration information kept current.
certification(s) for contract Technologist(s) shall be provided as they are renewed.
Licensing and registration information kept current.
No acceptable deviation.
Technical Proficiency
2.1.4 Technical Proficiency
of Ultrasound skills and competencies.
All (100%) contractor Technologist(s) will maintain technical proficiency and skills relating to ultrasound and follow the facilities Medical Staff By-Laws, Rules and regulations
100%
Training 2.1.6 Training – BLS, HER and VA Mandatory Training
All (100%) contract technologist (s) complete and maintain all annual and
100%
Page 6 of 10 Version 0007 Dated 02/18/2018 quarterly training.
Monthly Schedules and contact information
Special Contract Requirements
Monthly schedule of Techs on call
Contractor will provide a monthly schedule of Techs on call with a back up tech, with contact numbers for each tech.
100%
Monthly requirement
Page 7 of 10 Version 0007 Dated 02/18/2018
7. CPAR RATINGS ASSIGNED TO QASP ITEMS:
Metrics and methods are designed to determine rating for a given standard and acceptable quality level. The following ratings shall be used (Reference: CPARS User Manual https://www.cpars.gov/pdfs/CPARS-Guidance.pdf p. A2-1):
EXCEPTIONAL: Performance meets contractual requirements and exceeds many to the Government’s benefit. The contractual performance of the element or sub-element being assessed was accomplished with few minor problems for which corrective actions taken by the contractor were highly effective.
Note: To justify an Exceptional rating, you should identify multiple significant events in each category and state how it was a benefit to the GOVERNMENT. However a singular event could be of such magnitude that it alone constitutes an Exceptional rating. Also there should have been NO significant weaknesses identified.
VERY GOOD:
Performance meets contractual requirements and exceeds some to the Government’s benefit. The contractual performance of the element or sub-element being assessed was accomplished with some minor problems for which corrective actions taken by the contractor were effective.
Note: To justify a Very Good rating, you should identify a significant event in each category and state how it was a benefit to the GOVERNMENT. Also there should have been NO significant weaknesses identified.
SATISFACTORY:
Performance meets contractual requirements. The contractual performance of the element or sub-element contains some minor problems for which corrective actions taken by the contractor appear or were satisfactory.
Note: To justify a Satisfactory rating, there should have been only minor problems, or major problems the contractor recovered from without impact to the contract. Also there should have been NO significant weaknesses identified.
MARGINAL:
Performance does not meet some contractual requirements. The contractual performance of the element or sub-element being assessed reflects a serious problem for which the contractor has not yet identified corrective actions. The contractor’s proposed actions appear only marginally effective or were not fully implemented.
Note: To justify Marginal performance, you should identify a significant event in each category that the contractor had trouble overcoming and state how it impacted the GOVERNMENT. A Marginal rating should be supported by referencing the management tool that notified the contractor of the contractual deficiency (e.g. Management, Quality, Safety or Environmental Deficiency Report or letter).
UNSATISFACTO
RY: Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The contractual performance of the element or sub-element being assessed contains serious problem(s) for which the contractor’s corrective actions appear or were ineffective.
Note: To justify an Unsatisfactory rating, you should identify multiple significant events in each category that the contractor had trouble overcoming and state how it impacted the GOVERNMENT. However, a singular problem could be of such serious magnitude that it alone constitutes an unsatisfactory rating. An Unsatisfactory rating should be supported by referencing the management tools used to notify the contractor of the contractual deficiencies (e.g. Management, Quality, Safety or Environmental Deficiency Reports, or letters).
https://www.cpars.gov/pdfs/CPARS-Guidance.pdf
Page 8 of 10 Version 0004 Dated 6/19/2017
8. DOCUMENTING PERFORMANCE
a. The Government shall document positive and/or negative performance. Any report may become a part of the supporting documentation for any contractual action and preparing annual past performance using CONTRACTOR
PERFORMANCE ASSESSMENT REPORT (CPAR).
b. If contractor performance does not meet the Acceptable Quality level, the CO shall inform the contractor. This will normally be in writing unless circumstances necessitate verbal communication. In any case the CO shall document the discussion and place it in the contract file. When the COR and the CO determines formal written communication is required, the COR shall prepare a Contract Report (CR), and present it to CO. The CO will in turn review and will present to the contractor's program manager for corrective action.
The contractor shall acknowledge receipt of the CR in writing. The CR will specify if the contractor is required to prepare an action plan to document how the contractor shall correct the identified issue and avoid a recurrence. The CR will also state how long after receipt the contractor has to present this action plan to the CO. The Government shall review the contractor's action plan. The CO shall also assure that the contractor receives impartial, fair, and equitable treatment. The CO is ultimately responsible for the final determination of the adequacy of the contractor’s performance and the acceptability of the Contractor’s action plan.
Any CRs may become a part of the supporting documentation for any contractual action deemed necessary by the CO.
See Sample CR on following page.
9. COR AND CONTRACTOR ACKNOWLEDGEMENT OF QASP
SIGNED:
X James D. Ward Imaging Manager
COR NAME/TITLE
SIGNED:
CONTRACTOR NAME/TITLE DATE
Page 9 of 10 Version 0004 Dated 6/19/2017
CONTRACT REPORT
1. CONTRACT NUMBER 2. REPORT NUMBER FOR THIS ISSUE
3. TO: (Contracting Officer) 4. FROM: (Name of COR)
5. DATES
a. CR PREPARED
b. RETURNED BY
CONTRACTOR:
c. ACTION COMPLETE
6. Issue Identified: (Describe in detail. Include reference to PWS Directive; attach continuation sheet if necessary.)
7. SIGNATURE OF COR Date:
8. SIGNATURE OF CONTRACTING OFFICER Date:
9a. TO (Contracting Officer) 9a. FROM (Contractor)
10. CONTRACTOR RESPONSE AS TO CAUSE AND ACTIONS TO PREVENT RECURRENCE.
(Cite applicable quality control program procedures or new procedures. Attach continuation sheet(s) if necessary.)
11. SIGNATURE OF CONTRACTOR REPRESENTATIVE Date:
12. GOVERNMENT EVALUATION.
13. GOVERNMENT ACTIONS
14. CLOSE OUT
NAME TITLE SIGNATURE DATE
CONTRACTOR
NOTIFIED
COR
Page 10 of 10 Version 0004 Dated 6/19/2017
CONTRACTING
OFFICER
| Various methods exist to monitor performance. The COR shall use the surveillance methods listed below in the administration of this QASP. |
| a. DIRECT OBSERVATION. Direct observation by VA personnel during visits to warehouse facilities as well as Veteran homes |
| a. The Government shall document positive and/or negative performance. Any report may become a part of the supporting documentation for any contractual action and preparing annual past performance using CONTRACTOR PERFORMANCE ASSESSMENT REPORT (CPAR). |
| undefined: | |
| Measures: | |
| Performance Requirement: | |
| Standard: | |
| Acceptable Quality Level: | |
| Surveillance Method: | |
| PWS ReferenceAvailability of On Call Ultrasound Techs: | |
| Met AQLDID NOT MEET AQL CPAR RATINGADD COMMENTSPeriodic Inspection or Random Sampling: | |
| Privacy Confidentiality and HIPAA: | |
| Special Contract Requirements: | |
| 100 compliance no deviations: | |
| Met AQLDID NOT MEET AQL CPAR RATINGADD COMMENTSPeriodic Inspection or Random Sampling Contractor shall provide evidence of annual training required by VAMC reports violations per VA Handbook 65006: | |
| 212 and 213: | |
| Met AQLDID NOT MEET AQL CPAR RATINGADD COMMENTSPeriodic Inspection or Random Sampling_2: | |
| renewed Licensing and registration information kept current: | |
| certifications for contract Technologists shall be provided as they are renewed Licensing and registration information kept current No acceptable deviation: | |
| Technical Proficiency: | |
| 214: | |
| Technical Proficiency of Ultrasound skills and competencies: | |
| Training: | |
| 216: | |
| Training BLS HER and VA Mandatory Training: | |
| Periodic Inspection or Random Sampling Periodic Inspection or Random Sampling: | |
| quarterly training: | |
| Monthly Schedules and contact information: | |
| Special Contract Requirements_2: | |
| Monthly schedule of Techs on call: | |
| 100 compliance no deviations_2: | |
| Monthly requirement: | |
| EXCEPTIONAL: | |
| VERY GOOD: | |
| SATISFACTORY: | |
| MARGINAL: | |
| UNSATISFACTO RY: | |
| DATE: | |
| 1 CONTRACT NUMBER: | |
| 2 REPORT NUMBER FOR THIS ISSUE: | |
| 3 TO Contracting Officer: | |
| 4 FROM Name of COR: | |
| 5 DATES: | |
| a CR PREPARED: | |
| b RETURNED BY CONTRACTOR: | |
| c ACTION COMPLETE: | |
| 6 Issue Identified Describe in detail Include reference to PWS Directive attach continuation sheet if necessary: | |
| 7 SIGNATURE OF COR: | |
| Date: | |
| 8 SIGNATURE OF CONTRACTING OFFICER: | |
| Date_2: | |
| 9a TO Contracting Officer: | |
| 9a FROM Contractor: | |
| 10 CONTRACTOR RESPONSE AS TO CAUSE AND ACTIONS TO PREVENT RECURRENCE Cite applicable quality control program procedures or new procedures Attach continuation sheets if necessary: | |
| 11 SIGNATURE OF CONTRACTOR REPRESENTATIVE Date: | |
| 12 GOVERNMENT EVALUATION: | |
| 13 GOVERNMENT ACTIONS: | |
| 14 CLOSE OUTRow1: | |
| NAMECONTRACTOR NOTIFIED: | |
| TITLECONTRACTOR NOTIFIED: | |
| SIGNATURECONTRACTOR NOTIFIED: | |
| DATECONTRACTOR NOTIFIED: | |
| NAMECOR: | |
| TITLECOR: | |
| SIGNATURECOR: | |
| DATECOR: | |
| CONTRACTING OFFICER: | |
| 2022-06-21T14:12:21-0400 | |
| JAMES WARD |
| 2022-06-21T14:11:58-0400 | |
| JAMES WARD |
File details come from the government source that posted it. Updated .